Page 1: 00-Time Schedule l for Project New (Revised)14!5!2015 as Per Alby

TIME SCHEDULE FOR PROJECTS/# DATE UNIT NO UNIT NAME DURATION TYPE OF WORK TOTAL AREA

1 17/05/2015 UP TO 20/05/2015 SOUTH ROAD 4 DAYS MILLING + ASPHALT1263 M2

1 A 21/05/2015 UP TO 22/05/2015 2 DAYS CURING,PAINTING

2 23/05/2015 UP TO 24/05/2015 NORTH ROAD 2 DAYS MILLING + ASPHALT415 M2

2A 25/05/2015 UP TO 26/05/2015 2 DAYS CURING,PAINTING

3 27/05/2015 UP TO 28/05/2015 10-GH-025 TRUCK EXIT EAST217.80 M2

3 A 29/05/2015 UP TO 31/05/2015 3 DAYS CURING,PAINTING

4 01/06/2015 UP TO 02/06/2015 10-GH-026 TRUCK ENTRANCE EAST425.70 M2

4 A 03/06/2015 UP TO 05/06/2015 3 DAYS CURING,PAINTING

5 06/06/2015 UP TO 07/06/2015 10-GH-003 TRUCK ENTRANCE WEST349.80 M2

5 A 08/06/2015 UP TO 10/06/2015 3 DAYS CURING,PAINTING

6 11/06/2015 UP TO 22/06/2015 00-GLO MIDDLE ROAD5 DAYS MILLING

3383.3 M23 DAYS CLEANING4 DAYS ASPHALT

6 A 23/06/2015 UP TO 24/06/2015 2 DAYS CURING,PAINTING

7 25/06/2015 UP TO 29/06/2015 00-GLO 5 DAYS1000 M2

7 A 30/06/2015 UP TO 01/07/2015 2 DAYS CURING,PAINTING

8 02/07/2015 UP TO 06/07/2015 00-GLO OCR OF TRUCK EXIST WEST749.4 M2

8 A 07/07/2015 UP TO 09/07/2015 00-GLO 3 DAYS CURING,PAINTING

The cost of delay equipmet

Item Equipmet Type Item Equipmet Type Cost/Day SAR

1 Milling machine 6000 6 JCB 1000

2 Asphalt paver 3500 7 Bobcat 1000

3 Tire roller 1000 8 Loader 1000

4 Steel roller 1000 9 Trailer 1000

1 DAY1 DAY

MILLINGASPHALT

1 DAY1 DAY

MILLINGASPHALT

1 DAY1 DAY

MILLINGASPHALT

MIDDLE ROAD RMG RIAL SIDE WAY BETWEEN WATER TRENCH & CURB

REMOVING REPER B.C + COMPACTION ASPHALT

3 DAYS2 DAYS

MILLINGASPHALT

Cost/Day SAR

Page 2: 00-Time Schedule l for Project New (Revised)14!5!2015 as Per Alby

5 MC1 tank 2000

Page 3: 00-Time Schedule l for Project New (Revised)14!5!2015 as Per Alby

TIME SCHEDULE FOR PROJECTNOTS

Equipment IDLE no front work from 21/05/2015 UP TO 22/05/2015

Equipment IDLE no front work from 25/05/2015 UP TO 26/05/2015

Equipment IDLE no front work from 29/05/2015 UP TO 31/05/2015

Equipment IDLE no front work from 03/06/2015 UP TO 05/06/2015

Equipment IDLE no front work from 08/06/2015 UP TO 10/06/2015

Equipment IDLE no front work from 23/06/2015 UP TO 24/06/2015

Equipment IDLE no front work from 30/06/2015 UP TO 01/07/2015