WS Infrastructure Programme
Quarterly WorkshopGAUTENG REGION
Presented by: Jabulani MalulekeRBIG Project Manager: Date: 31 – 01 October 2013
WS Infrastructure Programme: Quarterly Workshop
Contents
A: Expenditure Status 2013/14
1. RBIG 2. MWIG3. ACIP4. NTP
B: Key Challenges
C: Feedback on letter sent on 9 September 2013 regarding RBIG/ACIP Programme management developments and requirements.
D: Project to be “Fast Track”
E: Projects to be Launched
F: Way forward
A1. RBIG : Expenditure 2013/14
Scheme Project Cost DWA Commitme
nt
Budget Allocation
2013/14
BAS Expenditure 31 Sept
2013
Invoices at Hand
Planned Cash Flow end Sept
2013
Proposed Budget
Reallocations
2013/14
Reason for Re-
allocation/ Movement
Implementation/
Construction Progress
Westonaria (HVN wwtw)
R 275 m R 65 m R 19,9 m R 11.84 m
R 35 m R 80 m +R 15 m Construction
Westonaria (ZBK wwtw)
R 346 m R 6 m R 6 m Planning
WHV R 486 m R 70 m R 28,5 m R 10 m R 34.7 m R 70 m Construction
SRSS (Sebokeng)
R 1,2 bn R 70 m R 0.31 m
R 2.5 m R 65 m -R 15 m Construction/ Demolition
SRSS (Meyerton)
R 256 m R10 m R 10 m EIA
Total R 221 m R 48.4 m R 22.15 m
0 R 221 m
0
A3. ACIP : Expenditure 2013/14 Scheme Project Cost
DWA Commitment
000
Budget Allocation
2013/14000
BAS Expenditure 31 Sept 2013
000
Invoices at Hand000
Proposed Budget
Reallocations 2013/14
000
Reason for Re-allocation/
Movement
Implementation/
Construction Progress
Illegal water use within the Vaal river system
R 23 255 R 3 000 R 2 115 0 0 N/A Implementation
Ekurhuleni WCWDM
R 10 000 R 9 550 R 478 R 675 0 N/A Implementation
Total R 33 255 R12 550 R 2 593 R 675 0
A4: NTP – Expenditure 2013/14 • To date we have spent R 37 260 543 at Ekangala
WWTW. • 2013/14 budget is R 14 000 000 (schedule 5)
R 10 000 000 has been transferred by now and the remainder will be transferred in the last quarter of our financial year.
• Schedule 6 – R 300 000
Fund are committed for the decommissioning of the Ekangala ponds. Environmental aspects such as EMP & Deregistration of the ponds with DWA will be done by the appointed consultant.
B: Key Challenges• Court order interdicting against the second phase of SRSS implementation • Delays to issue EIA approvals – (Meyerton WWTW upgrade)• Delays to appoint contractors – delayed programme (Westonaria, HVN)• Co-funding – delayed implementation (Westonaria, Zuurbekom)• Political influences – (SRSS, Emfuleni/ Midvaal LM)• Lack of RBIG funding for deteriorating bulk infrastructure in Metros(CoT &
CoJ)• Lack of commitment on O&M (Westonaria LM)• Bulk water supply schemes with no Water Utility (Western Highveld Scheme)
B: Key Challenges(ACIP&NT)
ACIP PROJECTS• Involvement of councillors in appointment of SMME in the
project.• IA submitting the invoices that are not talking to what has
been done or report submitted not talking to the invoice.
Transfers• Eskom application - The municipality has paid commitment
fees but Eskom delaying in giving a way forward with regard to design & quotes for installation of power lines to the plant.
• WULA – Mpumalanga office to avail themselves in guiding CoT with the application as the catchment is theirs.
• Strikes in Ekangala (Region 7 of CoT) – site was closed for 2 days last month.
C: Feedback on letter sent on 9 September 2013
D: Project to be “Fast Tracked”
• Westonaria Scheme, both Hannes van Niekerk and Zuurbekom : unlock economic activity and service delivery (housing)
• SRSS, Sebokeng WWTW upgrade : relieve the Vaal system of sewage inflows and improve service delivery (Sanitation)
E: Projects to be Launched
• Westonaria, Hannes van Niekerk – Fourth quarter of financial year 2013/14)
• Ekangala WWTW upgrade – Fourth Quarter of Financial year 2013/14)
F: Way forward
• Approval for funding (RBIG) to continue with Phase II, Westonaria Scheme – Zuurbekom WWTW construction
• RBIG Policy re-consideration to fund Metro bulk infrastructure – probably more stricter conditions for Metros
• MMC Infrastructure (Ekurhuleni Metro) will be meeting the councilors to clear the issues delaying progress on the continuation of WCWD project.