Objectives
Introduction
Open-cut Installation
Horizontal Directional Drilling Installation
Advantages of HDD vs. Open-cut
Social Cost
Project Description
Cost Comparison
Cost Summary
Conclusion
• Cost comparison of:
Horizontal Directional Drilling (HDD) with traditional
open-cut.
Actual HDD projects carried with theoretical open-cut
costs.
• Summarizing the cost comparison results based on
Contractor’s Bid and RS Means Cost Data 2010.
The cost effective
construction of a pipeline
project requires a clear
understanding of all cost
factors associated with the
specific project conditions.
Cost of a Project
The costs of new installation of water pipes depend on
many factors like the:
Project Size
Length
Depth
Location
Surface and Subsurface Conditions
Type of Application, etc
Work items:
Pipe transportation, handling,
and storage.
Trench excavation.
Foundation, bedding and
placing, and joining of pipe.
Embedment, backfill, and
compaction of the soil.
Costs associated withexcavation, backfilling andresurfacing can account toas high as 70% of the totalproject cost (Najafi, 2005)
Method of installing underground pipes and conduits
along a prescribed bore path from the surface
Minimal impact to the surrounding area.
Task Mini Rigs Midi Rigs Maxi Rigs
Mobilization and Set up < 6 hrs 1 – 3 days 3 – 10 days
Pilot Hole Drilling 100 – 400 ft/hr 60 – 300 ft/hr 20 – 180 ft/hr
Pre-reaming/Reaming (Per
Pass)100 – 300 ft/hr 60 – 240 ft/hr 20 – 180 ft/hr
Product Pullback 200 – 600 ft/hr 200 – 600 ft/hr 150 – 450 ft/hr
Cleanup and Demobilization 2 – 4 hrs 4 hrs to 2 days 2 – 7 days
Trenchless Technology
vs.
Open-Cut Method
Social 5%
Indirect /overhead
20%
Labor 40%
Material 35%
Trenchless Costs
Social 40%
Labor 30%
Materials 10%
Indirect /overhead
20%
Open-cut Costs
Najafi & Gokhale, 2005
Parameters Open-cut InstallationHorizontal Directional
Drilling Installation
Installation costs Installation can be expensive in urban areas Cost effective method in urban areas
Social costsHigh cost for noise, safety, damage to nearby
structures and utilities, health & business loss
Less noise, minimum health risk, no
obstruction to business
Indirect costs Traffic control, job site cost is highMinimum excavation, less traffic
congestion, and minimum equipment
Restoration costs High restoration cost Reduce clean-up and restoration cost
Labor costs High labor cost for excavation and backfilling Less costly, minimum labor force
Equipment Costs Includes excavator and truck Includes drilling rig and excavator
Rate of Production
(Duration)Low (takes more time) High (takes less time)
Location Eastland, Texas
Date of Installation March 10, 2010
Contractor Darnell and Dickson Construction Inc.
HDD Subcontractor Collier Directional Drilling
Length of Installation 318 ft
Nominal Diameter of the Pipe 6 in.
Dimension Ratio (DR) 18
Depth from Ground to Center of the Pipe 4 ft
Crew Details
1 Superintendent,
3 Workers,
1 Backhoe Operator
1 HDD Machine Operator,
1 Front-end Loader Operator,
1 Truck Operator
Equipment
HDD Model: Ditch Witch JT
2720,
Backhoe
Slurry Truck, and
Front-end Loader,
Vacuum Excavator
Soil Condition Clay, Sandy Soil, Gravel
Lubricant used for Drilling Bentonite, Polymer and Bore Gel
Size of the Reamer 10.5 in.
Access Pit and Receiving Pit 6 ft long, 4 ft wide and 4 ft deep
Scope - Case Study 1
Actual project carried out using HDD method of
installation
Product pipe used – Segmented 6” PVC pipe with
Bulldog Restrained Joint
Cost compared:
Open Cut vs. HDD
Using PVC (Internally restrained)
Open Cut vs. HDD
Using HDPE (Fusible)
Trench Cross-Section for Eastland, Texas
Bottom Width = 18 in.
Top width = 24 in.
De
pth
= 4
8 in
.
6 in. Embedment
6 in. PVC
Water Pipe
Bedding
Foundation
Parameters Quantity Take-off
Length = 318 ft
Depth = 4 ft
Top Width = 2 ft
Bottom Width = 1.5 ft
Area= Depth x (Top Width + Bottom Width)/2
= 4 x (2 + 1.5)/2 = 7.0 ft2
Volume of Excavation= Area x Length
= 7.0 x 318 = 2,226 ft3
6 in. PVC Pipe Installation by HDD
Method at Eastland, TexasAssembled Pipe Exit Pit Backfill Pipe Pull Back
Lined Pipe for Pull Back Entry Pit Pipe with Restrained Joints Section 2 Pull Back
Cost Breakdown Eastland, Texas
PVC PIPE
4,825
3,052
13,869
1,512
2,261
3,031
5,139
3,709
2,346
6,300
8711,454 1,632
2,936
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Open-cut HDD
Exit Pit
Entry
Pit
HDD Rig
Water Tank
Vacuum
Excavator
Proposed 4” PVC Water
Pipe
16 “ Corrugated Steel
Storm Sewer Pipe
Existing 2” Galvanized
Steel Water Pipe
Location Clay County, Florida
Date of Installation 02-24-2010
Owner Clay County Utility Authority
Contractor Bore Hawg, Inc, Contact: Jason Riggs, President
Project Contact Steve Rencarge, Operations Coordinator,
Length of Pipe Installation 540 ft
Nominal Diameter of the Pipe 4 in.
Dimension Ratio (DR) 18
Depth from Ground to the Center of the Pipe 5 ft.
Crew Details
1 Superintendent,
3 Workers,
1 Backhoe Operator
1 HDD Machine Operator
Truck Operator
Equipment
HDD Model: Ditch Witch JT
1720 BackhoeVacuum Excavator
Slurry Truck
Scope - Case Study 2
Actual project carried out using HDD method of
installation
Product pipe used – Segmented 4” PVC pipe with
Bulldog Restrained Joint
Cost compared:
Open Cut vs. HDD
Using PVC (Internally restrained)
Open Cut vs. HDD
Using HDPE (Fusible)
Trench Cross-Section for Clay County,
FloridaTop width = 24 in.
Dep
th =
60
in.
Bottom Width = 18 in.
4 in.
Embedment
4 in. PVC
Water Pipe
Bedding
Foundation
Parameters Quantity Take-off
Length = 540 ft
Depth = 5 ft
Top Width = 2 ft
Bottom Width = 1.5 ft
Area= Depth x (Top Width + Bottom Width)/2
= 5 x (2 + 1.5)/2 = 8.75 ft2
Volume of Excavation= Area x Length
= 8.75 x 540 = 4,725 ft3
4 in. PVC Pipe Installation by HDD
Method at Clay County, FloridaBell & Spigot Joint Vacuum Excavator Pipe Joint HDD Reamer
Pulling Head PVC Pipe Lubrication of Joint HDD Rig
Cost Breakdown Clay County, Florida
PVC PIPE
8,390
5,307
18,161
2,510
3,5764,359
7,615
4,588
2,902
7,912
1,649 1,871 2,122
3,788
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
Open-cut HDD
Location: Eastland, Texas
Open-cut HDD
Pipe Material PVC HDPE PVC HDPE
Total Cost, $ 33,690.63 41,867.39 19,250 24269.20
Unit Cost, $/ft 105.95 131.66 63.12 79.57
Location: Clay County, Florida
Open-cut HDD
Pipe Material PVC HDPE PVC HDPE
Total Cost, $ 49,917.60 62,080.93 24,833.47 32,531.22
Unit Cost, $/ft 92.40 114.96 45.99 60.24
Eastland Eastland Clay County Clay County
Open Cut 105.95 131.66 92.40 114.96
HDD 65.27 80.16 45.99 57.10
$105.95/ft
$131.66/ft
$92.40/ft
$114.96/ft
$63.12/ft
$79.57/ft
$45.99/ft
$60.24/ft
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
Un
it C
ost
$/L
Ft
PVC
PVC
PVC
HDPE
HDPE
HDPE
HDPE
PVC
• Open-cut is more expensive than HDD installation for
Eastland and Clay County Project:
• Eastland, Texas
– Open-cut is 41% expensive than HDD
• Clay County, Florida
– Open-cut is 50% expensive than HDD
• Average segmented PVC is 19% less expensive than
fused HDPE pipe for HDD installation.
References
• Harbuck, R. (2000). “Economic Evaluation of Trenchless Technology.” Proceeding of
AACE International Transactions.
• Hashemi, B., Najafi, M., and Mohamed, R., (2008). “Cost of Underground
Infrastructure Renewal: A Comparison of Open-Cut and Trenchless Methods.”
Proceedings of ASCE International Pipeline 2008 Conference, Atlanta, GA.
• Haword, A. (2002). “Pipeline Installation: A Manual of Construction of Buried Pipe,”
Relativity Publishing, Leakwood, CO.
• Najafi, M., & Gokhale, S. (2005). “Trenchless Technology: Pipeline and Utility
Design,
• Construction and Renewal.” McGraw-Hill, NY.
• RS Means Database. (2010). “Building Construction Cost Data.” Construction
Publishers &
• Consultants, Kingston, MA.
• Willoughby, D.A. (2005). “Horizontal Directional Drilling (HDD): Utility and Pipeline
Applications” McGraw-Hill, NY.