Birmingham Lend Lease Partnership
an education journeyan education journeyan education journey
cont
ents4 Four Dwellings Primary
6 Summerfield Primary
8 George Dixon Primary
10 Holte/Mayfield/Lozells
12 George Dixon International School
14 Moseley School
16 Stockland Green School
18 Broadway School
20 The International School
22 Park View School
24 Four Dwellings Secondary
26 Saltley School
28 Birmingham Ormiston Academy
30 Shenley Academy
32 Heartlands Academy
34 Aston University Engineering Academy
36 Dorrington Academy
As Western Europe’s largest local authority, Birmingham City Council’s vision of transforming its ageing schools into sophisticated and technology-led centres of education, fit for the next generation and beyond, was a challenge on a global scale.
Lend Lease was chosen as the authority’s development partner, designing, building and delivering 20 separate projects; primaries, secondaries and academies, both refurbishments and new-build, with a capital value of £330 million.
Lend Lease have also delivered managed services for Information & Communications Technology in 13 schools and Facilities Mangement for 10 locations.
The massive programme undertaken by the Birmingham Lend Lease Partnership - a public-private collaboration between council and developer - has achieved nothing short of a renaissance, to the delight of pupils, teachers - and the city council.
Four Dwellings PrimaryDESCRIPTION | PRIMARY NEW BUILDAPPROX PUPIL NUMBERS | 427CONTRACT SUM | APPROX £13 MILLIONSTART ON SITE DATE | 04.07.11COMPLETION DATE | 11.01.13TIME TO BUILD | 14 MONTHS
Summerfield Primary
DESCRIPTION | PRIMARY REFURBISHMENTAPPROX PUPIL NUMBERS | 302
CONTRACT SUM | APPROX £2 MILLIONSTART ON SITE DATE | 06.12.10
COMPLETION DATE | 04.11.11TIME TO BUILD | 10 MONTHS
Summerfield Primary
George Dixon PrimaryDESCRIPTION | PRIMARY NEW BUILDAPPROX PUPIL NUMBERS | 216CONTRACT SUM | APPROX £19 MILLIONCOMPLETION DATE | 06.02.13TIME TO BUILD | 17 MONTHS.
Holte | Mayfield | LozellsDESCRIPTION | HIGH SCHOOL/PRIMARY/SPECIAL NEEDS NEW BUILD
APPROX PUPIL NUMBERS | H 922M 161L 467
CONTRACT SUM | APPROX £34 MILLIONSTART ON SITE DATE | 02.02.09
COMPLETION DATE | 19.12.11TIME TO BUILD | 35 MONTHS
DESCRIPTION | HIGH SCHOOL REFURBISHMENTCONTRACT SUM | APPROX £19 MILLIONCOMPLETION DATE | 06.02.13TIME TO BUILD | 17 MONTHS.
George Dixon International School
DESCRIPTION | HIGH SCHOOL REFURBISHMENT AND NEW BUILD
APPROX PUPIL NUMBERS | 1381CONTRACT SUM | APPROX £17 MILLION
START ON SITE DATE | 06.06.11COMPLETION DATE | 15.02.13TIME TO BUILD | 15 MONTHS
MoseleySchool
DESCRIPTION | HIGH SCHOOL REFURBISHMENT AND NEW BUILD
APPROX PUPIL NUMBERS | 1381CONTRACT SUM | APPROX £17 MILLION
START ON SITE DATE | 06.06.11COMPLETION DATE | 15.02.13TIME TO BUILD | 15 MONTHS
MoseleySchool
Stockland Green School
DESCRIPTION | HIGH SCHOOL NEW BUILDAPPROX PUPIL NUMBERS | 679
CONTRACT SUM | APPROX £17 MILLIONSTART ON SITE DATE | 02.02.09
COMPLETION DATE | 01.04.11TIME TO BUILD | 26 MONTHS
Broadway SchoolDESCRIPTION | HIGH NEW BUILD & REFURBISHMENTAPPROX PUPIL NUMBERS | 1300CONTRACT SUM | APPROX £18 MILLIONSTART ON SITE DATE | 02.02.09COMPLETION DATE | 19.05.11TIME TO BUILD | 28 MONTHS
The InternationalSchool
DESCRIPTION | HIGH SCHOOLAPPROX PUPIL NUMBERS | 911
CONTRACT SUM | APPROX £11 MILLIONSTART ON SITE DATE | 31.01.11COMPLETION DATE | 30.06.12TIME TO BUILD | 18 MONTHS
Park View SchoolDESCRIPTION | HIGH SCHIOOL REFURBISHMENT AND NEW BUILDAPPROX PUPIL NUMBERS | 604CONTRACT SUM | APPROX £8 MILLIONSTART ON SITE DATE | 31.01.11COMPLETION DATE | 11.06.12TIME TO BUILD | 18 MONTHS
Four Dwellings Secondary
DESCRIPTION | HIGH SCHOOL REFURBISHMENTAPPROX PUPIL NUMBERS | 592
CONTRACT SUM | APPROX £13 MILLIONSTART ON SITE DATE | 04.07.11
COMPLETION DATE | 11.01.13TIME TO BUILD | 14 MONTHS
SaltleySchoolDESCRIPTION | HIGH SCHOOL REFURBISHMENT AND NEW BUILDAPPROX PUPIL NUMBERS | 936CONTRACT SUM | APPROX £11 MILLIONSTART ON SITE DATE | 23.06.11COMPLETION DATE | 25.10.12TIME TO BUILD | 14 MONTHS
Birmingham OrmistonAcademyDESCRIPTION | ACADEMY NEW BUILDAPPROX PUPIL NUMBERS | 950CONTRACT SUM | APPROX £23 MILLIONSTART ON SITE DATE | 12.04.10COMPLETION DATE | 07.10.11TIME TO BUILD | 18 MONTHS
Shenley AcademyDESCRIPTION | ACADEMY NEW BUILD
APPROX PUPIL NUMBERS | 1150CONTRACT SUM | APPROX £22 MILLION
START ON SITE DATE | 21.02.11COMPLETION DATE | 12.07.13TIME TO BUILD | 19 MONTHS
Heartlands AcademyDESCRIPTION | ACADEMY NEW BUILDAPPROX PUPIL NUMBERS | 755CONTRACT SUM | APPROX £19 MILLIONSTART ON SITE DATE | 21.02.11COMPLETION DATE | 23.07.13TIME TO BUILD | 19 MONTHS
Aston University Engineering Academy
DESCRIPTION | ACADEMY NEW BUILDAPPROX PUPIL NUMBERS | 600
CONTRACT SUM | APPROX £14 MILLIONSTART ON SITE DATE | 28.03.11
COMPLETION DATE | 03.09.12TIME TO BUILD | 17 MONTHS
DorringtonAcademy
DESCRIPTION | MODULAR NEW BUILDAPPROX PUPIL NUMBERS | 552
CONTRACT SUM | APPROX £1 MILLIONSTART ON SITE DATE | 13.02.12
COMPLETION DATE | 01.06.12TIME TO BUILD | 5 MONTHS
PROJECT DESCRIPTION APPROX PUPIL NUMBERS
CONTRACT SUM (APPROX)
START ON SITE DATE
COMPLETION DATE
TIME TO BUILD
HML (PFI) High/Primary/Special Needs New Build H 922 M 161 L 467
£34 million 02.02.09 19.12.11 35 months
STOCKLAND GREEN (PFI) High New Build 679 £17 million 02.02.09 01.04.11 26 months
BROADWAY High New Build & Refurb 1300 £18 million 02.02.09 19.05.11 28 months
GREET Primary Refurb 709 £3 Million 06.12.10 19.08.11 9 months
REGENTS PARK Primary Refurb 486 £3 million 06.12.10 05.09.11 9 months
SUMMERFIELD Primary Refurb 302 £2 million 06.12.10 04.11.11 10 months
DORRINGTON Modular New Build 552 £1 million 13.02.12 01.06.12 5 months
ORMISTON High 950 £23 million 12.04.10 07.10.11 18 months
INTERNATIONAL High 911 £11 million 31.01.11 30.06.12 18 months
PARK VIEW High Refurb and New Build 604 £8 million 31.01.11 11.06.12 18 months
FOUR DWELLINGS High Refurb/Primary New Build Primary 427 High 592
£13 million 04.07.11 11.01.13 14 months
MOSELEY High Refurb and New Build 1381 £17 million 06.06.11 15.02.13 15 months
GEORGE DIXON High Refurb/Primary New Build Primary 216 High 1050
£19 million 28.03.11 06.02.13 17 months
SALTLEY High Refurb and New Build 936 £11 million 23.06.11 25.10.12 14 months
ASTON Academy New Build 600 £14 million 28.03.11 03.09.12 17 months
HEARTLANDS Academy New Build 755 £19 million 21.02.11 23.07.13 19 months
SHENLEY Academy New Build 1150 £22 million 21.02.11 12.07.13 19 months
ST ALBANS Academy New Build 203 £17 million 27.06.11 05.08.13 25 months
NORTH BIRMINGHAM Academy New Build 1011 £23 million 25.07.11 04.11.13 28 months
WAVERLEY (PFI) Academy New Build 768 £27 million 23.01.11 12.09.14 40 months
SHELDON HEATH Academy New Build 1100 £25 million 09.11.11 20.06.14 30 months
TOTAL £328 million
Project Handover Inform
ation
Birmingham Lend Lease Partnership