Page 1: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

1

Replacing the Aging US 52Mississippi River Bridge

February 27, 2016

Faith Duncan, PE & Greg Hasbrouck, PE

Soci

ety

of W

omen

Eng

inee

rs R

egio

n H

Con

fere

nce

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Project Overview

• US 52 / IL 64 over the Mississippi River• Connecting Savanna, IL to Sabula, IA• Illinois DOT Led Project• Replacing Existing Cantilever Truss Bridge

– 520 ft main span

• Extensive Coordination– Environmental and Permitting– Railroads and Utilities

• Proposed 546 ft Main Span Tied Arch– Steel Plate Girder Approaches– Drilled Shafts with Coffercell Footings

2

Page 2: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

2

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Project Location

W I S C O N S I N

I L L I N O I S

I O WA

3

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Aerial View

• Sabula, IA– “Iowa’s only

island city”– Pop. 576

• Savanna, IL– “Sportman’s

Paradise”– Pop. 2,945

4

Page 3: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

3

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 5

Iowa Causeway

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 6

National Fish & Wildlife Refuge

Page 4: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

4

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

BNSF Railway

7

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Mississippi Palisades State Park & Bluffs

8

Bluffs along IL 84

Page 5: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

5

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 9

Mississippi River & Barges

The Upper Mississippi River System is theonly waterbody in the nation that has beenrecognized by Congress as a “nationallysignificant ecosystem and a nationallysignificant commercial navigation system.”(Section 1103 of the Water ResourcesDevelopment Act of 1986, PL 99-662)

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 10

History

• Constructed in 1932• Savanna-Sabula

Bridge Company• Private Toll Bridge

before being turned over to Iowa

• Illinois took over jurisdiction in 1987

• Listed as a Historic Structure in 1999

Page 6: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

6

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 11

Existing Bridge

• 947 ft Iowa Approach• 282 ft Simple Span Truss• 1,160 ft Cantilever Truss

• 520 ft main span• 78 ft Illinois Approach• 2,468 ft in total length

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Existing Bridge

12

Page 7: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

7

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 13

Open Deck Grate

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Repairs

• Major repairs in 1985• Minor repairs in 1999• Partial replacement of steel

grid deck in 2008– 28 day road closure and $2.9M– Major out cry from public

• Identified more repairs in 2009– $8M repairs + $8M user cost– 9 month closure, 37 mile detour

• Future repairs?

14

Page 8: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

8

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Key Issues

• Structurally Deficient– Entire Iowa approach substructure– Repairs needed for truss spans– Weight Limit

• Functionally Obsolete– 2 narrow 10 ft lanes– Trucks encroach into lane– Tight turning radius– Steel grid deck

• Remaining Service Life– 8 to 10 years in current state

15

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Average Daily Traffic (ADT) over the Mississippi

W I S C O N S I N

I L L I N O I S

I O WA

Dubuque, IAUS 20: 14,600US 61: 20,700

Savanna, IL US 52: 2,400

Fulton, IL & Clinton, IA IL 136: 10,500US 30: 12,600

Quad CitiesI-80: 37,200I-74: 76,700US 67: 30,300I-280: 19,800

16

• Vital Transportation Link– Education, Emergency & Jobs

– Nearest Alternate Crossingo Clinton, IA – 20 miles southo Dubuque, IA – 45 miles north

Page 9: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

9

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Cost & Schedule

17

$5 Million

Phase I

$5 Million

Phase II

$80.6 Million

Phase III

Identified for Replacement

Preliminary Concepts

Public Meeting(June 27, 2012)

Project Initiation

Data Collection

Existing StructureDemolished(Nov, 17 – Jan, 18)

Proposed Bridge Fully Open to Traffic(October 31, 2017)

Letting – Contractor Bids (September 19, 2015)

Plan Submittal(July , 2015)

Approved Project Report

(March 23, 2015)

Approved Environmental Assessment

(October 7, 2014)

Public Hearing(November 19, 2014)

Construction Begins(Mid January, 2016)

Proposed RetainingWall Completed(November 18, 2016)

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 18

Coordination & PartnersPartnersIllinois Department of Transportation (Lead Agency)Iowa Department of TransportationFederal Highway AdministrationParsons Team

Parsons Transportation Group – Prime Wang Engineering – Geotechnical Images – Public Involvement Snyder & Associates – Drainage Dan Brown & Associates – Foundations Michael Baker International – independent check of Tied Arch Design

CoordinationFederal Federal Aviation Administration* Federal Highways Administration US Fish & Wildlife Services US Army Corps of Engineers* US Coast Guard* Tribal Council

State IL & IA State Historic Preservation Office IL & IA Department of Natural Resources* IL & IA Environmental Protection Agency* Upper Mississippi Port District*

Local City of Savanna Savanna Park District Property Owners

Private BNSF Railway* River Industry Utilities (Windstream & JoCarroll Electric) Engineering & Construction Experts*Permitting Agencies

Page 10: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

10

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 19

Little Brown Bats

• Roosting under the bridge and in trees

• USFWS recommended restrictions

• October 1 – March 31

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 20

Shadflies (aka Mayflies)

• Attracted to light

• Males die after mating

• Females die after laying eggs

• Smell like dead fish

• Short adult life

• Swarms

Page 11: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

11

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 21

Bridge for Sale

• Free!• Half mile long steel truss

bridge• Must be kept “in its historical

significance in perpetuity”• Pay moving cost up to the

cost of demolishing it

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 22

Scope of Work

• Phase I– Preliminary Geotech– Geometric Design– Hydraulic Reports– Bridge Condition Report– Bridge Type Study– Public Involvement– Environmental Assessment– Project Report– TS&L Bridge Plans

• Phase II– Final Geotech– Final Roadway Plans– Final Structure Plans– Cost & Time Estimates– Load Rating– Public Communication

• Phase III– Public Communication– Shop Drawing Review– Construction Coordination

Page 12: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

12

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Constraints

• Iowa Causeway– Minimize Environmental Impacts– Minimize Causeway Construction

• Illinois Intersection– Between bluff and railroad– Minimal change to existing IL 84– Tie-in at highpoint– Limit ROW Impact

• Minimize grades to 4% if possible

23

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 24

Navigation Clearance

• Maintain Existing Clearances– Channel near Illinois bank– Steep grade with existing tie-in (> 4%)– Minimal Superstructure Depth

Page 13: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

13

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 25

Navigation Channel Shift

• Approach USCG with Channel Shift– Proposed 200 ft shift to west– Agreed to 150 ft shift to west– Maintain 350 ft channel during construction– 7.5 ft superstructure depth and 4% max grade

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Bridge Type Study

• Evaluated 3 Types– Tied Arch, Cable-stayed, Plate Girder

• Plate Girder abandoned due to structure depth– No supports in navigation channel

• Tied Arch– Basket-handle, vertical w/ bracing, vertical w/o bracing, single

arch– Carried forward basket-handle and vertical w/ bracing

• Cable-stayed– Evaluated various configurations– Carried forward 3 span w/ composite steel girder concrete deck

26

Page 14: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

14

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 27

Bridge Type Study

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Bridge Type Study Evaluation

Criteria– Initial Cost– Inspection & Maintenance– Aesthetics– Durability– Constructability– Environmental Impacts– Structure Depth– Geotech– Hydraulics– Future Widening

Results• Tied Arch

– Float-in Erection– Replaceable Deck

• Cable-stayed– Not fracture critical

• Similar costs• Selected Tied Arch

– Less length of complex structure

– IDOT familiarity

28

Page 15: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

15

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Preliminary Design Development

• Advance Structural Decisions before Final Design– Vessel Collision Study– Approved Design Criteria– Optimized Span Layout / Pier Locations– Foundation Type Study

• Tied Arch Concepts Advanced– Sections defined and sized (H, I, Box)– Floor beam sized and spacing optimized– Hanger arrangement and spacing– Floating deck concept advanced– Stringer fixities defined

• Final Design completed in 12 months to meet schedule29

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 30

Geotechnical

Page 16: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

16

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 31

Geotechnical

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 32

Proposed Structure

Iowa

Illinois

546 ft Tied Arch

8-span Steel Plate Girder = 1420 ft

3-span Steel Plate Girder = 488 ft

Page 17: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

17

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

River Pier Foundations

• Minimal cost aesthetic enhancement for arch piers

• Rock close to surface in IL• 130 ft of sand + on IA side• Deep river pool• Waterline footings

33

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 34

Drilled Shaft with Coffercell

Page 18: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

18

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 35

Tied Arch

• 546 ft span, 100 ft rise, span to rise ~ 5.5:1• Floor Beam Spacing – 31’-9”

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 36

Cross Section

Page 19: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

19

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Floating Floor System

• Replaceable deck with 1 lane of traffic• Stringers spanning over floor beams

– Bearings at center span fixed– Elastomeric bearings elsewhere– Deck full length of span– Allows deck replacement half at a time– Deck connected to tie at center

• Lower lateral K bracing for wind– Braces floor beam at mid-span

• Galvanized floor system– Lengths under 60 ft– Corrosion protection

37

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Tie Girder and Lower Hanger

• Bolted Box Tie full length– Tab plates– 6 ft deep– HPS50W

• Hanger connection offset from Floor beam

– Simplifies detailing

• Connection precompressed• 4 anchor rods provide

redundancy• Shim plates for length

adjustment38

Page 20: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

20

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Arch Rib and Upper Hanger

• Welded Box Rib– Longitudinal stiffener– 5 ft deep

• Hanger connection offset from bracing connection

– Simplifies detailing

• Two hangers – minimize strand size– easier replacement

• Hanger connections bolted to rib

39

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Upper Bracing

40

• X-bracing chosen– Smaller members than Vierendeel– Tension & Compression only– More modern look than K-bracing

• HSS 16x16– Efficient member section– Consistent box section

• Galvanized– Corrosion protection on inside of box– Distinct contrast with blue rib– Low maintenance / impact to traffic

Page 21: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

21

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Redundancy

• Tie Girder– HPS50W and bolted box provides internal member redundancy– Limits propagation of fracture– Still Fracture Critical– Designed for loss of tie web or flange plate

• Hangers– Two hangers per location– Loss of one hanger with fracture dynamic force (FDF)– Loss of both hangers without dynamic force

• Fracture Load Case– 1.1 DC + 0.75 (LL+IM) + 1.1 FDF– LL+IM for 2 striped lanes

41

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Constructability Review

• Provided IDOT a constructability review– During preliminary design phase

• Parsons Construction Group– Experience in Large River Bridge Construction– Identified staging and access areas– Identified potential construction issues

• Provided IDOT a contractor style estimate– Preliminary and Final Design

• In house construction estimating team

42

Page 22: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

22

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

3D Printing Model for Public Communication

• In house capability for conveying signature or complex details

43

On client’s desk!

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 44

Drivers’ Perspective Along IL 84

Page 23: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

23

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 45

Drivers’ Perspective Approaching Arch

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update

• Sept. 18, 2015 Letting– 5 Bids, Low Bid $80.6M to Kraemer, NA

• Construction Started Mid January 2016 – Clearing & Work Causeway work

• Reviewing Shop Drawings– Tied Arch Steel– Hangers– Bearings

• Reviewing Construction Drawings– Coffercell Construction Details– Tied Arch Cantilever Erection

• Scheduled Bridge Completion – December 2018

46

Page 24: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

24

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – West Abutment & Pier 1

47

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Pier 2

48

Page 25: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

25

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Pier 4

49

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Pier 6

50

Page 26: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

26

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Temp Access Illinois Side

51

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Summary

• Aging Bridge key to local economy• Extensive Coordination

– Environmental and Permitting– Railroads and Utilities

• Replace with new Steel Tied Arch– Improved geometrics

• Keys to Success– Strong Community Support– Early Client Involvement– Preliminary Design Development– Constructability Review from Contractor– Led to efficient Final Design phase

52

Page 27: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

27

Questions?