Hummock Pond Road Bike Path Hummock Pond Road Bike Path

Implementation UpdateImplementation Update

January 25, 2012January 25, 2012

• Bike path will run from end of Milk Street extension to Cisco Beach• Funding from the Town of Nantucket and private donations• Estimated completion date: May 2013• Implements path six years earlier than Transportation Improvement

Program funding

HPRBP –Implementation Summary

January 2012: - ConCom hearings (January 4th and 18th)- Receipt of abutter right of way comments- County public hearing for taking all easements- Utilities notified / initial design plans distributed

December 2011: - Staking of path centerline and property bounds for Stroll Weekend- Finalize Appraisals, ROW plans, and property owner notices- Conservation Commission review initiated

November 2011: - Development and review of initial design with VHB- Notice to abutters of strategy and property staking- ROW plan complete / initiate

October 2011: - BOS / County approval of implementation strategy- Finalize amendment to design contract with VHB- Wetland review with ConCom staff

HPRBP Implementation Schedule – Tasks Completed

May 2013: - Construction complete

October 2012: - Pre-Construction meetings- Construction Starts

September 2012: - Construction bid opening

July 2012: - Finalize design plans- Construction bid

May 2012: - Initiate final design of bike path

April 2012: - Construction funding ($3.2 million) approved at ATM / ballot- Taking filed at Registry if the funding is approved- Right of way damage award notifications

March 2012: - ROW secured via County taking (recorded after ATM / ballot vote in mid-April)

February 2012: - ConCom hearing – seek approval of Order of Conditions- County hearing of taking challenges

HPRBP Implementation Schedule – Tasks to be completed

Issues: WetlandApprox. 3,600 sqft of total wetland impacts at various locations

Wetland near Millbrook Road intersection


Recommended