Transcript

Paul Solomon 1

Integrating SystemsEngineering, Risk and Earned

Value Management

CPM Spring Conference 2001

San Diego, CA

24 May 2001

Presented by:

Paul Solomon

Northrop Grumman Corp.(661) 540 - 0618

[email protected]

Paul Solomon 2

• Threats to Program Success

• Systems Engineering (SE)– Develop a Product per Operational Needs– Requirements Management– Technical Performance Metrics (TPM)– Performance-Based Earned Value (PBEV)– Risk Management

• Government Requirements, Industry and ProfessionalStandards

• Integrated Processes

• Best Practices

Topics

Paul Solomon 3

Threats to Program Success

• Inadequate Early Warning

• Schedules, Metrics Overstate True Progress

• Remaining Work Underestimated

• Product Will Not Meet User Needs

CAN BE PREVENTED BY INTEGRATING: - SYSTEMS ENGINEERING (SE) - RISK MANAGEMENT (RM) - EARNED VALUE MANAGEMENT (EVM)

Paul Solomon 4

SE / What Is It?

• SE Processes Transform Operational Needs andRequirements into Systems

• Solution Includes– Design– Manufacturing– Test and Evaluation– Support of Product

• Balance Between Performance, Risk, Cost andSchedule

• Top-down, Iterative Process

As defined in Interim Reg. DoD 5000.2-R, Part 5.2

Paul Solomon 5

SE Process

• Requirements analysis

• Functional analysis and allocation

• Design synthesis and verification

• System analysis and control

Paul Solomon 6

SE Model

Oper.Needs

PerformanceSpecifications

DecomposedWork

Definition

Products

Processes

Tools

DetailedDesign

Build /Implement

Test

Integrate

Test

Test

Integrate

Thanks to Melissa Boord & Fred Manzer

Paul Solomon 7

DoD Requirements

Interim Regulation, DoD 5000.2, Jan. 4, 2001

Systems EngineeringPar. 5.2

Risk ManagementPar. 2.5, 5.2

EVMSPar. 2.9.3.4

Mandatory Proceduresfor MDAPs and MAIS

MDAP: Major Defense Acquisition ProgramMAIS: Major Automated Information System

Paul Solomon 8

• SE Technical Process

• SE Management Process

• Organization Process

• Configuration and DataManagement Process

SE Procedures

Int. Reg. DoD 5000.2

EIA/IS-731 Std.

ANSI/EIA-748-98 (EVMS)

Government / Industry/Professional Standards

Northrop Grumman,Integrated Systems Sector,Air Combat System (ACS)

SE Procedures

PMBOK® Guide (1)

(1) Project Management Institute, A Guide to the ProjectManagement Body of Knowledge, December 2000

CMMI-SE/SW V1.0

Paul Solomon 9

Requirements Management Products

• Concept of Operations

• System Integration Requirements Document (SIRD)

• Design Constraints / Key Drivers

• System Description Document (SDD)

• System Requirements Review (SRR) Documentation

• Functional Description Document (FDD)

• Specification / Document Tree

• Technical Performance Metrics (TPM) and Plan

• Trade Study Documentation

• Requirements Traceability Database (RTD)

• Configuration Baseline

Paul Solomon 10

REQUIREMENTS TRACEABILITY

• Verify that All Requirements are Addressed and Tested

• Traces Requirements From the Input to a Phase to theProduct of that Phase

• Reassure Team that are:– Building the right product (Validation)– Building the product right (Verification)

• Defined by Requirements Traceability Database (RTD)– To Documentation and Components– To Test Plan and Test Results

Paul Solomon 11

REQUIREMENTS TRACEABILITY MATRIXThrough Documentation and Components

DOCU MENT:SYS.SPEC. SRS

SYS.DESCSC

IGN DOC.CSU

TESTCSCI

PLAN:CSC

2.2.1 2.2.42.2.5

2.5.12.5.3

2.5.1.22.5.3.3

2.7.12.7.4

2.7.1.42.7.4.1

COMP ONENT:SYS-TEM CSCI CSC CSU CSCI CSC

1.0 1.1.0 1.1.0.1 1.0 1.1.0

Paul Solomon 12

Requirements Traceability / SLATE

Requirements Traceability

Configuration Control

SOW

TLR

TASKN

FUNCTIONALHIERARCHY

FUNCTIONAL FLOWBLOCK DIAGRAMS

FUNCTION 1

PHYSICALHIERARCHY

COMPONENTX

Requirements Parsing

Requirements Derivation

Specification Generation

System Definition

Mission Analysis

Requirements Allocation

RequirementsAnalysis

Req’ts Documents

Import

TLR

SOW

TASK1 SYSTEM

SPEC

SYSTEMPIDS

SEGMENTSPECS

SUBSYSTEMPIDS

Paul Solomon 13

Program X Requirements Management MatrixR

equ

irem

ents

(“S

hal

ls”)

0

Time (months)

ATP5/26/99

SRR8/25/99

SIR4/26/00

FRR12/22/00

SD

D (

97)

SIR

D (

65)

7/9/

99

KPP’s(3)

Rating: GREENRating: GREENRating: GREEN

F/T Complete8/15/01

100

Y2K

1000

500

Op

erat

ion

s (

7 p

er R

eq’t

)

1500

0

GREENREDYELLOW

2037

18 Sept.Time Now

200

Ph

ys

IC

D-

Pt

1

(

58

wa

s

54

)

300

Te

st

1;

DT

R/T

P’s

(46

SD

D R

eq’t

s)

Te

st

2;

DT

R/T

P’s

(8

SD

D R

eq

’ts)

Te

st

4;

DT

R/T

P’s

(35

SD

D R

eq’t

s)

Te

st

3;

DT

R/T

P’s

(17

SD

D R

eq’t

s)

Flig

ht

Tes

t E

TR

’s (

? R

eq’t

s )

Defined RequirementsValidated*

CW

ML

IC

N

(5

1)

Entered

Linked

Assigned

Status

VerificationECD

VerificationMethod

Test Report#

Operations Code (7)

Tes

t 5;

DT

R/T

P’s

(1

SD

D R

eq

’t)

Ph

ys

IC

D-

Pt

2

(1

7)

Paul Solomon 14

Requirements Traceability Database (RTD)SE Work Package EVM Technique

• 7 RTD Operations per Requirement

• Monthly Milestones with % Complete– Requirements Tool Calculates Metrics– % = # RTD Operations Complete / Total RTD Operations

• Closely Monitor Verification Activity

Paul Solomon 15

Performance Metrics

• SE System Analysis and Control activities include (1):– Performance metrics to measure

– Technical development and design, actual vs.planned

– Meeting system requirements:– Performance (TPM)– Progress in implementing risk handling plans– Producibility– Cost and schedule

– Performance metrics traceable to performanceparameters identified by operational user

(1) Interim Reg. DoD 5000.2-R, para. 5.2

Paul Solomon 16

QTR/YEAR

EVENTS

1Q99 2Q99 1Q003Q99 4Q99 3Q004/98 2Q00

EXTENSION:

RISKTECHNICAL

COST

SCHEDULE

888-552-5820DewRESPONSIBLE ENG..REQUIREMENTS REFERENCE:

ANTENNA TPMs - Gain and Radar Cross Section

Achievement (notional)

GAIN

LAB TESTS

SRRIDR 3/15 Qual Complete Flight Units

-3 dB

+3 dB

Qual Start

RCS

SPEC

min

max

1/30 2/30

0 db

FDR 6/15

DELTAFROM SPEC

DELTAFROM SPEC

SOURCE CONTROL DRAWING 3391P020

Notes:

Paul Solomon 17

Technical Performance Plan / TPM

100

125

150

Per

cen

t R

equ

ired

Val

ue

High Risk

Moderate Risk

Low Risk

Performance Measurement Milestones

Calendar

WBS xxxx.xx dd mm yy

Planned Value Profile

High

Mod

LowClosed

Risk Mitigation Profile

Milestones

Paul Solomon 18

Technical Performance Plan with Tolerance Bands

100

125

150

Per

cen

t R

equ

ired

Val

ue

Planned Value Profile

Tolerance Bands

Paul Solomon 19

Earned Value and TPMs

• Acceptable Deviation Should Decrease Over Time

• Parametric Data or Expert Judgement Available

• Maximum EV if No Deviation

• Less EV if within Tolerance Bands

• No EV if outside Tolerance Bands

Paul Solomon 20

PERFORMANCE-BASED EARNED VALUE• Lean Goal: Reduce EV costs; Measure what’s important

• Emphasize SE Performance Metrics– Progress of Technical Development, Design, Test– TPM– Risk drivers/critical path

• Measure Key Technical Performance Indicators– Products; not tasks, inchstones, reviews– Verification of TPMs (Successful test and documentation)

• Integrate Schedule, TPM, PBEV

SCHEDULE/TPMEV

Paul Solomon 21

Best Practices to Monitor ProgramTechnical Progress with SE Tasks

• SE products, milestones on IMS

• Discrete SE work packages and EV measures– Track progress of key SE products– Track progress of completing RTD

• Monitor SE schedule variances– Mirrors program’s overall technical progress– Small absolute value; high impact

• Use TPMs as a basis of PBEV for technical tasks

• Compare SE schedule variances with technical PBEV

Paul Solomon 22

• Risk: Uncertain event or condition that, if it occurs,has a negative (or positive) effect on a projectobjective

• Systematic process of identifying, analyzing andresponding to project risk

• Part of the SE Process

• Proactively Working to Prevent an Unfavorable Eventfrom Occurring which Threatens Objectives– Cost, Schedule, Technical

What Is Risk Management?

Paul Solomon 23

Potential Sources of Technical RiskPartial Listl Technology Maturity

l Lack of ApplicableHistorical Data

l Design Complexity

l Challenging Requirements

l Dependency Factors

l Estimating Bias

l Supplier Expertise andPerformance

l Customer Uncertainty

l Design and ConfigurationChanges

l Complex Interfaces

l Safety

l Lack of Experience/Expertise

l Complex ManufacturingProcesses

l Complex Software

l Performance Based onAnalysis Only

Paul Solomon 24

• Government Requirements:– Interim Reg. DoD 5000.2– OMB Circular No. A-11 (Fixed Assets), Section 300.7

– Analysis of goals (cost, schedule, performance)includes risk assessment

• Professional: PMBOK ®– 5.5.1.3: Implement a contingency plan or workaround

plans to respond to a risk– 7.4.3.4: EAC, forecast of most likely costs based on

project performance and risk quantification

• CMMI-SE/SW v1.02– Maturity Level 3 Process Area: Risk Management

Why Do We Manage Risk?

Paul Solomon 25

EVM GUIDES SILENT ON RISK

• Industry Standard

• EVM Implementation Guide (EVMIG)

• Company EVMS– Most EVM System Descriptions silent on risk– Risk mitigation plans not always

budgeted or scheduled– Program projections inconsistent with

risk assessments and risk mitigation plans

Paul Solomon 26

Risk Inherent in Contractors’ Practices

• Integrated Master Plan and Schedule

• Performance Measurement Baseline (PMB)

• Management Reserve

• Integrated Baseline Review

• Establish and monitor TPMs

• Develop EAC

• Trade offs to meet cost constraints

Paul Solomon 27

Risk Management Process

# 1 RiskIdentification

# 2 RiskAssessment

# 3 Risk Mitigation

# 4 Risk Monitoringand Control

Issues, Concerns,and

Potential Risks

Tools, Methods, and Processes

Feedback

Paul Solomon 28

Risk Assessment

• Two Parameters:– Probability of Not Achieving a Specified Program or

System Objective

– Consequences of Not Achieving the Objective– Impacts:

– Cost– Schedule– Technical Requirements– Customer Satisfaction

Paul Solomon 29

Risk Component Aircrew RequirementsArea of Impact Cost / Schedule

Rating: YellowRating: YellowRating: Yellow

1

5

Pro

babi

lity

08/12/00 RHG

Impact1 5

Risk Description:• Aircrew Requirements Not Fully Defined

May Drive Cost Increases and ScheduleSlips

Key Points:• Requirements Creep Adversely Impacts

Cost and Schedule

Mitigation Activity: ECD• Establish Customer Aircrew Working

Group to Prioritize Requirements.(A) 06/16/00

• Develop Draft ConOps to Identify RealNeeds. 10/31/00

• Identifying Minimum Capabilities 04/30/01

• Define Trade-offs with Customer Aircrew05/31/01

CS

IPT: Project X

Paul Solomon 30

Best Practices to Integrate RM with EV

• Include RM Activities on the Baseline Schedule– Define Exit Criteria for RM Decision Points– Establish Dependencies

• Budget the RM Effort, Track with EV

• Address RM in Performance Analysis

• Incorporate RM in EAC Development– If probability and impact are high (Most Likely)

Paul Solomon 31

Northrop Grumman ACS Process Integration

ConceptDevelop-

mentRequire-

mentsValidation

Require-ments

Manage-ment

SystemDesign

Interface&

Integration

SystemVerification

SE Technical

Outcomes / Decisions

ProductEvolution

ProcessManagement

& Improvement

InfrastructureManagement

TrainingManagement

Planning

RiskManage-

ment

Tracking &Oversight

Quality Assurance

Configuration/Data Management

SE Management

Plans / Direction

ProgramPlanning &Schedule

Integration

EVM

DenotesCriticalProcess

Paul Solomon 32

ACS EVM System Description (1)Linked to SE and Risk Procedures

• CAM Responsibilities– Integrate budget and schedule with technical SOW– Identify technical metrics– Use TPMs as a basis for EV– Incorporate risk assessment and corrective actions

into EVMS

• Program Manager Responsibilities– Assess EAC based on pressures, risks,

opportunities

1) Air Combat Systems Procedure DTM F208

Paul Solomon 33

ACS SE ProcedureLinks TPMs to EV

• SE Tracking and Oversight (E1-0401.9)– TPMs track key technical parameters– EV should be based on TPMs which best

indicate progress towards meetingtechnical requirements

Paul Solomon 34

ACS Risk ProcedureLinks to EVMS and SE

• Risk Management (D1-5002)– Sources of risk identification:

– Projected or actual adverse performance– Technical performance based on TPMs– Cost or schedule performance per EVMS

– Significant risk management activities are planned,budgeted and tracked in the EVM and schedulingsystems

– If the risk cannot be fully mitigated, immediately:– Revise the EAC– Report schedule impacts on affected schedules

Paul Solomon 35

Linked Controls and Procedures

ProcedureReq.

Trace. TPMsEV

MeasuresRiskItems

Req.Mgt. X X X X

SystemDesign X X X

SystemVerific. X X X

Planning X X X

EVM X X X X

RiskMgt. X X X

Controls

Paul Solomon 36

SUMMARY FOR SUCCESS

• Operational Needs: Define, Decompose, Validate, Verify

• Requirements Management Traceability

• Plan SE Tasks in PMB

• Use TPMs and Performance-Based Earned Value

• Correlate Progress of SE Tasks with Technical Progress

• Include Risk Management Activities in PMB

• Integrated, Documented Processes


Recommended