Upload
vanxuyen
View
214
Download
0
Embed Size (px)
Citation preview
Document of
The World Bank
Report No:
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
SMALLHOLDER TREE CROP REVITALIZATION SUPPORT PROJECT
P113273
BOARD APPROVAL DATE JUNE 5, 2012
TO THE
GOVERNMENT OF LIBERIA
{April 06, 2016}
AGRICULTURE GLOBAL PRACTICE
SUSTAINABLE DEVELOPMENT PRACTICE GROUP
COUNTRY DEPARTMENT AFCW1
AFRICA REGION
This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
ABBREVIATIONS AND ACRONYMS
CBL
Central Bank of Liberia
EPO Equatorial Palm Oil
EVD Ebola Virus Disease
FA Financing Agreement
FFB Fresh fruit Bunches
FO Farmers Organization
GoL Government of Liberia
IDA International Development Association
IL Investment Lending
ISDS Integrated Safeguards Data Sheet
LACRA Liberia Agricultural Commodity Regulatory Agency
LPMC Liberia Produce and Marketing Corporation
MARCO Morris America Rubber Company
MoA Ministry of Agriculture
MFDP Ministry of Finance and Development Planning
NGO Non-Governmental Organization
PCU Project Coordination Unit
PDO Project Development Objectives
PFI Participating Financial Institutions
PMU Project Management Unit
SRC Salala Rubber Company
STCRSP Smallholder Tree Crop Revitalization Support Project
VOSIEDA Volunteers to Support International Efforts in Developing Africa
Regional Vice President:
Makhtar Diop
Country Director: Henry Kerali
Senior Global Practice Director
Country Manager:
Practice Manager
Juergen Voegele
Inguna Dobraja
Simeon Ehui
Task Team Leader
Abimbola Adubi
LIBERIA
SMALLHOLDER TREE CROP REVITALIZATION SUPPORT PROJECT
P087145
CONTENTS
Page
A. SUMMARY ............................................................................................................... 1
B. PROJECT STATUS ................................................................................................. 2
C. PROPOSED CHANGES .......................................................................................... 4
Financing Plan/Funds Allocation ....................................................................................................... 4
Results Framework .............................................................................................................................. 4
Closing date .......................................................................................................................................... 4
Cost Reallocation ................................................................................................................................ 5
Component 1 ........................................................................................................................................ 5
Component 2 ........................................................................................................................................ 7
Component 3 ........................................................................................................................................ 8 ANNEX 1: REVISED FUND REALLOCATION TABLE ...................................................... 10
ANNEX 2: REVISED FUND ALLOCATION BY CATEGORY ........................................... 11 ANNEX 3: REVISIONS TO RESULT FRAMEWORK----------------------------------12
ANNEX 4: REVISED RESULTS FRAMEWORK .................................................................. 15
1
SMALLHOLDER TREE CROP REVITALIZATION SUPPORT PROJECT
RESTRUCTURING PAPER
A. SUMMARY
1. This Paper seeks the approval of the Country Director for a Level-2 restructuring
of the Smallholder Tree Crop Revitalization Support Project (P113273) in Liberia.
The proposed changes include: (i) the extension of the closing date of the project to
November 30, 2018 from the current closing date of December 31, 2016 (ii) a fund re-
allocation within the project categories and components in order to accommodate the two
year extension of the project, and also allow for the exchange rate differential between
Dollars and the SDR and (iii) a revision to some project targets in the Results Framework
to reflect financing adjustments made.
2. A request for an extension of the closing date of the project to December 2018
was received from Government of Liberia (GoL) on August 20, 2015. The request for
extension is based on the delay in implementation due to three main reasons: (i) there was
almost one year delay in project start-up due to need for ratification of the project by the
Liberia legislature; (ii) the assumptions made during the project design, particularly with
regard to the long term credit arrangements and the selection of implementation partners
were not tenable as the project began implementation. Therefore time was taken to re-
design and refocus the project; and (iii) the Ebola outbreak adversely affected field
activities and stalled most of the sequenced activities planned during the period. The
request for extension is therefore to cover additional two productive seasons of the tree
crops.
3. The Board approved IDA credit of USD 15 million on June 5, 2012 to assist the
Government of Liberia to increase the income of Smallholder Tree Crop Farmers in a
sustainable manner throughout the country. The credit became effective on July 20, 2013
and is expected to close on December 31, 2016. The project is being implemented by a
Project Coordinating Unit (PCU) established under the Ministry of Agriculture. After a
long delayed start-up due to bureaucratic difficulties (the Credit was declared effective
more than 11 months after Board approval), implementation of the main tree crops
revitalization sub-component (cocoa/coffee) started in early 2014, but stalled for over one
year due to the outbreak of the Ebola Virus Disease (EVD) in March 2014.
Implementation of the rubber and oil palm revitalization sub-components was also
blocked first by the inability to finalize the long-term credit arrangements, and then later
by the EVD outbreak. With the first restructuring of the project and the reduction of
Ebola outbreak by mid-2015, all the activities of the various sub-components commenced
and field activities started fully on the project. Management arrangements required to
implement the activities are largely in place and the institutional strengthening activities
are progressing as planned. The project conducted its Mid Term Review (MTR) in
November 2015, and set new agenda to ensure unhindered implementation of the
activities of the various sub-components with agreement of all stakeholders on the
project.
2
4. Due to the long start-up delays and the EVD outbreak, project implementation is
at least two years behind schedule, and the Project would need to be extended beyond the
current closing date of December 31, 2016, to be able to achieve its development
objectives. Fortunately, the GoL has written to the Bank to request a 2-year extension of
the project period resulting from the delays indicated above. The task team critically
reviewed the request of government and carried out a Mid-term Review (MTR) and
assessment of the project components in November 2015. The MTR mission noted the
continuing strong support of GoL and stakeholders for the Project and reconfirmed the
relevance of project development objectives. The mission also noted the significant
improvements in project implementation after the country was declared Ebola free and
resolved to process the request of government based on progress of implementation over
a few months. As at April 4, 2016, the project is 53.2% disbursed. Based on the current
improvement of project implementation, the task team is confident that, subject to a 23
months extension of the closing date, together with the adjustment of the appraisal targets
and cost reallocations, the Project should be able to achieve its project development
objectives. This will cover the additional 2 production cycles of the project and allow for
more expansion of tree crop rehabilitation and planting.
5. The main characteristics of the Liberia tree crop sector at present are the old age
of plantations and their low productivity. There have been no significant replanting
activities for the last twenty five years due to the war, and a large proportion of the
country’s rubber and oil palm plantations are now at the end of their productive life,
necessitating replanting. The Smallholder Tree Crop Revitalization Support Project
(STCRSP) aims at improving the income opportunities of poor farmers through a
combination of rehabilitating unproductive farms; undertaking replanting and new
planting programs; facilitating future replanting and development programs; and,
improved financing mechanisms and institutional arrangements.
B. PROJECT STATUS
6. As of April 4, 2016, all the components of the project are active and field work
has progressed significantly. Disbursement has thus increased from 14% last December,
2014 to 53.23% as of April 4, 2016. The Cocoa/Coffee operator has mapped out a total
of 2,103.88 ha for implementation in 2016. Due diligence on safeguard is already carried
out and rehabilitation is on-going on 1,829.43 ha for 1,155 Cocoa farmers, and 184.45 ha
for 87 Coffee farmers. Following the completion of baseline on these farms, farm inputs
such as files, knapsack sprayers, rain boots, nose masks, axes etc. were distributed to the
farmers as part of matching grants and the under-brushing has been completed
successfully. The control of pests and diseases is currently taking place using
recommended pesticides and fungicides. These farms are also geo-referenced with their
co-ordinates available on google map. The target farmers are spread within the 48
Farmer Field Schools (FFS) established by the project and cover the three counties of
Nimba, Bong and Grand Gedeh where a total of 200 ha of new Cocoa seedlings will be
planted next season. Arrangement is already made to purchase new variety of seeds and
establish nursery sites before the end of the year. The training and capacity building
activities have been rolled out through the FFS to strengthen the farmers groups, teach
modern farming methods and the PCU is closely monitoring the progress of this
3
intervention in the target counties. The FFS is being used to strengthen farmer’s
organizations and transform them into viable business oriented farmers cooperatives. The
Project is finalizing the Contract Management with ACE Global for the provision of
Collateral Management Services for the marketing of cocoa and coffee and already, four
ware houses of farmer’s cooperatives have been identified for initial renovation.
7. On Rubber, the project has started its out grower scheme with MARCO and a
total of 150 farmers have planted 300 ha of new Rubber stumps. The Afriland First Bank
Liberia, acting as Participating Financing Institution (PFI) under the scheme has assessed
the 150 Rubber farmers for credit worthiness and they will benefit from the long term
credit scheme of the project. A Concessionaire on Rubber production, Salala Rubber
Corporation (SRC), has also joined the out grower scheme. A project sub-unit has been
set up at SRC to work directly with the rubber smallholder farmers in Margibi County
under the technical supervision of SRC in collaboration with the Ministry of Agriculture.
Under the 2016 planting season, 100 smallholder farmers are expected to plant 200
hectares, adding 200 more hectares by next year. Activities mapped out include final
selection of farmers, environmental assessments, underbrushing of farmland and
preparation of rubber stumps for the revised target of 400 hectares for replanting.
8. On Oil Palm, the project is working with EPO- LIBINCO and VOSIEDA. The
EPO-LIBINCO is the main Concessionaire for the out growers scheme in Grand Bassa
County. It has worked with the PCU to identify farmers and farms and efforts are being
made to finalize its Management Contract so that planting of oil palm seedlings and
technical support can start during the next planting season. Already 54 farmers in Grand
Bassa County have been assessed for credit worthiness by Afriland First Bank Liberia,
assisted by the CDA to form a legally registered cooperative society and their farms have
been geo-referenced and are to start under brushing of 108 hectares. Dube Plantation in
Grand Gedeh County has also been assessed for initial operation through the
Cooperatives under the supervision of VOSIEDA. Free, Prior, Informed, Consent (FPIC)
to deed the 600 ha plantation to the Dube Multi-Purpose Farmers’ Cooperatives
(DPMFC) was successfully conducted by the Land Commission (LC) and Statement of
Declaration was made by the Community. LC is now processing the deeding of the
plantation. The planned activities in Dube include: (i) the control of harvesting of fresh
fruit bunches from the plantation and processing using four (4) motorized freedom mills
purchased by the Project; (ii) rehabilitation of 300 ha by under brushing; (iii) the setting
up of the nursery for the planting of the 300 ha. The processing of the Fresh Fruit
Bunches (FFBs) from the 600 ha will provide the startup capital for the DPMFC.
9. Due to the long period before tapping of rubber (seven years) and harvesting of
fresh fruit bunches of oil palm (four years) after planting, the Ministry of Agriculture
(MoA), Ministry of Finance and Development Planning (MFDP), and International
Development Association (IDA) working with Concessionaires under the project, have
agreed to set up a Long term credit facility to support smallholder farmers. The Liberian
Bank for Development and Investment (LBDI) was identified as the Agent Bank to
manage the Long term Credit Facility Account and the designated account has been
opened accordingly. Afriland First Bank Liberia (AFB) is the Participating Financing
Institution (PFI) to work with the Concessionaires to enhance farmers access the credit
4
facility on Rubber and Oil Palm. The identified and accredited farmers above will start
benefiting from the long term credit facility early in 2016.
10. The main constraint to the implementation of the project now is the time frame
for implementation given that past production cycles of the tree crops was missed due to
delays above. The request by GoL for an extension of the closing dates in order to cover
two production cycles is appropriate and will enhance the achievement of the project
objectives. The MTR mission considered this option and held several meetings with the
stakeholders to ensure that no momentum is lost in the implementation of the project. The
final agreement on the collaboration and the need to cover more production cycles of the
tree crops necessitates the level 2 restructuring of the project.
C. PROPOSED CHANGES
Financing Plan/Funds Allocation
11. The project will continue to follow the same fund flow pattern. However, there
will be funds re- allocation among the various components in order to account for
increased cost of inputs and also reducing some activities and non-essential costs under
components 2 and 3. The re-allocation is also done to provide for exchange rate
differential between SDR and US$, and also to account for the real cost of activities of
the sub components. Annex 1 provides the summary of the cost re-allocation and the
rationale for the changes while Annex 2 indicates the Revised Project Cost and
Financing.
Results Framework
12. A detailed review of the Results Framework was conducted and some targets
were revised given the realities of the implementation and financial constraints. Also the
yield indicators were moved up to the Project Development Objective (PDO) level to
give prominence while the PDO is still relevant and will be continued. Two indicators
were dropped due to lack of relevance and ambiguity in measurement. These are
“Incremental yearly net cash flow in project area “and “Coaching of MoA & CDA staff
(Person-days)”. The details of the Results Framework (RF) are indicated in Annex 2 of
the paper.
Closing date
13. It is proposed that the project closing date be extended by 2 years from December
31, 2016, to December 31, 2018. This will allow the new planting and rehabilitation of
the tree crops to cover two production cycles and enhance the achievement of project
objectives. The earlier positive results from the project implementation are indication
that the extension will assist the project to give more results for the sector and the
beneficiaries.
5
14. The proposed changes require the following amendments to the Financing
Agreement (FA): (i) revision of the table specifying cost allocation to the components in
Section IV A2 of Schedule 2; (ii) revision of the Results Framework; and (iii) revision of
the closing date in Section IV B.2 of Schedule 2. All other provisions of the Agreements
remain unchanged. The proposed changes would be effective from The approval date of
the project restructuring.
15. The Project Implementation Manual (PIM) will also be adjusted to reflect the new
changes in the implementation arrangements and the revision above. Cost Reallocation
The main principles to make activity and costs adjustments were as follows:
(i) Expanding the scope of rehabilitation and replanting of the cocoa/coffee
subcomponent and of the MARCO scheme & Dube subprojects, but reducing
the SRC & EPO sub-projects scope, while accounting for increased costs of
farm tools, inputs and implementation partner units;
(ii) accounting for real costs met under components 2 and 3 so far; and
(iii) reducing some activities and non-essential costs under components 2 and 3
until project end.
More details concerning changes made in the detailed costs table are indicated below:
Component 1
Sub-comp 1.1 (cocoa/coffee):
o Increase coverage areas for Cocoa to:
2,500 farmers targeted by next cropping season starting June.
2016;
cocoa rehabilitation: 3,700 ha medium input + 1,200 ha high input;
and
coffee rehabilitation: 371 ha medium input.
6
o Possible extension of contract of SOCODEVI until 2018 for expansion of
cocoa areas.
o Substantial reduction of provision for road rehabilitation (to about USD
100,000) for only urgent rehabilitation (small bridges and culverts) on
very critical points.
Sub-comp 1.2 (oil palm)
o Dube sub-project
Scope kept at 300 ha rehabilitation + 300 ha replanting under
medium input model .
Costs of VOSIEDA contract taken into consideration as it stands
(USD 246,000 over 24 months); however it is assumed that it
could be revised downward and/or the costs could be spanned over
a longer implementation period without cost increase.
Costs to be borne by PCU (vehicle, nursery, mini-mills, etc.) as
shown in the VOSIEDA contract negotiation minutes taken into
account but still need clarification.
Elimination of provision for roads as there is no need for road
rehabilitation for this sub-project.
o EPO sub-project
Plan is to increase target to about 75 farmers (most of them already
identified and hold more than 2 ha each) who will be supported to
rehabilitate 150 ha in 2016, then progressively replant the same
150 ha the next two seasons under high input model e.g. using LT
credit.
EPO costs and farm development (grant + credit + farmer labour)
recalculated as per information provided by EPO.
Road rehabilitation provision reduced to USD 68,000 (including
studies and supervision of work); to be used for some critical
points only.
Sub-comp 1.3 (rubber)
o MARCO sub-project
300 ha already planted. Plan to increase new planting in 2016 to
300 ha and tripled by 2017.
7
MARCO costs reduced as compared to signed contract (e.g. less
staff and Operation & Maintenance) to account for the fact that (a)
farmers are pretty well organized through the Todi cooperative; (b)
they are in close locations; (c) average farm size is at least 2
ha/participant, thus 2 technical staff are probably enough to
monitor 300 farmers.
Road rehabilitation provision reduced to USD 59,000 (incl. studies
and supervision of work) for some critical points only.
o SRC sub-project
Reduction of scope to 150 farmers/300 ha replanting or planting
(starting in 2016);
SRC costs reduced as compared to estimated costs at appraisal
(e.g. less staff and O&M) to account for reduced scope : 2
technical staff are far enough to monitor about 150 farmers that
might be scattered in different clans/localities.
Road rehabilitation provision reduced to USD 65,000 (incl. studies
and supervision of work) for some critical points only.
Component 2
Sub-comp 2.1 (institutional building):
o Scope/amount unchanged for capacity building of Moa/CDA.
o Support to MoA/CAO: includes the effective amount spent so far for
equipment + an agreed provision for recurrent costs support, as
discussed/agreed with the PCU.
o Support to PMU: includes the contribution to the PMU Director salary
(until Sept. 15) and the STCRSP contribution to the PMU operating
expenses based on current yearly expenses.
o Support to CDA: includes actual and planned expenses for equipment,
vehicles, development of national FO/coop policy/bills, allowances for
field visits and running costs (total USD 213,000).
o Securing of smallholders’ land use rights:
Ehud Foundation contract accounted for under this activity (and
not any more under component 1);
8
Provision for a review of land use rights validation and securing
activities in 2017 is kept, as per design; and,
Provision for land demarcation eliminated (this was only envisaged
for new planting) as it is too costly and complicated to organize; in
any case only initial steps to issue a proper tribal certificate (plus
off course land use rights validated at family/community level) are
required to proceed with new planting, as per PIM.
o Support to tree crop adaptive research: reduced to USD 30,000.
o Support to LPMC/LACRA: USD 70,000, as per ongoing MoU signed
with them.
o Preparation of LT large scale tree crop development programme:
Reduced amount for contribution to elaborating the tree crop
master plans and tree crop database (USD 200,000); and,
Preparation of large scale project: reduced to USD 25,000 (as a
provision to hire several national consultants to contribute to
drafting lessons learnt and proposals for larger scale project); the
bulk of funding for preparing the large scale project should
however come from a PPA/PPF under the STCRSP2.
o Reimbursement of PPA: adjusted to actual amount (USD 1,063,000)
Component 3
o Sub-comp. 3.1 (PCU)
Adjustment of duration per staff position; no hire of the Value
Chain Development Officer (VDO) neither of the tree crop
agronomist; hire of Procurement Assistant and Safeguards Officer
in 2016 to continue the procurement and safeguards functions until
project end (in Nov.. 2018);
Reduction of vehicles to keep up with reduced number of staff;
Implementation support:
adjustment of accounting and Management Information
System (MIS) software costs (shared with other projects);
reduced provision for short term (ST) National and
International Consultants to support implementation
according to felt needs by PCU
o Sub-comp 3.2 (M&E and communication)
9
EGIS contract reduced to USD 400,000 (instead of USD 503,000
which seems excessive); this is possible as is a time-based
contract;
Reduced amount for communication & knowledge sharing
activities: however we kept them as it will become more and more
important as long as the project achieves substantial results in
coming years; and,
Kept provision for participatory planning and evaluation
workshops at district and national level as it is good practice, not
costly and envisaged in both the Project Appraisal Document &
Project Implementation Manuel (although it has unfortunately not
been implemented so far)
Page 10 of 21
10
Annex 1: Revised Fund Allocation Table
Amount (original costab) (USD)
Amount (Revised costab) (USD)
Amount (original costab) (XDR)
Amount (Revised costab) (XDR)
COMPONENT - 1 (Smallholder Tree Crops Revitalization)
9,467,000
9,435,396
6,123,545
6,103,102
1. Cocoa & Coffee Revitalization 6,462,000 7,850,047 4,179,819 5,077,650
2. Smallholder Oil Palm Revitalization 1,013,000 872,106 655,239 564,105
3. Smallholder Rubber Revitalization 1,992,000 713,242 1,288,486 461,347
COMPONENT - 2 (Institution Building and Preparation of Future Large Scale Tree Crop Development Program
3,055,000 2,277,774 1,976,067 1,473,334
1. Institutional Capacity Building 1,327,000 863,341 858,344 558,435
2. Preparation of Large Scale Smallholder Tree Crop Development Program
503,000 249,799 325,356 161,578
3. STCRSP Project Preparation Advance 1,225,000 1,164,634 792,367 753,321
-
COMPONENT - 3 (Project Coordination and Management)
2,477,000 3,286,831 1,600,388 2,123,564
1. Strategic Planning, Coordination and Implementation Support
1,844,000 2,679,863 1,190,944 1,730,959
2. Monitoring & Evaluation and Knowledge Production & Sharing
633,000 606,968 409,444 392,605
TOTAL PROJECT COST 15,000,000
15,000,000
9,700,000
9,700,000
Page 11 of 21
11
Table 2: Revised Fund Allocation by Categories
CATEGORY Origninal Allocation
(US$)
Revised
Allocation
(US$)
Origninal
Allocation
(XDR)
Revised
Allocation
(XDR)
Category - 1 (Civil Works)
1,550,000
433,830
1,000,000
280,614
Category - 2 (Goods)
775,000
847,940
500,000
548,474
Category - 3 (Consultant's
Services and Training)
6,800,000
9,235,320
4,400,000
5,971,229
Category - 4 (Smallholder Sub-
grants)
2,950,000
2,390,447
1,900,000
1,546,214
Category - 5 (Smallholder -
credits)
300,000
293,602
200,000
189,911
Category - 6 (Incremental
Operating Costs)
600,000
634,312
400,000
410,292
Category - 7 (Refund PPF)
1,255,000
1,164,549
800,000
753,266
Unallocated
800,000
-
500,000
-
TOTAL
15,000,000
15,000,000
9,700,000
9,700,000
Page 12 of 21
12
Annex 3: Revisions to Results Framework
Original Revisions Rationale
PDO: to increase access to finance, inputs, technologies and markets
for smallholder tree crop farmers in Liberia, and to develop a long
term development program for the tree crops sector.
Continued PDO remains relevant and achievable.
PDO indicators
Area of smallholder tree crop farms rehabilitated, replanted or
planted under the project,
disaggregated
- Rehabilitation
- Replanting
- New Planting (ha)
Revised – targets revised
Targets have been revised to reflect decrease in project funding
Incremental yearly net cash flow in project area:
- High input rehabilitated cocoa
- Medium input rehabilitated cocoa
- Rehabilitated coffee
- Rehabilitated oil palm (farmers run plantation)
- Rehabilitated oil palm (out growers scheme) (Mt/ha)
Dropped The indicator has been dropped due to potential attribution
problems related to using the farm gate price in calculation of net
cash flow. This price is determined by demand-supply dynamics
outside of the sphere of project interventions.
Long term credit delivered to oil palm and rubber out growers under
the project (Yes/No)
Revised and moved to
intermediate level – ‘Out grower
schemes with long-term credit to
participating smallholders farmers
supported by the project
(number)’
The indicator has been revised to better reflect project
interventions (to establish out-grower schemes with credit
component) rather than setting an absolute target for credit
delivered.
Farm access roads rehabilitated (km) Continued and moved to
intermediate level
The indicator has been moved to intermediate level because it is an
output.
Direct project beneficiaries (number), (of which are female) (%) Revised – targets revised Target for female participation have been revised to reflect
experience from first year of implementation.
Long term large scale tree crop development program formulated and
approved by Ministry of Agriculture (Yes/No)
Continued
New – ‘Smallholder tree crops
farmers with access to finance,
input, markets and technologies as
a result of the project (number)’
Page 13 of 21
13
Intermediate indicators
Component One: Tree Crop Revitalization
Yield of high input rehabilitated cocoa (Mt/ha) Revised and moved to PDO level -
‘Yield of major tree crops: high
input cocoa, medium input cocoa,
rehabilitated coffee, rehabilitated
oil palm (tons/ha)’
This indicator has been revised as yield indicators are merged into
one indicator and moved to PDO level. Yield is considered a
medium-term outcome in this project and hence more appropriate
at the PDO level.
Yield of medium input rehabilitated cocoa (Mt/ha) Revised as yield indicators are
merged into one indicator and
moved to PDO level ‘Yield of
major tree crops: high input
cocoa, medium input cocoa,
rehabilitated coffee, rehabilitated
oil palm (tons/ha)’
This indicator has been revised as yield indicators are merged into
one indicator and moved to PDO level. Yield is considered a
medium-term outcome in this project and hence more appropriate
at the PDO level.
Yield of rehabilitated coffee (Mt/ha) Revised as yield indicators are
merged into one indicator and
moved to PDO level ‘Yield of
major tree crops: high input
cocoa, medium input cocoa,
rehabilitated coffee, rehabilitated
oil palm (tons/ha)’
This indicator has been revised as yield indicators are merged into
one indicator and moved to PDO level. Yield is considered a
medium-term outcome in this project and hence more appropriate
at the PDO level.
Yield of rehabilitated oil palm (Mt/ha) Revised as yield indicators are
merged into one indicator and
moved to PDO level ‘Yield of
major tree crops: high input
cocoa, medium input cocoa,
rehabilitated coffee, rehabilitated
oil palm (tons/ha)’
This indicator has been revised as yield indicators are merged into
one indicator and moved to PDO level. Yield is considered a
medium-term outcome in this project and hence more appropriate
at the PDO level.
Cocoa Farmer Organizations (FOs) strengthened (Number) Continued
Farmers’ run Oil Palm Plantation Cooperative strengthened
(Number)
Continued
FOs strengthened in out grower schemes Continued
Volume of cocoa bulked by project supported FOs (Mt) Continued
Component Two: Institutional Building and Preparation of Future Large Scale Tree Crop Development Program
Capacity building plan for MoA & CDA developed (Yes/No) Continued
Persons trained (Number) Continued
Coaching of MoA & CDA staff (Person-days) Dropped The indicator has been dropped as coaching of senior staff is no
longer relevant.
County Agricultural Offices equipped (Number) Continued
CDA field offices equipped (Number) Continued
Page 14 of 21
14
National Policy and Strategy for FO and Cooperative development
formulated and validated with all national stakeholders (Yes/No)
Continued
Methodology for community land use rights validation agreed with
stakeholders (Yes/No)
Continued
Tree crop master plans formulated in a participatory process under
MoA leadership
- Cocoa
- Coffee
- Oil Palm
- Rubber (Yes/No)
Continued
15
Annex 4: Revised Results Framework
Project Development Objective (PDO): to increase access to finance, inputs, technologies and markets for smallholder tree crop farmers in Liberia, and to develop a long
term development program for the tree crops sector
PDO Level Indicators
Co
re UoM Baseli
ne
Status
(Nov
2015)
2016 2017 2018 Frequen
cy
Data sources and
methodology
Responsibili
ty for data
collection
Description / comments
PDO Indicator 1: Area of
smallholder tree crop
farms rehabilitated,
replanted or planted under
the project,
disaggregated
- Rehabilitation
- Replanting
- New Planting
Ha 0 2,261
1,961
300
0
4,506
875
100
4,506
1,250
300
4,506
1,250
300
Annual Review of
contracted
concessionaires
and service
providers reports
and count of area
rehabilitated,
replanted and
newly planted
PMU/ PCU
M&E
function
PDO Indicator 2: Yield
of major tree crops:
- High input cocoa
- Medium input cocoa
- Rehabilitated coffee
- Rehabilitated oil palm
Mt/ha 0
0.12
0.12
0
0
0.12
0.12
0
1.00
0.75
0.37
0.40
4.00
1.30
0.50
0.50
5.00
Bi-
annual
Producer and value
chain
surveys data
PMU/ PCU
M&E
function
PDO Indicator 3: Smallholder tree crops
farmers with access to
finance, input, markets and
technologies as a result of
the project
Numb
er
0 1,392 2,925 3,025 3,025 Annual Review of
contracted
concessionaires
and service
providers reports
and count of
smallholder
farmers with
access
PMU/ PCU
M&E
function
PDO Indicator 4: Long
term large scale tree crop
development program
formulated and approved
Yes/N
o
No No No No Yes Annual Review of program
document
PMU/ PCU
M&E
function
Page 16 of 21
16
by Ministry of Agriculture
PDO Indicator 5: Direct
project beneficiaries (of
which female)
Numb
er (%)
0 1,392
(15)
3,000
(15)
3,100
(15)
3,100
(15)
Annual Review of service
providers reports
and CAO
supervision
and count of direct
project
beneficiaries
PMU/ PCU
M&E
function
Intermediate results
Component 1: Tree Crop Revitalization
IR Indicator 1.1:
Cocoa Farmer
Organizations (FOs)
strengthened
Numb
er
0 0 10 30 43 Review of service
providers reports
and CAO
supervision
reports and count
of FOs
strengthened
PMU/ PCU
M&E
function
IR Indicator 1.2:
Farmers’ run Oil
Palm Plantation
Cooperative
strengthened
Numb
er
0 0 1 1 1 Review of service
providers reports
and CAO
supervision
reports and count
of cooperatives
strengthened
PMU/ PCU
M&E
function
IR Indicator 1.3: FOs strengthened in
out grower schemes
Numb
er
0 0 5 15 20 Review of service
providers reports
and CAO
supervision
reports and FOs
strengthened
PMU/ PCU
M&E
function
IR Indicator 1.4: Volume of cocoa
bulked by project
supported FOs
Mt 0 0 300 500 1,000 Review of service
providers reports
and CAO
supervision reports
and estimate of
cocoa bulked by
supported FOs
PMU/ PCU
M&E
function
IR Indicator 1.5: Out grower schemes
with long-term
Numb
er
0 0 1 2 3 Review of
contracted
concessionaires
PMU/ PCU
M&E
function
Page 17 of 21
17
credit to
participating
smallholders farmers
supported by the
(number)
and service
providers reports
and count of out
grower schemes
IR Indicator 1.6: Farm access roads
rehabilitated (km)
Km 0 0 20 30 30 Review of
contracted
concessionaires
and service
providers reports
and count of km
farm access roads
rehabilitated
PMU/ PCU
M&E
function
Component 2: Institutional Building and Preparation of Future Large Scale Tree Crop Development Program
IR Indicator 2.1:
Capacity building
plan for MoA &
CDA developed
Yes/N
o
No No Yes Review of capacity
building plan
PMU/ PCU
M&E
function
IR Indicator 2.2:
Persons trained
Numb
er
0 0 70 70 70 Review of training
service provider
reports and count
of number of
number of trainees
PMU/ PCU
M&E
function
IR Indicator 2.3:
County Agricultural
Offices equipped
Numb
er
0 5 5 5 Review of CAO
reports and count
of CAO equipped
PMU/ PCU
M&E
function
IR Indicator 2.4:
CDA field offices
equipped
Numb
er
0 5 5 5 Review of CDA
reports and count
of CDA offices
equipped
PMU/ PCU
M&E
function
IR Indicator 2.5:
National Policy and
Strategy for FO and
Cooperative
development
formulated and
validated with all
national
stakeholders
Yes/N
o
No No Yes Review of regional
and national
validation
workshops reports
and participatory
evaluations reports
PMU/ PCU
M&E
function
IR Indicator 2.6:
Methodology for
Yes/N
o
No No Yes Review of
validation
PMU/ PCU
M&E
Page 18 of 21
18
community land use
rights validation
agreed with
stakeholders
workshops reports function
IR Indicator 2.7:
Tree crop master
plans formulated in
a participatory
process under MoA
leadership:
- Cocoa
- Coffee
- Oil Palm
- Rubber
Yes/N
o
No
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Review of Master
plans documents
and reports of
consultants on the
processes of
preparation &
validation
PMU/ PCU
M&E
function