Test And Inspect Overview:• Test operation of all devices that report to the Fire Alarm
Control Panel (FACP).• Check for their good operation, maintenance, and cleanings .• List and report all devices on maintenance ticket for office
and tenants records.• File smoke detectors maintenance Log Book that stays on
the premises.
Types of Services Provided:• Test and Inspect• Installation / Service Calls• Programming
Field Operations Department
3
List of devices to check throughout building: Smoke Detectors (SD) Duct Detectors (DD) Heat Detectors (HD) Manual Pull Stations (MPS) Water flow sensors (WF) Tamper Switches (TS) Warden Phones (WPH) Beam Detectors (BD)
Field Operations Department
4
Test and Inspect
Procedure Request for system to be put OFFLINE (FSD, BE,
Security, Technician) Call to Central Station (Statewide, AFA,
Central monitoring, etc.) Ask to be OFFLINE for four hours, or height
hours
Check for panel condition upon arrival at FACP Report on maintenance ticket Active points
and Disable points (Ap 0000, Dp 0000).
Si lent Test / L ive Test / Visual Test.
5
Test and Inspect
Silent Test
Put panel on TEST mode (IO-64, IO-500, EST-2, EST-3), or ensure all Audible and Visual devices are DISCONNECTED (Quick Start, NAC disconnect panels).
Disable Devices or Actions (Fan Shut Down, Elev. Recall, Door Release).
Check all devices when panel is on TEST and all Actions are DISABLED.
Write displayed message with last four numbers of device on maintenance ticket.
Reset panel and make sure all device are cleared, so won’t activate accidentally.
Take the panel OFF TEST, and ENABLE all Actions previously disabled.
Close ticket after made sure panel is in same or better condition at departure.
Si lent Test / L ive Test / Visual Test.
6
Test and InspectSi lent Test / L ive Test / Visual Test.
Live TestWhen Silent Test completed and panel put Off Test: Make announcement through Speakerphone. Activate any device that will put the building on Alarm. Check on every floor that all output devices of fire alarm system
are operational (Speaker/Strobes, Horn/strobes, Bells, Door release, Fan Shut Down, Elev. Recall) Acknowledge the Alarm message on FACP, then reset the FACP
to clear Alarm.
7
Test and InspectSilent Test / Live Test / Visual Test / Supervisory Test / Sensitivity Test.
Visual Test
No need to request account to be put Offline. Walk through all floors of the building and check if devices are in
good condition. Report with a check on maintenance ticket all devices that pass
visual inspection.
Supervisory Test
Tamper Pump Run/Fail Pressure High/Low Phase Reversal
8
Test And Inspect In PicturesCentral Station
Call to request system to be put offline Communicator Calls Fire Department if system not
offline
Panels (FACPs)
EST-2 EST-3Microphone
Quick Start (Disconnect NAC)
IO-64/IO-500 (Test Mode)
Commercial Fire
9
Conclusion
10
Recommendation to make the program better
Excellent program where intern can learn from the field to become good technicians.
A rotation between all departments of the Field Operation to have a better understanding of all parts of technical service.
Conclusion
What I’ve learned through this internship
The understanding of Fire alarm system. The need of effective communication. The necessity to pay attention to small details The overall qualities needed by a technician
11
Questions and Answers
Thanks to my mentor and to all the staff at High Rise for having given me this opportunity to succeed in this internship, and for having listened to my presentation.I hope you appreciated the time I dedicated to learning within your company.
If you have any questions, please feel free to ask me some.
With my Best regards,
Sincerely,
Gilles Bazabas
12