Year End Technical Stop DT work Mu Barrel Workshop 13 October 2011 A. Benvenuti (INFN Bologna)

Year End Technical Stop DT work

  • Upload
    edison

  • View
    41

  • Download
    0

Embed Size (px)

DESCRIPTION

Year End Technical Stop DT work. Mu Barrel Workshop 13 October 2011 A. Benvenuti (INFN Bologna). Year End Technical STOP. - PowerPoint PPT Presentation

Citation preview

Page 1: Year End Technical Stop DT work

Year End Technical Stop DT work

Mu Barrel Workshop13 October 2011

A. Benvenuti (INFN Bologna)

Page 2: Year End Technical Stop DT work

Year End Technical STOP• Technical coordination “Retreat” in Divonne on September 28-29 to

assess opportunity/necessity of opening the detector: https://indico.cern.ch/conferenceDisplay.py?confId=156000

• Main driver being access to Tracker for studying the humidity control, in view of operating at low temperature, - 20C after LS1

Not cost effective within a 13 weeks YETS; additional 4 weeks needed.

Not ruled out since LHC plans not yet final (Thermal amplifier tests..) but unlikely unless start of LS1, 17 November 2012, also shifts

Not very interesting for DT work since, at best, only limited access would be possible to wheels

Page 3: Year End Technical Stop DT work

Nicola Bacchetta

Page 4: Year End Technical Stop DT work

Year End Technical STOPProvisional Schedule

• 7/12 @ 18:00 Beam OFF (year end calibrations)• 8/12 @ 08:00 Magnet Ramp Down (DT shutdown )• 8/12 @ 14:00 Water Cooling Maintenance • 12/12 AUG tests UXC closed• 13/12 CASTOR Removal Test• 21/12 HF on the floor• 09/01 Cooling is back• 06/02 Skeleton Shift crew 24/7• 08/02 first MWGR• 23/02 Magnet Ramp to full field (Cosmics data taking)• 07/03 Beams back in LHC + 3 weeks commissioning with beams

Page 5: Year End Technical Stop DT work

HV Problems Summary

Compared to 9 chambers with HV problems and 132 channels lost at the end of 2010 (YB-2 MB4 S07 is intermittent, not included in 2010 statistics) September 28 2011

Page 6: Year End Technical Stop DT work

A Snapshot of DT and RPC (Barrel) Maintenance Work (as of today)

SUMMARY

Gianni Masetti: DT dead channels grand total = 1050 (0.6%)

• Only work requiring access to the detector is entered in the table

• Only RPC maintenance that requires moving the chambers is included

September 28 2011

Page 7: Year End Technical Stop DT work

7

1

42

356789 10 11

12

1

42

356789 10 11

12

1

42

356789 10 11

12

1

42

356789 10 11

12

1

42

356789 10 11

12DT HV Phi

+2 +1

0

-2 -1DT HV ThetaRPC ExtractRPC Replace

Problems in DT or RPC

Requires uncabling

Page 8: Year End Technical Stop DT work

Can DTs Benefit from Opening the Detector ?

It depends for how long and how far:1) Opening up to YB±2 allows access to the MiniCrates and

inspection of cooling and gas connections2) Opening up to YB±1 allows HV repairs on Phi SL of two

chambers in YB-2 and one in YB+2 plus maintenance of YB±13) Opening up to YB±1 allows also access to HO RBX in the

movable wheels. However, for YB±1 this requires removing DT gas and cooling lines from MB1.

4) Chamber extraction out of the iron pockets is not feasible in any “normal” scenario for the end of the year TS

Page 9: Year End Technical Stop DT work

Caveats• Opening and closing the detector are delicate operations that

might damage some components. • The risks must be weighted against the gains from the possible

fixes.• Each DT intervention requires time consuming tests with

cosmics data taking that are possible only when the general infrastructures (power, cooling, gas and DAQ) are operational

• The wheels cannot be closed until the tests are successfully completed

For the DTs, the balance is not in favor of opening the detector

Page 10: Year End Technical Stop DT work

DT Off Detector Maintenance: LV Connectors

• Melted connector found on 28/ 10/ 2009• Weak point identified in the poor match of

cable (Powerclaw) and CAEN supply connectors (PP75) exacerbated by rigid cables

• All jumper cables and connectors were replaced using very flexible cable in the 2009 -10 Technical Stop

• Monitoring of temperatures and Vdrops was extended considerably

• Still several problems in 2010 and 2011• Major cause of UXC access requests for DT

The way it should be

Page 11: Year End Technical Stop DT work

A Radical Solution“Pigtails” with AP connectors soldered on the LV modules4 modules have been modified and are in use since the July TS

Some numbers:• 26 A3050 and 2 A3100/ wheel • 112 pigtails/wheel • 1 – 1.5 hours/ module• Modules test : 8-12/day 1 Wheel/ week

• All pigtails should be ready before starting• 2 Soldering stations• Soldering procedures and trained

personnel (developed by M. Pegoraro)• Best place is in S1 (proximity to detector) Decision on the modules to modify, types

and quantity, by November at latest

Page 12: Year End Technical Stop DT work

LV Pigtails (continued)• Last Friday, Cristina presented the plan and requests for this

intervention during the TC meeting• Well received, HCAL interested in applying this solution• Space identified in area between S1 and elevator => OK• Draft of “Procedures Agreement” prepared by Cristina Critical items:

Test system(s) (Daniele F.)Components: cable, connectors, PENETROX (3 bottles from

MJ)…DerogationsPigtails preparation ( 26 A3050, 2 A3100, 8MAO/YB) = 720

pigtails in total (5 wheels) plus sparesDecouple RP clearance from intervention

• Logistics (moving in and out the modules), dressing cables in tower racks and testing afterwards is a very demanding task

Manpower requirements: 2 +1 technicians for soldering, 1+1 for moving and cabling

Total of 4-5 Technicians for 5 weeks + physicists for testing

Page 13: Year End Technical Stop DT work

LV Connectors (The Challenge)

• Define pigtails lengths and strain relief during next TS

• Identify equipment and procedures for moving modules

• MAO extraction and transportation is a major challenge (pain)

130 A3050, 10 A3100, 40 MAO

Page 14: Year End Technical Stop DT work

YETS 2011 (In Addition)• Check A3009 connections (Hotspots and currents to be done during

next TS, magnet OFF, not enough time before YETS power off) • Improve TJB noise shielding (present aluminum foil and aluminum

tape turkey wrap is not viable for the long run)• Insert new TJBs and check persistence of HV problems • Gas system maintenance/improvements to be agreed with Roberto

Guida:- Calibrate ~ 10 flow-meters- Replace humidity analysis system in four wheels- Install and commission the “inline gas chromatograph”- Isolate the VDC lines from the O2 reference gas - Determine time required to clear out gas in VDC during

analysis cycle (now set to 1 hour)• Some minor VDC interventions: new gas line connections, VDCs

intercalibration, improved air tightness by adding a VDC “hood” AOB, depending on what happens between now and 06 December

Page 15: Year End Technical Stop DT work

• First measurement after the “reference gas” point is out of norm for all VDC.

• Effect disappears if measurement time is increased to ~4 hours

• Measurements for YB±1 have ~ factor 2 larger errors

Daniel is investigating the cause

Page 16: Year End Technical Stop DT work

Summary

• The LV supplies modification is the main activity for this YETS• All pigtails must be ready before January 16 for the intervention to

succeed The intervention can proceed in stages: modify all MAO, all A3100

(SC), all A3050 in a wheel in order to minimize the risks• In case the detector will be opened we can take the opportunity to

fix the know MC problems in YB±2 and inspect gas and water connections.

• This would not interfere with the other DT planned activities But of course, plans can change…….

Page 17: Year End Technical Stop DT work

Backup

Page 18: Year End Technical Stop DT work

Extraction tool mounted on MB2S09. Similar position as needed for YB0 MB3S06 and MB2S09. The SL cover to open is located in the upper part of the chamber for MB2S09 and in the bottom part for MB3S06.

Page 19: Year End Technical Stop DT work

Interventions on top sectors are done with heavy equipment above the beampipe

Page 20: Year End Technical Stop DT work
Page 21: Year End Technical Stop DT work

1) Remove MABs: S03/S04, S01/S02 and S05/S06 (Maf + alignment team)

2) Remove covers from radial cable trays3) Remove Thermal Shields from Vacuum Tank

to access ECAL LV Patch Panels, 2 TS/sector4) Disconnect ECAL LV Cables ( 98 ) from PP on

VT 5) Pull cables to Sector periphery and secure on

cable trays ( 2 persons on scissor lift + 1 person on periphery)

6) Mount platforms on VT, where needed7) Remove ECAL radial cable trays 8) Disconnect, pull-out and secure the optical

fibers (DT technicians) 9) Disconnect DT and RPC cables ( DT+RPC tecs)10) Pull cables to the periphery and secure them11) Disconnect Gas and cooling (DT+RPC techs)

Z0+ Cables Removal

Platforms are not needed for the cables removal in S06.The extraction tool can be mounted with a scissor liftThe HV repair can be carried out from the scissor lift