Transcript
Page 1: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 1

Chapter 4

Building the Work Breakdown Structure

Page 2: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 2

The Work Breakdown Structure (WBS)

The Work Breakdown Structure (WBS) is a hierarchicaldescription of the work that must be done to complete theproject as defined in the Project Overview Statement (POS)

Several processes can be used to create this hierarchy

Page 3: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 3

WBS

Page 4: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 4

Decomposition

Decomposition is breaking down work into a hierarchy of activities, tasks, andwork packages.

Important to the overall project plan because it allows you to estimate theduration of the project, determine the required resources, and schedule thework.

The complete decomposition will be developed by using the completenesscriteria discussed later.

Page 5: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 5

The WBS has four uses:Thought process toolIt helps the project manager and the project team visualize exactly how thework of the project can be defined and managed effectivelyNot unusual to consider alternative ways of decomposing the work untilproject manager is comfortableArchitectural design toolIs a picture of the work of the project and how the items of work are related toone anotherPlanning toolGives the project team a detailed representation of the project as a collectionof activities that must be completed in order for the project to be completedProject status reporting toolProject activities are consolidated (rolled up) from the bottom as lower-levelactivities are completedAs work is completed, activities will be completedWBS defines milestone events that can be reported to senior managementand to the customer

Uses for the WBS

Page 6: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 6

Approaches to Building WBS

There is no one correct way to create the WBS.The choice is subjective and based more on the projectmanager’s preference than on any other requirements.If try to follow one approach and find that it is making theproject work more confusing rather than simpler, text’s advice issimply to throw away the work you have done and start all overagain with a fresh approach.

Page 7: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 7

There are three general approaches to building the WBS:Noun-type approachesDefine the deliverable of the project work in terms of the components(physical or functional) that make up the deliverable. (Currently recommendedby PMI)Verb-type approachesDefine the deliverable of the project work in terms of the actions that must bedone to produce the deliverable.Include the design-build-test-implement and project objectives Approaches.Organizational approachesDefine the deliverable of the project work in terms of the organizational unitsthat will work on the project.Includes the department, process, and geographic location approaches

Approaches to Building WBS – continued

Page 8: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 8

Noun-Type Approaches

Physical decompositionIn projects that involve building products, it is tempting to followthe physical decomposition approachTake a bicycle for example. Its physical components are frame,wheels, seat, fork, rims, gears, brakes, and so on. If each is to bemanufactured, this approach may produces a simple WBS that iseasily understood by all concerned parties.

Can build the WBS using the functional components of an itemUsing the bicycle example, we can build the WBS using thefunctional components of the bicycle. The functional componentsinclude the steering system, gear-shifting system, braking system,and pedaling system.

Functional decomposition

Page 9: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 9

Noun-Type Appr.

Representing the WBS

Indented outline Version WBS for a Bicycle

Page 10: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 10

Design-build-test-implementCommonly used in those projects that involve a methodology,such as application systems development, for example.These are just representative categories.When the detail-level activity schedules are summarized up tothem, they present a display of meaningful information to therecipient of the report.Remember, the WBS activities at the lowest levels mustalways be expressed in verb form.After all, we are talking about work, and that implies action,which, in turn, implies verbs.

Verb-Type Approaches

ObjectivesSimilar to the design-build-test-implement approach.(Used when progress reports at various stages of project completion are prepared for senior management)

Page 11: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 11

Design build test, Implement

Verb-Type Appr.Design-build-test-implement

Representing the WBS

Page 12: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 12

Representing the WBS

Page 13: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 13

Each activity must possess six characteristics to be consideredcompletely decomposed.

Status/completion is measurableStart/end events are clearly definedActivity has a deliverableTime/cost is easily estimatedActivity duration is within acceptable limitsActivity Independence

Test for Completeness in WBS

Page 14: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 14

The project manager can ask for the status of an activity at anypoint in time during the project.

If the activity has been defined properly, that question isanswered easily.A simple metric that has met with some success is tocompute the proportion of tasks completed as a percentage ofall the tasks that make up the activity:

Although it may seem somewhat inaccurate, it is agood technique (It doesn’t say anything about thequality of the Work, best of all, it is quick).

Measurable Status

Page 15: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 15

Each activity should have a clearly defined start and end event.Once the start event has occurred, work can begin on theactivity.The deliverable is most likely the end event that signals work isclosed on the activity.

Start/end events are clearly defined (Bounded)

Page 16: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 16

Deliverable

The result of completing the work that makes up the activity isthe production of a deliverable.It is a visible sign that the activity is complete:Could be an approving manager’s signature, a physicalproduct or document, the authorization to proceed to the nextactivity or some other sign of completionThe deliverable(s) from an activity is output from that activity,which then becomes input to one or more other activities thatfollow its completion.

Page 17: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 17

Each activity should have an estimated time and cost ofcompletion.Being able to do this at the lowest level of decomposition in theWBS allows you to aggregate to higher levels and estimate thetotal project cost and the completion date.This experience at lower levels of definition gives you a strongerbase on which to estimate activity cost and duration for similaractivities.

Cost/Time Estimate

Page 18: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 18

While there is no fixed rule for the duration of an activity, textrecommend that activities have a duration of less than twocalendar weeks. (Common practice in many organizations)

Exceptions when the activity defines process work, such as willoccur in many manufacturing situations.

The danger you avoid is longer-duration activities whose delaycan create a serious project-scheduling problem.

Acceptable Duration Limits

Page 19: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 19

It is important that each activity be independent.Once work has begun on the activity, it can continue reasonablywithout interruption and without the need of additional input orinformation until the activity is complete.The work effort could be contiguous, but it can be scheduledotherwise for a variety of reasons:You can choose to schedule it in parts because of resourceavailability, but you could have scheduled it as one continuousstream of work.

Avoid the temptation to micromanage an activity:Best practices suggest that you manage an individual’s workdown to units of one week.

Activity Independence

Page 20: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 20

Generating the WBS

Text suggests the best way to generate the WBS is as part ofthe Joint Project Planning JPP session.There may be as many as 10 to 20 participants involved inbuilding the WBS, so gathering around a computer screen won’tdo the job.Text suggests use Post-It notes, marking pens, and plenty ofwhiteboard space.

It is sloppy, but it gets the job done

Two approaches can be used to identify the project activities:1. Top-Down approach2. Bottom-up approach

Page 21: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 21

Top-Down approach

The top-down approach begins at the goal level andsuccessively partitions work down to lower levels of definition untilthe participants are satisfied that the work has been sufficientlydefined.Once the project activities have been defined, they will be at asufficient level of detail to allow you to estimate time, cost, andresource requirements first at the activity level and then aggregateto the project level.Once the activities are described, you can sequence the projectwork so that as many activities as possible are performed inparallel, rather than in sequence.

goal level lower levels

Page 22: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 22

Bottom-up approach

More like a brainstorming session than an organized approachto building the WBS.

Each group makes a list of the activities that must be completedin order to complete the first-level activity. To do this, they proceedas follows:

1. Someone in the group identifies an activity and announces it tothe group. If the group agrees, then the activity is written on a slipof paper and put in the middle of the table. Process repeats itselfuntil no new ideas are forthcoming. ( Brainstorming !)

Page 23: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 23

2. The group then sorts the slips into activities that seem to berelated to one another. This should help the planning team addmissing activities or remove redundant ones.

3. Once the team is satisfied it has completed the activity list forthe first-level breakdown, each group then reports to the entireplanning team the results of its work.

4. Final critiques are given, missing activities added, andredundant activities removed

Bottom-up approach, cont.

Page 24: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 24

To create the WBS, assemble a facilitator, the project manager,the core members of the project team, and all other managerswho might be affected by the project or who will affect the project:

Important to have the expertise and the decision makerspresent who can give input into the WBS.

This exercise should be continuous; you do not want to interruptit while you go looking for input from people who should alreadybe in the session.

The tools are low-tech (Post-It notes, marking pens, andwhiteboards), and they greatly facilitate the orderly completion ofthe task.

Using JPP Session to Build WBS

Page 25: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 25

Sample Gantt Chart (MS Project)

The WBS is on the left, and each task’s start and finish date are shown on the right using acalendar timescale.

Page 26: Chapter 4 Building the Work Breakdown Structuresite.iugaza.edu.ps/aabuzarifa/files/IUGAZA-PM_20171_CH4.pdf · The Work Breakdown Structure (WBS) The Work Breakdown Structure (WBS)

Dr. Anwar Abu-Zarifa . Islamic University of Gaza . Department of Mechanical & Industrial Engineering © 2017/2018 26

Primavera Systems, Inc, which was founded in May 1983, was a private company based inPennsylvania(USA) which develops software solutions for the Project Portfolio Management market. OnJanuary 1, 2009 Oracle Corporation took legal ownership of Primavera.

Sample Gantt Chart (Primavera)


Recommended