Test 1, Question 2
WYX is a web site to which qualified individuals are encouraged to contribute information about the law. Contributors may write original articles, or comment on and edit articles written by others.
WYX wishes to encourage high-quality contributions by a wide range of contributors. For this purpose, it plans to extend its current computer system to provide incentives that will reward participation. The incentives are of four categories:
(a) Points for certain types of activity. (b) Badges given as recognition of specific accomplishments. (c) Rewards based on the quality and extent of contribution. (d) Bonus rewards derived from the other three categories.
CS 5150 4
Test 1, Question 2 (continued)
You are asked to recommend a software development process for the proposed extension to the WYX system.
(a) i Is the modified waterfall model a good choice for developing this system?
No
ii Give two reasons for your answer.
(-) The requirements are poorly understood, e.g. the details of the incentive categories. This will probably lead to major revisions of the system.
(-) The user interface will need testing with users. This requires some form of iteration.
CS 5150 5
Test 1, Question 2 (continued)
(b) i Is iterative refinement leading to a single release of the system a good choice for developing this system?
No or Not very good but better than (a)
ii Give two reasons for your answer.
(+) Iterative refinement allows testing and revision of the user interface.
(-) The commitment to a single release does not allow modification of the incentive categories based on experience.
CS 5150 6
Test 1, Question 2 (continued)
(c) i Is incremental releases of small increments of software a good choice for developing this system?
Yes
ii Give two reasons for your answer.
(+) Small incremental releases allow modification of the incentive categories based on experience.
(+) If the incentive system is clearly a failure, the project can be cancelled or extensively modified before great expenditure.
(d) What software development process would you recommend?
Option (c) – incremental releases
CS 5150 7
The Aim of Project Management
To complete a project:
• On time
• On budget
• With required functionality
• To the satisfaction of the client
• Without exhausting the team
To provide visibility about the progress of a project
CS 5150 8
OS 360
The operating system for the IBM 360 was two years late.
Question: How does a project get two years behind schedule?
Answer: One day at a time!
Fred Brooks Jr., The Mythical Man Month
CS 5150 9
Aspects of Project Management
Planning
• Outline schedule during feasibility study
• Fuller schedule at the beginning of a project or for each phase of a project (e.g., each iteration)
Progress tracking
• Regular comparison of progress against plan
• Regular updating of the plan
Final analysis
• Analysis of project for improvements during next project
CS 5150 10
Terminology
Deliverable
Work product that is provided to the client (report, presentation, documentation, code, etc.)
Milestone
Completion of a specified set of activities (e.g., delivery of a deliverable, completion of a process step or iteration, incremental release)
CS 5150 11
Terminology
Activity
Part of a project that takes place over time (also known as a task).
Event
The completion of a group of activities.
Dependency
An activity that cannot begin until some event is reached
Resource
Staff time, equipment, or other limited resources required by an activity.
CS 5150 12
General Approach to Project Planning
Identify deliverables and milestones
Divide project into activities (tasks)
For each activity estimate:
• time to complete from when activity begins
• dependencies on events before beginning
• resource requirements (e.g., personnel)
Build a model that uses this data to create a work-plan, including schedule, resource allocation, and flexibility
CS 5150 13
Project Planning Methods
Critical Path Method, Gantt charts, Activity bar charts, etc.
• Build a work-plan from activity data.
• Display work-plan in graphical form.
Project planning software
• Maintain a database of activities and related data
• Calculate and display schedules
• Provide progress reports
CS 5150 15
Gantt Charts
• Dates run along the top (days, weeks or months).
• Each row represents an activity. Activities may be scheduled sequentially, in parallel or overlapping.
• The schedule for an activity is a horizontal bar. The left end marks the planned beginning of the task. The right end marks the expected end date.
• The chart may be updated by filling in each activity to a length proportional to the work accomplished.
• Progress to date can be compared with the plan by drawing a vertical line through the chart at the current date.
CS 5150 17
Estimating the Time for an Activity
With experienced staff, estimating the actual time to carry out a single task is usually fairly accurate, but ...
The little bits and pieces are underestimated
• The time from almost "done" to completely "done" is much longer than anticipated. (There's just one thing to tidy up. I need to put the comments into better shape. I really should get rid of that patch.)
• The distractions are not planned for. (My system crashed and I decided to upgrade the software. My child's school was closed because of snow. I spent the day showing visitors around.)
• Some things have to be done twice.
CS 5150 18
Start-up Time
On a big project, the start-up time is typically three to six months:
• Personnel have to complete previous projects (fatigue) or be recruited.
• Hardware and software has to be acquired and installed.
• Staff have to learn new domain areas and software (slow while learning).
• Clients may not be ready.
CS 5150 19
Final Analysis with Critical Path Method
Administrative computing department at Dartmouth used the Critical Path Method for implementation phase of major projects (plan developed after project was well-understood).
Experience: Elapsed time to complete projects was consistently 30% to 40% longer than predicted by model.
Analysis:
• Some tasks not anticipated (incomplete understanding)• Some tasks had to be redone (change of requirements, technical changes)• Key personnel were on many activities (schedule conflicts)• System ZZZ (non-billable hours)
CS 5150 20
Activity Graph
An activity (task)
A dummy activity (dependency)
An event
A milestone
A scheduling technique that emphasizes dependencies
CS 5150 21
Example: Activity Graph for a Distance Learning Course (part of a large project)
START
Edit 1
Script TV
Make TV
Edit 2
Prototype Software
WriteSoftware
DocumentSoftware
Plan TV
Plan 1
Write 1
Plan 2
Plan Software
Write 2
Typeset 1
Typeset 2
CS 5150 22
Scheduling: Background
PERT
Program Evaluation and Review Technique introduced by the U.S. Navy in 1957 to support the development of its Polaris submarine missile program.
PERT/Time
Activity graph with three time estimates (shortest, most probable, longest) on each activity to compute schedules.
PERT/Cost
Added scheduling of resources (e.g., facilities, skilled people, etc.)
CS 5150 23
Critical Path Method
Uses an Activity Graph with single time estimate for each activity.
A standard method for managing large construction projects.
On big projects, activity graphs with more than 10,000 activities are common.
CS 5150 25
Earliest Event Dates and Earliest Start Dates
Earliest start date: the earliest date that it is possible to start an activity.
Earliest event date: the date that all the activities ending at that node will be completed, assuming that every activity begins at its earliest start date.
Earliest project completion date: the date on which the project is completed assuming that every activity begins on its earliest start date.
CS 5150 26
Earliest Event Dates and Earliest Start Dates
6
4
2
2
3
3
3
3
82
11
4
12
12
1
4
0
1
12
12
4
17
19
23
5
2522
17
17
15
15
8
2023 24
Earliest dates for an event are in red
CS 5150 27
Latest Event Dates and Latest Start Dates
Latest start date: the latest date that it is possible to start an activity and still complete the project by the earliest project completion date.
Latest event date: the latest date that all the activities ending at that node must be completed, in order to complete the project by the earliest project completion date.
CS 5150 28
Latest Event Dates and Latest Start Dates
6
4
2
2
3
3
3
3
82
11
4
12
12
1
11
12
14
13
15
20
23 24 25
4 22
0
17
17
10
1817
2019
Each event must be achieved by the date shown or the final date will not be met.
Latest event dates in blue
CS 5150 29
Slack and Critical Path
Slack: the difference between the latest start date and the earliest start date of an activity
Critical path: a path through the graph where every activity has zero slack
If an activity on the critical path is not started on its earliest start date or takes longer than the predicted time to complete, then the project completion date is delayed.
CS 5150 30
Slack
0/0
1/11
17/17
23/24
1
22
12/12
12/14
4/13
15/15 17/17
17/17 19/20
22/23 25/25
4
8
123 2
312
4
4
3
3
6
1 1
10 10
00 0
0
00
9
9
2
2
23
11
11
5
Slack in purple
CS 5150 31
Critical Path
0/0
1/11
12/12
12/14
4/13
15/15 17/17
17/17
17/17
19/20
22/23 23/24 25/25
Every activity on the critical path must begin on the earliest start date.
Critical path in orange
CS 5150 32
Adding Resources to Activity Graph or Gantt Chart
Each activity is labeled with resources, e.g.,
Number of people (e.g., 2 Java programmers)
Key personnel (e.g., chief system architect)
Equipment (e.g., 3 servers with specified software)
Facilities (e.g., video conference center)
Each resource is labeled with availability, e.g.,
Hiring and training
Vacations
Equipment availability
CS 5150 33
Using Critical Path Method for Resources
Assume every activity begins at earliest start date:
In each time period, calculate:
resources required
resources available
Identify shortage / surplus resources
Adjust schedule
acquire extra staff (e.g., consultants)
rearrange schedule (e.g., change vacations)
change order of carrying out activities
The earlier that a problem is known, the easier it is to fix.
CS 5150 34
Key Personnel: The Mythical Man Month
In computing, not all people are equal
• The best are at least 5 times more productive.• Some tasks are too difficult for everybody.
Adding more people adds communications complexity
• Some activities need a single mind.• Sometimes, the elapsed time for an activity can not be
shortened.
What happens to the project if a key person is sick or quits?
CS 5150 35
The Project Manager
• Create and maintain the schedule.• Track progress against schedule.• Keep some slack in the schedule (minimize risk).• Continually make adjustments:
Start activities before previous activity completeSub-contract activitiesRenegotiate deliverables
• Keep senior management informed (visibility).
The project manager needs the support of the head of the development team and the confidence of the team members.