ITT PMO Update
Brad Ring
ITT PMO Council chair
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
2
ITT Mission & Vision
MISSION
“To deliver quality utility solutions on-time and on-budget”
VISION
“To build a 100% online, interactive, anytime, anywhere, any device, secure, reliable, and scalable enterprise for employees,
customers, partners and vendors.”
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
3
Part 1: History: Establish 5 Project key performance indicators (KPIs)Focus: Reactionary, firefighting, chaos theory.
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
4
Part 1: History: 5 key performance indicators (KPIs)Focus: Reactionary, firefighting, chaos theory.
Historical KPI progress
1. Project communication: Inconsistent
2. Supporting processes: PMO On-line (BOT) Microsoft Server Project 2003
3. Resource planning: Ad hoc
4. Financial reporting: Focus on CIP projects
5. Baseline scheduling: Limited
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
5
Part 1: History Focus: Reactionary, firefighting, chaos theory.
ITT prior Project challenges
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
6
Part 1: History Focus: Reactionary, firefighting, chaos theory.
Resource gridlock
Schedule slippage
Low probability of success
Cost overruns
ITT Project challenges
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
7
Part 1: History Focus: Reactionary, firefighting, chaos theory.
Resource gridlock
Schedule slippage
Low probability of success
Cost overruns
Scope creep Incomplete projects No quality control Most important project
“of the week”.
ITT Project operating environment:
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
8
Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
9
Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability
KPI 1- Project communication (ITT Focus)
Established weekly project status reporting cycle includes distribution to all ITT management and BSA’s.
Established periodic detailed status reviews (DSR) for peer review, schedule review, risks, and feedback.
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
10
Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability
KPI 2 - Supporting Processes
Established 5 new processes & process owners:
PM Mentoring: coaching & mentoring new & existing staff.
Formal resource request process: written approval from RM.
Issue Escalation: Issues sent to all Division Managers & CIO.
Project Prioritization
On-going PM best practices (purchasing, scheduling, etc.)
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
11
Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability
KPI 3 - Resource Planning
Define resource utilization rate for lifecycle tasks: analysis, projects, operations, maintenance and support. (activity tracking sheet)
Established standard utilization factor of 20% for all meetings, overhead, etc.
Created accurate global resource pool
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
12
KPI 4 - Financial Reporting
Created work orders for all active projects to capture all related projects costs (June)
Able to track resources, capital costs, labor, and related expenses in MS Project Server
Coordinating with BSA’s to establish initial work order for lifecycle mgt.
Part 2: KPI Current Accomplishments (Jan 05 to Present)Focus: Repeatability and predictability
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
13
Part 2: KPI current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability
KPI 5 - Baseline Scheduling
Snapshot: current portfolio projected workload of 42 active projects including 18 CIP projects (May)
Training: 25 staff attended formal schedule estimating techniques including PERT, WBS levels, risk mgt.
Pilot project: Service Center replacement
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
14
Service Center Replacement Pilot
Scope:
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
15
Service Center Replacement Pilot
Scope:
Accomplishments:
1. Document high level WBS for entire project
2. Formal cost & schedule estimate for each work package
3. Schedule in MS Project: dependencies, critical path, resources
4. Supporting PM documents: Charter, project plan, risk plan, etc.
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
16
Service Center Replacement Pilot
Scope:
Accomplishments:
1. Document high level WBS for entire project
2. Formal cost & schedule estimate for each work package
3. Schedule in MS Project: dependencies, critical path, resources
4. Supporting PM documents: Charter, project plan, risk plan, etc.
Result: High probability of success
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
17
Part 3: Future Strategies Focus: Integrated workload and resource management
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
18
Part 3: Future Strategies Focus: Integrated workload and resource management
Strategy #1
A. Re-estimate & baseline all existing projects using formal estimating techniques.
B. Require formal estimating on all new proposed projects
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
19
Part 3: Future Strategies Focus: Integrated workload and resource management
Strategy #2
Define resource utilization rate for analysis, projects, operations, maintenance and support by skill, resource, and division.
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
20
Part 3: Future Strategies Focus: Integrated workload and resource management
Strategy #3
Prioritize and rank all projects& support initiatives within eachbusiness unit (including ITT) and across the organization
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
21
Part 3: Future Strategies Focus: Integrated workload and resource management
Strategy #4
A. Link prioritized projectsto global resource pool.
B. Determine resource availability, conduct resource planning and forecasting. Revise project completion dates.
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
22
Part 3: Future Strategies Focus: Integrated workload and resource management
A. Re-estimate & baseline all existing projects using formal estimating techniques.
B. Require formal estimating on
all new proposed projects
Provide resource utilization and availability rate using global resource pool by division and skill set.
Link prioritized projectsto resource plan.
Prioritize projects withineach division and across the organization
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
23
Benefits of Integrated workload and resource management
1. Customers: realistic project delivery dates
2. Sponsors: high degree of success for all projects
3. ITT staff: manageable workload
4. ITT management: Accurate resource allocation & forecasting Resource alignment with highest priority projects Project predictability and repeatability
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
24
Summary
A. Re-estimate & baseline all existing projects using formal estimating techniques.
B. Require formal estimating on all new proposed projects
Provide resource utilization and availability rate using global resource pool by division and skill set.
To successfully complete the Mission Statement “To deliver quality utility solutions on-time and on-budget”
The following foundation pieces must be in place:
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
25
Acknowledgements
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
26
Questions, comments, feedback
Contact:
Brad Ring Ext 6347 TLC 457
© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only
27
DSR I TT DETAILED STATUS REVIEW DSR 3.0
Project:
Project Manager: Project Start Date:
Customer: Est. Completion Date:
Sponsor: Priority:
Project Scope:
1. Scope Yes No NA Date Notes
a. Clearly defined with customer signoff?
b. Identified in MS Project as a note?
c. PMP completed, signed, archived?
2. Schedule/ Budget Yes No NA Date Notes
a. Schedule accurate and updated?
b. Demonstrate progress of milestones & deliverables. Identify next deliverable.
c. Identify the critical path
d. I f CIP, document current cost & budget
e. Work Order established
f. Formal estimation process used
3. Remaining Schedule and Effort
Effort (hours)
Duration (days)
Date Notes
a. Estimated remaining effort
4. Risk Management Yes No NA Date Notes
a. Risk plan completed, signed, archived?
b. Identify any significant issues that may adversely affect project deliverables
5. Procurement Yes No NA Date Notes
a. RFP Requirements? Identify stage.
b. Outstanding issues?
c. Estimated procurement cost & budget ($$)
6. Resource Management Yes No NA Date Notes
a. Are all tasks and deliverables properly resourced?
b. Written commitment from Res. Mgr?
7. Dependencies – Task/ Resource/ Project
Yes No NA Date Notes
a. Any critical dependencies not identified in risk plan?
b. Part of a Program or Multi-Phase initiative?