Implementation Considerations
Timeframe Roles Implementation Plan Structure Integration with Work Plan Revisions to the Strategic Plan
“When the Council meets to review the draft… should clarify how the plan will be adopted into the Council process and what body will be accountable for overseeing the plan’s implementation. For example, if the Executive Committee were assigned oversight of the strategic plan, how often would the committee meet to review the plan and when? How would the plan’s implementation mesh with the Council’s current workload planning process? If a change to the strategic plan was necessary, how would the plan be amended?
It is important for the Council to provide clear answers to these and other process questions in order to maintain stakeholder engagement and fulfill the promise of an operational strategic plan.”
Pam Lyons GromenExecutive Director, Wild Oceans
Implementation Time Frame
3-year outlook
2-year outlook
1-year Implementation
Plan
• 1-year intervals• Rolling review/
development process
2014 2015 2016 2017 2018
2015-2017 Outlook
2015-2017 Outlook
2015
2019
2014-2016 Outlook
2014-2015 Outlook
2014
Strategic Plan Development
2018
Visioning & Stakeholder Engagement
2017-2018 Outlook
2017
2016-2018 Outlook
2016-2017 Outlook
2016
2014-2018 Strategic Plan
Who Is Responsible?
Oversight– Executive Committee– Executive Director
Implementation Plan Development– Council Technical Staff
Review– Executive Committee– Full Council
Revisions to the Strategic Plan
When would revisions be necessary?
To accommodate external factors such as major policy changes– e.g. MSA reauthorization,
budget/resource limitations To clarify ambiguous language In respond to significant public input If progress on achieving goals &
objectives is significantly faster or slower than expected
Implementation Plan Structure
Summary of previous years’ activities*
Overview– 1-Year Activities– 2 & 3 Year Outlooks
1-Year Implementation Plans – Communication– Science– Governance– Management
*2015 onward
More detailed
Implementation Plan Structure
For Each 1-Year Implementation Section: Situation Overview- internal and external Major Activities
– Tasks– Implementation Schedule– Expected Outcome– Responsible Parties
Performance Monitoring Resource Needs Points-of-Contact
Implementation Plan vs. Work Plan
Implementation plan (IP) will supplement and enhance the Council’s work plan (WP)– May include activities or specific tasks
not previously listed on WP– IP could integrate WPs for amendments
More structured and more detail
2012 Work Plan
Next StepsAug-Oct 2013 Technical staff and Executive
Director develop draft implementation plan
October 2013 Review/revision by Executive Committee
December 2013 Review by full Council
January 2014 Implementation
Next Steps, 2014Aug-Oct 2014 Update on progress and expected
outcomes in 2014; Public comment and Council discussion of 2015 priorities
Aug-Oct 2014 Staff develop draft 2015 implementation plan
Oct 2014 Review by Executive Committee
December 2014 Review by full Council
QUESTIONS?