Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
01.00.00 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD
01.01.00 CONSTRUCIONES PROVISIONALES
01.01.01 ALAMACEN M2 15.00
AREA M2 3.00 5.00 01 15.00
01.01.02 CASETA DE GUARDIANIA M2 15.00
M2 3.00 5.00 01 15.00
01.01.03 CERCO M2 70.50
M2 70.50 01 70.50
01.01.04 SERVICIOS HIGIENICOS M2 3.00
M2 1.20 2.50 01 3.00
01.02.00 INSTALACIONES PROVISIONALES
01.02.01 AGUA PARA LA CONSTRUCCION GLB 1.00
GLB 1.00 01
01.02.02 DESAGUE PARA LA CONSTRUCCION GLB 1.00
GLB 1.00 01
01.02.03 ENERGIA ELECTRICA PROVISIONAL GLB 1.00
GLB 1.00 01
01.03.00 TRABAJOS PRELIMINARES
01.03.01 LIMPIEZA DEL TERRENO M2 998.49
M2 998.49 01 998.49
01.03.02 TALA DE ARBOLES UND 4.00
UND 04
01.03.03 EXTRACCION DE RAICES UND 4.00
UND 04
01.04.00 TRAZOS, NIVELES Y REPLANTEO
01.04.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 998.49
M2 998.49 01 998.49
01.04.02 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO M2 0.00
SEGUNDO PISO M2 01 0.00
TERCER PISO M2 01 0.00
01.05.00 SEGURIDAD Y SALUD
01.05.01 EQUIPOS DE PROTECCION INDIVIDUAL UND 10.00
UND 1.00 10
01.05.02 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00
GLB 1.00 01
01.05.03 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00
GLB 1.00 01
N° DE VECES
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
02.00.00 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD
02.01.00 CONSTRUCIONES PROVISIONALES 0 0.00
0 ALAMACEN M3 0.00
AREA
0 CASETA DE GUARDIANIA
0 CERCO M3 0.00
0 SERVICIOS HIGIENICOS M3 0.00
0 CORTE 4-4 M3 0.00
0 Z-1 CON C-2 M3 0.00
0 0 0 0.00
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
02.02.00 CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 C:H M3 28.80
#REF! #REF! #REF! #REF!
02.02.02.01 CONCRETO SOBRECIMIENTO DE 1:8 CEM-HOR ANCHO=0.15 MT M3 8.90
#REF! #REF! #REF! #REF!
02.02.03 FALSO PISO DE 4" DE CONCRETO 1:8 0 0.90
02.03.00 OBRAS DE CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 M3 166.40
02.03.01.02 ACERO DE REFUERZO Fy=4200 kg/cm2 KG 44.41
02.03.02 COLUMNAS
02.03.02.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3 48.90
02.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNAS M2 0.00
0 eje 5-A 5.15 0.00
0 eje 7-A
0 eje 4-F 5.15 0.00
0 eje 1 - F 5.15 0.00
0 eje 1 - D" 5.15 0.00
0 eje 1 - B
0 C-2 0 0.00
0 VP-102(.35x.60) 0.6 0.00
0 0 0 0.00
0 0
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
0 0 0 0.00
0 aligerado primer piso 0 0.00
0 0 34.3 0.00
0 eje EF - 10 Y 5
0 0 25 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
LARGO ANCHO ALTO LONG. AREA VOL. KG.
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTOS DE TIERRAS
02.01.01 EXCAVACIONES
02.01.01.01 EXCAVACIONES MASIVAS M3
M3 433 01 998.49
02.01.01.02 EXCAVACIONES SIMPLES M3
ZAPATAS M3
Z-1 M3 1.60 1.60 1.70 08 34.80
Z-2 M3 3.10 2.80 1.70 21 309.90
Z-3 M3 1.20 1.20 1.70 16 39.20
Z-4 1.50 2.00 1.70 04 20.40
CIMENTACION CORRIDA M3 0.00
CORTE 1-1 M3 59.47 0.40 0.60 01 14.30
CORTE 2-2 M3 58.41 0.40 0.60 01 14.00
CORTE 3-3 M3 0.90 0.40 0.60 01 0.20
CORTE 4-4 M3 1.23 0.40 0.60 01 0.30
02.01.02 RELLENO M3
02.01.02.01 RELLENO CON MATERIAL PROPIO M3
Z-1 CON C-1 M3 1.60 1.60 1.00 06 15.40
0.30 0.30 1.00 06 -0.50
Z-1 CON C-2 M3 1.60 1.60 1.00 02 5.10
0.30 0.60 1.00 02 -0.40
Z-2 CON C-2 M3 3.10 2.80 1.00 21 182.30
0.30 0.60 1.00 21 -3.80
Z-3 CON C-3 M3 1.20 1.20 1.00 16 23.00
0.25 0.25 1.00 16 -1.00
Z-4 CON C-2 M3 1.50 2.00 1.00 04 12.00
0.30 0.60 1.00 04 -0.70
02.01.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA
CIMIENTO CORRIDO M3
seccion 1-1 M3 59.47 0.40 0.60 01 14.30
seccion 2-2 M3 58.41 0.40 0.60 01 14.00
seccion 3-3 M3 0.90 0.40 0.60 01 0.20
seccion 4-4 M3 1.23 0.40 0.60 01 0.30
ZAPATAS M3
Z-1 M3 1.60 1.60 1.70 08 34.80
Z-2 M3 3.10 2.80 1.70 21 309.90
Z-3 M3 1.20 1.20 1.70 16 39.20
Z-4 M3 1.50 2.00 1.70 04 20.40
RELLENO Y COMPACTADO M3
Z-1 M3 1.60 1.60 1.00 08 20.50
Z-2 M3 3.10 2.80 1.00 21 182.30
Z-3 M3 1.20 1.20 1.00 16 23.00
Z-4 M3 1.50 2.00 1.00 04 12.00
02.01.03 NIV. INTERIOR Y APISONADO P/RECIBIR FALSO PISO C/EQUIPO m2
Altar m2 67.66 0.05 01 3.40
estar m2 13.30 0.05 01 0.70
cocina - comedor m2 24.60 0.05 01 1.20
dormitorio 1 m2 12.50 0.05 01 0.60
dormittorio 2 m2 16.20 0.05 01 0.80
sacristia m2 12.20 0.05 01 0.60
baño m2 3.25 0.05 01 0.20
estrado m2 24.60 0.05 01 1.20
atrio m2 245.00 0.05 01 12.30
02.02.00 CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 C:H M3
seccion 1-1 M3 59.47 0.40 0.60 1.00 14.30
seccion 2-2 M3 58.41 0.40 0.60 1.00 14.00
seccion 3-3 M3 0.90 0.40 0.60 1.00 0.20
seccion 4-4 M3 1.23 0.40 0.60 1.00 0.30
02.02.02 SOBRECIMIENTOS
02.02.02.01 CONCRETO SOBRECIMIENTO DE 1:8 CEM-HOR ANCHO=0.15 MT M3
ancho de 0.13 m M3 222.24 0.13 0.30 1.00 8.70
ancho de 0,15 m M3 4.20 0.15 0.30 1.00 0.20
02.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO H=0.40 M M2
laterales M2
ancho de 0.13 m M2 222.00 0.30 2.00 133.20
N° DE VECES
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
LARGO ANCHO ALTO LONG. AREA VOL. KG.N° DE
VECES
ancho de 0,15 m M2 4.20 0.30 2.00 2.52
02.02.03 FALSO PISO DE 4" DE CONCRETO 1:8
CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO:HORMIGON PARA PISO PULI M3
patio 7.70 1.20 0.05 1.00 0.40
rampa 10.80 0.90 0.05 1.00 0.50
CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO:HORMIGON M3
Altar 67.60 0.05 1.00 3.40
estar 13.30 0.05 1.00 0.70
cocina - comedor 24.60 0.05 1.00 1.20
dormitorio 1 12.50 0.05 1.00 0.60
dormittorio 2 16.20 0.05 1.00 0.80
sacristia 12.20 0.05 1.00 0.60
baño 3.25 0.05 1.00 0.20
estrado 24.60 0.05 1.00 1.20
atrio 245.00 0.05 1.00 12.30
02.03.00 OBRAS DE CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 M3
Z-1 M3 1.60 1.60 0.70 8.00 14.30
Z-2 M3 3.10 2.80 0.70 21.00 127.60
Z-3 M3 1.20 1.20 0.70 16.00 16.10
Z-4 M3 1.50 2.00 0.70 4.00 8.40
02.03.01.02 ACERO DE REFUERZO Fy=4200 kg/cm2 KG
02.03.02 COLUMNAS
02.03.02.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3
C-3
primer piso
eje 1-A M3 0.25 0.25 4.60 1.00 0.30
eje 2-A M3 0.25 0.25 4.60 1.00 0.30
eje 3-A M3 0.25 0.25 4.60 1.00 0.30
eje 4-A M3 0.25 0.25 4.60 1.00 0.30
eje 5-A M3 0.25 0.25 4.60 1.00 0.30
eje 6-A M3 0.25 0.25 4.60 1.00 0.30
eje 7-A M3 0.25 0.25 4.60 1.00 0.30
eje 4-F M3 0.25 0.25 4.60 1.00 0.30
eje 3- F M3 0.25 0.25 4.60 1.00 0.30
eje 2- F M3 0.25 0.25 4.60 1.00 0.30
eje 1 - F M3 0.25 0.25 4.60 1.00 0.30
eje 1- E" M3 0.25 0.25 4.60 1.00 0.30
eje 1 - E M3 0.25 0.25 4.60 1.00 0.30
eje 1 - D" M3 0.25 0.25 4.60 1.00 0.30
eje 1 - B" M3 0.25 0.25 4.60 1.00 0.30
eje 1 - B M3 0.25 0.25 4.60 1.00 0.30
C-3
segundo piso
eje 1-A M3 0.25 0.25 2.40 1.00 0.20
eje 2-A M3 0.25 0.25 2.40 1.00 0.20
eje 3-A M3 0.25 0.25 2.40 1.00 0.20
eje 4-A M3 0.25 0.25 2.40 1.00 0.20
eje 5-A M3 0.25 0.25 2.40 1.00 0.20
eje 6-A M3 0.25 0.25 2.40 1.00 0.20
eje 7-A M3 0.25 0.25 2.40 1.00 0.20
eje 4-F M3 0.25 0.25 2.40 1.00 0.20
eje 3- F M3 0.25 0.25 2.40 1.00 0.20
eje 2- F M3 0.25 0.25 2.40 1.00 0.20
eje 1 - F M3 0.25 0.25 2.40 1.00 0.20
eje 1- E" M3 0.25 0.25 2.40 1.00 0.20
eje 1 - E M3 0.25 0.25 2.40 1.00 0.20
eje 1 - D" M3 0.25 0.25 2.40 1.00 0.20
eje 1 - B" M3 0.25 0.25 2.40 1.00 0.20
eje 1 - B M3 0.25 0.25 2.40 1.00 0.20
C-2
Altar
eje B - 9 M3 0.60 0.30 9.15 1.00 1.60
eje B - 8 M3 0.60 0.30 9.15 1.00 1.60
eje B - 7 M3 0.60 0.30 9.15 1.00 1.60
eje B - 6 M3 0.60 0.30 9.15 1.00 1.60
eje B - 5 M3 0.60 0.30 9.15 1.00 1.60
eje B - 4 M3 0.60 0.30 9.15 1.00 1.60
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
LARGO ANCHO ALTO LONG. AREA VOL. KG.N° DE
VECES
eje B - 4y5 M3 0.60 0.30 9.15 1.00 1.60
eje B - 3 M3 0.60 0.30 9.15 1.00 1.60
eje C - 3 M3 0.60 0.30 9.15 1.00 1.60
eje D - 3 M3 0.60 0.30 9.15 1.00 1.60
eje E - 3 M3 0.60 0.30 9.15 1.00 1.60
eje E - 4y3 M3 0.60 0.30 9.15 1.00 1.60
eje E - 4 M3 0.60 0.30 9.15 1.00 1.60
eje E - 5 M3 0.60 0.30 9.15 1.00 1.60
eje E - 6 M3 0.60 0.30 9.15 1.00 1.60
eje E - 7 M3 0.60 0.30 9.15 1.00 1.60
eje E - 8 M3 0.60 0.30 9.15 1.00 1.60
eje E - 9 M3 0.60 0.30 9.15 1.00 1.60
C - 2 0.00
E - 10 M3 0.60 0.30 7.00 1.00 1.30
F - 10 M3 0.60 0.30 7.00 1.00 1.30
F - 9 M3 0.60 0.30 7.00 1.00 1.30
F - 8 M3 0.60 0.30 7.00 1.00 1.30
F - 7 M3 0.60 0.30 7.00 1.00 1.30
F - 6 M3 0.60 0.30 7.00 1.00 1.30
F - 5 M3 0.60 0.30 7.00 1.00 1.30
C - 1 0.00
A - 8 M3 0.30 0.30 6.00 1.00 0.50
A - 9 M3 0.30 0.30 6.00 1.00 0.50
A - 10 M3 0.30 0.30 6.00 1.00 0.50
B - 10 M3 0.30 0.30 6.00 1.00 0.50
C - 10 M3 0.30 0.30 6.00 1.00 0.50
D - 10 M3 0.30 0.30 6.00 1.00 0.50
02.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNAS M2
C-3
primer piso
eje 1-A M2 1.00 5.15 1.00 5.15
eje 2-A M2 1.00 5.15 1.00 5.15
eje 3-A M2 1.00 5.15 1.00 5.15
eje 4-A M2 1.00 5.15 1.00 5.15
eje 5-A M2 1.00 5.15 1.00 5.15
eje 6-A M2 1.00 5.15 1.00 5.15
eje 7-A M2 1.00 5.15 1.00 5.15
eje 4-F M2 1.00 5.15 1.00 5.15
eje 3- F M2 1.00 5.15 1.00 5.15
eje 2- F M2 1.00 5.15 1.00 5.15
eje 1 - F M2 1.00 5.15 1.00 5.15
eje 1- E" M2 1.00 5.15 1.00 5.15
eje 1 - E M2 1.00 5.15 1.00 5.15
eje 1 - D" M2 1.00 5.15 1.00 5.15
eje 1 - B" M2 1.00 5.15 1.00 5.15
eje 1 - B M2 1.00 5.15 1.00 5.15
C-2
Altar
eje B - 9 M2 1.80 7.30 1.00 13.14
eje B - 8 M2 1.80 7.30 1.00 13.14
eje B - 7 M2 1.80 7.30 1.00 13.14
eje B - 6 M2 1.80 7.30 1.00 13.14
eje B - 5 M2 1.80 7.30 1.00 13.14
eje B - 4 M2 1.80 7.30 1.00 13.14
eje B - 4y5 M2 1.80 7.30 1.00 13.14
eje B - 3 M2 1.80 7.30 1.00 13.14
eje C - 3 M2 1.80 7.30 1.00 13.14
eje D - 3 M2 1.80 7.30 1.00 13.14
eje E - 3 M2 1.80 7.30 1.00 13.14
eje E - 4y3 M2 1.80 7.30 1.00 13.14
eje E - 4 M2 1.80 7.30 1.00 13.14
eje E - 5 M2 1.80 7.30 1.00 13.14
eje E - 6 M2 1.80 7.30 1.00 13.14
eje E - 7 M2 1.80 7.30 1.00 13.14
eje E - 8 M2 1.80 7.30 1.00 13.14
eje E - 9 M2 1.80 7.30 1.00 13.14
C - 2
E - 10 M2 1.80 5.20 1.00 9.36F - 10 M2 1.80 5.20 1.00 9.36F - 9 M2 1.80 5.20 1.00 9.36F - 8 M2 1.80 5.20 1.00 9.36F - 7 M2 1.80 5.20 1.00 9.36F - 6 M2 1.80 5.20 1.00 9.36F - 5 M2 1.80 5.20 1.00 9.36C - 1
A - 8 M2 1.20 4.20 1.00 5.04A - 9 M2 1.20 4.20 1.00 5.04A - 10 M2 1.20 4.20 1.00 5.04B - 10 M2 1.20 4.20 1.00 5.04C - 10 M2 1.20 4.20 1.00 5.04
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
LARGO ANCHO ALTO LONG. AREA VOL. KG.N° DE
VECES
D - 10 1.20 4.20 1.00 5.04
CONCRETO EN VIGAS F'C=210KG/CM2 46.80VP-101(.30x.40) M3 0.30 0.40 4.10 21.00 10.33
VP-102(.35x.60) M3 0.35 0.60 7.84 6.00 9.88
VP-103(.30x.40) M3 0.30 0.40 3.80 8.00 3.65
VP-104(.35x.40) M3 0.35 0.40 2.10 6.00 1.76
VP-201(.30x.40) M3 0.30 0.40 4.10 16.00 7.87
VP-202(.35x.60) M3 0.35 0.60 7.84 6.00 9.88
VP-203(.30x.40) M3 0.30 0.40 3.80 3.00 1.37
VP-204(.35x.40) M3 0.35 0.40 2.10 7.00 2.06
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 390.07VP-101(.30x.40)
laterales M2 0.80 4.10 21.00 68.88
inferior M2 0.30 4.10 21.00 25.83
VP-102(.35x.60)
laterales M2 1.20 7.84 6.00 56.45
inferior M2 0.35 7.84 6.00 16.46
VP-103(.30x.40) M2
laterales M2 0.80 3.80 8.00 24.32
inferior M2 0.30 3.80 8.00 9.12
VP-104(.35x.40)
laterales M2 0.80 2.10 6.00 10.08
inferior M2 0.35 2.10 6.00 4.41
VP-201(.30x.40)
laterales M2 0.80 4.10 16.00 52.48
inferior M2 0.30 4.10 16.00 19.68
VP-202(.35x.60)
laterales M2 1.20 7.84 6.00 56.45
inferior M2 0.35 7.84 6.00 16.46
VP-203(.30x.40)
laterales M2 0.80 3.80 3.00 9.12
inferior M2 0.30 3.80 3.00 3.42
VP-204(.35x.40)
laterales M2 0.80 2.10 7.00 11.76
inferior M2 0.35 2.10 7.00 5.15
ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS
aligerado primer piso
dormitorio 1
M2 19.00 1.00
dormitorio 2 y cocina - comedor
M2 15.50 1.00
M2 13.50 1.00
M2 12.00 1.00
M2 3.70 1.00
eje EF - 10 Y 5
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
LARGO ANCHO ALTO LONG. AREA VOL. KG.N° DE
VECES
M2 25.00 1.00
M2 32.00 1.00
M2 34.00 1.00
M2 34.10 1.00
M2 34.30 1.00
aligerado segundo piso
eje EF - 10 Y 5
M2 25.00 1.00
M2 32.00 1.00
M2 34.00 1.00
M2 34.10 1.00
M2 34.30 1.00
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
LARGO ANCHO ALTO LONG. AREA VOL. KG.N° DE
VECES
TOTAL
0.00
998.49
433.10
231.40
670.90
21.00
28.80
8.90
135.72
TOTAL
0.90
21.00
166.40
44.41
48.90
TOTAL
TOTAL
TOTAL
TOTAL
HOJA DE METRADOS
PROYECTO : ACERO KG/ML
1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 12mm 0.94
1/2" 1.00
FECHA : HECHO POR : 5/8" 1.55
3/4" 2.24
ESPECIALIDAD : HOJA N° : 1" 3.97
Nº DESCRIPCIONMEDIDAS ACERO KG/ML
N° DE VECES TOTALUND LONG. 1/4” 3/8” 1/2” 5/8” 3/4”
04.00.00 OBRAS DE CONCRETO ARMADO
04.01.00 ZAPATAS
04.01.02 ACERO DE REFUERZO Fy=4200 kg/cm2 44.41
DIAMETRO
Zapata Z-2 eje 1 - xx Ø 3/8 '' Kg 0.85 04 0.56 04 7.62
eje 1 - yy Ø 3/8 '' Kg 0.65 04 0.56 05 7.28
Zapata Z-3 eje 1 - xx Ø 3/8 '' Kg 0.65 01 0.56 07 2.55
eje 1 - yy Ø 3/8 '' Kg 1.20 01 0.56 04 2.69
Zapata Z-1 eje 3 Ø 3/8 '' Kg 0.85 03 0.56 10 14.28
Zapata Z-3 eje 3 - xx Ø 3/8 '' Kg 0.65 01 0.56 07 2.55
eje 3 - yy Ø 3/8 '' Kg 1.20 01 0.56 04 2.69
Zapata Z-1 eje 4 Ø 3/8 '' Kg 0.85 01 0.56 10 4.76
04.02.00 COLUMNAS
04.02.03 ACERO DE REFUERZO Fy=4200 kg/cm2 928.52
ACERO PRINCIPAL DIAMETRO
C - 1 (ejes 1-C,D,E) Ø 5/8 '' Kg 4.50 03 1.55 04 83.70
C - 1 (ejes 3-C) Ø 5/8 '' Kg 4.50 01 1.55 04 27.90
C - 1 (ejes 3-D) Ø 5/8 '' Kg 4.50 01 1.55 04 27.90
C - 1 (ejes 3-E) Ø 5/8 '' Kg 4.50 01 1.55 04 27.90
C - 5 (ejes 4-D´) Ø 1/2 '' Kg 4.50 01 1.00 06 27.00
C - confin Ø 3/8 '' Kg 1.80 22 0.56 04 88.70
C - confin Ø 3/8 '' Kg 5.20 10 0.56 04 116.48
C - 4 (ejes 2-A) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 3 (ejes 2-B) Ø 3/8 '' Kg 4.50 01 0.56 04 10.08
C - 4 (ejes 2-B´) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 4 (ejes 2-F) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 4 (ejes 3-A) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 2 (ejes 3-B´) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 3 (ejes 3-D´) Ø 3/8 '' Kg 4.50 01 0.56 04 10.08
C - 3 (ejes 3-E´) Ø 3/8 '' Kg 4.50 01 0.56 04 10.08
C - 2 (ejes 3-F) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 4 (ejes 4-A) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 3 (ejes 4-B) Ø 3/8 '' Kg 4.50 01 0.56 04 10.08
C - 4 (ejes 4-B´) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 4 (ejes 4-C) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 4 (ejes 4-D) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 2 (ejes 1-B´) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
C - 2 (ejes 1-F) Ø 1/2 '' Kg 4.50 01 1.00 04 18.00
ESTRIBOS DIAMETRO
C - 1 (ejes 1-C,D,E) Ø 1/4 '' Kg 0.96 03 0.25 31 22.32
C - 1 (ejes 3-C) Ø 1/4 '' Kg 0.96 01 0.25 33 7.92
C - 1 (ejes 3-D) Ø 1/4 '' Kg 0.96 01 0.25 33 7.92
C - 1 (ejes 3-E) Ø 1/4 '' Kg 0.96 01 0.25 33 7.92
C - 5 (ejes 4-D´) Ø 1/4 '' Kg 0.75 01 0.25 50 9.34
C - confin Ø 1/4 '' Kg 0.80 22 0.25 10 44.00
C - confin Ø 1/4 '' Kg 0.80 10 0.25 38 76.00
C - 4 (ejes 2-A) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 3 (ejes 2-B) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 4 (ejes 2-B´) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 4 (ejes 2-F) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 4 (ejes 3-A) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 2 (ejes 3-B´) Ø 1/4 '' Kg 0.96 01 0.25 30 7.20
C - 3 (ejes 3-D´) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 3 (ejes 3-E´) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 2 (ejes 3-F) Ø 1/4 '' Kg 0.96 01 0.25 30 7.20
C - 4 (ejes 4-A) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 3 (ejes 4-B) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 4 (ejes 4-B´) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 4 (ejes 4-C) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 4 (ejes 4-D) Ø 1/4 '' Kg 0.76 01 0.25 30 5.70
C - 2 (ejes 1-B´) Ø 1/4 '' Kg 0.96 01 0.25 30 7.20
C - 2 (ejes 1-F) Ø 1/4 '' Kg 0.96 01 0.25 30 7.20
04.03.00 VIGAS DE CIMENTACION
SUB TOTAL KG.N° DE
ELEM12 mm
HOJA DE METRADOS
PROYECTO : ACERO KG/ML
1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 12mm 0.94
1/2" 1.00
FECHA : HECHO POR : 5/8" 1.55
3/4" 2.24
ESPECIALIDAD : HOJA N° : 1" 3.97
Nº DESCRIPCIONMEDIDAS ACERO KG/ML
N° DE VECES TOTALUND LONG. 1/4” 3/8” 1/2” 5/8” 3/4”
SUB TOTAL KG.N° DE
ELEM12 mm
04.03.03 ACERO DE REFUERZO Fy=4200 kg/cm2 52.55
ACERO PRINCIPAL DIAMETRO
VC-101 Ø 1/2 '' Kg 6.60 06 1.00 01 39.60
ESTRIBOS DIAMETRO
VC-101 Ø 1/4 '' Kg 1.40 37 0.25 01 12.95
04.04.00 VIGAS
04.04.03 ACERO DE REFUERZO Fy=4200 kg/cm2 597.54
ACERO PRINCIPAL DIAMETRO
eje 2, A-B / VENTANA Ø 3/8 '' Kg 1.50 03 0.56 01 2.52
eje 2, B-B´ / PUERTA Ø 3/8 '' Kg 1.30 03 0.56 01 2.18
eje 3, D-D´ / PUERTA Ø 3/8 '' Kg 1.40 03 0.56 01 2.35
eje 3, D´-E / VENTANA Ø 3/8 '' Kg 1.50 03 0.56 01 2.52
eje 3, E-E´ / VENTANA Ø 3/8 '' Kg 1.50 03 0.56 01 2.52
eje 4, A-B / VENTANA Ø 3/8 '' Kg 1.90 03 0.56 01 3.19
eje 4, B-B´ / PUERTA Ø 3/8 '' Kg 1.30 03 0.56 01 2.18
eje 4, B´-C / VENTANA Ø 3/8 '' Kg 1.90 03 0.56 01 3.19
eje 4, C-D / VENTANA Ø 3/8 '' Kg 1.90 03 0.56 01 3.19
eje B, 1-2 / VENTANA Ø 3/8 '' Kg 1.90 03 0.56 01 3.19
eje B, 3-4 / PUERTA Ø 3/8 '' Kg 1.30 03 0.56 01 2.18
eje F, 1-2 / VENTANA Ø 3/8 '' Kg 1.60 03 0.56 01 2.69
eje F, 2-2´ / VENTANA Ø 3/8 '' Kg 1.60 03 0.56 01 2.69
eje 1 / V - 100 Ø 3/8 '' Kg 12.30 04 0.56 01 27.55
eje 1 / V - 107 Ø 3/8 '' Kg 3.50 04 0.56 01 7.84
eje 1 / 2v Ø 3/8 '' Kg 0.50 02 0.56 01 0.56
eje 2 / V - 100 Ø 3/8 '' Kg 3.70 04 0.56 01 8.29
eje 2/ 2v Ø 3/8 '' Kg 3.60 02 0.56 01 4.03
eje 3 / VCH-2 Ø 1/2 '' Kg 3.70 06 1.00 01 22.20
eje 3 / V-103 Ø 1/2 '' Kg 12.30 04 1.00 01 49.20
eje 3 / 2v Ø 3/8 '' Kg 5.90 02 0.56 01 6.61
eje 4 / V-104 Ø 1/2 '' Kg 9.20 04 1.00 01 36.80
eje 4 / 2v Ø 3/8 '' Kg 10.70 02 0.56 01 11.98
eje A / V-105 Ø 3/8 '' Kg 6.15 04 0.56 01 13.78
eje A / VCH-4 Ø 1/2 '' Kg 1.20 04 1.00 01 4.80
eje B / V-102 Ø 1/2 '' Kg 8.20 04 1.00 01 32.80
eje B / VCH-4 Ø 1/2 '' Kg 1.20 04 1.00 01 4.80
eje C / VCH-1 Ø 1/2 '' Kg 3.10 06 1.00 01 18.60
eje D / V-105 Ø 3/8 '' Kg 2.70 04 0.56 01 6.05
eje D / VCH-4 Ø 1/2 '' Kg 1.20 04 1.00 01 4.80
eje E / VCH-3 Ø 1/2 '' Kg 1.20 06 1.00 01 7.20
eje F / V-102 Ø 1/2 '' Kg 6.00 04 1.00 01 24.00
eje F / VCH-4 Ø 1/2 '' Kg 1.20 06 1.00 01 7.20
eje F / 2v Ø 3/8 '' Kg 6.55 02 0.56 01 7.34
ejes C, D, E / V-101 Ø 1/2 '' Kg 6.30 06 1.00 03 113.40
ESTRIBOS DIAMETRO
eje 2, A-B / VENTANA Ø 1/4 '' Kg 0.52 08 0.25 01 1.04
eje 2, B-B´ / PUERTA Ø 1/4 '' Kg 0.52 07 0.25 01 0.91
eje 3, D-D´ / PUERTA Ø 1/4 '' Kg 0.52 07 0.25 01 0.91
eje 3, D´-E / VENTANA Ø 1/4 '' Kg 0.52 08 0.25 01 1.04
eje 3, E-E´ / VENTANA Ø 1/4 '' Kg 0.52 08 0.25 01 1.04
eje 4, A-B / VENTANA Ø 1/4 '' Kg 0.52 10 0.25 01 1.30
eje 4, B-B´ / PUERTA Ø 1/4 '' Kg 0.52 07 0.25 01 0.91
eje 4, B´-C / VENTANA Ø 1/4 '' Kg 0.52 10 0.25 01 1.30
eje 4, C-D / VENTANA Ø 1/4 '' Kg 0.52 10 0.25 01 1.30
eje B, 1-2 / VENTANA Ø 1/4 '' Kg 0.52 10 0.25 01 1.30
eje B, 3-4 / PUERTA Ø 1/4 '' Kg 0.52 07 0.25 01 0.91
eje F, 1-2 / VENTANA Ø 1/4 '' Kg 0.52 08 0.25 01 1.04
eje F, 2-2´ / VENTANA Ø 1/4 '' Kg 0.52 08 0.25 01 1.04
eje 1 / V - 100 Ø 1/4 '' Kg 0.79 79 0.25 01 15.60
eje 1 / V - 107 Ø 1/4 '' Kg 0.66 20 0.25 01 3.30
eje 1 / 2v Ø 1/4 '' Kg 0.30 03 0.25 01 0.22
HOJA DE METRADOS
PROYECTO : ACERO KG/ML
1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 12mm 0.94
1/2" 1.00
FECHA : HECHO POR : 5/8" 1.55
3/4" 2.24
ESPECIALIDAD : HOJA N° : 1" 3.97
Nº DESCRIPCIONMEDIDAS ACERO KG/ML
N° DE VECES TOTALUND LONG. 1/4” 3/8” 1/2” 5/8” 3/4”
SUB TOTAL KG.N° DE
ELEM12 mm
eje 2 / V - 100 Ø 1/4 '' Kg 0.79 26 0.25 01 5.14
eje 2/ 2v Ø 1/4 '' Kg 0.30 18 0.25 01 1.35
eje 3 / VCH-2 Ø 1/4 '' Kg 1.50 21 0.25 01 7.88
eje 3 / V-103 Ø 1/4 '' Kg 0.79 79 0.25 01 15.60
eje 3 / 2v Ø 1/4 '' Kg 0.30 31 0.25 01 2.32
eje 4 / V-104 Ø 1/4 '' Kg 0.82 37 0.25 01 7.59
eje 4 / 2v Ø 1/4 '' Kg 0.30 55 0.25 01 4.13
eje A / V-105 Ø 1/4 '' Kg 0.76 36 0.25 01 6.84
eje A / VCH-4 Ø 1/4 '' Kg 0.60 07 0.25 01 1.05
eje B / V-102 Ø 1/4 '' Kg 0.76 54 0.25 01 10.26
eje B / VCH-4 Ø 1/4 '' Kg 0.60 07 0.25 01 1.05
eje C / VCH-1 Ø 1/4 '' Kg 1.00 19 0.25 01 4.75
eje D / V-105 Ø 1/4 '' Kg 0.76 16 0.25 01 3.04
eje D / VCH-4 Ø 1/4 '' Kg 0.60 07 0.25 01 1.05
eje E / VCH-3 Ø 1/4 '' Kg 0.80 07 0.25 01 1.40
eje F / V-102 Ø 1/4 '' Kg 0.76 36 0.25 01 6.84
eje F / VCH-4 Ø 1/4 '' Kg 0.60 07 0.25 01 1.05
eje F / 2v Ø 1/4 '' Kg 0.50 34 0.25 01 4.25
ejes C, D, E / V-101 Ø 1/4 '' Kg 1.16 28 0.25 03 24.36
04.05.00 SOBRECIMIENTO ARMADO
04.05.03 ACERO DE REFUERZO Fy=4200 kg/cm2 316.55
ACERO PRINCIPAL DIAMETRO
Eje 1 Corte 1 Ø 1/2 '' Kg 12.55 04 1.00 01 50.20
Eje 2 Corte 2 Ø 1/2 '' Kg 3.70 04 1.00 01 14.80
Eje 3 Corte 9 Ø 1/2 '' Kg 5.80 04 1.00 01 23.20
Eje 3 Corte 8 Ø 1/2 '' Kg 1.20 04 1.00 01 4.80
Eje 3 Corte 10 Ø 1/2 '' Kg 5.60 04 1.00 01 22.40
Eje 4 Corte 1 Ø 1/2 '' Kg 9.20 04 1.00 01 36.80
Eje A Corte 1 Ø 1/2 '' Kg 5.70 04 1.00 01 22.80
Eje B Corte 2 Ø 1/2 '' Kg 3.55 04 1.00 01 14.20
Eje B Corte 9 Ø 1/2 '' Kg 5.65 04 1.00 01 22.60
Eje D Corte 7 Ø 1/2 '' Kg 3.30 04 1.00 01 13.20
Eje F Corte 10 Ø 1/2 '' Kg 5.90 04 1.00 01 23.60
ESTRIBOS DIAMETRO
Eje 1 Corte 1 Ø 1/4 '' Kg 0.90 62 0.25 01 13.95
Eje 2 Corte 2 Ø 1/4 '' Kg 0.90 18 0.25 01 4.05
Eje 3 Corte 9 Ø 1/4 '' Kg 0.90 28 0.25 01 6.30
Eje 3 Corte 8 Ø 1/4 '' Kg 0.90 05 0.25 01 1.13
Eje 3 Corte 10 Ø 1/4 '' Kg 0.90 27 0.25 01 6.07
Eje 4 Corte 1 Ø 1/4 '' Kg 0.90 45 0.25 01 10.12
Eje A Corte 1 Ø 1/4 '' Kg 0.90 29 0.25 01 6.52
Eje B Corte 2 Ø 1/4 '' Kg 0.90 17 0.25 01 3.82
Eje B Corte 9 Ø 1/4 '' Kg 0.90 26 0.25 01 5.85
Eje D Corte 7 Ø 1/4 '' Kg 0.90 16 0.25 01 3.60
Eje F Corte 10 Ø 1/4 '' Kg 0.90 29 0.25 01 6.52
04.06.00 LOSAS ALIGERADAS
04.06.03 ACERO DE REFUERZO Fy=4200 kg/cm2 500.35
ACERO PRINCIPAL DIAMETRO
ZONA A Ø 3/8 '' Kg 24.10 08 0.56 01 107.97
ZONA B Ø 3/8 '' Kg 27.45 10 0.56 01 153.72
ZONA C Ø 3/8 '' Kg 21.30 11 0.56 01 131.21
TEMPERATURA DIAMETRO
ZONA A Ø 1/4 '' Kg 2.00 59 0.25 01 29.50
ZONA B Ø 1/4 '' Kg 2.75 68 0.25 01 46.75
ZONA C Ø 1/4 '' Kg 2.60 48 0.25 01 31.20
04.07.00 MESA DE COCINA Y LAVADERO
04.07.03 ACERO DE REFUERZO Fy=4200 kg/cm2 46.96
ACERO PRINCIPAL DIAMETRO
HOJA DE METRADOS
PROYECTO : ACERO KG/ML
1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 12mm 0.94
1/2" 1.00
FECHA : HECHO POR : 5/8" 1.55
3/4" 2.24
ESPECIALIDAD : HOJA N° : 1" 3.97
Nº DESCRIPCIONMEDIDAS ACERO KG/ML
N° DE VECES TOTALUND LONG. 1/4” 3/8” 1/2” 5/8” 3/4”
SUB TOTAL KG.N° DE
ELEM12 mm
Losa Ø 3/8 '' Kg 0.55 31 0.56 01 9.55
Ø 3/8 '' Kg 7.20 08 0.56 01 32.26
Apoyo Ø 3/8 '' Kg 1.15 05 0.56 01 3.22
Ø 3/8 '' Kg 1.15 03 0.56 01 1.93
04.08.00 LAVADERO DE OLLAS
04.08.03 ACERO DE REFUERZO Fy=4200 kg/cm2 20.24
ACERO PRINCIPAL DIAMETRO
Losa Ø 3/8 '' Kg 1.00 05 0.56 01 2.80
Ø 3/8 '' Kg 0.95 05 0.56 01 2.66
Apoyo Delantero y posterior Ø 3/8 '' Kg 0.50 05 0.56 02 2.80
Ø 3/8 '' Kg 1.00 02 0.56 02 2.24
Apoyo Lateral Ø 3/8 '' Kg 1.10 05 0.56 02 6.16
Ø 3/8 '' Kg 0.80 04 0.56 02 3.58
04.09.00 ALMACEN DE VIVERES
04.09.03 ACERO DE REFUERZO Fy=4200 kg/cm2 19.32
ACERO PRINCIPAL DIAMETRO
Losa Superior de 7.5 cm Ø 3/8 '' Kg 2.25 05 0.56 02 12.60
Ø 3/8 '' Kg 0.75 08 0.56 02 6.72
04.10.00 LAVADERO Y PAÑALERO
04.10.03 ACERO DE REFUERZO Fy=4200 kg/cm2 15.85
ACERO PRINCIPAL DIAMETRO
Losa Superior de 7.5 cm Ø 3/8 '' Kg 0.59 03 0.56 01 0.99
Ø 3/8 '' Kg 0.68 04 0.56 01 1.52
Losa Inferior de 10 cm Ø 3/8 '' Kg 0.59 06 0.56 01 1.98
Ø 3/8 '' Kg 1.38 04 0.56 01 3.09
Apoyo Lateral de 10 cm Ø 3/8 '' Kg 1.00 04 0.56 01 2.24
Ø 3/8 '' Kg 0.59 05 0.56 01 1.65
Losa Delantera de 10 cm Ø 3/8 '' Kg 1.60 03 0.56 01 2.69
Ø 3/8 '' Kg 0.50 06 0.56 01 1.68
04.07.00 MESA DE COCINA Y LAVADERO
04.07.03 ACERO DE REFUERZO Fy=4200 kg/cm2 15.85
ACERO PRINCIPAL DIAMETRO
Losa Superior de 7.5 cm Ø 3/8 '' Kg 0.59 03 0.56 01 0.99
Ø 3/8 '' Kg 0.68 04 0.56 01 1.52
Losa Inferior de 10 cm Ø 3/8 '' Kg 0.59 06 0.56 01 1.98
Ø 3/8 '' Kg 1.38 04 0.56 01 3.09
Apoyo Lateral de 10 cm Ø 3/8 '' Kg 1.00 04 0.56 01 2.24
Ø 3/8 '' Kg 0.59 05 0.56 01 1.65
Losa Delantera de 10 cm Ø 3/8 '' Kg 1.60 03 0.56 01 2.69
Ø 3/8 '' Kg 0.50 06 0.56 01 1.68
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
02.00.00 ESTRUCTURAS
02.01.00 MOVIMIENTOS DE TIERRAS 0 0.00
0 0 M3 0.00
0 Z-2
0 Z-3 M3 0.00
0 CORTE 1-1 M3 0.00
0 CORTE 4-4 M3 0.00
0 Z-1 CON C-2 M3 0.00
0 0 0 0.00
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF!
02.02.00 CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 C:H M3 28.80
#REF! #REF! #REF! #REF!
02.02.02.01 CONCRETO SOBRECIMIENTO DE 1:8 CEM-HOR ANCHO=0.15 MT M3 8.90
#REF! #REF! #REF! #REF!
02.02.03 FALSO PISO DE 4" DE CONCRETO 1:8 0 0.90
02.03.00 OBRAS DE CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 M3 166.40
02.03.01.02 ACERO DE REFUERZO Fy=4200 kg/cm2 KG 44.41
02.03.02 COLUMNAS
02.03.02.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3 48.90
02.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNAS M2 0.00
0 eje 5-A 5.15 0.00
0 eje 7-A
0 eje 4-F 5.15 0.00
0 eje 1 - F 5.15 0.00
0 eje 1 - D" 5.15 0.00
0 eje 1 - B
0 C-2 0 0.00
0 VP-102(.35x.60) 0.6 0.00
0 0 0 0.00
0 0
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
0 0 0 0.00
0 aligerado primer piso 0 0.00
0 0 34.3 0.00
0 eje EF - 10 Y 5
0 0 25 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
0 0 0 0.00
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 1.00
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
05.00.00 COBERTURA
05.01.00 COBERTURA LADRILLO PASTELERO ASENTADO C/MEZCLA M2 125.76
AREA M2 01 125.76
06.00.00 ALBAÑILERIA
06.01.00 MUROS DE SOGA LADRILLO KK 18 HUECOS DE ARCILLA M2 141.73
EJE 1 , A-B´ M2 2.90 2.70 01 7.83
EJE 1 , B´-C M2 2.00 2.70 01 5.40
EJE 1 , C-D,D-E,E-F M2 3.00 2.70 03 24.30
EJE 2 , A-B M2 0.80 3.10 01 2.48
EJE 2 , A-B ventana M2 1.20 1.70 01 2.04
EJE 3 , B´-C M2 1.00 3.50 01 3.50
EJE 3 , C-D M2 1.50 3.50 01 5.25
EJE 3 , C-D abierto M2 1.50 1.00 01 1.50
EJE 3 , D´-E M2 0.55 3.42 01 1.88
EJE 3 , D´-E ventan a M2 1.20 2.02 01 2.42
EJE 3 , E-E´ ventana M2 1.20 2.02 01 2.42
EJE 3 , E´-F M2 1.55 3.42 01 5.30
EJE 4 , A-B M2 0.63 2.70 01 1.69
EJE 4 , A-B ventana M2 1.50 1.30 01 1.95
EJE 4 , B´-C M2 0.40 2.62 01 1.05
EJE 4 , B´-C ventana M2 1.50 1.22 01 1.83
EJE 4 , C-D M2 1.45 2.62 01 3.80
EJE 4 , C-D ventana M2 1.50 1.22 01 1.83
EJE A , 1-2 M2 1.90 2.70 01 5.13
EJE A , 2-3 M2 3.10 3.10 01 9.61
EJE A , 2-3 triangulo sobre muro M2 3.10 0.40 01 0.62
EJE A , 3-4 M2 1.90 2.70 01 5.13
EJE A , 3-4 triangulo sobre muro M2 1.90 0.60 01 0.57
EJES B´, 1-2 M2 0.60 2.90 01 1.74
EJES B, 1-2 triangulo sobre muro M2 0.60 0.20 01 0.06
EJES B´, 1-2 ventana M2 1.50 1.50 01 2.25
EJES B´, 2-3 M2 3.10 2.90 01 8.99
EJES B, 2-3 triangulo sobre muro M2 3.10 0.40 01 0.62
EJES B´, 3-4 M2 0.90 2.70 01 2.43
EJES B´, 3-4 triangulo sobre muro M2 0.90 0.40 01 0.18
EJE B´ , 3-4 sobre puerta M2 0.90 1.30 01 0.59
ENTRE EJES B y C, MUROS H=1.8 M3 2.35 1.80 01 4.23
EJES D, 3-4 M4 1.80 2.70 01 4.86
EJES D, 3-4 triangulo sobre muro M5 1.80 0.80 01 0.72
EJES F, 1-2 M6 0.90 2.70 01 2.43
EJES F, 1-2 triangulo sobre muro M7 0.90 0.40 01 0.18
EJES F, 1-2 ventana M8 1.90 2.70 01 5.13
EJES F, 2-3 M9 3.10 3.10 01 9.61
EJES F, 2-3 triangulo sobre muro M10 0.90 0.40 01 0.18
07.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
07.01.00 TARRAJEO DE MUROS CON C:A, 1:5, EN EXTERIORES M2 124.66
Tarrajeo en Muros 317.19
M2 2.90 2.70 01 7.83
M2 2.90 2.60 01 7.54
M2 2.00 2.80 01 5.60
M2 2.38 2.60 01 6.18
M2 3.00 2.80 03 25.20
M2 9.95 2.60 01 25.87
M2 0.80 3.20 01 2.56
M2 0.80 3.05 01 2.44
M2 1.20 1.80 01 2.16
M2 1.20 1.65 01 1.98
M2 1.00 3.60 02 7.20
M2 1.50 3.60 02 10.80
M2 1.50 1.00 02 3.00
N° DE VECES
EJE 1 , A-B´ - INTERIOR
EJE 1 , A-B´ - EXTERIOR
EJE 1 , B´-C INTERIOR
EJE 1 , B´-C - EXTERIOR
EJE 1 , C-D,D-E,E-F - INTERIOR
EJE 1 , C al F - EXTERIOR
EJE 2 , A-B INTERIOR
EJE 2 , A-B EXTERIOR
EJE 2 , A-B INTERIOR ventana
EJE 2 , A-B EXTERIOR ventana
EJE 3 , B´-C INTERIOR
EJE 3 , C-D INTERIOR
EJE 3 , C-D INTERIOR
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 1.00
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
N° DE VECES
M2 0.80 3.60 01 2.88
M2 0.80 3.35 01 2.68
M2 1.20 2.20 01 2.64
M2 1.20 1.95 01 2.34
M2 1.20 2.20 01 2.64
M2 1.20 1.95 01 2.34
M2 1.80 3.60 01 6.48
M2 2.05 3.35 01 6.87
M2 0.63 2.80 01 1.75
M2 0.63 2.55 01 1.61
M2 1.50 1.40 01 2.10
M2 1.50 1.15 01 1.72
M2 0.60 1.80 01 1.08
M2 0.90 2.55 01 2.30
M2 1.50 1.30 01 1.95
M2 1.50 2.05 01 3.07
M2 1.60 1.80 01 2.88
M2 1.60 2.55 01 4.08
M2 1.50 1.30 01 1.95
M2 1.50 2.45 01 3.68
M2 2.20 2.70 01 5.94
M2 2.35 2.60 01 6.11
M2 3.45 3.20 02 22.08
M2 3.45 0.40 01 0.69
M2 3.45 2.95 01 10.18
M2 3.45 0.40 01 0.69
M2 1.90 2.80 01 5.32
M2 1.90 0.80 01 0.76
M2 2.00 2.55 01 5.10
M2 2.00 0.40 01 0.40
M2 1.50 1.60 01 2.40
M2 1.50 1.45 01 2.18
M2 0.60 3.00 01 1.80
M2 0.60 0.20 01 0.06
M2 0.60 2.85 01 1.71
M2 0.60 0.20 01 0.06
M2 3.35 3.20 02 21.44
M2 2.35 0.40 02 0.94
M2 0.90 1.10 02 1.98
M2 0.90 2.80 02 5.04
M2 0.90 0.80 02 0.72
M2 2.35 1.80 02 8.46
M2 1.90 2.80 01 5.32
M2 1.90 0.80 01 0.76
M2 2.05 2.55 01 5.23
M2 2.05 0.80 01 0.82
M2 2.20 2.80 01 6.16
M2 2.35 0.20 01 0.24
M2 2.20 2.55 01 5.61
M2 2.35 0.20 01 0.24
M2 3.45 3.30 01 11.39
M2 3.45 0.20 01 0.35
M2 3.70 3.05 01 11.29
M2 3.70 0.20 01 0.37
07.02.00 TARRAJEO DE MUROS CON C:A, 1:5, EN INTERIORES M2 192.54
M2 01 192.54
07.03.00 TARRAJEO DE SUPERFICIE Y ARISTAS DE COLUMNAS M2 14.45
EJE 1 - B´,F COLUMNAS M2 0.20 2.82 02 1.13
EJE 1 - C,D,E COLUMNAS M2 0.45 2.82 03 3.81
EJE 3 - B´ COLUMNAS 25x25 M2 0.20 3.60 01 0.72
EJE 3 , D´-E - INTERIOR
EJE 3 , D´-E - EXTERIOR
EJE 3 , D´-E - INTERIOR ventana
EJE 3 , D´-E - EXTERIOR ventana
EJE 3 , E -E´- INTERIOR ventana
EJE 3 , E-E´ - EXTERIOR ventana
EJE 3 , E´-F - INTERIOR
EJE 3 , E´-F - EXTERIOR
EJE 4 , A-B - INTERIOR
EJE 4 , A-B - EXTERIOR
EJE 4 , A-B - INTERIOR ventana
EJE 4 , A-B - EXTERIOR ventana
EJE 4 , B´-C - INTERIOR
EJE 4 , B´-C - EXTERIOR
EJE 4 , B´-C - INTERIOR ventana
EJE 4 , B´-C - EXTERIOR ventana
EJE 4 , C-D - INTERIOR
EJE 4 , C-D - EXTERIOR
EJE 4 , C-D - INTERIOR ventana
EJE 4 , C-D - EXTERIOR ventana
EJE A , 1-2 - INTERIOR
EJE A , 1-2 - EXTERIOR
EJES A, 2-3 - INTERIOR
EJE A, 2-3 TRIANGULO - INTERIOR
EJES A, 2-3 - EXTERIOR
EJE A, 2-3 TRIANGULO - EXTERIOR
EJES A, 3-4 - INTERIOR
EJE A, 3-4 TRIANGULO - INTERIOR
EJES A, 3-4 - EXTERIOR
EJE A, 3-4 TRIANGULO - EXTERIOR
EJES B´, 1-2 - INTERIOR ventana
EJES B´, 1-2 - EXTERIOR ventana
EJES B´, 1-2 - INTERIOR
EJES B´, 1-2 TRIANGULO - INTERIOR
EJES B´, 1-2 - EXTERIOR
EJES B´, 1-2 TRIANGULO - EXTERIOR
EJES B´, 2-3 -INTERIOR
EJES B´, 2-3 TRIANGULO - INTERIOR
EJE B´ , 3-4 - INTERIOR puerta
EJES B´, 3-4 - INTERIOR
EJES B´, 3-4 TRIANGULO - INTERIOR
ENTRE EJES B y C, MUROS H=1.8 INTERIOR
EJES D, 3-4 - INTERIOR
EJES D, 3-4 TRIANGULO - INTERIOR
EJES D, 3-4 - EXTERIOR
EJES D, 3-4 TRIANGULO - IEXERIOR
EJES F, 1-2 - INTERIOR
EJES F, 1-2 TRIANGULO - INTERIOR
EJES F, 1-2 - EXTERIOR
EJES F, 1-2 TRIANGULO - EXTERIOR
EJES F, 2-3 - INTERIOR
EJES F, 2-3 TRIANGULO - INTERIOR
EJES F, 2-3 - EXTERIOR
EJES F, 2-3 TRIANGULO -EXTERIOR
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 1.00
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
N° DE VECES
EJE 3 - C COLUMNAS 25x25 M2 0.60 3.60 01 2.16
EJE 3 - D COLUMNAS 25x25 M2 0.55 3.60 01 1.98
EJE 3 - E COLUMNAS 25x25 M2 0.45 3.60 01 1.62
EJE 3 - F COLUMNAS 25x25 M2 0.20 3.60 01 0.72
EJE 4 - D´ COLUMNA CIRCULAR M3 0.79 2.95 01 2.32
07.04.00 TARRAJEO DE SUPERFICIE DE VIGAS CON C:A, 1:4 M2 9.97
EJE C,D,E / 1-3 COLUMNAS M2 0.61 5.45 03 9.97
07.05.00 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA M3 135.78
AREA DE USO MULTIPLE M2 11.20 5.65 01 63.28
BAÑOS M2 5.40 1.90 01 10.26
PATIO M2 3.30 2.20 01 7.26
COCINA M2 5.35 3.30 01 17.65
ALEROS M2 33.40 1.00 01 33.40
ENTRADA M2 2.45 1.60 01 3.92
07.06.00 TARRAJEO PRIMARIO RAYADO CON C:A, 1:5 M2 17.54
ENTRE EJES B y C, MUROS H=1.8 interno M2 2.50 1.00 02 5.00
EJE 2 , A-B M2 1.15 0.60 01 0.69
EJE 4 , A-B M2 0.63 0.60 01 0.38
EJE 4 , B´-C M2 2.10 1.00 01 2.10
EJE 4 , C-D M2 2.50 0.60 01 1.50
EJE 4 , C´-D M2 1.00 0.60 01 0.60
EJE 4 , C´-D M2 0.60 0.60 01 0.36
EJES A, 2-4 M2 5.30 0.60 01 3.18
EJES B´, 3-4 M2 2.00 1.00 01 2.00
EJES D, 3-4 M2 2.90 0.60 01 1.74
07.07.00 VESTIDURA DE DERRAMES ANCHO=0.15M. ML 74.05
EJE 2 , A-B ventana ML 5.20 01 5.20
EJE 2 , B-B´ puerta ML 3.00 01 3.00
EJE 3 , C-D ML 6.70 01 6.70
EJE 3 , D-D´ puerta principal ML 10.40 01 10.40
EJE 3 , D´-E ventana ML 5.20 01 5.20
EJE 3 , E -E´ ventana ML 5.20 01 5.20
EJE 4 , A -B ventana ML 5.80 01 5.80
EJE 4 , B-B´ puerta cocina ML 3.00 01 3.00
EJE 4 , B´-C ventana SS.HH. Madre cuidad ML 4.00 01 4.00
EJE 4 , C-D ventana SS.HH. Niños ML 4.00 01 4.00
EJES B, 1-2 ventana area descanso ML 5.80 01 5.80
EJES B, 3-4´ puerta cocina-wawawasi ML 3.00 01 3.00
ENTRE EJES B y C, MUROS H=1.8 ML 2.35 01 2.35
EJES F, 1-2 ventana area uso multiple ML 5.20 01 5.20
EJES F, 2-3 ventana area uso multiple ML 5.20 01 5.20
07.08.00 REVESTIMIENTO DE MOLDURAS M2 10.00
M2 5.00 2.00 01 10.00
07.09.00 BRUÑAS E = 1 CM ML 32.28
EJE 1 , B´-C ML 2.20 01 2.20
EJE 1 , C-D, D-E ,E-F ML 3.45 03 10.35
EJE 3 , B´-C ML 1.58 01 1.58
EJE 3 , C-D ML 1.95 01 1.95
EJE 3 , D-E ML 2.45 01 2.45
EJE 3 , D´-E ML 1.43 01 1.43
EJE 3 , E -F ML 3.43 01 3.43
EJES B´, 1-3 ML 4.45 01 4.45
EJES F, 1-3 ML 4.45 01 4.45
08.00.00 PISOS Y VEREDAS
08.01.00 PISO DE CERAMICO ANTIDESLIZANTE DE 30x30 CM. M2 112.79
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 1.00
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
N° DE VECES
AREA DE USO MULTIPLE M2 11.20 5.65 01 63.28
BAÑOS M2 5.40 1.90 01 10.26
PATIO M2 6.75 2.05 01 13.84
COCINA M2 7.70 3.30 01 25.41
08.02.00 VEREDA DE CONCRETO DE 4", ACAVADO FRATACHADO Y BRUÑADO M2 15.00
M2 1.00 15.00 01 15.00
09.00.00 ZOCALOS Y CONTRAZOCALOS
09.01.00 ZOCALO DE MAYOLICA DE 15 X 15 CM DE COLOR DE 1RA M2 15.90
INC. MAYOLICA EN MUEBLE DE BAÑOS Y DISPENSADOR DE ALIMENTOS Y COCINA
EJE 3 , C-D M2 2.40 1.00 01 2.40
EJE 3 , C-D en mueble SS.HH. Niños M2 0.60 0.60 01 0.36
EJE 4 , B-B´ M2 0.95 1.00 01 0.95
EJE 4 , A-B en mueble de cocina M2 0.63 0.60 01 0.38
EJE 4 , B´-C M2 2.10 1.00 01 2.10
ENTRE EJES B y C, MUROS H=1.8 M2 2.20 1.00 01 2.20
EJE 4 , C-D M2 2.40 1.00 01 2.40
EJE 4 , C-D M2 0.60 0.60 01 0.36
EJES A, 2-4 M2 4.35 0.60 01 2.61
EJES B´, 3-4 M2 1.00 1.00 01 1.00
EJES D, 3-4 M2 1.90 0.60 01 1.14
09.02.00 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM ML 51.70
EXTERIOR
EJE 1 , A-F ML 15.70 01 15.70
EJE 3 , D-F ML 5.65 01 5.65
EJE 4 , A-D ML 9.10 01 9.10
EJES A, 1-4 ML 7.00 01 7.00
EJES D, 3-4 ML 2.10 01 2.10
EJES F, 1-3 ML 5.00 01 5.00
PATIO
EJE 1 , A-B ML 2.50 01 2.50
EJE 2 , A-B ML 2.50 01 2.50
EJES B, 1-2 ML 2.15 01 2.15
10.00.00 CARPINTERIA DE MADERA
10.01.00 PUERTAS DE MADERA TORNILLO DE TABLERO REBAJADO M2 5.88
M2 1.00 2.10 01 2.10
M2 0.90 2.10 02 3.78
10.02.00 PUERTA CONTRAPLACADA 35 MM. C/TRIPLAY 4MM.+ MARCO CEDRO 2X M2 4.06
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
05.00.00 COBERTURA
05.01.00 COBERTURA LADRILLO PASTELERO ASENTADO C/MEZCLA M2 125.76
06.00.00 ALBAÑILERIA
06.01.00 MUROS DE SOGA LADRILLO KK 18 HUECOS DE ARCILLA M2 141.73
07.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
07.01.00 TARRAJEO DE MUROS CON C:A, 1:5, EN EXTERIORES M2 124.66
07.02.00 TARRAJEO DE MUROS CON C:A, 1:5, EN INTERIORES M2 192.54
07.03.00 TARRAJEO DE SUPERFICIE Y ARISTAS DE COLUMNAS M2 14.45
07.04.00 TARRAJEO DE SUPERFICIE DE VIGAS CON C:A, 1:4 M2 9.97
07.05.00 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA M3 135.78
07.06.00 TARRAJEO PRIMARIO RAYADO CON C:A, 1:5 M2 17.54
07.07.00 VESTIDURA DE DERRAMES ANCHO=0.15M. ML 74.05
07.08.00 REVESTIMIENTO DE MOLDURAS M2 10.00
07.09.00 BRUÑAS E = 1 CM ML 32.28
08.00.00 PISOS Y VEREDAS
08.01.00 PISO DE CERAMICO ANTIDESLIZANTE DE 30x30 CM. M2 112.79
08.02.00 VEREDA DE CONCRETO DE 4", ACAVADO FRATACHADO Y BRUÑADO M2 15.00
09.00.00 ZOCALOS Y CONTRAZOCALOS
09.01.00 ZOCALO DE MAYOLICA DE 15 X 15 CM DE COLOR DE 1RA M2 15.90
09.02.00 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM ML 51.70
10.00.00 CARPINTERIA DE MADERA
10.01.00 PUERTAS DE MADERA TORNILLO DE TABLERO REBAJADO M2 5.88
10.02.00 PUERTA CONTRAPLACADA 35 MM. C/TRIPLAY 4MM.+ MARCO CEDRO 2X3" M2 4.06
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 0.99
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
01.00.00 SISTEMA DE DESAGUE
01.01.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 4" ML 15 15.00
01.02.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 2" ML 05 5.00
01.03.00 CAJA DE REGISTRO DE DESAGUE 12" X 12" PZA 03 3.00
01.04.00 SUMIDEROS DE 2" PZA 02 2.00
01.05.00 REGISTROS ROSCADO DE BRONCE DE 4" PZA 04 4.00
01.06.00 SALIDAS DE PVC SAL PARA VENTILACION DE 2" PTO 6.00
Salida Desague PVC 2" Lavat. Adulto PTO 01
Salida Desague PVC 2" Lavat. Baby PTO 01
Salida Desague PVC 2" Lavad. 2 Pozas. PTO 02
Salida Desague PVC 2" Lavadero Ollas PTO 01
Salida Desague PVC 2" Rebose Tq. Elev. PTO 01
01.07.00 SALIDAS DE PVC SAL PARA DESAGUE DE 4" PTO 03 3.00
01.08.00 SALIDAS DE PVC SAL PARA DESAGUE DE 2" PTO 02 2.00
02.00.00 SISTEMA DE AGUA FRIA
02.01.00 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP DE 3/4" a 1/2" PTO 11 11.00
02.02.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 2" ML 36 36.00
03.00.00 APARATOS Y ACCESORIOS SANITARIOS
03.01.00 INODORO TANQUE BAJO BLANCO PZA 3.00
Inodoro Tanque Bajo Blanco PZA 01
Inodoro Tanque Bajo Mod. Baby c/acc. PZA 02
03.02.00 LAVATORIO DE PARED BLANCO 1 LLAVE PZA 02 2.00
03.03.00 LAVADERO DE COCINA DE ACERO INOXIDABLE PZA 01 1.00
03.04.00 TOALLERA C/SOPORTE DE LOSA Y BARRA PLASTICA, COLOR BLANCO UND 02 2.00
03.05.00 PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO UND 02 2.00
03.06.00 GANCHO DOBLE DE LOZA BLANCA PZA 01 1.00
03.07.00 COLOCACION DE APARATOS SANITARIOS PZA 06 6.00
03.08.00 COLOCACION DE ACCESORIOS SANITARIOS CORRIENTES PZA 05 5.00
04.00.00 VARIOS
04.01.00 TANQUE ELEVADO DE ETERNIT DE 1.00 M3 PZA 01 1.00
04.02.00 TANQUE CISTERNA DE ETERNIT PZA 01 1.00
04.03.00 ELECTROBOMBA MONOFASICO 0.5 HP UND 01 1.00
05.00.00 TANQUE SEPTICO
05.01.00 LIMPIEZA DE TERRENO MANUAL M2 4.90 1.30 01 6.37 6.37
05.02.00 TRAZO Y REPLANTEO DE OBRA M2 4.90 1.30 01 6.37 6.37
05.03.00 EXCAVACION MASIVA MANUAL M3 4.90 1.30 2.03 01 12.90 12.90
05.04.00 NIVELACION INTERIOR Y APISONADO MANUAL M2 4.90 1.30 01 6.37 6.37
05.05.00 ELIMINACION DE MATERIAL EXCEDENTE CON CARRETILLA M3 4.90 1.30 2.03 01 15.48 15.48
05.06.00 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON M2 4.90 1.30 01 6.37 6.37
05.07.00 CONCRETO EN CISTERNA SUBTERRANEA F'C=210 KG/CM2 M3 6.34
Losa fondo M3 4.90 1.30 0.15 01 1.15
Pared 1 M3 1.30 0.15 1.85 01 0.43
Pared 2 M3 1.30 0.15 1.60 03 1.12
Pared 3 M3 2.45 0.15 1.73 02 1.52
M3 0.50 0.15 1.60 02 0.29
M3 1.35 0.15 1.60 02 0.78
Techo M3 4.90 1.30 0.15 01 1.15
M3 0.80 0.80 0.15 -01 -0.12
M3 0.70 0.70 0.15 -02 -0.18
Tapas KG 0.800 0.80 0.10 01 0.08
KG 0.700 0.70 0.10 02 0.12
05.08.00 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA SUBTERRANEA M2 50.79
Pared 1 M2 1.300 1.85 02 4.81
Pared 2 M2 1.300 1.60 06 12.48
Pared 3 M3 2.45 1.73 04 16.91
M3 0.50 1.60 04 3.20
M3 1.35 1.60 04 8.64
N° DE VECES
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 0.99
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
N° DE VECES
Techo M2 4.900 1.30 01 6.37
M2 0.800 0.80 -01 -0.64
M2 0.700 0.70 -02 -0.98
05.09.00 ACERO DE REFUERZO Fy=4200 kg/cm2 KG 324.31
Losa fondo KG 5.300 07 Ø 3/8 '' 0.56 20.78
KG 1.300 25 Ø 3/8 '' 0.56 18.20
Pared 1 KG 2.550 09 Ø 3/8 '' 0.56 12.85
KG 1.300 15 Ø 3/8 '' 0.56 10.92
Pared 2 KG 2.100 27 Ø 3/8 '' 0.56 31.75
KG 1.300 39 Ø 3/8 '' 0.56 28.39
Pared 3 KG 2.338 38 Ø 3/8 '' 0.56 49.74
KG 2.175 30 Ø 3/8 '' 0.56 36.54
KG 5.300 28 Ø 3/8 '' 0.56 83.10
Techo KG 1.350 09 Ø 3/8 '' 0.56 6.80
KG 1.350 09 Ø 3/8 '' 0.56 6.80
KG 0.850 09 Ø 3/8 '' 0.56 4.28
KG 0.850 09 Ø 3/8 '' 0.56 4.28
Tapas KG 0.800 08 Ø 3/8 '' 0.56 3.58
KG 0.700 16 Ø 3/8 '' 0.56 6.27
05.10.00 TARRAJEO CON IMPERMEABILIZANTES M2 28.52
Losa fondo M2 1.00 4.30 01 4.30
Pared 1 M2 1.00 1.85 01 1.85
Pared 2 M2 1.00 1.60 05 8.00
Pared 3 M2 2.45 1.73 02 8.45
M2 0.50 1.60 02 1.60
M2 1.35 1.60 02 4.32
05.11.00 CODO PVC SAL 4"X90º PZA 02 2.00
05.12.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 4" M 10 10.00
05.13.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 4" A CURSO NATURAL M 50 50.00
06.00.00 CANALETA PLUVIAL DE CONCRETO
06.01.00 CONCRETO EN CANAL PLUVIAL 1:8, C:H M3 16.80 16.80
06.02.00 ENCOFRADO Y DESENCOFRADO PARA CANAL PLUVIAL M2 62.01 62.01
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
01.00.00 SISTEMA DE DESAGUE
01.01.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 4" ML 15.00
01.02.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 2" ML 5.00
01.03.00 CAJA DE REGISTRO DE DESAGUE 12" X 12" PZA 3.00
01.04.00 SUMIDEROS DE 2" PZA 2.00
01.05.00 REGISTROS ROSCADO DE BRONCE DE 4" PZA 4.00
01.06.00 SALIDAS DE PVC SAL PARA VENTILACION DE 2" PTO 6.00
01.07.00 SALIDAS DE PVC SAL PARA DESAGUE DE 4" PTO 3.00
01.08.00 SALIDAS DE PVC SAL PARA DESAGUE DE 2" PTO 2.00
02.00.00 SISTEMA DE AGUA FRIA
0 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP DE 3/4" a 1/2" PTO 11.00
0 RED DE DERIVACION PVC SAL PARA DESAGUE DE 2" ML 36.00
03.00.00 APARATOS Y ACCESORIOS SANITARIOS
03.01.00 INODORO TANQUE BAJO BLANCO PZA 3.00
03.02.00 LAVATORIO DE PARED BLANCO 1 LLAVE PZA 2.00
03.03.00 LAVADERO DE COCINA DE ACERO INOXIDABLE PZA 1.00
03.04.00 TOALLERA C/SOPORTE DE LOSA Y BARRA PLASTICA, COLOR BLANCO UND 2.00
03.05.00 PAPELERA DE LOSA Y BARRA PLASTICA, COLOR BLANCO UND 2.00
03.06.00 GANCHO DOBLE DE LOZA BLANCA PZA 1.00
03.07.00 COLOCACION DE APARATOS SANITARIOS PZA 6.00
03.08.00 COLOCACION DE ACCESORIOS SANITARIOS CORRIENTES PZA 5.00
04.00.00 VARIOS
04.01.00 TANQUE ELEVADO DE ETERNIT DE 1.00 M3 PZA 1.00
04.02.00 TANQUE CISTERNA DE ETERNIT PZA 1.00
04.03.00 ELECTROBOMBA MONOFASICO 0.5 HP UND 1.00
05.00.00 TANQUE SEPTICO
05.01.00 LIMPIEZA DE TERRENO MANUAL M2 6.37
05.02.00 TRAZO Y REPLANTEO DE OBRA M2 6.37
05.03.00 EXCAVACION MASIVA MANUAL M3 12.90
05.04.00 NIVELACION INTERIOR Y APISONADO MANUAL M2 6.37
05.05.00 ELIMINACION DE MATERIAL EXCEDENTE CON CARRETILLA M3 15.48
05.06.00 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON M2 6.37
05.07.00 CONCRETO EN CISTERNA SUBTERRANEA F'C=210 KG/CM2 M3 6.34
05.08.00 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA SUBTERRANEA M2 50.79
05.09.00 ACERO DE REFUERZO Fy=4200 kg/cm2 KG 324.31
05.10.00 TARRAJEO CON IMPERMEABILIZANTES M2 28.52
05.11.00 CODO PVC SAL 4"X90º PZA 2.00
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
05.12.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 4" M 10.00
05.13.00 RED DE DERIVACION PVC SAL PARA DESAGUE DE 4" A CURSO NATURAL DE AGUA M 50.00
06.00.00 CANALETA PLUVIAL DE CONCRETO
06.01.00 CONCRETO EN CANAL PLUVIAL 1:8, C:H M3 16.80
06.02.00 ENCOFRADO Y DESENCOFRADO PARA CANAL PLUVIAL M2 62.01
HOJA DE METRADOS
ACERO KG/ML
PROYECTO : 1/4" 0.25
3/8" 0.56
SUBPRESUPUESTO : 1/2" 0.99
5/8" 1.55
FECHA : HECHO POR : 3/4" 2.24
1" 3.97
ESPECIALIDAD: : HOJA N° :
Nº DESCRIPCION UND
MEDIDAS SUB TOTAL
TOTALLARGO ANCHO ALTO LONG. AREA VOL. KG.
01.00.00 SALIDA DE LUZ Y FUERZA
01.01.00 SALIDA DE TECHO CENTRO DE LUZ PTO 07 7.00
01.02.00 SALIDA DE INTERRUPTOR SIMPLE PTO 07 7.00
01.03.00 SALIDA DE PARED (BRAQUETES) CON PVC PTO 03 3.00
01.04.00 SALIDA PARA TIMBRE TIPO GONG CON PVC PTO 01 1.00
01.05.00 SALIDA PARA TELEFONO DIRECTO (DE SERVICIO PUBLICO) PTO 01 1.00
01.06.00 SALIDA PARA ANTENA DE TELEVISION CON PVC PTO 01 1.00
01.07.00 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC PTO 07 7.00
01.08.00 SALIDA PARA CAJA DE PASE PTO 01 1.00
02.00.00 TABLEROS Y CUCHILLAS
02.01.00 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLO PZA 01 1.00
02.02.00 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 20A PZA 02 2.00
02.03.00 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A PZA 02 2.00
03.00.00 ARTEFACTOS ELECTRICOS
03.01.00 BRAQUETE CON FOCO "WS"150R JOSFEL + LAMPARA 1OOW. UND 03 3.00
03.02.00 FLUORESCENTE RECTO ISPE 2 X 40 W INCLUYENDO EQUIPO Y PANTALL UND 07 7.00
N° DE VECES
HOJA DE RESUMEN DE METRADOS
PROYECTO :SUBPRESUPUESTO :FECHA :
ESPECIALIDAD :
HECHO POR :
DESCRIPCIONNº UND TOTAL
01.00.00 SALIDA DE LUZ Y FUERZA
01.01.00 SALIDA DE TECHO CENTRO DE LUZ PTO 7.00
01.02.00 SALIDA DE INTERRUPTOR SIMPLE PTO 7.00
01.03.00 SALIDA DE PARED (BRAQUETES) CON PVC PTO 3.00
01.04.00 SALIDA PARA TIMBRE TIPO GONG CON PVC PTO 1.00
01.05.00 SALIDA PARA TELEFONO DIRECTO (DE SERVICIO PUBLICO) PTO 1.00
01.06.00 SALIDA PARA ANTENA DE TELEVISION CON PVC PTO 1.00
01.07.00 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC PTO 7.00
01.08.00 SALIDA PARA CAJA DE PASE PTO 1.00
02.00.00 TABLEROS Y CUCHILLAS
02.01.00 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLO PZA 1.00
02.02.00 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 20A PZA 2.00
02.03.00 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A PZA 2.00
03.00.00 ARTEFACTOS ELECTRICOS
03.01.00 BRAQUETE CON FOCO "WS"150R JOSFEL + LAMPARA 1OOW. UND 3.00
03.02.00 FLUORESCENTE RECTO ISPE 2 X 40 W INCLUYENDO EQUIPO Y PANTALL UND 7.00