WS Infrastructure Programme
Quarterly WorkshopNorthern Cape
Presented by: K.I. KgaraneRBIG Manager: WSS Directorate
Date: 31 – 01 October 2013
Sub-Title here (if needed)PRESENTATION TITLE HERE (if needed)
ContentsA: Expenditure Status 2013/14
1. RBIG 2. MWIG3. ACIP4. NTP
B: Key Challenges
C: Project to be “Fast Track”
D: Projects to be Launched
E: Way forward
A1. RBIG : Expenditure 2013/14 Scheme Total Project Cost
DWA CommitAllocation 2013/14 BAS Exp Oct 13/14 Invoice inhand
Planned Exp Oct 2013/14
Proposed Budget Reallocation
Reason for Reallocation
Status
Bulk water supply to Porth Nolloth
22 600 000 3 000 000 0 0 0 0Still to finalise IRS. Not able to Co-fund, apply for 100% funding.
Prelim Design
Replacement of Namakwa Bulk Water Supply
564 000 000 125 200 000 153 814 741 0113 168 739
156 540 705 Construction
Oranje river - Colesberg Bulk Water Supply
142 296 000 35 352 559 18 898 819 014 169 986
35 388 688 Construction
Noupoort Bulk Water Supply
51 276 000 8 000 000 6 774 418 01 646 421
8 000 000Delay in finalizing of the design.
Design / Tender
De Aar Borehole Development
33 240 000 1 000 000 0 0 0 0
secure co-funding. Agreement with land owners where boreholes are located
Design (On hold)
Thembelihle Bulk Water Supply
25 100 407 2 748 282 1 015 794 1 358 3161 377 993
2 748 282 Construction
Strydenburg Groundwater Project
13 110 000 3 399 594 0 0 0 0Still awaiting coucil resolution on co- funding.
IRS
Niekerkshoop Bulk Water Supply
11 097 364 8 283 633 3 847 895 181 3133 859 788
6 283 633Expected savings on the civil works.
Construction
Vaal Gamagara Groundwater Resource Development
To be finalised 31 500 000 14 181 901 908 628
12 230 279
28 000 000 IRS & Borehole Development
Homewale Waste Water Treatment Works
78 000 000 15 600 000 15 616 928 015 000 000
15 616 928 Construction
Heuningvlei / Moshaweng Bulk Water Supply
113 980 000 52 187 847 35 663 338 2 600 26131 362 480
52 187 847 Construction
Kuruman Bulk Water Supply
37 000 000 15 400 000 1 660 333 0
2 000 000
5 000 000
Delay in the procurement and finalisation of the project documents.
Construction
Kathu Waste Water Treatment Works
29 000 000 628 085 594 284 0594 284
628 085 Construction
Sub Total 1 120 699 771 302 300 000 251 336 573 5 048 518 195 409 970 310 394 167
A1. RBIG : Expenditure 2013/14 Scheme
Total Project Cost DWA Commit
Allocation 2013/14 BAS Exp Oct 13/14 Invoice inhandPlanned Exp Oct
2013/14Proposed Budget
ReallocationReason for
ReallocationStatus
Bulk Water Supply to Brandvlei
600 000 600 000 Feasibility
Loeriesfontein BWS 900 000 1 250 000 Feasibility
Williston BWS 900 000 900 000 Feasibility
Kalahari East to mier pipeline
800 000 450 000Municipality administration
Feasibility
Pixley ka Seme BWS FS: Marydale R1,2; Norvalspont R400 and Vanderkloof WWTW R300
1 900 000 220 699 333 348 1 900 000 Feasibility
Van Wyksvlei Groundwater
900 000 900 000 IRS
Kakamas WWTW 700 000 700 000 Feasibility
Windsorton to Holpan Bulk Water Supply
200 000 200 000 Feasibility
Warrenton WTW 400 000 400 000 Feasibility
Kathu Bulk Water Supply 600 000 498 483 600 000 Feasibility
RRU 1 000 000 926 905 1 000 000
Goods and services 200 000 76 818 200 000
Sub Total 0 9 100 000 1 722 905 36 694 0 9 100 000
Total1 296 955
607311 400 000 253 059 479 5 418 560 195 409 970 322 994 167
A2. MWIG: Expenditure 2013/14Scheme nr. and Project
Name
Project Cost DWA Commitme
nt
Budget Allocation
2013/14
BAS Expenditur
e 30 Sept 2013 (Transfer 7
August 2013)
Expenditure Reported
by IA
Second Transfe
r amount 25 Oct 2013
Proposed additional Budget 2013/14
Reason for additional funding
Implementation/
Construction Progre
ss
ZNC031 Drieloop
6 980 488.66 6 980 488.66 3 490 000.00 2 632 012.54 R3,546 m 38%
ZNC035 Gadiboe
6 539 000.00 55 120.00 0.00 0.00 6 483 488.66 Contractor on site and can complete the project IF additional funds is available
ZNC105 Ga-Ruele
6 952 772.06 1 871 811.00 1 771 500.00 562 307.00 5 080 961.06 Contractor on site and can complete the project IF additional funds is available
8%
ZNC106 Gaseboloa
5 168 138.56 1 671 188 .00 1 771 500.00 564 005.00 3 496 950.56 Contractor on site and can complete the project IF additional funds is available
11%
ZNC001 Olifantshoek
5 792 000.00 5 792 000.00 2 896 000.00 3 758 324.54 R2,896 m 0.00 10%
Total 16 371 000.00 9 929 000.00 R6,442 m 15 061 400.2
A3. ACIP : Expenditure 2013/14 Scheme
Project Cost DWA
Commitment
Budget Allocation
2013/14
BAS Expenditure 31 July 2013
Invoices at Hand
Planned Cash Flow end
September 2013
Proposed Budget
Reallocations 2013/14
Reason for Re-allocation/ Movement
Implementation/ Construction
Progress
WWIR Nama Khoi: Refurbishment of Wastewater Treatment Works and Pump station 1 700 000 1 700 000 1 186 969.42 0 1 200 000 None None
70% Construction stage.
Gamagara: Upgrading of Sewer Pump stations 2 000 000 2 000 000 1 533 166.92 600 000 None None
77%Construction stage
Richtersveld: Upgrading/Refurbishment of sewerage pump stations 2 000 000
1 000 000 (Revised) 0 0 0 None (2 000 000)
Delayed start of the project due to
procurement challenges.
15%Construction stage.
Siyancuma: Upgrading/Refurbishment of Douglas Wastewater Treatment Works 5 300 000
1 200 000 (Revised) 0 346 910.44 0 None (2 000 000)
Delayed start of the project due to
procurement challenges.
21%Construction stage.
Thembelihle: Wastewater Treatment Works Refurbishment 800 000 800 000 4 677.75 100 186.52 250 000 None None
34%Construction stage
Regional Support: Blue & Green Drop Support.
1 600 000 1 600 000 0 570 000 200 000 None None
36%, Progressing well, and
scheduled for completion in
December 2013.Hantam: Waste Water Refurbishment 10 000 000 10 000 000 2 779 585.41 0 0
None (Advanced 4 700 000)
Progress good, and to save
escalation costs)36% Construction
stage
TOTAL 23 400 000 18 300 000 3 971 232.58 2 550 263.88 2 250 000 0 None 36%
A4: NTP – Expenditure 2013/14 Scheme nr. and Project
Name
Project Cost DWA Commitme
nt
Budget Allocation
2013/14
BAS Expenditur
e 30 Sept 2013 (Transfer 7
August 2013)
Expenditure Reported
by IA
Second Transfer
amount 25 Oct 2013
Proposed additional Budget 2013/14
Reason for additional funding
Implementation/
Construction
Progress
Pampierstad BW
(Phokwane)R15,000 R10,000 R8,000
R2,750 (Actual R6,361,482 -
63%) R2,000 + R5,000
Project could be completed by end of Dec
2013 73%
Kudumane RWS
(Joe Morolong)R8,000 R8,000 R4,000
R2,200 (Actual R1,004,
888 – 12%) R4,000 R- 21%
Kudumane RWS
Rudimentary
Crisis RWS Goudveld
(Ga-Segonyana)
R8,000 R6,500 R3,500R1,787(Actual R
1,043,789 – 16%)
R3,000 R- 7%
Vaal-Gamagara
R4,900 R4,900 R1,524 R2,388
Actual R1,524 (31%)
N/A R- 10%
Total R29,400 R17,024 R9,000 R5,000
B: Key Challenges• Municipality do not adhere to their commitments
– (Project Co-funding , utilise MIG for Co-funding.)– (Request for 100% funding)
(MWIG) • Lack of funding to implement and complete projects• Unit cost very high in low density communities• Rural area’s and HH are not planned according to normal Town Planning
Guidelines • (ACIP):
– Delays in procurement of service providers– Impact of BAS version 4– Funding shortfalls (partial allocations)(NT)
• Disagreement between WSA and WSP on important issues, delay project implementation.
C: Project to be “Fast Track”MWIG: •ZNC 035: Gadiboe•ZNC 105: Ga- Ruele•ZNC 106: GaseboloaNT:• PampierStad BWS Phokwane
D: Projects to be LaunchedCode Scheme
District Municipality
Local Municipality
Phase/ section StatusCompletion
date
Revised completion
date
NCR010Oranje river - Colesberg Bulk Water Supply
Pixley ka Seme UmsobomvuColesburg WWTW
Complete Feb-13
NCR010Oranje river - Colesberg Bulk Water Supply
Pixley ka Seme UmsobomvuColesburg BWS
Construction Oct-13 Apr-14
NCR014Thembelihle bulk water supply
Pixley ka Seme ThembelihleHopetown WTW
Construction Oct-13Jan-14
NCR022Niekerkshoop Bulk Water Supply
Pixley ka Seme SiyathembaNiekershoop BWS
Construction Mar-14
NCR019
Kathu Waste Water Treatment Works
John Taolo Gaetsewe
Gamagara Kathu WWTW Construction Oct-13
Jan-14
ZNC031 DrieloopJohn Taolo Gaetsewe
Joe - Morolong
Construction Jan -14
ZNC001 OlifantshoekJohn Taolo Gaetsewe
Gamagara Construction Mar- 14
Way forward
• MIG cannot be used to co-fund RBIG funded projects.
• Assist AI secure external funding to projects.• Engagement meeting with the IA and their
services providers• 100% allocation for ACIP, (over MTEF where
necessary).