POMPANO G.O. BOND STREETSCAPEDR. MARTIN LUTHER KING JR. BLVD. RECONSTRUCTIONPHASE 2 (BETWEEN NW 10th AVE. AND NW 6th AVE.)
CITY PROJECT NO. 19356SECOND PUBLIC OUTREACH MEETING
JULY 29, 2019
PROJECT BACKGROUND
CONSTRUCTION PHASING - 2014
BLA
NC
HE
ELY
/ 6TH
AVE
ATLANTIC BLVD
I-95
MLK/HAMMONDVILLE RD
PHASE 2PHASE 2 PHASE 1PHASE 1
MLK BLVD. – PHASE 2
MLK BLVD. – PHASE 2
PROJECT BACKGROUND
LANDSCAPE CONCEPT - 2012
MLK BLVD. – PHASE 2PREVIOUSLY DESIGNED AND PERMITTED PLANS
MLK BLVD. – PHASE 2PROJECT DESCRIPTION –ROADWAY RECONSTRUCTION AND STREETSCAPECOMPLETED PHASE 1 (EAST OF NW 6th AVENUE)
MLK BLVD. – PHASE 2PROJECT DESCRIPTION –LANDSCAPE & HARDSCAPE BEAUTIFICATION / MULTI‐MODAL / PEDESTIAN SAFETYCOMPLETED PHASE 1 (EAST OF NW 6th AVENUE)
MLK BLVD. – PHASE 2PROJECT CONSTRUCTION
• MLK PHASE 1 AND 2 WERE PREVIOUSLY FULLY DESIGNED AND PERMITTED.
• SOME PERMITS HAVE EXPIRED FOR PHASE 2 AND ARE CURRENYLY BEING REPROCESSED.
• THE CITY’s INTENT IS TO HAVE THIS PROJECT BE THE FIRST UNDER THE G.O. BOND TO GO UNDER CONSTRUCTION.
• THE CITY IS IN THE PROCESS OF FORMALLY SELECTING THE CONTRUCTION‐MANAGER‐AT‐RISK (CMAR)
• PROJECT SCHEDULECONSTRUCTION COMPLETION – 2021ANTICIPATED CONSTRUCTION DURATION 12‐MONTHS