WPEG Petition Filed

Embed Size (px)

Citation preview

  • 8/8/2019 WPEG Petition Filed

    1/23

  • 8/8/2019 WPEG Petition Filed

    2/23

    PLANNING BOARD OF THE TOWN OF CAPE VINCENT (planning

    board or board).

    2. The approvals lack substantial support in the record of the board's review

    in this matter because the board ignored the findings and opinions of its

    own engineering and acoustic consultants regarding the noise that would be

    expected from the project, and Wind Power Ethics Group's (WPEG's)

    acoustic consultant, and instead the board elected to rely on SLW's findings

    and opinions regarding noise impacts.

    3. The board's and WPEG's acoustic consultants both rejected not only

    SLW's findings, but found that SLW's noise assessment is based on

    methods not approved in acoustics.

    4. Although two members of the planning board abstained from voting on

    the board's environmental findings due to conflicts of interest, up to the

    time of the vote these two members were actively involved in the board's

    discussion of the SLW project.

    5. Although three members of the board voted to approve the findings, one

    or more of these three had and have direct or indirect material interests in

    the SLW project.

    6. The planning board was obligated to but did not coordinate their

    environmental impact review with other involved agencies, including the

  • 8/8/2019 WPEG Petition Filed

    3/23

    Town of Lyme planning board, thereby hindering involved agencies' ability

    to develop their own findings. See 6 N.Y.C.R.R. 617.2(s).

    7. Notwithstanding that the planning board was provided with credible

    scientific information showing significant impacts of SLW's project would

    remain, even after a lengthy environmental impact review, the board

    disregarded its obligation to avoid or mitigate serious impacts because

    doing so would make it too difficult to induce a developer to build a wind

    farm. Under these conditions, the Court should find the majority of the

    board was biased and unwilling to take a hard look at potential adverse

    impacts of its action.

    II. PARTIES

    8. Petitioner-Plaintiff WIND POWER ETHICS GROUP is an

    unincorporated association of Cape Vincent and Lyme landowners

    dedicated to protecting the rural amenities and environment of the area. The

    association and its members have participated vigorously in the town

    boards review of the SLW project, more so than most residents of the

    town.

    9. All or most members of WPEG own land in relatively close proximity to

    the SLW project area and therefore would be harmed by the approvals

  • 8/8/2019 WPEG Petition Filed

    4/23

    challenged here, differently than the general public.

    10. Respondent-Defendant PLANNING BOARD is a municipal agency with

    responsibility for permitting certain land uses in the Town of Cape Vincent,

    and is lead agency for review of the SLW project pursuant to the State

    Environmental Quality Review Act, N.Y. Envtl. Conserv. L. 8-0101 et

    seq. (SEQRA), and its implementing regulations.

    11. Respondents-Defendants RICHARD EDSALL, TOM RIENBECK,

    GEORGE MINGLE, ANDREW BINSLEY, and KAREN BOURCY were

    planning board members throughout 2010, including at the time of the

    actions complained of here, and are current planning board members.

    12. Respondent ST. LAWRENCE WINDPOWER, LLC is a corporation

    authorized to do business in New York with offices at 122 South Point

    Street in the Town of Cape Vincent, New York. SLW is a subsidiary of

    Acciona Energy North America.

    13. SLW is a necessary party in this matter because it is its proposed project

    that is the subject of the approvals challenged here.

    III. VENUE

    14. Venue is properly located in Jefferson County pursuant to CPLR 506(b)

    as the county in which the Respondent planning board made the decisions

    complained of here.

  • 8/8/2019 WPEG Petition Filed

    5/23

    IV. EXHAUSTION OF ADMINISTRATIVE REMEDIES

    15. In January 2007 the planning board scheduled a formal public comment

    period on a Draft EIS (DEIS) prepared by SLW for the SLW project

    proposal.

    16. On March 25, 2009 the board scheduled a public comment period on a

    Draft Supplemental EIS (DSEIS) it directed SLW to prepare, inviting

    public comments until May 30, 2009.

    17. Several supplemental reports and documentation were provided by SLW

    after the public comment period on the DEIS and the DSEIS, and these

    were incorporated into a proposed Final EIS (FEIS) prepared by SLW for

    the board's approval and adoption.

    18. WPEG and its members, together with involved and interested agencies

    and other members of the public submitted written comments and

    supporting documentation on the DEIS, SDEIS, and proposed FEIS,

    asserting a number of significant potential adverse impacts would result

    from the project as proposed.

    19. On September 15, 2010 the board approved and adopted a Findings

    Statement supporting its approval of the proposed FEIS pursuant to

    SEQRA, and approved and adopted the FEIS as the board's basis for its

    findings.

  • 8/8/2019 WPEG Petition Filed

    6/23

    20. The board's September 15, 2010 findings were filed with the town clerk

    on September 29, 2010.

    21. The board's September 15, 2010 findings conclude that all identified

    significant potential adverse impacts have been avoided or minimized as

    much as is feasible to do.

    22. The board's September 15, 2010 findings will now be incorporated into

    the planning board's site plan review of the SLW project but their substance

    will not be revisited during the site plan review. Therefore, no further

    remedy is available to the petitioner.

    V. FACTUAL BACKGROUND

    23. The following is a summary of the facts relevant to this petition.

    24. Petitioner members all own land in the Town of Cape Vincent or the

    Town of Lyme.

    25. The value of petitioner members land lies in its rural setting and the

    environmental, recreational and aesthetic amenities that characterize the

    land and the community to which it is tied.

    26. The physical environment, the recreational practices and the aesthetic and

    community values of petitioner members would be harmed by the town

    board decision complained of here because this decision is inseparably tied

    to a plan to attract large commercial wind farms to Cape Vincent, including

  • 8/8/2019 WPEG Petition Filed

    7/23

    dozens of industrial wind turbines and miles of access roads and power

    lines.

    27. There are no industrial wind turbines in Cape Vincent.

    28. In 2001 at least two different wind developers began purchasing land use

    rights, including from Cape Vincent local officials, in order to secure

    sufficient land for a multi-turbine wind energy facility or wind farm in

    Cape Vincent and Lyme. These companies are British Petroleum (BP)

    and Acciona.

    29. On or about July 13, 2002, the planning board approved a request for

    approval for the installation of meteorological towers to test wind

    conditions in Cape Vincent, and to otherwise assess the prospects for

    constructing a wind farm.

    30. In 2003, the Village and the Town of Cape Vincent adopted a Joint

    Comprehensive Plan (termed the General Plan under the town's zoning

    code) that encourages development that has a minimum impact on scenic

    natural vistas and tourism assets, and discourages towers or utility facilities.

    31. Under Cape Vincent's zoning code, wind farms may be deemed

    utilities, in which case their approval is subject to site plan review by the

    town's planning board.

    32. Cape Vincent's zoning code lacks any specific regulation for wind farms.

    33. The SLW project is proposed to be sited in the town's Agricultural

  • 8/8/2019 WPEG Petition Filed

    8/23

    Residential District, requiring the planning board to condition approval in a

    manner that preserves the rural character of the town or, if it finds the

    deleterious effects of a wind farm proposal cannot be mitigated because of

    the particular conditions on the site it is to occupy, to deny approval.

    34. No later than 2006, both BP and Acciona had obtained sufficient land use

    rights from local property owners to support their respective wind farm

    project proposals.

    35. The project area required for the SLW project is approximately 7,900

    acres, however this represents only parcels leased or otherwise controlled

    by SLW or Acciona for the proposed SLW project.

    36. As proposed, and as directed by the planning board, Acciona (SLW) and

    BP must utilize a common transmission line in Cape Vincent and Lyme and

    must cooperate to implement common use of a single transmission line.

    37. On June 13 and 14, 2007, WPEG submitted written comments to the

    board on a Draft Environmental Impact Statement (DEIS) provided to the

    board by SLW, noting that the project is inconsistent with the town's

    Comprehensive Plan, and noting that the DEIS lacks an analysis of

    alternative project layouts.

    38. In 2007 the nearby towns of Clayton and Orleans began review of a wind

    project proposed by Atlantic Wind, LLC, and that review continues today.

    39. In 2009 a wind farm began operating on nearby Wolfe Island and plans

  • 8/8/2019 WPEG Petition Filed

    9/23

    for the expansion of the Wolfe Island wind project were announced.

    40. On June 10, 2010, the Cape Vincent Town Board formed a Wind Turbine

    Economic Impact Committee to evaluate the effect of siting wind farms in

    the town on local employment, private property values, and the town's

    property tax base.

    41. In January 2009, at the direction of the board, Acciona prepared a

    Supplemental DEIS (SDEIS) to address critical comments on the DEIS

    submitted by the board's consultants, involved agencies and the public.

    42. On March 10, 2009, the board's engineering consultant, based in part on

    the board's acoustic consultant's review of the SDEIS conclusions regarding

    potential noise impacts of the SLW project, concluded that the analysis of

    noise impacts of the SLW project in the SDEIS is not supported by data,

    and failed to respond to the board's previous criticisms of the analytic

    methods for assessing noise in the SDEIS; and noting that the SDEIS lacks

    an analysis of the potential cumulative impacts of several planned or

    operating wind farms in the area.

    43. On March 25, 2009, the board accepted the SDEIS prepared by Acciona

    for purposes of further comment by involved agencies and the public.

    44. The board scheduled a public comment period on the SDEIS in May and

    June 2009.

    45. During the comment period in May 2009 involved agencies and the

  • 8/8/2019 WPEG Petition Filed

    10/23

    public, including WPEG and its members, submitted to the board additional

    written comments and technical supporting information, including an

    independent analysis by WPEG acoustic engineer of background sound

    levels in the vicinity of Cape Vincent, noting that properly measured

    background sound levels characteristic of the community are substantially

    lower than background sound levels asserted in the SDEIS, and explaining

    the difference as resulting from several methodological shortcomings.

    46. SLW's acoustic consultant, WPEG's acoustic consultant, and the board's

    acoustic and engineering consultants agreed that the SLW project's noise

    impacts should not exceed 6 decibels above existing background sound

    levels, a standard derived from guidelines for assessing noise impacts

    issued by the New York State Department of Environmental Conservation

    (NYSDEC).

    47. Comments submitted in May 2009 by the public, including by Petitioner,

    also provided substantial evidence from realtors and other experts in real

    estate valuation supporting the conclusion that the analysis in the SDEIS of

    the potential for adverse impacts on property values in the community that

    would result from the SLW project is based on widely discredited analysis

    prepared for the wind industry.

    48. WPEG's acoustic consultant, and the board's acoustic and engineering

    consultants also commented that cumulative impacts on wildlife and other

  • 8/8/2019 WPEG Petition Filed

    11/23

    local environmental amenities of all those wind farms planned and

    operating in the area must be analyzed in any final EIS (FEIS).

    49. In June and July 2010 the planning board's consultant was still

    identifying deficiencies in the proposed FEIS in comment letters to SLW,

    regarding impacts to roads, residential wells, the acoustic environment, and

    land and water that would be disturbed by construction, among other

    potential adverse impacts, and in response to these comments SLW

    provided supplemental responses, supporting information and changes to

    the proposed FEIS that had not been included in the SDEIS.

    50. However, for several areas of concern the board allowed SLW to develop

    plans detailing potential impacts and how they would be mitigated during a

    site plan review subsequent to the approvals, or even following the

    conclusion of site plan review.

    51. The board did not provide any formal comment period during which

    involved agencies and the public would be invited to comment on the

    supplemental materials submitted by Acciona after June 2009.

    52. On August 13, 2010, Petitioner submitted additional written comments

    addressed to changes in the DEIS and SDEIS proposed since the May-June

    2009 public comment period.

    53. On August 17, 2010, the Town of Lyme planning board as an involved

    agency faxed to the planning board additional written comments addressed

  • 8/8/2019 WPEG Petition Filed

    12/23

    to changes in the DEIS and SDEIS proposed since the May-June 2009

    public comment period.

    54. On or before August 17, 2010, the Town of Cape Vincent Wind Turbine

    Economic Impact Committee submitted comments to the board criticizing

    the analysis of potential impacts of the SLW project on property values and

    the town's tax based proposed FEIS.

    55. On or about August 18, 2010, at a regularly scheduling meeting, the

    planning board accepted SLW's proposed FEIS as complete but took no

    other action on the FEIS or the SLW project.

    56. At the September 8, 2010 meeting of the planning board, the board

    chairman opened mail that included Petitioner's and others' comments

    received in August, as well as correspondence going back as far as May, but

    the chairman directed that since the May-June 2009 public comment period

    had closed, these materials be put in a do nothing file, meaning they

    would be disregarded and never reviewed by the board.

    57. On or about September 15, 2010, upon a 3-2 vote, the planning board

    approved the FEIS, adopted the FEIS in support of its conclusions about the

    SLW project, concluded that all SEQRA requirements have been met, and

    approved findings purporting to be a reasoned explanation of the basis for

    its action.

  • 8/8/2019 WPEG Petition Filed

    13/23

    FIRST CAUSE OF ACTION

    Failure to take a hard look at potential environmental impacts

    58. Petitioner repeats and realleges the prior paragraphs as if fully set forth

    here.

    59. The planning boards approval of findings regarding the SLW project is

    an action subject to SEQRA. Envtl. Conserv. Law (ECL) 8-0105(4).

    60. Prior to deciding whether to approve an action subject to SEQRA,

    environmental factors shall be considered, (ECL 8-0103(7)), and the

    lead agency shall act and choose alternatives which, consistent with social,

    economic and other essential considerations, to the maximum extent

    practicable, minimize or avoid adverse environmental effects, including

    effects revealed in the environmental impact statement process. ECL 8-

    0109(1).

    61. A planning board considering an action subject to SEQRA must, among

    other things, set forth in writing a reasoned elaboration of the basis for

    the action and provid[e] reference to any supporting documentation. 6

    N.Y.C.R.R. 617.7(b)(4).

    62. The reasoned elaboration of the basis for the action referred to in the

    previous paragraph is commonly termed a findings statement. See 6

    N.Y.C.R.R. 617.2(p).

    63. The environmental impact state process for the SLW project, including

  • 8/8/2019 WPEG Petition Filed

    14/23

    comments and supporting information provided to the board by interested

    and involved agencies and the public, revealed that serious adverse impacts

    to the acoustic environment, scenic resources, property values, wildlife and

    community character remained, but the FEIS and the board's findings fail to

    consider measures to avoid or minimize such impacts.

    64. In approving the SLW project findings, the board relied on future noise

    complaint procedures and other future, as yet unavailable evaluations and

    mitigation of effects of the project once operational without, however,

    analyzing the effectiveness of such future measures.

    65. Therefore, the action of the town board was in violation of lawful

    procedures, was unreasonable, and was made without sufficient basis in

    substantial evidence, and should be overturned.

    SECOND CAUSE OF ACTION

    Failure to Undertake Coordinated Review Pursuant to SEQRA

    66. Petitioners repeat and reallege the prior paragraphs as if fully set forth

    here.

    67. Designation of a Type I action by one involved agency requires

    coordinated review by all involved agencies. 6 N.Y.C.R.R. 617.4(a)(2).

  • 8/8/2019 WPEG Petition Filed

    15/23

    68. If an agency determines that the action may have a significant adverse

    impact on the environment, it must then coordinate with other involved

    agencies. 6 N.Y.C.R.R. 617.6(b)(4)(ii).

    69. A notice of completion of an EIS . . . must be filed with . . . all involved

    agencies. 6 N.Y.C.R.R. 617.12(b)(1).

    70. An EIS includes a Draft EIS as well as a Final EIS. 6 N.Y.C.R.R.

    617.2(n).

    71. The Cape Vincent Planning Board at the beginning of its review of the

    SLW project proposal designated the proposal as a Type I action pursuant to

    SEQRA.

    72. The Cape Vincent Planning Board at the beginning of its review of the

    SLW project proposal determined that the project as proposed may have

    significant impacts on the environment.

    73. The Lyme Planning Board is listed in the DEIS and the FEIS for the

    SLW project as an involved agency pursuant to SEQRA.

    74. However, the Cape Vincent Planning Board failed to undertake

    coordinated review with the Lyme Planning Board as evinced, for example,

    in the Cape Vincent Planning Board's neglect to provide a copy of the FEIS

    or any notification that a proposed FEIS was accepted as complete, thereby

    failing to provide the Lyme Planning Board with a meaningful opportunity

    to review, comment, and make recommendations or otherwise coordinate

  • 8/8/2019 WPEG Petition Filed

    16/23

    its review with Cape Vincent.

    75. The Cape Vincent planning board published notice of its acceptance of a

    complete FEIS for the SLW project in NYSDEC's Environmental Notice

    Bulletin on September 1, 2010.

    76. However, actual notice of acceptance of the FEIS was required to be

    filed with the Town of Lyme Planning Board because the Lyme board is an

    involved agency; it is not sufficient that the notice was published and

    available to the general public. 6 N.Y.C.R.R. 617.12(b)(3).

    77. The Cape Vincent Planning board did not provide the Town of Lyme

    Planning Board with notice of acceptance of the FEIS or a copy of the FEIS

    for the SLW project.

    78. Therefore, the action of the town board was in violation of lawful

    procedure, and should be annulled.

    THIRD CAUSE OF ACTION

    Failure to consider public comments pursuant to SEQRA

    79. WPEG and the Town of Lyme planning board submitted comments on

    the proposed but not yet accepted the FEIS for the SLW project on or about

    August 17, 2010, one month prior to the Cape Vincent planning board's

    acceptance of the FEIS.

  • 8/8/2019 WPEG Petition Filed

    17/23

    80. The FEIS for the SLW project is identical to the proposed FEIS on which

    WPEG and the Town of Lyme planning board commented on August 17.

    81. Once the board accepted the FEIS for the SLW project, it was required to

    afford agencies and the public a reasonable time period (not less than 10

    calendar days) in which to consider the final EIS before issuing its written

    findings statement. 6 N.Y.C.R.R. 617.11(a).

    82. However, the Cape Vincent planning board did not review, read or

    otherwise consider in any way the August 17 comment letters submitted to

    it by WPEG, the town's Wind Turbine Economic Impact Committee, and

    the Town of Lyme planning board.

    83. Nor did the board provide notice of acceptance of the FEIS or a copy of

    the FEIS to the Lyme planning board.

    84. Because the Cape Vincent planning board deprived the public and an

    involved agency of the opportunity to present comments, expert testimony

    or documentary evidence or examine and comprehend the submissions

    made by SLW in 2010, the board's adoption of the findings statement was

    done in violation of lawful procedure and should be annulled.

    FOURTH CAUSE OF ACTION

    Failure to consider cumulative impacts

    85. Petitioners repeat and reallege the prior paragraphs as if fully set forth

  • 8/8/2019 WPEG Petition Filed

    18/23

    here.

    86. Before the Cape Vincent planning board accepted and adopted an FEIS

    for the SLW project, it was aware that a commercial wind energy project

    was operating nearby on Wolfe Island; was aware of plans to expand the

    Wolfe Island project; was aware that another commercial wind energy

    project was under review by the nearby towns of Orleans and Clayton; and

    was aware that BP had submitted an application to the board for another

    proposed commercial wind energy project in Cape Vincent and Lyme.

    87. The SEQRA regulations required the board to consider whether, in light

    of planned and operating wind farms near the SLW project area, the

    development of another would have significant cumulative impacts. 6

    N.Y.C.R.R. 617.7(c)(1)(xii), 617.7(c)(2).

    88. Written comments submitted to the board by WPEG, involved agencies

    and other members of the public specifically urged the board to consider

    the potential cumulative impacts the SLW project may have in light of the

    four wind energy projects operating or proposed in Wolfe Island, Clayton,

    Orleans, Cape Vincent and Lyme.

    89. Because the Cape Vincent planning board did not consider the potential

    cumulative impacts of the SLW project prior to adopting findings

    supporting its approval of the project FEIS, its approval was done in

    violation of lawful procedure and should be annulled.

  • 8/8/2019 WPEG Petition Filed

    19/23

    FIFTH CAUSE OF ACTION

    Conflict of interest violations

    90. Petitioners repeat and reallege the prior paragraphs as if fully set forth

    here.

    91. Pursuant to General Municipal Law, 809[2], where an application for

    approval of a project is involved, a municipal officer or employee is

    deemed to have an interest in the applicant when he, his spouse, or their

    brothers, sisters, parents, children, grandchildren, or the spouse of any of

    them is a party to an agreement with such an applicant, express or implied,

    whereby he may receive any payment or other benefit, whether or not for

    services rendered, dependent or contingent upon the favorable approval of

    such application, petition or request.

    92. Violation of a specific section of the General Municipal Law is not

    critical to a finding of an improper conflict of interest. An actual conflict of

    interest, or the significant appearance thereof is sufficient to require

    compliance with the disclosure provisions of General Municipal Law

    809, and failure to provide such disclosure under those circumstances is a

    defect requiring invalidation of the approval.

    93. Because one or more of the voting members of the planning board voting

    on the approvals on September 15, 2010 had a prohibited appearance of

  • 8/8/2019 WPEG Petition Filed

    20/23

    conflict of interest, or had actual conflicts of interest at the time of their

    September 15, 2010 votes approving the SLW project FEIS, the vote was

    defective requiring invalidation of the approval.

    SIXTH CAUSE OF ACTION

    Violations of the Town of Cape Vincent Code of Ethics

    94. As authorized by General Municipal Law 806, the Town of Cape

    Vincent has adopted a local code of ethics imposing rules of ethical conduct

    in addition to those imposed by Article 18 of the General Municipal Law,

    including the requirement that members of the town board publicly

    disclose on the official record the nature and extent of any direct or indirect

    financial or other private interest he has in such legislation.

    95. The towns Code of Ethics also precludes town board members from

    holding any investment directly or indirectly in any financial, business,

    commercial or other private transaction, which creates a conflict with his

    official duties.

    96. On information and belief, a majority of the Cape Vincent planning board

    hold direct or indirect, financial or non-financial private interests in wind

    farm development assets in the town, or their family and friends have such

    interests such that any reasonable person would conclude under the

    circumstances there is a significant appearance of conflicts of interest in

  • 8/8/2019 WPEG Petition Filed

    21/23

    most town board members.

    97. Because a majority of the planning board hold or expect in the future to

    hold investments in land that would be used for wind farm development in

    Cape Vincent, the planning boards September 15, 2010 votes approving

    the FEIS and certifying that all identified adverse impacts that may result

    from the project have been adequately avoided or minimized were defective

    requiring invalidation of the approvals.

    WHEREFORE, Petitioner-Plaintiff demands judgment against Respondent

    PLANNING BOARD OF THE TOWN OF CAPE VINCENT and its members:

    (1) Declaring that Respondents decision approving the SLW project Final EIS

    violates SEQRA and is invalid and null and void;

    (2) Ordering Respondents to comply with SEQRAs procedural mandates,

    including but not limited to coordinating its review of the SLW project with

    the Town of Lyme, as mandated by SEQRA;

    (3) Declaring that the September 15, 2010 approvals are null and void for

    failure of one or more of the voting members to recuse themselves from

    voting on the approvals;

    (4) Awarding costs and disbursements and attorney fees of this proceeding;

    (5) And ordering such other and further relief as the Court may deem just and

    proper.

  • 8/8/2019 WPEG Petition Filed

    22/23

    DATED: October 26, 2010

    Allegany, New York

    ____________________________________Gary A. Abraham, Esq.

    Attorney for Petitioner-Plaintiff170 No. Second Street

    Allegany, New York 14706

    716-372-1913

  • 8/8/2019 WPEG Petition Filed

    23/23

    VERIFICATION

    STATE OF NEW YORK )

    COUNTY OF JEFFERSON ) s.s.:

    JOHN BRYNE, being duly sworn, states that he is the Chairman of Wind

    Power Ethics Group (WPEG); that on behalf of WPEG as well on his own behalf he

    states that the annexed Petition is true to his own knowledge, except as to matters therein

    alleged upon information and belief, and as to those matters he believes it to be true.

    _____________________________________________________JOHN BYRNE, CHAIRMAN

    WIND POWER ETHICS GROUP

    Subscribed and sworn to before me this ____ day of October, 2010.

    _____________________________________

    Notary Public