6
You are looking for a solution… WHATEVER THE CONFIGURATION OF YOUR PHOTOVOLTAIC POWER PLANT > 250 kWp we develop EARLY EFFICIENT SYSTEM …You are getting ! 60 90142 - 1 Investor Project Developper EPC Contractor Rectangle Split Spread ECONOMIC EASY EFFICIENT

…You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: …You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

You are looking for a solution…

WHATEVER THE CONFIGURATION OF YOUR PHOTOVOLTAIC POWER PLANT > 250 kWp

we develop

EARLY EFFICIENT SYSTEM

…You are getting !

60 90142 - 1

Investor Project Developper EPC Contractor

Rectangle Split Spread

ECONOMIC EASY EFFICIENT

Page 2: …You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

EASYEFFICIENT

The Early EfÞ cient architecture increases the Internal Rate of Return thanks to:

• Initial cost investment savings of the BoS (civil work, transformation stations, cabling, installation)

• Revenues increase (improved efÞ ciency)

• Operating expenses decrease. (no dedicated maintenance team)

• An increase of the inverter life duration.

EFFICIENTECONOMICECONOMIC

A Set is the smallest brick of the system. It is made of PV modules, a 10 kWp inverters and 3 meters DC cables (4 mm²) to connect a string to the inverter through a DC breaker.

A Block is made of 10 Sets each connected together thanks to 30 meters of 400 V cables up to a 400V protection unit and an Early Solar Transformer (EST) 100 kVA buried transformer (400 V / 6,6 kV).

A Line is a 6,6 kV cables with different sections. It ga-thers the energy from 10 Blocks. It connects buried transformers up to a single transformation station. In the station, are 6,6 kV Mega Solar Protection Unit (MSPU) & 20 kV protections and a heading transfor-mer 6,6 kV / 20 kV.

Plug & Play a 10 MWp power plant

Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever the plant power, only one single transformation station is needed.No costly trenches for 20 kV cables but basic 6,6 kV cables underground installation. Power Line Communication can be a reliable and inex-pensive solution.

The products are evenly distributed in a 10 MWp power plant

EFFICIENT

EFFICIENT

EASYECONOMIC

EASY

Inverters

Buried Transformers

6,6kV tranches

Pits

e

10 kWp Set

10 Sets = 100 kWp Block

10 Blocks = 1MWp Line

10 Lines = 10 MWp Power Plant

Page 3: …You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

ECONOMIC

A versatile architecture

30 m of 5x400V 10m m

Buried transformer 100 kVA 400V / 6,6kV

10 kWp inverter

3 m 1000 V DC cable

Few kilometers of 6,6kV cables 1 single station

Thanks to the 6,6 kV energy transport and its reduced current, the total cable length is reduced as well as the cable sections. It allows easy power plant construction for :• stretched Þ elds (along roads, …)• Þ elds on a slope• split Þ elds

This very innovative energy distribution system for a photovoltaic power plant with medium voltage of 6.6 kV aims to increase the voltage as Early as possible, decreasing the current and therefore the cable losses, to be as EfÞ cient as possible. Thanks to its unique architecture, the efÞ ciency is not very sensitive to the Þ eld pattern.In addition, it reduces mismatch losses and there is no consumption for inverter watchdogs, air vent, and air conditioning.

EASY ECONOMICCONOMIC

EFFICIENT

EFFICIENT

EASY

EASY EFFICIENT

Page 4: …You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

Decrease the CAPEX - Thanks to the reliable and inexpensive technology to transport the power at 6.6 kV, the

Early EfÞ cient system saves the over costs of the 20 kV lines: deeper trenches, metal

shields. There are no DC cables to bury and most of the 400 VAC cables are installed

in the solar mounting system. The trenches and cables lengths are shorter. The cables

sections are much smaller and need less raw materials. Therefore, the cables costs are

cheaper as their installations because the turrets / reels can be either smaller or getting

a longer cable length.

- The Early EfÞ cient system reduces drastically the cost of the transformation stations as

most of the transformers are buried in the ground.

- This system allows to consider inexpensive Þ elds (split, stretch, slope) and to increase the plot Þ lling ratio

while its efÞ ciency is not sensitive to Þ eld pattern thanks to its unique architecture .

- The Power Line Communication system avoid the costs of the wires for communication and their installation

while the reliability is as good as by wires and much better than radio communications.

Increase the Revenues

- The Early EfÞ cient system increases the efÞ ciency as it reduces the cable and the mismatch losses. There is

no consumption for inverter watchdogs, air vent, and air conditioning.

- Thanks to the electrical architecture, only small segments are affected in case of few faulty equipments

remaining the rest of the production available.

Reduce the OPEX - Smart power plant monitoring aims to propose no dedicated maintenance team in the

power plants. A subcontractor, within 50 kms, could operate the maintenance.

The monitoring alert system sends a SMS / Email to the maintenance staff. This one

goes on a website to locate the faulty equipment and to evaluate the consequences.

According to the diagnosis, the electrician goes to the power plant to either clean, check,

repair or change the material.

- Thanks to On the shelve equipments, times for changes are quick and the inventories

linked to the equipments in warehouse are narrowed.

Improve the life time and the reliability - All the equipments are highly maintainable as the wearing components can be changed.

- The Mega Solar Protection Units allow to disconnect all the inverters during the night even their watchdogs.

Therefore all the capacitors (weakest component within an inverter) life times are saved.

- Even if this system looks very innovative to transport the energy in a photovoltaic power plant, the 6,6 kV is a

basic standard used for many decades in public lighting while the Power Carrier Communication is common

to communicate with reliability along numerous kilometers of cables to supply airport runaway lighting or in

public lighting.

ECONOMIC

CONOMIC

The Early EfÞ cient system aims toEFFICIENT

EFFICIENT

EASY

EASY

Page 5: …You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

AUGIER product offer

Power Line

Communication

MonitoringLow Voltage Switch Board

DC

AC

DC

AC

DC

AC

All products communi-cate thanks to Power Line Communication from and up to the delivery station through and up to several kilometers of cables.

Power Line

Communication

In the delivery station, protect and supply- lighting, electrical plugs- web logger, Power Line

Communication master- Mega Solar Protection

Unit

Buried in a pit within the trench,- watertight and operates in wet conditions- integrates inner electrical protection on top- 3 efÞ ciency classes:

Premium: 99,2% EU for 100 kVA Optimum: 98,5% EU for 100 kVA Medium: 98% EU for 100 kVA

- exists in 10, 16, 32, 50, 63, 100, 125, 160 kVA- 30 years life time- Warranty: 15, 20, 25 years

Early Solar Transformer

In the delivery station to protect 6,6 kV cables- electrical protection (homopolar, breaker, fuse)- ease the maintenance- increase the inverter s life times- lightning protection (option)Either for 2 or 3 MW

Mega Solar Protection Unit

Set on the ground and close to the Early Solar Transformer, it is an outdoor watertight cabinet to:- protect the 400 V cables with fuses (option breakers)- lightning protection- ease the maintenance- in option and in case of use of inverters with no power line

communication abilities, a Power Line Communication Slave is integrated in the Solar Protection Unit

Solar Protection Unit

ESCI is set on the solar mounting system- 10 kWp Triphase, Transformer-less,- 1000 Vdc, 5x400 Vac, neutral rating TN,- 97,4% EU, 97,8% CEC, 98,1% max- Adjustable power factor up to 0,8 cos ϕ

- IP 55 & corrosion protection thanks to special coating.

- Highly maintainable thanks to wearing components: DC bus capacitors, power semi-conductors, varistors, fans, seal & hood.

- Warranty : 5, 10, 15, or 20 years- Option lightning arrestors DC & AC- CertiÞ ed VDE 126-1- Bankable

ESCI communicates with :- the Monitoring: Power Line Communication,

RS485, (option Ethernet)- the maintenance staff: Bluetooth and USB

for tablet or laptop connection

Early Solar Communicative Inverter

Maintenance - alert- locate- identify- fault list

Production- supervise- power factor

control

Page 6: …You are getting - Augier energy · Plug & Play a 10 MWp power plant Energy transport is at 6,6 kV as Early as possible. It improves the plot Þ lling ratio. From 250 kWp and whatever

AUGIER® SA Tél +33 (0) 492 086 200

ZI CARROS 1ère avenue 2243 m Fax +33 (0) 493 290 140

BP 131 • 06513 CARROS Cedex [email protected]

FRANCE www.augier.com

A W O R L D O F E N E R G Y U N D E R C O N T R O L

U N M O N D E D ’ É N E R G I E M A Î T R I S É E

No

n c

on

tra

ctu

al p

ictu

res -

Te

ch

nic

al sp

ec

ific

ati

on

s s

ub

jec

t to

ch

an

ge

wit

ho

ut

no

tic

e

AGC

on

se

il +

33

(0

) 4

97

19

1 1

50

- F

oto

lia

- F

oto

se

arc

h -

Sto

cklib

MORE THAN 55 YEARS OF EXPERIENCE

IN TRANSPORTATION, CONVERSION AND ENERGY MANAGEMENT

SOME REFERENCES…

EUROPA France Highways, expressways, ring roads, Eurotunnel, railways, High speed rail line (TGV)

Charles de Gaulle, Nice, Marseille, Lyon, Toulouse airports

Ile de la Réunion (Routes des Tamarins)…

Italy Highway Valdastico A41, Roma Fiumicino airport

Portugal Taje bridge, Montijo airbase

Turkey Istanbul, Ankara, Antalya airports

AFRICA Algeria El Merk oil & gas field, Oum el bouaghi airbase, Oran harbour

Equatorial Guinea City of Malabo, Mongomeyen airport

Nigeria City of Benin, Lagos – Port Harcourt airports

Senegal NDiass highway – Dakar airport

MIDDLE EAST UAE Fujairah fencing – Mafraq highway 78 km

KSA Training center, Janadria resort, Arar – Riyadh airbases

Iran Tehran + 25 domestic airports

ASIA China Bridges on Yang Tse river, Hong Kong and Guangzhou airports

Malaysia Kuala Lumpur highway, a lot of airports

Indonesia Djakarta airport

AUSTRALIA Sydney – Darwin – Melbourne