User Acceptance Automated Testing
Updates to Automated Frameworks
Project Planning for Automated Testing Frameworks Framework Improvements Framework Updates Framework Upgrades Modular formats for Existing Test Cases Write new test cases Production Tests Logging
Implementation IDE Updates – Eclipse Neon Selenium Updates - selenium jar 2.53 chrome driver 2.22 Continuous Integration – Jenkins plugins / Sauce Labs Change Control – Git / Eclipse Che / Docker / Vagrant / Virtual
Machines (VMs)
Framework Update Objectives Complete update to :
Bootstrap, Selenium Grid, Export, Import Remaining Test Cases Production Framework - Logging Integration Framework – Testing Services and Performance Benchmarking
Testing Framework Improvements
Sprint #1Start: Mon 6/6/16 ID: 1Finish: Mon 6/13/16Dur: 1.2 wksRes:
Sprint #2Start: Mon 6/13/16 ID: 2Finish: Mon 6/20/16Dur: 1.2 wksRes:
AnalysisStart: Mon 6/20/16 ID: 3Finish: Mon 6/27/16Dur: 6 daysRes:
DesignStart: Mon 6/27/16 ID: 4Finish: Mon 7/4/16 Dur: 6 days?Res:
CodingStart: Mon 7/4/16 ID: 5Finish: Mon 7/11/16Dur: 6 days?Res:
DeploymentStart: Tue 7/12/16 ID: 7Finish: Tue 7/12/16 Dur: 1 day?Res:
TestStart: Mon 7/11/16 ID: 6Finish: Mon 7/18/16Dur: 6 days?Res:
Deliverables Updated Automated Test Framework Accurate Test Case Development and Reporting Updates to framework libraries and services
Work Breakdown Chart for Update Improvements
Sprint #1 Sprint #2 Analysis Design Coding Test Deployment0 hrs
5 hrs
10 hrs
15 hrs
20 hrs
25 hrs
30 hrs
35 hrs
Work
Training Planning ScheduleStart
Wed 6/15/16FinishWed 8/17/16
Jun 19, '16
Jun 26, '16
Jul 3, '16
Jul 10, '16
Jul 17, '16
Jul 24, '16
Jul 31, '16
Aug 7, '16
Aug 14, '16Stage 1 - Automated Testing
PlanningWed 6/15/16 - Wed 6/29/16 Stage 2 - Training
CommencementMon 6/27/16 - Fri 7/8/16
Stage 3 - Project Implementation and ControlMon 7/11/16 - Thu 7/28/16
Stage 4 - Training Close Out and ConclusionMon 8/1/16 - Wed 8/17/16
Remaining Work and Tasks
6/19/16 7/3/16 7/17/16 7/31/16 8/14/160 hrs
100 hrs
200 hrs
300 hrs
400 hrs
500 hrs
600 hrs
Remaining Cumulative WorkRemaining Cumulative Actual WorkBaseline Remaining Cumulative Work
6/19/16 7/3/16 7/17/16 7/31/16 8/14/160
10
20
30
40
50
60
70
Baseline Remaining Tasks Remaining TasksRemaining Actual Tasks
Success Factors Identify elements that are key to the success of the project, such as:
Increase framework reliability Increase number of test cases automated Complete updates within time lime Reduce effort to update test cases
Quality Management and Performance Benchmarking Quality Management Plan Integrating updates across frameworks Timely updates and email notifications