Upload
buimien
View
226
Download
0
Embed Size (px)
Citation preview
Document of
The World Bank
Report No: ICR00003566
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IBRD-79710)
ON A
LOAN
IN THE AMOUNT OF US$150 MILLION
TO THE
REPUBLIC OF BELARUS
FOR A
ROAD UPGRADING AND MODERNIZATION PROJECT
October 28, 2016
Transport and ICT Global Practice
Belarus, Moldova and Ukraine Country Unit
Europe and Central Asia Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective as of June 16, 2016)
Currency Unit = Belarussian Ruble
US$ 1.00 = 20,044 BYR
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS AM Aide-Memoire ICT Information Communications Technology
BoQs Bill of Quantities IP Implementation Progress
CAS Country Assistance Strategy ISR Implementation Status Report
CMU Country Management Unit MA-C MINSKAVTODOR-Center
CPS Country Partnership Strategy M&E Monitoring and Evaluation
CR (Borrower’s) Completion Report MOTC Ministry of Transport and Communication
DPL Development Policy Lending MS Marginally Satisfactory
EA Environmental Assessment NAS National Academy of Science
ECA Europe and Central Asia NPV Net Present Value
EIA Environmental Impact Assessment OVOS Official Environmental Impact Assessment
EIRR Economic Internal Rate of Return OP Operational Policy
EMP Environmental Management Plan PAD Project Appraisal Document
EU European Union PDO Project Development Objective
FIDIC International Federation of Consulting
Engineers
PIT Project Implementation Team
FM Financial Management PPP Public Private Partnership
FSU Former Soviet Union RUE Republican Unitary Enterprise
GDP Gross Domestic Product US$ United States Dollar (Currency unit)
HDM-4 Highway Design and Maintenance model,
Version4
VAT Value added Tax
HQ Headquarters VOC Vehicle Operations Costs
IBRD International Bank for Reconstruction and
Development
WB World Bank
ICB International Competitive Bidding WIM Weigh in Motion
ICR Implementation Completion & Results
Report
Regional Vice President: Cyril E. Muller
Country Director: Satu Kristiina J. Kahkonen
Country Manager: Young Chul Kim
Senior Global Practice Director: Pierre Guislain
Practice Manager: Juan Gaviria
Project Team Leader: Simon David Ellis, Nijat Valiyev
ICR Team Leader: Wei Winnie Wang
REPUBLIC OF BELARUS
Road Upgrading and Modernization Project
CONTENTS
Data Sheet
B. Key Dates ................................................................................................................... 1
C. Ratings Summary ....................................................................................................... 1
D. Sector and Theme Codes ........................................................................................... 2
E. Bank Staff ................................................................................................................... 2 F. Results Framework Analysis ...................................................................................... 2 G. Ratings of Project Performance in ISRs .................................................................... 4 H. Restructuring (if any) ................................................................................................. 5
I. Disbursement Profile .................................................................................................. 7 1. Project Context, Development Objectives and Design ................................................... 8
2. Key Factors Affecting Implementation and Outcomes ................................................ 12
3. Assessment of Outcomes .............................................................................................. 18
4. Assessment of Risk to Development Outcome ............................................................. 22
5. Assessment of Bank and Borrower Performance ......................................................... 23
6. Lessons Learned............................................................................................................ 25
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners............... 26
Annex 1. Project Costs and Financing .............................................................................. 27
Annex 2. Outputs by Component...................................................................................... 28
Annex 3. Economic and Financial Analysis ..................................................................... 37
Annex 4. Bank Lending and Implementation Support/Supervision Processes ................. 41
Stage of Project Cycle ............................................................................................... 42
Staff Time and Cost (Bank Budget Only)................................................................. 42
No. of staff weeks ..................................................................................................... 42
USD Thousands (including travel and consultant costs) .......................................... 42
Lending ..................................................................................................................... 42
Annex 5. Beneficiary Survey Results ............................................................................... 43
Annex 6. Stakeholder Workshop Report and Results ....................................................... 44
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ......................... 49
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ........................... 56
Annex 9. List of Supporting Documents .......................................................................... 57
Annex 10. Map.................................................................................................................. 58
1
A. Basic Information
Country: Belarus Project Name: Road Upgrading and
Modernization Project
Project ID: P118375 L/C/TF Number(s): IBRD-79710
ICR Date: 10/28/2016 ICR Type: Core ICR
Lending Instrument: SIL Borrower: REPUBLIC OF
BELARUS
Original Total
Commitment: USD 150.00M Disbursed Amount: USD 146.11M
Revised Amount: USD 146.11M
Environmental Category: B
Implementing Agencies:
Minskavtodor-Center (MA-C)
Cofinanciers and Other External Partners:
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 10/29/2009 Effectiveness: 03/09/2011 07/05/2011
Appraisal: 09/03/2010 Restructuring(s):
02/21/2013
10/01/2014
11/26/2015
Approval: 11/11/2010 Mid-term Review: 11/05/2012 11/09/2012
Closing: 11/30/2014 05/31/2016
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Satisfactory
Risk to Development Outcome: Moderate
Bank Performance: Moderately Satisfactory
Borrower Performance: Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Satisfactory Government: Moderately Satisfactory
Quality of Supervision: Satisfactory Implementing
Agency/Agencies: Satisfactory
Overall Bank
Performance: Moderately Satisfactory
Overall Borrower
Performance: Moderately Satisfactory
2
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments (if
any) Rating
Potential Problem Project at
any time (Yes/No): No Quality at Entry (QEA): None
Problem Project at any time
(Yes/No): No
Quality of Supervision
(QSA): None
DO rating before
Closing/Inactive status: Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Public administration- Transportation 1 1
Rural and Inter-Urban Roads and Highways 99 99
Theme Code (as % of total Bank financing)
Export development and competitiveness 20 20
Infrastructure services for private sector development 40 40
Regional integration 40 40
E. Bank Staff
Positions At ICR At Approval
Vice President: Cyril E Muller Philippe H. Le Houerou
Country Director: Satu Kristiina J. Kahkonen Martin Raiser
Practice Manager/Manager: Juan Gaviria Henry G. R. Kerali
Project Team Leader: Simon David Ellis Andreas Schliessler
ICR Team Leader: Wei Wang
ICR Primary Author: Wei Wang
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document) The development objective of the project is to reduce transport costs for road users on the upgraded
sections of the M5 road, and introduce electronic tolling in Belarus as an efficient cost recovery
mechanism.
Revised Project Development Objectives (as approved by original approving authority)
The objectives of the Project are to reduce transport costs for road users on the upgraded sections of
the M5 road and introduce a modern axle-load control system in Belarus as a tool to increase road
sector sustainability.
3
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Reduced vehicle operating costs on the upgraded section of the M5 road.
Value
quantitative or
Qualitative)
100
94
94
86
Date achieved 02/10/2010 11/30/2014 06/30/2015 06/30/2015
Comments
(incl. %
achievement)
This indicator was measured by percentage and was over achieved in target year.
Indicator 2 :
Axle load monitoring and control system has been supplied and installed on non-
tolled main roads in Bela
Value
quantitative or
Qualitative)
No
Yes
Yes
Date achieved 06/15/2013 03/31/2015 10/31/2016
Comments
(incl. %
achievement)
This indicator was achieved in target year. Now there are 100% of trucks weighed
on the network where WIM has been installed and where trucks are identified for
further weighing the processing time has been reduced by 75% (from 20 min to 5
min).
Indicator 3 : Tolling system
Value
quantitative or
Qualitative)
No
Yes
Not Applicable
Date achieved 02/10/2010 11/30/2014 11/30/2014
Comments
(incl. %
achievement)
This indicator and related component was dropped in 2013. The Government
decided to accelerate the full implementation and signed a PPP concession contract
in 2012 with a leading European firm. The target was still achieved successfully.
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Axle Load Monitoring and Control System installed and operational.
Value
(quantitative
or Qualitative)
No
Yes
Yes
4
Date achieved 06/15/2013 03/31/2016 10/31/2016
Comments
(incl. %
achievement)
This was achieved in target year. 100% of trucks are weighed on the network. The
processing time has been reduced by 75% (from 20 min to 5 min). There have been
2000 more special certificates issued for overweight vehicles than last year.
Indicator 2 : Roads constructed, non-rural (Kilometers, Core)
Value
(quantitative
or Qualitative)
0
52.70
52.70
Date achieved 02/12/2010 11/30/2014 09/30/2014
Comments
(incl. %
achievement)
This indicator was achieved before target date.
Indicator 3 :
Road Roughness measured through International Roughness Index (IRI) on
upgraded sections of M5 road (Number, Custom)
Value
(quantitative
or Qualitative)
3.30
2.00
1.14
Date achieved 02/10/2010 11/30/2014 09/30/2014
Comments
(incl. %
achievement)
This indicator was achieved before target date. By the time of ICR, the IRI was
further improved to 1.14, over achieving the target value.
Indicator 4 : Traffic Fatalities (Number, Custom)
Value
(quantitative
or Qualitative)
12.00
5.00
5.00
Date achieved 02/10/2010 11/30/2014 11/30/2014
Comments
(incl. %
achievement)
This indicator was achieved in target year.
Indicator 5 : Capacity to manage FIDIC type contracts (Text, Custom)
Value
(quantitative
or Qualitative)
No
Yes
Yes
Date achieved 02/10/2010 11/30/2014 09/30/2014
Comments
(incl. %
achievement)
This indicator was achieved before target date.
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual Disbursements
(USD millions)
1 06/13/2011 Moderately Satisfactory Moderately Satisfactory 0.00
2 12/13/2011 Satisfactory Satisfactory 9.90
5
3 08/10/2012 Satisfactory Satisfactory 32.14
4 12/26/2012 Moderately Satisfactory Satisfactory 54.97
5 06/29/2013 Moderately Satisfactory Moderately Satisfactory 81.79
6 12/30/2013 Moderately Satisfactory Moderately Satisfactory 131.48
7 06/30/2014 Moderately Satisfactory Moderately Satisfactory 134.92
8 01/06/2015 Moderately Satisfactory Moderately Satisfactory 135.78
9 07/02/2015 Moderately Satisfactory Moderately Satisfactory 136.00
10 12/18/2015 Satisfactory Satisfactory 139.19
11 06/06/2016 Satisfactory Satisfactory 145.90
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved PDO
Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring in
USD millions
Reason for Restructuring & Key
Changes Made DO IP
02/21/2013 Y MS S 67.95
Under the original design of the
project, the first stage of the
tolling system would have
been implemented with World
Bank funding, with the intention
to gradually expand the system
to about 2,600 km of major
highways in Belarus over several
subsequent years with the
Government's own funding. The
full implementation of the tolling
system would have taken about 5
to 7years. However, while the
functional design of the system
was carried out during the first
year of implementation of the
World Bank funded project, the
Government decided to
accelerate the full
implementation of the tolling
system. In early 2012, it signed a
PPP concession contract with a
leading European firm for the
supply and installation of the
system on about 2,600 km of
major highways, and its
operation during 20 years. The
contract is under implementation
and the first phase of the
new tolling system would be
operational in mid-2013. The
6
Restructuring
Date(s)
Board
Approved PDO
Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring in
USD millions
Reason for Restructuring & Key
Changes Made DO IP
proposed change is to replace the
support for the tolling system by
support for the design, supply,
installation and commissioning
of a countrywide state-of-the-art
axle load monitoring and control
system.
10/01/2014 N MS MS 135.55
The Government of the Republic
of Belarus requested an
extension to the closing date by
12 months from November 30,
2014 to November 30, 2015. The
purpose of the extension is to
ensure sufficient time to
complete component 2 of
the project which is the
installation of a weigh-in-motion
(WIM) system which is required
for satisfactory achievement of
the Project Development
Objective.
11/26/2015 N MS MS 137.79
The Government requested an
extension of the closing date to
ensure sufficient time for
achievement of the Project
Development Objective. The
proposed change consists in an
extension of the closing date by
6 months from November
30, 2015, to May 31, 2016.
If PDO and/or Key Outcome Targets were formally revised (approved by the original approving body) enter
ratings below:
Outcome Ratings
Against Original PDO/Targets Satisfactory
Against Formally Revised PDO/Targets Satisfactory
Overall (weighted) rating Satisfactory
8
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
1. Country Background. At the time of appraisal, Belarus’ economic growth was facing
increasing constraints due to the limited flexibility of its economy, low levels of technological
innovation, and Russia’s policy of bringing the price of oil and gas supplied to Belarus to world market
levels. Belarus GDP expanded by 0.2 percent in 2009. Growth was projected to strengthen again in
2010, but to levels below those preceding the crisis, as capital markets were likely to remain risk
averse and as domestic investment was likely to grow at a more moderate pace. Lending by state
owned banks continued at a high rate in the first half of 2009, but this was curtailed later in the year
as credit policy was tightened. Net reserve targets under the IMF Stand-by Agreement for end-
September 2009 were met. Under the aegis of its Development Policy Loan (DPL), the World Bank
worked with the authorities on measures in liberalizing prices, reducing entry barriers, hardening
budget constraints, and enhancing social protection. Since the expiry of the IMF program in March
2010, monetary and fiscal policies loosened again and external imbalances had widened. To sustain
ambitious growth targets, while ensuring macroeconomic stability, the authorities were working on a
new liberalization and reform program. In particular, the aim was to attract significant Foreign Direct
Investment and benefit from Belarus’ strategic location and membership in the customs union with
Russia and Kazakhstan.
2. Sector Background. Contributing about 6 percent of GDP in 2008, transport was an important
economic sector in Belarus. The sector generated significant revenues from transit services, facilitates
trade and transportation, and contributed to the country’s balance of payments. In addition, the
transport sector accounted for about 6 percent of total employment in Belarus in 2008, with the largest
proportion of transport employment in roads (117,100 persons), followed by rail (70,400 persons).
The advantageous geographic position of Belarus, which serves as a bridge between the Russian
Federation and Western Europe, has made the country an important partner in the provision and
development of transportation infrastructure and services in Europe. The Trans-European Corridor II
(Berlin – Warsaw – Minsk - Moscow) and Corridor IX (Black Sea – Kiev –Minsk - Baltic countries),
which receive high priority from the Government, pass through the territory of Belarus. The M1/E30
highway is part of Corridor II, connecting the EU and Russia. Transit trade – largely by rail for goods
and by pipeline for oil and gas – is therefore a significant part of the economy. However, significant
investment in the transport infrastructure would be required to maintain and improve the contribution
that transport makes to the economy.
3. Despite the good track record in the past, sustainability of funding for roads was one of the
key issues to be addressed by the Government in the transport sector. The abolition of the National
Road Fund in early 2010 and the continued effects of the global financial and economic crisis in 2008
and 2009 exerted downward pressure on the Government’s fiscal space.
4. Belarus introduced road tolling in 1996 when a manual and open tolling system started to
operate on the M1/E30 road between Brest, Minsk and the border with the Russian Federation. Based
on the positive experience with road tolling on the M1 motorway over the last decade, the Government
saw road tolling as a future key source of funding for assuring the maintenance of the road network.
It planned to modernize the existing tolling facilities on the M1 motorway and gradually introduce
modern electronic tolling on most main roads over the next decade. The Government believed that the
introduction of a new tolling system in Belarus on the basis of state-of-the-art technologies would
9
help drastically raise efficiency and ensure a non-discriminatory tolling policy in relation to both
domestic and foreign users according to the rate of utilization of the road network and in compliance
with the EU directives. In addition, the tolling system would also help to raise the volume of financial
revenues into the budget.
5. Rationale for Bank Involvement. The rational for Bank assistance in this project was
twofold: (i) the Government requested a DPL and lending to support their investment programs in the
roads and railways sectors, and additional financing for the on-going Post-Chernobyl Recovery
Project on top of support for investments originally planned in the CPS; (ii) the World Bank had
extensive experience with road projects in the Former Soviet Union (FSU) and in the more recent EU
member countries (Poland, Romania, Bulgaria, and Hungary). In the particular context of the
originally proposed project, the Bank was also able to contribute its good knowledge in the area of
road tolling (original project Component 2).
1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)
6. The original PDO as approved and stated in November 2010 Loan Agreement and consistent
with the Project Appraisal Document (PAD) was to reduce transport costs for road users on the
upgraded sections of the M5 road, and introduce electronic tolling in Belarus as an efficient cost
recovery mechanism.
(i) Project Outcome Indicators:
Reduced vehicle operating costs on upgraded section of the M5 road.
Electronic road tolling system introduced in Belarus on a section of the M5 road.
(ii) Intermediate Outcome Indicators:
Length of the M5 road sections upgraded.
IRI (International Roughness Index) reduced on the upgraded section of the M5 road.
Number of fatalities on the upgraded sections of the M5 road reduced.
Modern electronic road toll system is installed and operational on the section from km 22 to
km 131 of the M5 road.
Local institutions have good capacity to supervise FIDIC based road works.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and
reasons/justification
7. In 2012, the Government decided to accelerate the introduction of a country-wide electronic
tolling (later referred as e-tolling) system for trucks by signing a large PPP contract with a specialized
firm, outside the scope of this project. As a consequence, the content of Component 2 was redefined
as part of a Level-1 project restructuring approved on February 7, 2013. The support for the
introduction of the electronic road tolling system was replaced by supporting for the introduction of a
state-of-the-art axle load monitoring and control system which was later referred to as a Weight-in-
Motion system (WIM). The WIM was designed to be another key component of the overall asset
management system in Belarus.
8. Therefore, the revised PDO, as approved in September 2013 Loan Agreement Amendment,
was to reduce transport costs for road users on the upgraded sections of the M5 road and introduce a
modern axle-load control system in Belarus as a tool to increase road sector sustainability. The original
10
project outcome indicator “Electronic road tolling system introduced in Belarus on a section of the
M5 road” was replaced by “Axle Load Monitoring and control system introduced on non-tolled roads1
in Belarus” and the original project intermediate outcome indicator "Modern electronic road toll
system is installed and operational on the section from km 22 to km 131 of the M5 road" was replaced
by "Modern axle load control system is installed and operational". The summary of changes to the
monitoring indicators is presented in Annex 2, Section B.
1.4 Main Beneficiaries
9. Before project restructuring in 2013, the primary target group (beneficiaries) were road users
and residents in the area of influence of the project road. A social assessment was undertaken during
project preparation to identify social issues relevant to project objectives and execution. These
beneficiaries were expected to benefit from (i) reduced vehicle operating costs due to upgraded road
conditions; (ii) reduced travel time due to improved road conditions and operations of modern
electronic toll system; (iii) safer travel on the improved project road sections; (iv) employment
generation as the project created important employment opportunities during the construction phase,
mostly in the road construction industry.
10. The secondary target group included government institutions that were expected to benefit
from improved capacity in: (i) managing modern electronic road rolling system; (ii) conducting
economic evaluation of road investments using HDM-4 software (Highway Design and Maintenance
model); (iii) supervising FIDIC (International Federation of Consulting Engineers) based road works;
and (iv) road construction, repair and maintenance in accordance with European and international
standards.
11. After project restructuring in 2013 the secondary beneficiaries, namely government
institutions, changed slightly to reflect the change in Component 2 from the introduction of electronic
tolling to the introduction of a modern axle load monitoring and control system. Therefore the
improved capacity of managing modern electronic road rolling system was replaced by the improved
capacity to manage a modern axle load monitoring and control system.
1.5 Original Components (as approved)
12. The original project was approved by the Board on November 11, 2010 and became effective
on July 5, 2011. The project consisted of three components: (i) road upgrading; (ii) modernization of
road tolling system; and (iii) technical assistance and capacity building.
13. Component 1 – Road Upgrading (US$131 million). This component included: (i)
reconstruction of the existing two lanes and the construction of two additional lanes to carry a design
axle load of 11.5 tons; (ii) improvement of road safety features in line with EU road standards; (iii)
construction of about six two-level interchanges, seven overpasses, four bridges, two pedestrian
underpasses and bypasses at the village of Sosnovy (about 5.7 km long) and at the 8 village of Boyary
(about 4.2 km), where the alignment was shifted in order to increase the distance between the road
and the nearest houses; and (iv) implementation of a number of environmental impact management
1 The WIM was originally conceived to run independently from the e-tolling system and on non-tolled roads. However
during the design phase of the WIM it became apparent that the same infrastructure could be used and that the tolled
network had expanded rapidly. WIM has now been installed on tolled parts of the network.
11
features, such as protective noise barriers in the villages that were located near the alignment. The
total cost for construction was estimated to be US$131 million (approximately US$2.5 million per
kilometer on average) including contingencies.
14. Component 2 – Modernization of Road Tolling System (US$18 million). This component
included supply and installation of a modern electronic road tolling system based on microwave
technology on a 109 km section (from km 22 to km 131) of the M5 road between Minsk and Bobrujsk,
including supply of equipment such as (i) on-road tolling equipment, (ii) specialized vehicles and
equipment for control purposes, (iii) a centralized data processing center, (iv) software and computers,
and (v) on-board devices for vehicles.
15. Component 3 – Technical Assistance and Capacity Building (US$1 million). This
component aimed at strengthening of the institutional capacity of road sector institutions of the
Borrower by providing technical assistance and training, including (i) training on the new electronic
tolling system; (ii) support to BELGIPRODOR for updating its economic evaluation tools for road
projects, including training on HDM4 and procurement of software licenses; (iii) support to improve
the capacity of local institutions involved in supervision of road works at a level to carry out
supervision under FIDIC rules; (iv) technical assistance to BELAVTODOR in carrying out
benchmarking and harmonization of Belarusian road construction, repair and maintenance standards
and expenditure levels against and in accordance with European and international standards; (v)
support for carrying out the project audits; and (vi) other minor project-related technical assistance,
training and/or goods to support capacity building and Government institutions in the road sector.
1.6 Revised Components
16. There were changes to the name and the project activities of Component 2, which were done
as part of a Level -1 restructuring. Component 2 was changed from “Modernization of Road Tolling
System” to “Axle Load Monitoring and Control System, i.e., Weigh-in-Motion system”. The
procurement plan was revised to reflect the change in Component 2. The "Supply and Installation of
a road tolling system" was replaced by "Supply and Installation of Axle Load Monitoring and Control
System (i.e., Weigh-in-Motion or WIM)". Consulting services under this component were also
changed accordingly.
1.7 Other significant changes
17. The second restructuring was a Level -2 restructuring approved on October 1, 2014 to extend
the project closing date by 12 months from November 30, 2014 to November 30, 2015, as requested
by the Government. The purpose of the extension was to ensure sufficient time to complete
Component 2 of the project which was the installation of a weigh-in-motion (WIM) system and full
achievement of the project development objectives as well as full disbursement of loan funds. The
third restructuring was a Level -2 restructuring as requested by the Government of Belarus to further
extend the closing date by another six months to May 31, 2016 to allow for the successful completion
of the project following delays with the implementation of the WIM system.
12
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
18. Soundness of the project preparation. The project preparation was initiated in late 2009 in
response to the Government’s request for a DPL and lending to support their investment programs in
the roads and railways sectors. The World Bank has extensive experience with road projects in the
FSU and in the more recent EU member countries that justified the rational for Bank involvement. In
the particular context of the originally proposed project, the Bank was able to contribute its good
knowledge in the area of road tolling (original project Component 2). The Board Approval was on
November 11, 2010 and the project became effective on July 5, 2011. Lessons of earlier operations
were taken into account during project preparation, in particular regarding to: (i) Complexity:
Experience showed that projects in transition countries need to be simple in design as the Government
was keen to deliver immediate and visible benefits to the population in line with agreed sector
priorities. Accordingly, this project was simple in design and was closely aligned with the
Government’s national road sector investment program, which targeted investments in the
rehabilitation, upgrading and modernization of transport infrastructure; (ii) Supporting Client
Objectives: Bank experience in Belarus showed that technical capacity was generally high, and that
implementation can proceed satisfactorily given the supportive governance environment and track
record of good governance. World Bank funded projects in Belarus faced difficulties in achieving
their objectives and scored low on sustainability if they included Bank-driven components, largely
due to the inability and unwillingness to implement difficult reform conditions with uncertain
outcomes. This project was closely aligned with the Government’s national road sector investment
and development program.
19. Assessment of the project design. The PDOs were important for the country and sector and
furthered the Bank’s Country Assistance Strategy (CAS). The PDOs reflected borrower’s
development priorities and the restructuring and the revised PDOs responded effectively to borrower’s
changing circumstances. However, both the original and revised PDOs and also the corresponding
PDO indicators refer to introduction of e-tolling/modern axle load control system, which is more of
an output than outcome and the formulation of the PDO itself should have actually referred to an
outcome. The PDO indicators for Component 1 of the project were well defined, but as described in
section 2.3, the PDO indicators for Component 2 were more output orientated which prevented
assigning satisfactory for this assessment.
20. Technical designs were prepared and completed by the clients and the World Bank team
reviewed the detailed design and the technical standards applied and was satisfied with the design
parameters and methods. The first project restructuring replaced e-tolling with WIM. WIM
complements the e-tolling because it uses the same infrastructure (gantries, electricity etc.) and is a
part of the overall road asset management strategy for MoTC.
21. Social and environmental safeguards were taken into consideration in project design. The
project was classified as Environmental Category "B" in accordance with World Bank Operational
Policy 4.01, "Environmental Assessment”. An EIA and an EMP for both construction and operation
phases were prepared by the Borrower.
22. The financial management arrangements were designed to place reliance on existing
institutional FM systems, i.e. by the existing departments of MA-C and using the existing institutional
13
mechanisms of financial management. Specifically, project financial management was primarily
carried out by the existing departments of MA-C. Elements of the existing accounting and reporting
as well as the system of internal controls of MA-C were used for project financial management.
23. Assessment of government commitments and participatory processes. Government’s
commitment appeared solid. On one hand, the project was in direct support of the Government’s
objectives for the road sector that were expressed in its program “Roads of Belarus 2006 – 2015”. On
the other hand, the Government’s commitment was demonstrated through funding 48.9 Belarussian
Rubles for road feasibility design, preparing bidding documents and technical supervision for
Component 1 of 52.7 km of roads from the state budget.
24. Key stakeholders such as residents along project impact area were consulted and interviewed
during project preparation through social assessment in order to identify social issues relevant to
project objectives and execution for Component 1 of road upgrading works. For the original
Component 2 of road tolling local consultations were carried out during project preparation for key
stakeholders such as truck owners and operators through the Association of International Road
Carriers of Belarus given that the road toll was to be collected from heavy vehicles only. No
consultations were carried out for the revised Component 2 of installing Weigh-in-Motion system.
25. Assessment of the project risks and mitigation measures. All risks were fiduciary oversight,
while most procurement activities were well-advanced at the time of appraisal and therefore, these
risks were downgraded to moderate with mitigation measures, so as the overall risk rating of the
project.
26. To summarize, strengths at entry include: the project’s alignment with the Government’s
strategy and the Bank’s CPS, the simple design of the project to address a fundamental need and
deliver immediate and visible benefits to the population without heavy reform agendas, strong
government commitment and the realistic assessment of risks and practical mitigation measures. The
Quality at Entry is rated as Moderately Satisfactory.
2.2 Implementation
27. Implementation arrangements. Since the project was first approved the road sector had
undergone some reform to optimize the institutional structure at the MoTC. When the project was
approved, the roads agency, Belavtodor, had responsibility for planning, implementation and
management of the network and “owned” the country’s contractors and consultants. As part of the
reform, on July 1st, 2013, Belavtodor was liquidated and replaced by the Head Directorate of the Road
Network, which is a structural unit responsible for network management, at the MoTC. The new
structure provides a road organization (‘Avtodor’) in each Oblast to perform the project and road
owner functions. A new organization called Belavtodor Holding Management Company Republican
Unitary Enterprise (RUE) was founded in July 2013, which comprises 19 independently managed
road and bridge contractors of Belarus (i.e., large and small size construction companies). However,
for the whole implementation period the MoTC formally delegated the responsibility for managing
the day-to-day preparation and implementation of the project to the Republican Unitary Enterprise
MINSKAVTODOR-Center (MA-C). MA-C has experienced staff in the areas of engineering,
procurement, project management and financial management. Within MA-C, a Project
Implementation Team (PIT) was created for the project, which consisted of experienced officials who
were assigned to work on the various aspects of project preparation and implementation. The World
14
Bank team supported MA-C in the necessary training of the specialists on the use of World Bank
guidelines and procedures for procurement, financial management, and environmental/social
safeguards management.
28. Progress of implementation. The implementation progress (IP) started as Marginally
Satisfactory (MS) reflecting the delay in project effectiveness. The main reason was the fact that
MoTC included the Value Added Tax (VAT) exemption provision in the Presidential Effectiveness
Decree. Normally, this was done by a separate document once a contract was in place. However, at
that time, there was a sense that this approach would be more efficient and would accelerate
implementation. On the contrary, it ended up delaying effectiveness exactly because it was a non-
standard VAT exemption request. Despite the eight months it took for project effectiveness, the
procurement of civil works contracts progressed well, and once the project became effective on July
5, 2011, the overall IP rating was upgraded to Satisfactory (S). By this time, four contracts for road
upgrading in Component 1 were signed and contractors mobilized, the design for the initially
envisaged electronic tolling under Component 2 was also completed with bidding documents prepared,
and capacity building activities were fully underway for Component 3, which indicated great
governance and project management from the Borrower. The IP was still rated as Satisfactory during
midterm review in November 2012. The review resulted in an agreement on the restructuring of the
project – Component 2 only. After that, the IP was downgraded to MS because the civil works were
delayed under Component 1 due to the contractor running into some financial difficulties because of
high inflation in 2011/12, and their inability to manage the subcontractors. Progress subsequently
picked up and the contracts were completed well within the project period.
29. Additionally, project restructuring to replace electronic tolling (e-tolling) with weigh-in-
motion (WIM) system of Component 2 caused another delay. The Government originally decided to
use the Bank loan to finance a pilot e-tolling on M5 road for 960 km, but later the Government saw
the urgency and critical value of implementing such a system and decided to accelerate the full
implementation of the e-tolling system and signed a PPP concession contract in 2012 with a leading
European firm Kapsch for the supply and installation of the system and its operation for 20 years.
After the original Component 2 was dropped, two options for the redesign of Component 2 were
discussed: (i) the introduction of WIM system in Belarus to protect road assets from premature
deterioration, and (ii) the design and partial implementation of an Intelligent Traffic Management
System in and around Minsk. As Belarus has substantial transit traffic it was decided that stopping
over-loaded trucks was the priority and it was decided to go ahead with the WIM system. The other
option of designing and implementing an Intelligent Traffic Management System is now being
implemented through the ongoing Transit Corridor Improvement Project in Belarus. The Bank team
has been fully behind the Government’s decision to roll out e-tolling and WIM as part of their strategy
on sustainable road asset management. The Government had a robust road sector strategy in place,
the re-scoping of the Bank’s support was more straightforward as it addressed the next priority
intervention.
30. However, the fact that the decision to drop the e-tolling component was done without Bank
consultation left much to be desired. Still, the e-tolling is now fully functional and covers national
road network for 1512 km till now, more than 50% of the original proposed pilot. It also reached the
proposed outcome as stated in the original PDO – e-tolling as an efficient cost recovery mechanism.
More details about how this component supports road sector financial sustainability are provided in
Section 4 Assessment of Risk to Development Outcome.
15
31. Since project restructuring in February 2013, progress was made on defining new scope of
work but the progress was not fast enough to meet the original agreed project closing date by
November 2014. The IP rating remained MS due to extremely tight time line for this revised
Component 2 though Component 1 of road upgrading and Component 3 of technical assistance and
capacity building were completed in advance with satisfactory results. The procurement process for
both the design consultancy services and the subsequent procurement of equipment suffered from
substantial delays for a number of reasons including: (i) delays in defining technical specification of
the system; (ii) protracted negotiations with operator of existing e-tolling system on integration issues;
(iii) delays in concluding contract negotiations due to unresolved issues on unavailability of
counterpart payments of VAT; and (iv) delays in contract award as the highly rated consultant firm
refused to follow up with contract negotiations and the employer had to proceed with SWEROAD
Solna – the secondly rated consultant. Though such issues were fully resolved later, such substantial
delays necessitated the extension of the project by 12 months. The project was further extended by 6
months to May 31, 2016 to accommodate delays in the procurement of the "Weigh-in-Motion" system.
Despite the initial procurement delays the installation, commissioning and testing went smoothly and
a state of the art WIM system is now in operation on the roads of Belarus (see Annex 2 Section C for
details).
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
Design
32. M & E Design. The results framework was in general well designed to capture outcome of
each component except Component 2. The original project outcome indicators well assessed the road
transport costs reduction of the upgraded road section along M5 corridor by measuring reduced
vehicle operating cost, but the second outcome of cost recovery from road users that would enhance
sustainability of road investments by measuring whether the electronic road tolling system would be
successfully introduced in Belarus on a section of the M5 road was not well captured and measured
as the corresponding indicator was more output oriented instead of an outcome. The electronic road
tolling system indicator was later replaced with axle load monitoring and control system introduced
during the first restructuring, and there was a similar issue with the corresponding indicator that only
captured the output. No changes were made to the Results Framework during the last two Level-2
restructuring.
33. Definition and measurement of the Intermediate Results Indicators was straightforward, as
these indicators were by their nature more specific and thus easier to define.
34. The indicators for Component 1 were appropriately targeted to measure improvements in the
roads riding quality and road safety. The indicators for Component 2 were well designed to capture
the output - if the modern electronic road toll system was installed and operational for the selected
road sections, but not for the outcome of “cost recovery mechanism”. After the first Level-1 project
restructuring, this indicator was revised to capture whether the axle load monitoring and control
system was installed and operational, which similar to the tolling indicator is an output and not a
measure of the stated outcome which was “increased sector sustainability”. However, as can be seen
from Section 3.2 and Section 4 (related to increased revenues from e-tolling) it can be seen that
implementation of these two network management tools have had substantial impact both on cost
recovery in the sector and long term sector sustainability.
16
35. The indicator for Component 2, both before and after restructuring – “modern electronic road
toll system is installed and operational” and “axle Load Monitoring and Control System installed and
operational” were more outputs oriented and did not capture the stated outcome as “e-tolling as
efficient cost-recovery mechanism” and “WIM as a tool to increase sector sustainability” in the PDOs.
Though both outcomes were achieved in the end of project completion, the M & E design could be
further improved to better capture the expected outcomes.
36. The indicator for Component 3 measured the local institution’s capacity to supervise FIDIC-
based road works with annual assessment, which was appropriate and was used to reflect improved
performance in this regard.
37. Implementation. MINSKAVTODOR-Center (MA-C) was responsible for the collection of
the project’s performance indicator data and analysis of the results. Progress towards the achievement
of the final targets was monitored through regular project progress reports and Bank’s implementation
reviews and Implementation Status and Results Reports (ISRs). The data needed for monitoring the
selected indicators were of the type that were normally collected by the Belarusian government
departments and agencies and thus were easily monitored.
38. Utilization. MA-C collected and reported on the requisite data at regular intervals. The
intermediate results indicators were used as intended to track physical progress of civil works and
capacity development. At project end, values also were obtained for all of the key indicators for project
assessment purposes.
2.4 Safeguard and Fiduciary Compliance
39. Safeguards. The project was classified as Environmental Category "B" in accordance with
World Bank Operational Policy 4.01, "Environmental Assessment", based on the fact that (i)
construction works as such were essentially confined to the existing right-of-way which was fully
owned by the State, (ii) there was no resettlement of people or businesses; and land acquisition was
limited to transfer of land between different State agencies, (iii) the potential environmental impacts
of the project were not expected to be significant or only of a temporary nature.
40. Overall, project implementation was in full compliance with the EMP and the environmental
management in this project was exceptional. Project documentation was in good order and
environmental issues and mitigation measures were properly reflected in contracts/Bill of Quantities
(BoQs), Environmental Assessment (EA)/ Official Environmental impact assessment (OVOS) reports
and other documents. Representatives of the National Academy of Science (NAS) provided their
recommendations regarding protection of endangered species since project design stage and were
involved in monitoring of impacts of road construction on biodiversity, especially on valuable forest,
wetland and water ecosystems. Contractors of civil works were prepared and addressed emerging
environmental issues properly. Special mitigation measures to protect affected Red Book species –
construction of designated artificial ponds for relocation of the population of crested newt and
replanting of bears onion and coralwort were taken jointly by the contractors and experts from NAS.
Permanent monitoring of forest ecosystems adjacent to the construction site was undertaken by NAS.
41. A social assessment as part of the original project appraisal was undertaken by the Government
in November 2009 to identify social issues relevant to project objectives and execution. Regarding
Component 1 of road upgrading works, it was found that the project had mostly positive impacts on
17
the living standards of the population of Belarus through its direct effects on employment and
contribution to economic growth. Regarding the original Component 2 of e-tolling and the revised
Component 2 of WIM, taking into account the successful implementation of e-tolling in Europe and
in the country, no negative impacts were expected.
42. The civil works were carried out within existing rights of way, except for the bypass of the
village of Sosnovy (about 5.7 km long) and at the village of Boyary, where the road alignment was
moved by about 50 meters from the existing road in order to increase the distance between the road
and the nearest houses. In both of these cases, the construction was on land owned by the State and
did not have any adverse impact on community or private land use. No private land needed to be
acquired, nor any private business affected in any way by the bypass at Sosnovy and the realignment
at Boyary.
43. Procurement. Procurement under the project was carried out by MA-C in accordance with
the World Bank’s “Guidelines: Procurement under IBRD Loans and Credits” dated May 2004, revised
October 2006 and May 2010; and “Guidelines: Selection and Employment of Consultants by World
Bank Borrowers” dated May 2004, revised October 2006 and May 2010, and provisions stipulated in
the Loan Agreement. A procurement capacity assessment was carried out in February 2010 to assess
the capacity of PIT. The risk level of the environment of conducting procurement under the project
(before mitigation measures) was assessed as “substantial”. A plan to mitigate the procurement risks
and strengthen implementation capacity was agreed with PIT and MoTC. Intensive training was
conducted to help PIT to improve its capacity in procurement under World Bank guidelines. All
contracts were subject to prior review by the World Bank. Frequent implementation reviews were
carried out by the World Bank project team that included technical staff, financial management
specialists and procurement accredited staff.
44. Since the first project restructuring to replace Component 2 with axle load monitoring and
control system (namely, weigh-in-motion), the procurement process for both the design consultancy
services and the subsequent procurement of equipment suffered from substantial delays that
necessitated the extension of the project by 12 months. The technical nature of this contract caused
delay in the procurement process. The team monitored the progress closely and frequently. It should
be noted that since award of the supply contract, implementation was to schedule.
45. Financial Management (FM). Financial management was carried out successfully
throughout project implementation. The design of FM placed much reliance on existing institutional
FM systems, i.e. by the existing departments of MA-C and using the existing institutional mechanisms
of financial management. The FM arrangements in BELAVTODOR and particularly in MA-C were
acceptable and the FM capacity was sufficient that satisfied the Bank’s requirements. Audit reports
were completed on time, and the auditor’s opinions for the financial statements for each year were
unqualified.
2.5 Post-completion Operation/Next Phase
46. The Bank continues to engage in the transport sector with an ongoing operation to improve
M6 transit corridor (P149697 - Transit Corridor Improvement Project). The same implementation
agency is involved in both lending projects. The ongoing project supports MoTC to establish a traffic
management center, provides MoTC and Beldor Center with state-of-the-art equipment for highway
monitoring, operations and maintenance. Other activities under the ongoing operation such as (i)
18
incorporating road safety measures into road reconstruction; (ii) integrating associated infrastructure
and equipment, including WIM from this project, and (iii) utilizing Information Communications
Technology (ICT) for enhanced traffic and road assets management will help further strengthen the
technical capacity of the implementation agency on maintaining roads and ICT infrastructure as well
as sustaining the good practice established with this closing project.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
47. Despite restructurings, the project objectives remained consistent with the Bank’s CAS. The
results framework of the CPS Progress Report clearly identified this project as a World Bank operation
in support of Pillar 2 (Entry, Regulatory Reform, and Competitiveness). Within that Pillar, one of the
higher-level objectives was to “facilitate competitiveness of the transport sector by supporting
modernization and upgrading of critical physical infrastructure in road and railway sectors” through
investment operations such as this project. The project was also in direct support of the Government’s
objectives for the road sector that were expressed in its program “Roads of Belarus 2006 – 2015”.
After the first project restructuring, the objectives were revised according to changing circumstances
and properly reflected the development priority to increase road sector sustainability.
48. For Component 1 which remained unchanged during the project, the design supporting
upgrading of 52.7 km of the M5 road from a 2-lane (Category 2) road to a 4-lane (Category 1B)
motorway together with road safety measures contributed to reduced vehicle operating costs and
traffic fatalities on the upgraded section of the M5 road. Component 2, both the originally planned e-
tolling system, and the later replaced installation of WIM supported both an efficient cost recovery
mechanism and increased sector sustainability. The Government accelerated full implementation of
the tolling system and signed a PPP concession for the supply and installation of the system on about
2,600 km of major highways, and its operation for 20 years. The revised component with WIM
complemented the electronic tolling because it uses the same infrastructure (gantries, electricity etc.)
and is a part of the overall asset management strategy for the Ministry and contributed to improved
road sector sustainability. It now includes 12 WIM installations and a systems architecture which links
with mobile and fixed weigh stations. These initiatives have all helped the Belarus road sector to be
among the best in the region with a well-maintained network and stable expenditure and funding (see
more details in Section 4 Assessment of Risk to Development Outcome). For Component 3 which
remained unchanged during the project, the training and technical assistance activities contributed to
improved institutional capacity of national and local road agencies as the overall objective of road
sector sustainability.
49. The Bank’s implementation assistance was responsive to client’s changing needs. Despite a
change of project component, the operation remained highly important to achieving country and Bank
development objectives.
50. Taken together, the overall relevance of objectives, design and implementation against both
original and revised PDO is Substantial.
3.2 Achievement of Project Development Objectives
19
51. The achievement of the overall original PDO is rated Substantial.
The achievement of the first sub-objective – to reduce transport costs for road users on the
upgraded sections of the M5 road – is rated High. Road roughness decreased from 3.2 to 2.0
after completion of civil works. Vehicle operating cost reduced by 14% as end target by June
2015, which surpassed the original target as 6%.
The achievement of the second sub-objective – to introduce electronic tolling in Belarus as an
efficient cost recovery mechanism – is rated Substantial. Despite the client’s decision to
finance the system themselves, it turned out to be ultimately successful with 1,5122 kilometers
of national roads operated for electronic tolling (See more details in Annex 2, Section C). The
electronic system BelToll has been in commercial operation since August 1, 2013. As of July
2015, more than 220,000 vehicles have been registered for the system being controlled by
more than 90 automatic stations3. The system generates sustainable financing for the road
network and infrastructure. For 2015, the estimated revenues were BYR 537 billion (US434
million, refer to Section 4 Sustainable Sector Finance for more statistics).
52. The achievement of the overall revised PDO is rated Substantial.
The achievement of the first sub-objective remains the same as in the original PDO and the
rate remained High.
The achievement of the second sub-objective – to introduce a modern axle load control system
in Belarus as a tool to increase sector sustainability – is rated Substantial. This sub-objective
was implemented well. Despite initial delays all equipment including the weigh-in-motion
control points, portable weight control stations, sensors, cameras, computing center and data
links were installed properly and to schedule with quality control. WIM was designed to
capture and record axle weights and gross vehicle weights as vehicles drive over a
measurement site. Following five months of operation the results are very encouraging - the
system is fully operational, there is weighing of 100% of trucks and those pre-identified as
being overweight are processed in a much reduced time frame (from 20 minutes to 5 minutes).
There have also been 2000 more special certificates issued for overweight vehicles in the
period to end of September 2016 than for the similar period in 2015.
3.3 Efficiency
53. The economic evaluation at appraisal stage was carried out in 2010 for project Components 1
(road investment) and 2 (tolling system).
54. For Component 1 of road investment the economic analysis was originally carried out using
the HDM4 software package, an evaluation period of 30 years and a discount rate of 12 percent. The
economic return of the project was sufficiently high to justify the proposed project. The discounted
net present value (NPV) of the World Bank financed section (52.7 km) was US$159 million with an
economic internal rate of return (EIRR) of 21 percent. Based on the sensitivity analysis, the project
was more sensitive to changes in traffic growth rates than in construction costs. The World Bank
team performed the ex-post economic evaluation of the project adopting all the actual data available
related to the investment costs, timing of the investments, annual traffic growth rate, and road user
benefits due to ride quality and road safety improvements. The actual cost of the road improvements
2 http://www.beltoll.by/index.php/en/beltoll-system/toll-roads/list-of-toll-segments 3 http://tollroadsnews.com/news/kapsch-belarus-expansion
20
was about 12 percent higher than appraisal estimates (see Annex 3). Rather than increasing by 5
percent for light vehicles and 3 percent for trucks and buses as forecast, traffic counts in fact declined
between 2010 and 2015 due to weaker than expected domestic economic growth, reduced
international freight traffic due to the worsening of the political and economic relations between the
Russian Federation and the European Union, and lower numbers of trips of light vehicles from Belarus
to Ukraine due to the conflict in the latter. As a result of these factors, the ex-post economic analysis
indicated that the actual discounted NPV of the project was US$ 36 million with an EIRR of 15.9
percent. The increase in the investment costs and the traffic reduction observed in 2015 were in part
compensated by the higher than expected roughness and road safety improvements. The ex-post EIRR
of 15.9 percent indicated the satisfactory economic justification of the project. More details of the ex-
post economic analysis are provided in Annex 3.
55. For Component 2 of road tolling at appraisal stage which was dropped later, the feasibility
study for the introduction of electronic road tolling for trucks over 12 tons on Belarus’ main highways
analyzed and compared eleven proposed combinations of different tolling technologies and toll levels.
For each of the eleven options the study looked at investment costs, annual operating and maintenance
expenditures, and expected toll revenues. It recommended introducing a tolling system based on
microwave technology, with retention and upgrade of the existing tolling system on the M1/E30 road.
56. For the revised Component 2 of “supply and installation of axle load monitoring and control
system”, the Borrower prepared feasibility study. The Bank team reviewed and confirmed the
technical and operational feasibility of the planned axle load monitoring and control system. The
detailed functional and technical design of the system was carried out by an international consulting
firm. The technology needed for the system was available from several suppliers. The proposed
technological option was to implement weigh-in-motion devices embedded in the pavement of all
major roads that carry large numbers of trucks. These devices were combined with vehicle recognition
technology and with ICT technology. Unlike static scales, WIM systems are capable of measuring
vehicles traveling at a reduced or normal traffic speed and do not require the vehicle to come to a stop,
which makes the weighing process more efficient. To address the gaps in the truck regulatory
framework and sustain the road sector, this option was by then regarded the most effective solution.
57. The efficiency is rated High against both the original and revised PDO.
3.4 Justification of Overall Outcome Rating
Rating: Satisfactory
58. As detailed above, the project was highly relevant to the Government’s strategy for the road
sector and the Bank’s most recent CPS. Most outcome targets were met and the PDO was achieved
efficiently. The project design was relevant to the project’s objectives and the investments were
economically justified. Despite the delays of Component 2 related to the change and installation of
Weigh-in-Motion system, given the complexity of the technical and procurement aspects, the Project
Implementation Team (PIT) from the counterpart and the project team from the Bank did a great job
to ensure quality implementation for each component.
59. As summarized in the table blow, against original PDO, the overall outcome rating is
satisfactory (substantial relevancy, substantial efficacy, and high efficiency), and against the revised
21
PDO, the overall outcome rating is satisfactory (substantial relevancy, substantial efficacy, and high
efficiency). Using the split evaluation, the combined overall outcome rating is Satisfactory.
Against Original
PDOs
Against Revised
PDOs
Overall
Relevance of PDOs,
design and
implementation
Substantial Substantial
Achievement of the
PDOs (Efficacy)
Substantial Substantial
Efficiency High High
Overall rating Satisfactory Satisfactory
Overall rating value 5 5
Weight (% disbursed
before/after PDO
change)
45.3% 54.7%
Weighted value 2.265 2.735 5
Final rating Satisfactory
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
60. Poverty impacts were not explicitly reflected in the PDO and results framework, but
experience elsewhere confirmed that upgraded and safer roads contributed to equitable growth and
reduced vulnerability, especially for those who remain near the poverty line, such as studies shown in
Cambodia. With respect to Belarus, over the past decade, rapid economic growth translated into
remarkable progress in poverty reduction, although the recent crisis was associated with a modest
poverty increase. The absolute poverty rate (national poverty line) declined from 30 percent in 2002
to about 6.3 percent in 2012. The country was also one of the most successful countries in the region
in sharing growth with the lowest 40 percent income group. In the 2006-2011 period mean income
growth averaged 6.4 percent, while growth of the lowest 40 percentile averaged 9.1 percent.
61. A social assessment was undertaken during project preparation to identify social issues
relevant to project objectives and execution (see Annex 6). Concerning the road upgrading works, the
implementing agency claimed that the project would have mostly positive impacts on the living
standards of the population of Belarus through its direct effects on employment and contribution to
economic growth. The PIT is planning to carry out another stakeholder workshop upon project
completion.
(b) Institutional Change/Strengthening
62. Institutional strengthening was a key feature of the project design. Within MA-C, a Project
Implementation Team (PIT) was created for this project, which consisted of experienced officials
from BELAVTADOR, MA-C, and other road sector agencies who have been assigned to work on the
various aspects of project preparation and implementation. The World Bank supported MA-C in the
necessary training of those specialists on the use of World Bank guidelines and procedures for
22
procurement, financial management, and environmental/social safeguards management. Additionally,
training and technical support were provided to staff of BELDORCENTER for the supervision of road
works under FIDIC rules. As project implementation was carried out by MA-C staff, the knowledge
gained will be maintained within the Ministry as long as key staff are retained.
(c) Other Unintended Outcomes and Impacts (positive or negative)
63. There are no noticeable negative impacts of the project.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
64. There was a stakeholder workshop conducted during project preparation regarding Component
1 of the road rehabilitation (see Annex 6). There were no objections from the public and concerns
about environmental impact caused by road rehabilitation work, ensuring road safety and roadside
service arrangement were addressed with proper mitigation measures. The PIT is planning to conduct
such a study after the full completion of the project.
4. Assessment of Risk to Development Outcome
Rating: Moderate
65. The development outcomes were: (1) to reduce transport cost; (2) to introduce modern axle-
load control system/WIM in Belarus as a tool to increase road sector sustainability.
66. At the time of this evaluation, there was negligible risk to the first outcome of reducing
transport cost.
Belarus has a good capacity to plan, manage and maintain its road infrastructure, with a very
good track record over the past decades. The state operates several enterprises for road
design, planning, research, standards, maintenance, and construction. The condition of the
road network is generally good, which is due in large part to the adequate allocation of
resources for road maintenance over the past decades.
Sustainable sector finance. Following a number of years of declining sector revenues the
Government undertook important steps towards sustainable sector finance and introduced
substantial increases in sector revenues and budget allocations for the road sector starting
2014. An important development was the promulgation of a new vehicle tax from January
2014 which was collected during the annual technical inspection of motor vehicles. In 2015
the estimated government revenues collected form this new fee were some BYR 2.3 trillion
(US$147 million and accounted for 71% of total road fund revenues) and were spent mostly
to finance expenditures on construction (39%), capital and current maintenance (20% and
2% respectively) of the republican road corridors and some on local roads.
Another significant development was the introduction of the e-tolling system, which has now
been deployed in selected roads in the country under concession to an international private
operator. The system has been operational since 2013, now covers 1,512 km and will be
expanded to cover all major road corridors including the M6 corridor. The e-tolling system
now generates sustainable financing for the road network and infrastructure. Estimated
revenues to the budget for 2015 were BYR 537 billion (US$34 million). Other sources of
revenue include minor revenues from axle load fees, transit cargo fees and fees paid by
foreign passengers cars accounting for a further BYR 372 billion (US$23.4 million) per year.
23
Establishment of the axle load monitoring and control system supported by Component 2 of
the project will directly ensure effective protection of the road assets and improve
sustainability of the current and future road investments in Belarus. Now that the system is
fully operational, there is weighing of 100% of trucks and those pre-identified as being
overweight are processed in a much reduced time frame (from 20 minutes to 5 minutes).
There have also been 2000 more special certificates issued for overweight vehicles in the
period to end of September 2016 than for the similar period in 2015. With this increased
focus on weight control this system is expected to become one of the key elements of the
effective institutional framework for sustainability of the road network. Thus,
implementation of both the original and revised project components address the important
development priority to increase the road sector sustainability in Belarus.
67. For the second outcome, the principle risk that the achieved development outcome may not be
sustained was moderate, and it involved the ability to maintain the WIM system and its integration
with the existing electronic tolling system. Although MA-C generally has good capacity but this
requires technically qualified staff and close coordination between multiple stakeholders. Through the
project implementation, the Bank was able to provide technical assistance and capacity building to
the clients, which was very helpful to keep the effectiveness of these investments. Meanwhile, the
Government is very committed in implementing and enforcing the WIM system, which is critical to
prevent overloaded trucks driving on roads and thus increase road sector sustainability. The
achievements after 5 months of WIM operation have clearly demonstrated the value of the system.
68. There were no financial, economic, political or environmental risks envisaged at the time of
this ICR. The Government is committed and takes ownership of the project, which is good to
sustainable the development outcome.
69. Taken together, the risk to development outcome is Moderate.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Moderately Satisfactory
70. The Bank’s preparation was thorough and collaborative, and built on lessons learned. The
scope of the project was strategically relevant and the approach was appropriate. Specific analyses of
technical, financial and economic aspects were carried out by experts in their respective fields. The
PDO and project design was simple and straightforward, though as mentioned above, parts of the
formulation of the PDO should have actually referred to an outcome not an output. The
implementation plan was practical with support for implementation agency on the use of World Bank
guidelines and procedures for procurement, financial management, and environmental/social
safeguards management. The project also included strengthening of the institutional capacity of road
sector institutions of the Borrower by providing technical assistance and training, in particular, the
capacity of local institutions to manage FIDIC-type civil works contracts. Despite change of
Component 2 requested by the Government that led to change of PDO, the scope of the project stayed
focused and uncomplicated. The M&E arrangement was well prepared and indicators were
24
uncomplicated with baseline collected properly, except the indicators for Component 2 as mentioned
the assessment of M & E design. Very detailed AMs from each mission demonstrated the Bank team’s
close collaboration with the recipient and implementing agency in preparation, appraisal and
implementation of the project. The only shortcoming at entry was that both the PDO and result
framework did not capture the outcome of “cost recovery” from the original Component 2 (e-tolling),
or the outcome of “increased sector sustainability” from the revised Component 2 (WIM). No PDO
level or intermediate indicators were included in the original and revised result framework to measure
these two outcomes. Admittedly, increased sustainability of roads might be difficult to measure as an
end-of-project outcome, especially attributing this to one specific element such as a new axle load
measuring & control system. But, even so, the PDO could have been changed to include another more
directly attributable and measurable outcome, or at least an indicator of the actual utilization of the
new WIM system as measured by the number of measurements generated, the number of enforcement
actions taken, or the percentage reduction of overweight vehicles. These shortcomings therefore
prevented assigning Satisfactory rating to the quality at entry.
(b) Quality of Supervision
Rating: Satisfactory
71. Despite a small delay of project effectiveness, the procurement of most project activities were
well advanced after Board approval. The Bank was proactive in carrying out a series of fiduciary and
technical training programs following project effectiveness. The Bank’s supervision of fiduciary
aspects was exemplary. Supervision was carried out at regular intervals in the areas of environment
and social safeguards, financial management and procurement. Mission oversight in each area was
supplemented by training and assistance when requested, and proactively offered when deemed
necessary.
72. Mission reporting was timely and thorough, and assessments of performance were realistic
and accurately reported in ISRs. Harmonized systems and coordinated efforts were a major source of
success, with one implementation manual, one system for government to implement and one set of
reports to prepare.
73. The technical nature of the contract for the supply and installation of the WIM system for the
revised Component 2 caused a delay in the procurement process. In addition to slow procurement
processing there were a number of reasons for this including: (i) delays in defining technical
specification of the system; (ii) protracted negotiations with operator of e-tolling system on integration
issues; and (iii) delays in concluding contract negotiations due to delays of getting agreement on a
government waiver for VAT. The Bank team closely monitored this contract and promptly discussed
with the Country Management Unit (CMU) possible remediation actions. It should be noted that after
award of the supply contract, implementation was to schedule.
(c) Justification of Rating for Overall Bank Performance
Rating: Moderately Satisfactory
74. The Bank’s performance was rated Moderately Satisfactory for quality at entry and
Satisfactory for quality of supervision. Therefore the overall Bank performance rating is Moderately
Satisfactory.
25
5.2 Borrower Performance
(a) Government Performance
Rating: Moderately Satisfactory
75. The Government’s ownership and commitment were strong, as the objectives of RUMP were
consistent with the CPS and Belarus’ evolving development strategy and in direct support of the
Government’s objectives for the road sector that are expressed in its program “Roads of Belarus 2006
– 2015”. The Government also funded supervision of civil works for Component 1, which was
executed by specialized state agencies.
76. The project had a slow start due to delayed project effectiveness as discussed in Section 2.2.
Upon effectiveness, the project progressed well. All covenants were compiled with. Fiduciary
compliance was good, audit reports were submitted on time and auditor’s opinions unqualified,
environmental and social oversight were carried out with due diligence, and good implementation
plan endorsed. Follow-up actions were generally taken on a timely basis when required. However,
there were some delays to the project caused by the high-level Government interference in project
management such as redirecting the activities of Belarussian sub-contractors that slowed down
construction works on M5, and some delays with getting agreement on a waiver for VAT for
Component 2, which prevented from assigning Satisfactory performance to the Recipient.
(b) Implementing Agency or Agencies Performance
Rating: Satisfactory
77. After the aforementioned initial delays, the project was implemented efficiently and
effectively by MA-C. Within MA-C, a Project Implementation Team was created, which consisted of
experienced officials who performed well with supervision; environmental and social monitoring;
financial management, accounts and audits; and data collection for economic evaluation. All major
civil works contracts and most of institutional activities were completed by the project closing date.
78. Mission review meetings were well attended, including high level officials whenever possible.
Implementation problems were usually addressed promptly and supervision was generally timely.
(c) Justification of Rating for Overall Borrower Performance
Rating: Moderately Satisfactory
79. The Borrower ensured quality of preparation and implementation, and complied with
covenants and agreements towards the achievement of development outcomes. The combination of
the Government’s performance rating of Moderately Satisfactory and the Implementing Agency rating
of Satisfactory results in an overall Borrower Performance rating of Moderately Satisfactory.
6. Lessons Learned
80. The combination of supervision by local Bank staff whose proximity enabled them to
provide timely advice and solve problems, with the participation of international staff with
expertise in specific areas when needed, yields good results. In the case of RUMP, the successful
26
performance of the implementing agency in the areas of civil works, safeguards and financial
management, for example, was due both to the commitment and qualifications of MA-C staff and the
effective, timely support from local and HQ-based Bank staff when needed.
81. On-the-job training for PIU staff clearly improved implementing agency’s capacity to
manage FIDIC type contracts.
82. Sufficient flexibility in project design. Though the implementation agency has strong
capacity, experiences showed that decisions made at the ministerial level can sometimes be overturned
(permanently or temporarily). In a case of a sophisticated client country, project design as reflected in
legal documents needs to consider introducing sufficient flexibility to allow minor changes without
major restructuring and complex approval processes.
83. M & E design. For this project, most of the M & E system relied on data already routinely
collected - the data needed for monitoring the selected indicators was of the type that was normally
collected by the Belarusian government departments and agencies and thus were easily monitored.
84. Sustainable financing of road maintenance. In the case of Belarus, introducing electronic
tolling is a creative and diverse solution for financing the road sector.
85. Streamline the operation of e-tolling and WIM systems. Choice of the operational
mechanism, institutional setup, government commitment and the choice of appropriate technology
and regulatory framework are critical for successful operation of such advanced systems.
86. Procurement of contractors. Experience from Belarus and more widely in the region is that
some contractors present very low prices in the winning bids and afterwards delay the execution of
works through requests for variations. There is also a problem where large international contractors
obtain awards and then sub-contract a significant portion of works to local contractors. It is therefore
important to pay particular attention to prequalification criteria and the past performance of
contractors in the region. Also, it is important to be aware of differences between local legislations
and the Bank’s standard procurement policies.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
87. The Borrower had no specific comments. The overall assessment and rating on the
performance of the project was found acceptable. A summary of the Borrower's ICR is presented in
Annex 7.
(b) Cofinanciers
N/A
(c) Other partners and stakeholders N/A
27
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Components Appraisal Estimate
(USD millions)
Actual/Latest
Estimate (USD
millions)
Percentage of
Appraisal
Component 1: Road Upgrading 131.00 134.30 102.51%
Component 2: Axle Load
Monitoring and Control System 18.00 10.38 57.64%
Component 3: Technical
Assistance and Capacity Building 1.00 1.06 106.04%
Front-end Fee 0.375 0.375 100%
Total Project Costs 150.00 146.11 97.40%
(b) Financing
Source of Funds Type of
Cofinancing
Appraisal
Estimate
(USD
millions)
Actual/Latest
Estimate
(USD
millions)
Percentage of
Appraisal
Borrower 0.00 0.00
International Bank for Reconstruction
and Development 150.00 146.11 97.40%
28
Annex 2. Outputs by Component
A. Outputs by Component
Project Activities Outputs Changes and Current
Status
Component 1: Road Upgrading
Upgrade of 52.7 km of the M5
road
Upgraded 52.7 km of the M5 road (km 65-93 and km106-131 from a
2-lane (Category 2) road to a 4-lane (Category 1B) motorway
Completed
Road Safety Wider medians and shoulders in line with EU standards;
Six two-level interchanges, seven overpasses, four bridges, two
pedestrian underpasses and bypasses at the village of Sosnovy
(about 5.7 km long) and at the village of Boyary (about 4.2 km)
were constructed, where the alignment will be shifted in order to
increase the distance between the road and the nearest houses;
Speed limits were adjusted along the alignment at the remaining
level crossings.
Completed
Component 2: Axle Load Monitoring and Control System
Design and implementation of
an automated axle load
monitoring and control system
(WIM)
4 stationary weight control points installed
8 portable weight control stations installed
12 WIM portals installed
Sensors, cameras, computing center, and data links installed for 12
WIM locations
Completed
Component 3: Technical Assistance and Capacity Building Technical Assistance HDM-4 software was purchased for BELGIPRODOR and the
Individual Consultant was hired to provide training on the software
HDM-4 version 2.5 for BELGIPRODOR staff.
Project audited.
Completed
Capacity Building Training provided to staff at PIU.
Loius Berger SAS has been recruited and has been working since
mid-2011, giving practical advice and guidance to local institutions
on the management of the four road rehabilitation contracts
(FIDIC-type civil works contracts) under Component 1.
Completed
29
B. Assessment of the Overall Outcome
Baseline Original Target First
Restructuring
Target
Second
Restructuring
Target
Third
Restructuring
Target
Status at
Closing
Remarks
PDO Indicators
Reduced vehicle operating
costs on upgraded section
of M5 (%)
100 94 94 94 94 86 Completed
Electronic road tolling
system
introduced in Belarus on a
section of the M5 road
No 960 km of
national highway
under e-tolling
Dropped Dropped Dropped Dropped Dropped
Intermediate Outcome Indicators
Component 1: Road Upgrading
Road constructed (km) 0.00 52.70 52.70 52.70 52.70 52.70 Completed
Road roughness 3.30 2.00 2.00 2.00 2.00 1.14 Completed
Traffic fatalities 12 5 5 5 5 5 Completed
Component 2: Axle Load Monitoring and Control System
Axle Load Monitoring and
Control System installed
and operational (Date)
No Yes, 30-Nov-
2014
Yes, 30-Nov-
2014
Yes, 30-Nov-
2015
Yes, 31-Mar-
2016
Yes, 31-Mar-
2016
Completed
Component 3: Technical Assistance and Capacity Building
Capacity to manage FIDIC
type contracts
No Yes Yes Yes Yes Yes Completed
30
C. Description of Weigh-in-Motion System and E-tolling in Belarus
1. As a transit country, Belarus has a large percentage of trucks travelling on its road network.
Recently, the government implemented microwave based e-tolling (see Figure 1) and through this
project have installed WIM to link with existing e-tolling system. In all 12 WIM sites were
equipped throughout the country, and the sites are installed with all required hardware and based
on Beltoll toll roads system control gates.
Figure 1: Location of Beltoll control gates
Source: http://belarusfacts.by/upload/kartaru_en.pdf
2. The systems consist of a set a control gates on the main republican roads that provide
information of overweight vehicles to Transport Inspection, the operators for further inspection of
overloaded trucks. A brief demonstration of the WIM site/gate is showed in Figure 2 below.
31
Figure 2: Belarus WIM diagram.
Source: http://www.kapsch.net/by/ktc/Portfolio/Intelligent-Mobility-Solutions/Safety-
Security/Road-Safety-Enforcement/Weigh-In-Motion
3. The goal of the system is a pre-selection of trucks that should be enforcement weighed.
This goal is reached with a combination of high-speed weigh-in-motion systems, centralized data
center and equipment update at the weight control stations.
4. There are three truck “statuses” in the system: 1) weighed in motion and not overweight;
2) weighed in motion and there’s a possible overweight; 3) did not pass the gate. Inspectors will
check vehicles falling in the last two categories while the first category of vehicles will not be
stopped which minimizes inspector efforts and traffic disruptions.
5. For each single dynamic weighing station, a set of strain-gauge sensors were installed in
the road bed and were connected with the digital block by cables for data transmission to the
camera portal and the computing center. And a set of vehicle license-plate recognition and photo
fixation cameras were installed on the portals above the road directly behind the sensors in the
road. These equipment were connected with the digital block by cables for data transmission to
the computing center.
6. The purpose/function for different units are illustrated in the following Figure 3.
32
Figure 3: Assembly diagram indicating the purpose of units
Source: RUE Minskavtodor-Center
Overall system architecture
7. The overload control system includes 12 WIM sites (Figure 4), 4 fixed heavy vehicle
inspection centers (Figure 5) and 8 mobile stations (Figure 6) with locations strategically
distributed through the network.
Figure 4: WIM site – installation process
Installing video and number plate recognition cameras
33
The electronic systems at road side
Narrow weight measuring sensor to ease installation
Source: World Bank.
8. There are 4 heavy weight and overall dimensions control stations (e.g., heavy vehicle
inspection center) on both sides of roads throughout the republican road network.
34
Figure 5: Belarus heavy vehicle inspection center
Source: World Bank.
9. Additionally, there are 8 mobile stations that are self-contained and can be used flexibly
through the network.
Figure 6: Mobile Stations of WIM
Source: World Bank
35
10. WIM control sites process raw data locally and send information of weighed vehicles to the
central system unit or to the directly connected mobile station / Transport Inspection patrol.
The processed “weighing results” contain all needed information, including weight, vehicle plate
number, vehicle type, air temperature etc.
11. Each mobile station / patrol and the heavy vehicle inspection center may receive information
from the central unit or directly from the configured gates and have access to data collected through
any of the 12 WIM sites/gates (Figure 7 and 8).
Figure 7: Weighing station architecture
Figure 8: Overall system architecture
Source: RUE Minskavtodor-Center
12. It is worth to mention that when an overloaded vehicle was sent to a nearby mobile station
for further measurement, the conversation between the driver and inspection officers will
be recorded to prevent potential bribe/corruption.
36
13. Central processing unit is placed in Beltoll system data center and provides further storage
and analysis for all received information. For example, in Belarus, WIM data has been used
to understand traffic flow patterns that lead to better traffic management.
37
Annex 3. Economic and Financial Analysis
1. At appraisal the World Bank team analyzed the economic feasibility of the upgrading of the
53 km sections of the M-5/E271 road from two-lane to a four lane road using the Highway
Development and Management Model (HDM-4). The economic evaluation compares the economic
costs and benefits of the “Project Scenario” with those of the “Base Case Scenario”, which assumed
that no major capital investment takes place on the road (maintenance only). The economic benefits
were derived from lower maintenance and repair of the upgraded road, lower vehicle operating cost,
travel time savings and accident rate reduction. The evaluation period was set to 30 years from the
planned start of construction in 2010 until 2039 and the discount rate was set to 12 percent.
2. At appraisal the World Bank funded section was estimated to have a length of 52.7 km and the
road works were expected to cost US$120 million, including local and environmental taxes, on a two
years construction period. The 2009 traffic levels on the project road varied between different sections,
with an average of about 8,400 vehicles per day. The average annual traffic growth was expected to
be 5 percent for light vehicles and 3 percent for trucks and buses over the period 2010-2039. Applying
these growth assumptions, the project road traffic was assumed to grow from 8,380 vehicles per day
in 2009 to 10,824 vehicles per day in 2015 and 30,956 vehicles per day by 2039. No generated traffic
was considered in the evaluation.
3. The project road sections were in fair condition in 2009 with an average roughness of about
3.3 IRI, m/km, which was expected to reduce to 2.0 IRI, m/km, after the road upgrading to four lanes.
The ex-ante economic evaluation considered road safety benefits in terms of reduction of road
accidents with fatalities and with injuries. The rate of accident with fatalities was estimated to decrease
from 5 fatality accidents per 100 million vehicle –km on the two lane road to 4 fatality accidents per
100 million vehicle –km on the four lane road, while the rate of accident with injuries was assumed
to decrease from 12 injury accidents per 100 million vehicle –km to 9 injury accidents per 100 million
vehicle –km. The ex-ante economic analysis indicated that the estimated discounted net present value
(NPV) of the project was US$ 159 million with an internal rate of return (EIRR) of 21.1 percent. Since
the economic analysis for Component 2 was more in the nature of feasibility studies, the analysis here
refer to Component 1 of road works only.
4. The project ex-post economic analysis was done also using the HDM-4 model, using the same
road use costs and assumptions adopted on the ex-ante analysis, but the ex-post analysis adopted: (i)
the actual investment costs; (ii) the actual construction period and disbursements profile; (iii) actual
annual traffic growth observed on the project road sections from 2009 to 2015; (iv) actual roughness
of the road sections after the improvement works; and (v) actual accident rates on the project road
sections after the improvement works.
5. The project road was subdivided into four road sections that were upgraded under four
contracts. The table below presents the basic contracts characteristics. The total contracts cost as
signed is US$123.60 million, while after contracts revisions, the actual upgrading cost is US$134.26
million, which is 12 percent higher than the total cost estimated at appraisal (US$120 million).
38
Table 1. Contracts Characteristics
Lot Length
Contract
Cost
Actual
Cost
No Lot Description (km) (US$ M) (US$ M)
1
М-5 Minsk-Gomel road, km 65.18 -
km 82.60 17.42 33.80 36.14
2
М-5 Minsk-Gomel road, km 82.60 -
km 93.00 10.40 31.90 34.15
3
М-5 Minsk-Gomel road, km 106.01
- km 122.60 16.59 30.10 33.30
4
М-5 Minsk-Gomel road, km 122.60
- km 131.00 8.40 27.80 30.66
Total 52.81 123.60 134.26
6. The road works started on November 2011 and were completed on November 2013 (table
below). In 2011 and 2012, 43 percent of the contract costs were disbursed (US$ 53.38 million) and
the rest afterwards. This represents a two year delay in relation to the construction period assumed on
the ex-ante economic evaluation (2010 to 2011)
Table 2. Contracts Dates
Lot Contract Commencement Completion Completion
No Signing of Works (initial) (final)
1 7/19/2011 11/10/2011 8/9/2013 11/15/2013
2 7/20/2011 11/10/2011 8/9/2013 11/15/2013
3 7/21/2011 11/10/2011 8/9/2013 11/15/2013
4 7/22/2011 11/10/2011 8/9/2013 11/15/2013
7. Traffic counts available for 2010 to 2015 show that the average traffic of the project road
sections actually decreased from 2010 from 2015 (table below). At appraisal the average traffic was
estimated to be 8,380 vehicles per day in 2009, in 2010 the average traffic was 8,456 vehicles per day,
while in 2015 the average traffic decreased to 7,593 vehicles per day, representing a decrease of
around 2 percent per year from 2010 to 2015. In contrast, the ex-ante economic analysis considered
the annual traffic growth was expected to be 5 percent for light vehicles and 3 percent for trucks and
buses over this period. Passenger cars represent about 66 percent of the vehicle fleet composition. The
traffic decrease was caused by both internal and external factors:
The decrease in truck freight, that has the largest share (approximately 95 percent) of the entire
freight volume, is due to a reduction of contracted construction, industrial and agricultural
production. According to the National Statistical Committee of the Republic of Belarus, in
2015 construction and installation work was 88.0 percent of that in 2014, industrial production
was 93.4 percent of that in 2014, and agricultural output – 90.5 percent of that in 2014.
Reduction of the volumes of international, inter alia, transit, road freight through the Republic
of Belarus is primarily due to the factors that determine the status of the foreign trade of the
Russian Federation with the European Union. The trade in 2015 between the Russian
Federation and the European Union amounted to USD 230 bln, or 60 percent, as compared to
the year of 2014. It was caused by worsening of the political and economic relations between
39
the Russian Federation and the European Union, EU sanctions against selected sectors of the
Russian economy and retaliatory sanctions by the Russian Federation on import of food from
the countries that have imposed sanctions on Russia. Because of these sanctions, the number
of foreign truck transit trips reduced by 18.5 percent.
Car traffic reduction is due to social, as well as external geopolitical factors. The internal social
factors include the reduction of actual available income, which, according to the National
Statistical Committee of the Republic of Belarus, is 94.1 percent in 2015, as compared to the
year 2014. The external factors are related to the conflict situation in Ukraine, which resulted
to decrease in the number of trips of light vehicles owned by Belarusian citizens to Ukraine
for tourism and recreation.
Table 3. Road Sections Traffic
Lot 2010 2015
No (AADT) (AADT)
1 8,699 6,249
2 8,699 6,249
3 8,185 9,089
4 8,185 9,089
Average 8,456 7,593
8. Roughness measurements done on the project road sections in 2014 and 2015 show that the
average roughness of the road sections after the improvement works is about 1 IRI, m/km, which is
lower than the 2 IRI, m/km, adopted on the ex-ante economic analysis for the roughness after the road
works. This indicates that the upgrading work were of very good construction quality.
9. The table below shows the total fatalities and injuries per year on the project road sections
from 2011 to 2015. The average total fatalities per year from 2011 to 2013 (before the project) is 6.3
fatalities per year and from 2014 to 2015 (after the project) is 3.5 fatalities per year, which represents
a 45 percent reduction in fatalities. The ex-ante economic analysis considered a 20 percent reduction
in the fatality rate. The average total injuries per year from 2011 to 2013 is 17.7 injuries per year and
from 2014 to 2015 is 8.5 injuries per year, which represents a 52 percent reduction in injuries. The
ex-ante economic analysis considered a 25 percent reduction in the injury rate. Therefore, the actual
reduction in road fatalities and injuries with the project were higher than the ones estimated at
appraisal.
Table 4. Road Fatalities and Injuries
Lot Number of Fatalities per Year
No 2011 2012 2013 2014 2015
1 7 1 0 1 1
2 2 3 2 1 0
3 0 1 3 0 3
4 0 0 0 0 1
Total 9 5 5 2 5
Lot Number of Injured per Year
No 2011 2012 2013 2014 2015
1 5 4 3 1 1
2 6 6 3 3 0
3 5 12 8 3 7
40
4 0 0 1 1 1
Total 16 22 15 8 9
10. The World Bank team performed the ex-post economic evaluation of the project adopting all
the actual data available related to the investment costs, timing of the investments, annual traffic
growth rate, and road user benefits due to ride quality and road safety improvements. The ex-post
economic analysis indicates that the actual discounted net present value (NPV) of the project is US$ 36
million with an internal rate of return (EIRR) of 15.9 percent. The increase in the investment costs
and the traffic reduction observed from 2009 to 2015 were in part compensated by the higher than
expected roughness and road safety improvements. The ex-post EIRR of 15.9 percent indicates the
satisfactory economic justification of the project.
41
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Names Title Unit Responsibility/
Specialty
Lending
Rodrigo Archondo-Callao Sr Highway Engineer GTIDR Highway Engineer
Andreas Schliessler Lead Transport Specialist GTIDR Task Team Leader
Elena Klochan Sr Country Program Officer ECCBY Country Program
Officer
Dmytro Kryshchenko Projects Officer CNGF8 Projects Officer
Alexander Rukavishnikov Sr Procurement Specialist GGODR Procurement
Specialist
Arcadii Capcelea Sr Environmental Specialist GENDR Environmental
Specialist
Bekim Imeri Sr Social Development Specialist GSURR Social Development
Irina Babich Sr Financial Management
Specialist GGODR
Financial
Management
Romain Pison Junior Professional Associate GTIDR Road Engineer
Jukka-Pekka Strand Infrastructure Finance Specialist GEEDR Economist
Svetlana Vukanovic Transport Specialist GTIDR Transport Specialist
Irina Trukhan Team Assistant ECCBY Team Assistant
Supervision/ICR
Andreas Schliessler Lead Transport Specialist GTIDR Team Leader from
2009 to August 2013
Rodrigo Archondo-Callao Sr Highway Engineer GTIDR Highway Engineer
Elena Klochan Sr Country Program Officer ECCBY Country Program
Officer
Simon David Ellis Lead Transport Specialist GTIDR
Team Leader from to
August 2013 to June
2016
Barbara Ziolkowska Procurement Analyst GGODR Procurement Analyst
Arcadii Capcelea Sr Environmental Specialist GENDR Environmental
Specialist
Nijat Valiyev Sr Infrastructure Specialist GTIDR
Co-Team Leader
from November 2015
to June 2016
Bekim Imeri Sr Social Development Specialist GSURR Social Development
Maria L. Amelina Sr Social Development Specialist GGODR Social Development
Sara Gonzalez Flavell Special Assistant IEGDG Special Assistant
Wei Wang Transport Specialist GTIDR Big Data and ICT
Yevhen Bulakh Transport Specialist GTIDR Road Engineer
Juan Navas-Sabater Lead ICT Policy Specialist GTIDR ICT Specialist
42
Alexei Slenzak Sr Environmental Specialist GENDR Environmental
Specialist
Irina Trukhan Team Assistant ECCBY Team Assistant
Alexander Rukavishnikov Sr Procurement Specialist GGODR Procurement
Specialist
Funda Canli Program Assistant GTIDR Program Assistant
Hanna Shvanok E T Temporary ECCBY Team Assistant
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
2010 35.56 157,724.3
2011 18.99 61,179.4
Total 54.55 218,903.70
Supervision/ICR
2012 20.21 111,779.3
2013 20.82 87,365.1
2014 34.83 113,072.8
2015 24.29 97,261.6
2016 24.99 99,458.2
Total: 125.14 508,937.00
44
Annex 6. Stakeholder Workshop Report and Results
1. During project preparation, the RUE Minskavtodor-Center conducted public consultations
with stakeholders such as local authorities, individuals living closely to upgraded roads and etc. There
were no objections from the public. Concerns about the potential environmental impact on the wildlife,
on road safety and roadside services were properly addressed with mitigation measures. The original
minutes are attached here.
2. The Borrower suggested that the following lessons learned from this project will make the
implementation of such projects in the future more efficiently:
Discussion of all designs that would affect public interests at all stages of project preparation
Informing the public in advance with mass media about the objectives and positives impacts
of the project
Analyze public satisfaction after project implementation
49
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR
1. On December 29, 2015, MA-C, the Project Implementing Unit submitted to the Bank its final
Project Completion Report. Below is the original from the Recipient’s Report covering project
description, project objectives and results achieved, project implementation management, assessment
of the performance of the Recipient and the Implementing Agency, and of the World Bank, as well as
lessons learned. The Borrower had no specific comments. The overall assessment and rating on the
performance of the project was found acceptable.
Project Description
2. Ministry of Transport and Communication of the Republic of Belarus represented by RUE
“Minskavtodor-Center” (MA-C) is implementing Road Upgrading and Modernization Project
(Project), financed by World Bank. The Borrower is the Republic of Belarus.
3. Road Upgrading and Modernization Project is the first World Bank supported operation in
Belarusian road sector. The Loan Agreement for the amount of 150 mln. USD was signed on
November 19, 2010 and became effective on July 5, 2011.
4. The initial development objective of the project was to reduce transport costs for road users
on the upgraded sections of the M5 road, and introduce electronic tolling in Belarus as an efficient
cost recovery mechanism. On March 18, 2013 the Project was restructured and the objective of the
Project was amended and replaced to read as follows: “The objectives of the Project are to reduce
transport costs for road users on upgraded sections of the M5 road and introduce axle-load control
system as a tool to increase road sector sustainability”.
5. The proposed Road Upgrading and Modernization Project is part of the overall lending
pipeline, which has been identified in the 2009 Belarus Country Partnership Strategy.
6. The section to be upgraded is located between Minsk and Bobrujsk and is part of the 508 km
long Belarusian section of the Trans-European Transport Corridor IXb linking Baltic Sea and Black
Sea ports, between Klaipeda – Vilnius – Minsk – Kiev and Odessa. The Project provides for upgrading
and modernization of a 53 km section of the M-5/E271 road from a two-lane to a four-lane road and
is part of the Government’s road sector investment plan.
7. Initially it was supposed to implement the Project within 4 years, but the closing date was
twice extended and is May 31, 2016.
Project Development Objective
8. The objectives of the Project are to reduce transport costs for road users on the upgraded
sections of the M5 road and introduce a modern axle-load control system in Belarus as a tool to
increase road sector sustainability.
9. The Project consists of three components. The details of each component are indicated below.
10. Component 1 – Upgrading of 53 km section of the M-5 Minsk-Gomel Highway. Estimated
cost was 131 mln USD. The existing road has traffic levels in the order of close to 9,000 vehicles per
day, with traffic growth rates averaging 10 percent. This component includes: (i) reconstruction of the
existing two lanes and the construction of two additional lanes to carry a design axle load of 11.5 tons;
50
(ii) improvement of road safety features in line with EU road standards; (iii) construction of about six
two-level interchanges, seven overpasses, four bridges, two pedestrian underpasses and bypasses at
the village of Sosnovy (about 5.7 km long) and at the 8 village of Boyary (about 4.2 km), where the
alignment will be shifted in order to increase the distance between the road and the nearest houses;
and (iv) implementation of a number of environmental impact management features.
11. Component 2 - Axle-Load Monitoring and Control System. Estimated cost was 18 mln
USD. The Component 2 of the project consists of the design, procurement and implementation of
weighing- motion devices embedded in the pavement of major roads that carry large numbers of
trucks. The system would bring Belarus to the forefront of efficient axle load control and thus protect
its road assets from premature deterioration. The stations will be along the non-tolled portion of the
main road network, since the axle load control along the toll roads will be integrated in the tolling
system.
12. Component 3 - Road Sector Institutional Support. Estimated cost was 1 mln USD. This
component is aimed at strengthening of the institutional capacity of road sector institutions of the
Borrower by providing technical assistance and training, including
(i) support to BELGIPRODOR for updating its economic evaluation tools for road projects, including
training on HDM4 and procurement of software licenses;
(ii) support to improve the capacity of local institutions involved in supervision of road works at a
level to carry out supervision under FIDIC rules;
(iii) support for carrying out the project audits;
(iv) assistance by a specialized consultant firm for development and introduction of Axle-Load
Monitoring and Control System in Belarus and
(vi) other minor project-related technical assistance, training and/or goods to support capacity building
and Government institutions in the road sector.
Project Implementation
13. Component 1 Upgrading of 53 km section of the M-5 Minsk-Gomel Highway. The road
Component was divided into 4 lots. Civil works were performed by Todini Costruzzioni s.p.a. within
4 Contracts, awarded for the total amount of 87,6 mln euro. The actual amount of certified payment
under the Contracts - 73,7 mln euro (the reduction is caused by the depreciation of Byelorussian ruble).
Although the original completion date was stated on August 9, 2013 an extension of Time for the
Contractor was agreed at no cost for the Employer and the total scope of Works provided by the design
documentation was substantially completed by November 15, 2015.
14. The full responsibility for the supervision of the civil works has been with Beldorcenter - a
state owned consultancy company, which undertook the role of Engineer of four civil works contracts
administered by using, as contractual framework, 2005 FIDIC Conditions of Contract for
Construction.
15. Feasibility study, drafting of the project and bidding documents, technical supervision were
financed by the budget and amounted to 48.9 bln Byelorussian rubles.
16. Component 2 Axle-Load Monitoring and Control System. This Component initially
provided for supply and installation of a modern electronic road tolling system based on microwave
technology on a 106 km section of the M5 Road between Minsk and Bobrujsk. As a result of a bid on
July 7, 2011 the Contract was awarded to Zierl Gmbh, which drafted the terms of reference for
51
system’s supply and installation. On February 29, 2012 the Government of the Republic of Belarus
signed the investment agreement with Kapsch TrafficCom AG for the installation of the Electronic
Toll Collection System for the national motorways, covering mentioned M-5 section as well. As a
result, the Contract with Zierl Gmbh was terminated and the Loan agreement was amended on March
18, 2013 as to introduce the Axle-Load Monitoring and Control System in Belarus.
17. The new bid was launched in March 2013 and the Contract for Consulting services for
introduction of a dynamic weighing system at the national roads was signed with SWEROAD Solna
(Sweden) on April 2, 2014. The delay in Contract award took place as the highly-rated Consultant
refused to follow up Contract negotiations and the Employer had to proceed with SWEROAD Solna
as with secondly rated Consultant. On November 26, 2014 the bid for Design, Supply and Installation
of Dynamic Weighing System at the National Roads of Belarus was launched and on April 10, 2015
the Contract with JV Betamont s.r.a (leader) and ITS Bel was signed. As the DWS system is
implemented based on existing Electronic Collection System infrastructure, the integration of these
two systems became necessary and the Contract providing for such an integration was signed with
Kapsch TrafficCom AG.
18. Component 3 - Road Sector Institutional Support. Within this component HDM-4 software
was purchased for BELGIPRODOR and the Individual Consultant was hired to provide training on
the software HDM-4 version 2.5 for BELGIPRODOR staff.
19. On July 7, 2011 the Contract with Loius Berger SAS was signed to provide technical assistance
for support for supervision of FIDIC-type civil works and conduct training for benchmarking and
harmonization of the Byelorussian road construction, repair and maintenance standards and
expenditure levels to European and international standards. Loius Berger SAS worked closely with
the Employer and the Engineer (RUE Beldorcenter) over the period of 3 years, in which practical day-
to-day advices have been given through on-call services, missions to the Republic of Belarus and the
permanent presence on Site of a FIDIC Highway Engineer starting from the second year of
assignment. The Consultant also provided two formal training sessions with the aim to improve The
Employer’s and Engineer’s capacity in supervising contracts under FIDIC Conditions of Contract.
20. The Component also financed the audit of the Project and RUE Minskavtodor-Center for the
period 2012 – 2015 and the training of the Employer’s staff aimed at PIU’s capacity improvement.
Evaluation of the Borrower’s Own Performance during the Project Preparation and
Implementation
21. The performance of the Borrower and Ministry of Transport and Communication in carrying
out the responsibilities assigned to them was satisfactory. RUE Minskavtodor-Centre (MA-C) as the
Project Implementing Agency has sole responsibility for overall project implementation. MA-C was
in charge of day-to-day project operation. The General Director has been appointed to be responsible
for project implementation. The Chief Accountant has been appointed to coordinate fiduciary aspects
of project implementation.
22. The Project Implementing Agency has been working for effective solution of all problems
arisen in the process of project implementation. Safeguard measures were implemented in full in order
to mitigate the negative social and ecological impact of the Project. The Borrower and Implementing
Agency carried out their obligations of full payment of compensation to persons negatively affected
by the Project out of republican budget.
52
23. The capacity of Project Implementing Agency increased from the beginning of the project
implementation.
Evaluation of the Performance of the Bank during the Project Preparation and Implementation
24. The performance of the Bank was considered successful. On a regular basis the World Bank
carried out review missions during the Project Implementation. These missions were focused on
projects inputs and outcomes. The World Bank worked closely with the Ministry of Transport and
Communication and MA-C to resolve issues arisen during the Project implementation and provide
necessary assistance. Form the side of the World Bank there were no delays in payments or review
the inquiries.
Conclusions and Lessons Learned
25. By the December of 2015 the Components 1 and 3 were successfully completed. The weigh-
in-motion system under the Component 2 is planned to be completed by the end of March 2016.
26. The M-5 Minsk-Gomel highway conditions were improved to 4 lanes-dual carriageway
expressway standards on 52.7 km. The project’s original target was met by project closure (see
Attachment 2 Project Development Objective Indicators). The civil works performed were of good
quality, despite significant delays due to the necessity of introduction of modification in origin design
project. The necessity of conducting additional works arose frequently in the process of the project
construction works. Delay in civil works completion also was caused by decision of the Minister of
Transport and Communication to review the project design regarding the possibility of optimization
the costs for engineering structures. In order to minimize risks of significant changes occurrence at
the stage of project implementation in future it is necessary to enhance the designing and detailed
Bidding documentation development.
27. The completion of WIM-system installation under Component 2 is planned to be completed
by the end of March, i.e. the project’s revised target will be achieved before the Closing Date. Delays
in implementation of Component 2 are connected with the project restructuring. Another delays
occurred at the stages of selection of Consultant for Bidding documentation development (the
originally selected Consultant withdrew at the stage of Contract negotiations) and Contract
negotiations with the Contractor for WIM-system supply and installation (long procedure of
harmonization of Bank’s Standard Contract Forms and Belarusian legislation).
28. In order to avoid such delays it is necessary to carefully assess the Bidding and Contract
documentation on discrepancies between Bank’s standard forms and local requirements and ensure
their compliance with the local legislation.
53
Appendix 1. Contracts (initial and final amounts)
№ Company Contract Currency of
Contract
Amount of
signed
Contract,
excluding
VAT
Final Amount
of Contract,
excluding
VAT
Component 1. Upgrading of 53 km section of the M-5 Minsk-Gomel Highway
1 Todini
Costruzioni
Generali S.p.A.
Upgrading of
M-5 Road, km
65,18 – km
82,6. Lot 1
euro 23 962 977,62 27 258 435,11
2 Todini
Costruzioni
Generali S.p.A.
Upgrading of
M-5 Road, km
82,6 – km
93,0. Lot 2
euro 22 643 123,69 25 820 512,31
3 Todini
Costruzioni
Generali S.p.A.
Upgrading of
M-5 Road, km
106,01 – km
122,6. Lot 3
euro 21 304 982,67 25 235 573,60
4 Todini
Costruzioni
Generali S.p.A.
Upgrading of
M-5 Road, km
122,6 – km
131,0. Lot 4
euro 19 732 912,28 23 316 024,03
Component 2. Axle-Load Monitoring and Control System
1 ZIERL Consult Supply and
installation of a
modern
electronic road
tolling system
based on
microwave
technology on
a 106 km
section of the
M5 Road
between Minsk
and Bobrujsk
USD and
Byelorussian
rubles
168 210 USD
and
54 000 000
BYR
168 210 USD
and
54 000 000
BYR
2 Kapsch
TrafficCom
AG
Integration of
the Weigh in
Motion in
Electronic Toll
Collection
euro 496 435
3 JV
«BETAMONT
s.r.o.» and
«ITS-Bel»
Design,
manufacture,
test, deliver,
install,
euro and
Byelorussian
rubles
8 065 162 €
and
54
complete and
commission
Dynamic
Weighing
System at the
National Roads
of Belarus
3 704 186 400
BYR (без
НДС)
Component 3. Road Sector Institutional Support
1 Louis Berger
SAS
Technical
assistance for
support for
supervision of
FIDI-type civil
works and
conduct
training for
benchmarking
and
harmonization
of the
Byelarussian
road
construction,
repair and
maintenance
standards and
expenditure
levels to
European and
international
standards
euro 297 056 595 668,85
2 KPMG Audit of the
Project and
RUE
Minskavtodor-
Center for the
period 2012 –
2015
Byelorussian
rubles
2 284 480 000 2 284 480 000
3 Human
Systems (1C
adaptation)
1C adaptation Byelorussian
rubles
15 660 000 15 660 000
4 Training Byelorussian
rubles
52 201 060 52 201 060
5 TRL Ltd HDM-4 USD 14 640 14 640
55
6 IC Contract
with A.
Spernol
HDM-4
training
euro 4 567, 56 4 567, 56
4 Translation
services
Byelorussian
rubles
13 275 249 19 434 849
Appendix 2. Project Results monitoring
Project Outcome Indicators Baseline
(2010)
2015
Reduced vehicle operating costs on the upgraded
section of the M-5 road
Target value 94%
Actual value 100% 86%
Axle load control system introduced in Belarus n/a n/a
Intermediate Outcome Indicators
Length of the M5 road sections upgraded (km)
Target value 52,7
Actual value 0 52,7
IRI reduced on the upgraded section of the M5
road
Target value <2
Actual value 3,2 1,14
Number of fatalities on the upgraded section of
the M5 road
Target value 5/year
Actual value 12/год 5/ year
Modern axle load monitoring and control system is
installed and operational on non-tolled roads
n/a n/a
Local institutions have food capacity to supervise
FIDIC-based road works.
n/a yes
57
Annex 9. List of Supporting Documents Documents
Project Information Document (Concept Stage), 10/07/2009
Integrated Safeguards Data Sheet (Concept Stage), 11/03/2009
Project Information Document (Appraisal Stage), 06/17/2010
Integrated Safeguards Data Sheet (Appraisal Stage), 07/15/2010
Project Appraisal Document, 10/13/2010
Loan Agreement, 11/19/2010
Restructuring Project Paper, 02/04/2013
Amendment to Loan Agreement, 09/16/2013
Mission Aide-Memoires and Implementation Status Reports
Implementation Status and Results Report Sequence 1 | Date : 06/13/2011
Implementation Status and Results Report Sequence 2 | Date : 12/13/2011
Implementation Status and Results Report Sequence 3 | Date : 08/10/2012
Implementation Status and Results Report Sequence 4 | Date : 12/26/2012
Implementation Status and Results Report Sequence 5 | Date : 06/29/2013
Implementation Status and Results Report Sequence 6 | Date : 12/30/2013
Implementation Status and Results Report Sequence 7 | Date : 06/30/2014
Implementation Status and Results Report Sequence 8 | Date : 01/06/2015
Implementation Status and Results Report Sequence 9 | Date : 07/02/2015
Implementation Status and Results Report Sequence 10 | Date : 12/18/2015
Implementation Status and Results Report Sequence 11 | Date : 06/06/2016
Other Documents and Reports
Guidelines
Implementation Completion Report Guidelines, OPCS, Aug 2006, last updated July 22, 2014
Guidelines for Reviewing World Bank Implementation Completion and Results Reports, a
Manual for Evaluators, Independent Evaluation Group, last updated Nov 12, 2013