Page 1: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Calculate the critical pathArrow diagram

CriticalPathMethod

Edina NagyLajos Kiss

Szabolcs Hornyák

Page 2: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Time analysis

Time analysis goals:

- How much time is needed to implement the schedule?

- When can I start and finish the activities at the earliest?

- When can I start and finish the activities at the latest?

Page 3: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Activities

A list of all activities required to complete the project.

The time that each activity will take to completion.

The dependencies between the activities.

Page 4: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Basic rules

• Starting point and terminus• Arrows, circles• Activities time• ES,LS,EF,LF• Dummy

Page 5: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

4 activities example

Page 6: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

ES, EF, LF, LS

ES - earliest start time

EF- earliest finish time

LF- latest finish time

LS- latest start time

Page 7: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

ES, EF, LF, LS Formulas

• Ei = ESij• Ej = EFij = ESij+tij• Li = LSij = LFij-tij• Lj = LFij

Page 8: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

The time course analysis

→ TFij – total float, TFij = Lj-Ei-tij = LFij-ESij-tij→ FFij – free float, FFij = Ej-Ei-tij→ IFij – independent float IFij = Ej-Li-tij→ CFij – conditional float CFij = TFij-FFij

Page 9: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

The time course analysis

The Forward pass (first phase) gives the turnaround time and the earliest possible occurence of events.

The Backward pass (second phase) gives the latest possible occurrence of events.

Page 10: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 11: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 12: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 13: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 14: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 15: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 16: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 17: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 18: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 19: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 20: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 21: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 22: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 23: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 24: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 25: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 26: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 27: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 28: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 29: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 30: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Example

Page 32: Calculate the critical path Arrow diagram Critical Path Method Edina Nagy Lajos Kiss Szabolcs Hornyák

Thanks…