Transcript
Page 1: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 1

Monthly Status ReportReport due 4/25/00

Schedule statused as of April 7, 2000

Page 2: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 2

Project Status Summary

Technical

Feb Mar Apr

Detailed Description: (for items identified as yellow or red)

Programmatic

Feb Mar Apr

Schedule

Feb Mar Apr

Resources

Feb Mar Apr

•The contract is now in place at SwRI. This is no longer a (big) worry.

•We do not see any problems at this time either technical, schedule, or programmatic. We are still on schedule though the schedule is tight. We have been continuing to use additional personnel (while remaining on our spend plan) to maintain the schedule.

•Latest project photos are available on Aspera-3 web site.

Page 3: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 3

Problem and Concern Summary

P=Problem C=Concern R=Resolved

Description Item Month ID'D Jan Feb Mar AprGet ELS EGSE up and running January C <C RFinish ELS prototype parts for delivery to plating by early Feb. January C RGetting final contract in place by March 1, 2000 (now April 1, 2000) January C C C RFabrication of the IMA MCP holder February <C RAssembly process for ELS w/ Coating March C CDelivery of MCPs for ELS from Burle April CFine alignment of ELS April C

Page 4: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 4

Accomplishments of the Last Month -ELS

• Completed UV coating of the prototype parts. Finished fabrication of the MCP holder for the prototype, flight

and flight spare instrument. Continued bench level compatibility tests between HVPS and

FEE. Continued work on the ELS EGSE completing the cabling,

software and test setup.

• We decided that the current printed circuit boards (HVPS and FEE) that were used for the prototype are suitable for flight. (Note: They were bought with certs. And are in the prcess of being blessed by QA)

• Finished the Dynamic Analysis of the ELS sensor.

• Began drafting test procedures for upcoming prototype testing.

Page 5: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 5

Accomplishments of the Last Month - IMA

• Finished populating the anode board and the digital board.

• Bench tested the IMA electronics to determine the noise floor and sensitivity. Boards look very good!

• Finished the machining of the mechanical parts for IMA prototype, flight and flight spare IMA detector.

• Performed fit check with IMA electronics, MCPs, and mechanical parts. Two mechanical parts needed to be remade / modified. They are now complete.

• Following the bench test and the fit check, we decided that the current printed circuit boards (anode and digital) that were used for the prototype are suitable for flight. (Note: They also were bought with certs.)

• Finished the Dynamic Analysis of the IMA detector.

Page 6: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 6

Accomplishments of the Last Month - IMA (cont.)

• IMA MCPs are in house.

• Continued design and coding of the IMA GSE.

• Designed test set-up and fabricated IMA test Break Out Box.

• Began drafting test procedures that will be used for IMA prototype testing.

Page 7: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 7

Accomplishments of the Last Month - Data Reduction Software

Configured ASPERA-3 Development Computer (phobos.space.swri.edu)

Updated ASPERA-3.org Web Site Documentation Provided Technical Assistance for EPO Web Information Continued Defining and Implementing IDFS Web Tools Provided Support for ELS Characterization Software Held monthly ASPERA-3 Software Status Meeting (April

20, 2000)

Page 8: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 8

Planned Activities for the Next Month - ELS

• Perform fit check of housing, HVPS and FEE when housing is received back from UV coating at Walton Plating. Note: The parts were held up in customs for about a week coming back from England but are now in-house at SwRI as of 4/24/00.

• Finalize cabling for ELS vacuum tests.

• Finalize testing of the Astrid EGSE to use for ELS.

• Decide on course of action regarding ELS alignment (fab in-house, fab out-of-house)

• Continue to monitor status of ELS vs. IMA prototype to determine which one will be ready to go into cal chamber first.

Page 9: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 9

Planned Activities for the Next Month - IMA

• Finish testing the IMA EGSE.• Finish drafting IMA test procedures.

• Continue to monitor status of ELS vs. IMA prototype to determine which one will be ready to go into cal chamber first. It looks like it will be IMA due to lack of MCPs for ELS.

• Begin vacuum testing the IMA detector.

Page 10: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 10

Planned Activities for the Next Month - Data Reduction Software

Tasks

• Release Software Development Plan, Version 1.1

• Deliver Project Data Management Plan, Version 1.0 (by May 5, 2000)

• Baseline ASPERA-3.org Web Site Documentation

• Continue Providing Technical Assistance for EPO Web Information

• Continue Defining and Implementing IDFS Web Tools

• Provide Software Support for ELS Characterization

Page 11: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 11

Problem and Concern Status

Getting final contract in Place by March 1, 2000 (now April 1 2000):

• The contract is now in place. We will now start to get our subcontracts in place with outside vendors (Burle, MSSL) and CoI’s.

Assembly Process for ELS with UV Coated Parts:

• Still a concern. We have received the prototype parts back from Walton Plating and are now developing procedures, processes, jigs etc. to aid in the assembly of ELS.

Page 12: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 12

Problem and Concern Status (cont.)

. Delivery of MCP’s from Burle :

• This is a new concern. The microchannel plates were ordered Dec 5, 1999 with an incentive fee to be awarded if they were delivered within 12 weeks (2/27/00) ARO and a penalty if they were delivered after 15 weeks (3/19/00) ARO. As of 4/11/00 the projected delivery date was 4/28/00, well beyond the penalty date. If we do not receive the prototype plates in early May, we will start to impact our prototype schedule. We are actively tracking this problem and may be visiting Burle in the next couple of weeks to better assess the problem.

Page 13: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 13

Problem and Concern Status (cont.)

Alignment of ELS :

• This is a new concern. We have finally received a quote from an outside machine shop, Hyperfine of Boulder, CO, for manufacture of the ELS deflection plate system to meet the desired tolerance limits. The quote is substantially more expensive than we currently have budgeted and is slightly longer than scheduled. We are currently looking at other options including an optics machine shop at MSFC, in-house fab, other outside shops, and operational workarounds.

Page 14: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 14

Schedule Summary

• Total float on the tasks in the schedule has increased since the last schedule reporting period for two reasons:

– Modifying the flow of flight printed circuit board flow– Adjusting some of the predecessor / successor logic to better reflect the current

build and test plan

• Mechanical activities are the critical path for ELS (28 days float) and electrical interconnects is the critical path for IMA activities (23 days float). As with last month:

– Schedule still has 21 days slack at the end (DEL0050) in addition to float shown for each task

– Most flight activity is serial with prototype activities. We can (will) do activities in parallel to maintain schedule.

• We have modified the schedule to reflect using the “proto” ELS boards for flight. We will update the schedule accordingly for IMA assuming they are bought off by QA for flight..

• Software activities continue to be on schedule. • The full-up schedule is available on the ASPERA-3 Web site.

Page 15: ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused

ASPERA-3

Apr. 25, 00

Monthly Status Report

ASPERA Monthly Status Report Monthly 4_25/ Page 15

J J A S O N D2003

J J A S O N D J F M A M2002

J J A S O N D J F M A M2001

J J A S O N D J F M A M2000

J J A S O N D J F M A M

MAJOR MILESTONES / REVIEWS

Southwest Research Institute Approval: John Scherrer, Project Mgr.

Orig Approval: 6/25/99 Last Change: 8/13/99 Status As Of: 4/21/00

MA1999

INSTRUMENT DEVELOPMENTELS

Rev: None

ASPERAPDR

ASPERACDR ESA LAUNCH

- Electron Spectrometer Imager

MCPs Avail

ELSPDR

Denotes a Change/Slip

MechanicalDesignDetail DesignMechanical FabricationMicrochannel Plates (MCP’s)

MCP ProcurementMCP Characterization

Structural Thermal Model (STM) FabricationSTM Test & Delivery

IRF ELS & IMADelivery to ESA

CDR

KEY

MAJOR MILESTONE

SCHEDULED START

SCHEDULED COMPLETION

EARLY START/COMPLETIONLATE START/COMPLETION

RESERVES

CRITICAL PATH

SUMMARY

STM

STM Delivery

Electrical

HVPS DesignHVPS LayoutHVPS FabricationHVPS Testing

HV Power Supply (HVPS)

Anode Board Design ModificationsAnode PWA LayoutAnode FabricationAnode Testing

Anode Assemby

Sensor Integration & TestSensor Assembly

Sensor Bench TestSensor Testing & Characterization (@ SwRI)

ELS FM/Flt. SpareDelivery to IRF

ELS Calibration (@ IRF) & Delivery to ESAELS FM/FSDelivery toASPERA / ESA

IMA- Ion Mass Analyzer ImagerIMAPDRPrototype Development

IMA Definition

CDR

SwRI ELS FM/FSDelivery

Prototype DesignPrototype LayoutPrototype Fabrication & Testing

Flt. Model / Flt. Spare DevelopmentFM/FS Design ModificationFM/FS LayoutFM/FS Fabrication & AssemblyMCP Need Date MCP’s Req’d

IMA FM/FSDelivery toASPERA / ESA

IMA FM/Flt. SpareDelivery to IRF

SwRI IMA FM/FSDelivery

FM Sensor Characterization (@ SwRI)IMA Calibration (@ IRF) & Delivery to ESA

Processing SoftwareSoftware Concept & RequirementsVirtual Instrument DesignVirtual Instrument S/W CodingVirtual Instrument S/W Testing

S/W Integration w/Sensor Calibration

SwRI ELS & IMADelivery to IRF

Instrument SupportEngineering SupportScience Planning & SupportSoftware Development & Support

IMA FM/FS I&T

FP

F

F

F

P

P

P

FP

F

P

FP

FP

FP

FP

FP

FP

P

FP

F

P PROTOTYPE

F FLIGHT

P

Deliver IMA Prototype

ASPERA-3 PHASE B/C/D MASTER SCHEDULE


Recommended