Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
1
Environmental Impact Assessment
Executive Summary
For
Relocation Project of
Wanzhou Maternal and Child Hospital
Chongqing , China
Chongqing Dehe Environment Engineering Co.Ltd
January 2015
E2960 V3 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
2
Content
1. INTRODUCTION ............................................................................................................................. 3
2. ENVIRONMENTAL LEGAL FRAMEWORK ................................................................................. 3
3. PROJECT OVERVIEW ..................................................................................................................... 5
4. GENERAL ENVIRONMENTAL SETTINGS ................................................................................ 11
5. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ............................................. 14
6. ANALYSIS OF ALTERNATIVE PLAN ......................................................................................... 21
7. RESETTLEMENT PLAN ............................................................................................................... 26
8. ENVIRONMENT MANAGEMENT AND MONITORING PLAN ............................................... 26
9. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ............................................. 35
3
Relocation Project of
Wanzhou Maternal and Child Hospital
Executive Summary
1. INTRODUCTION
According to Chinese laws and regulations for environmental assessment and the World
Bank’s safeguard policies including 4.01-Environmental Assessment, an overall
Environmental Impact Assessment (EIA) report is needed for the Relocation Project of
Wanzhou Maternal and Child Hospital(WZMCH). This Executive Summary, prepared on
the basis of the Environmental Impact Assessment (EIA) of the Relocation Project of
WZMCH, summarizes the environment impact assessment and highlights the key issues
and conclusions in its environment impact assessment and environment management plan.
Chongqing Dehe Environmental Engineering Co. Ltd with a Class B certificate (No. 3125)
on environmental impact assessment by the Ministry of Environmental Protection (MEP),
was entrusted Wanzhou Maternal and Child Hospital to prepare the EIA in accordance with
the EIA laws/regulations and technical guidelines in China and safeguard policies of the
World Bank.
The EIA, submitted to the World Bank for review on its conformity with the Bank policy
guidelines regarding environmental and social issues, has been approved by Wanzhou
Environmental Protection Bureau(EPB) and concludes the proposed project to be feasible
in construction.
In summary, the environment management will cover the whole process including project
design, construction and operation and reasonable and feasible measures will be applied to
enhance project benefits and mitigate adverse impacts, including having the adverse impact
under control in an effective way, improving medical service quality in the project area,
assuring physical and psychological health of local resident and achieving social and
economic harmony in development with environment protection.
2. ENVIRONMENTAL LEGAL FRAMEWORK
The preparation of the Environmental Impact Assessment (EIA) complied with the World
Bank’s environmental protection requirements and information disclosure policies detailed
below in Table 2-1.
Table 2-1 Compliance with World Bank Safeguards Policies
Safeguard Policies Actions
Environmental - Full EA including EMP has been prepared.
4
Assessment
(OP/BP 4.01)
Consultation - A combination of opinion surveys and public meetings were
held in community committee for affected people during
preparation of the safeguards documents through internet, public
notice, questionnaire and forum.
The EIA is prepared in terms of national and local environmental laws, regulations,
policies, the World Bank’s environmental and social safeguard policies including:
① Environmental Protection Law of the PRC (Dec 26, 1989)
② Law of the PRC on Environmental Impact Assessment (Oct 28, 2002)
③Law of the People's Republic of China on Prevention and Control of Water
Pollution (revised in 208)
④Law of the PRC on the Prevention and Control of Atmospheric Pollution (revised
in April 2000)
⑤Law of the PRC on the Prevention and Control of Pollution by Solid Waste (Apr 1,
2005)
⑥Law of the PRC on the Prevention and Control of Environmental Noise Pollution
(Oct 29, 1996)
⑦Law of the PRC on Prevention and Control of Radioactive Pollution (Oct 1, 2003)
⑧Technical Regulation for Environmental Impact Assessment and any standard
applied for Air, Water and Noise
Safeguard Policy issued by Bank: OP/BP4.01 Environmental Assessment
Main Environmental Assessment Standards of the report are given in Table 2-2
Table 2-2 Environmental Assessment Standard
Category Name of Standard
Environment
Quality
Standard
Ambient Air Quality Standard (GB3095-1996), II grade standard
Environmental quality standards for surface water standard (GB
3838—2002) Grade III
Environmental Quality Standard for Noise(GB3096-2008), Category
II Applied
Regulations for electromagnetic radiation protection ( GB 8702-88)
Emission
standards of
Pollutant
Emission standards of air pollutants for coal-burning boiler
(GB 13271—2001)
Discharge standard of water pollutants for medical
organization (GB18466-2005) Table 3
Integrated emission standard of air pollutants (GB16297-1996)
Emission standard of cooking fume ( GB 18483-2001 )
Discharge standard of water pollutants for medical
organization(GB18466-2005)
5
Table 2 Pretreatment Standard
(GB 18466-2005)
Emission standard of environment noise for boundary of construction
site ( GB 12523-2011 )
Emission standard for industrial enterprises noise at boundary
(GB12348-2008)
Technical Code for Electronic Radiation of 500kv Power Transmission
Engineering Work
3. PROJECT OVERVIEW
3.1 Components and Contents
The new hospital targeted to a first – class level-3 maternal and child hospital providing
medical treatment and healthcare service occupies a land of 51.63mu, among which
8495.2m2
is for a complex building(including a tower of 2 floors underground and 13
floors on the ground and a podium of 5-floor) with a total construction area of
71007.10m2(including ground area of 47249m
2 and underground area of 23758.10m
2)
and 8348 m2
is reserved for future development. After completion, its total bed number
will reach 500 and outpatient volume be 800-1000 person-time.
The new hospital consists of emergency section, healthcare and outpatient section, medical
technical section, inpatient section, administration section and logistical section with the
key departments as follows: department of pediatrics, department of obstetrics and
gynecology, new pediatric department, department of infection control, health education
center, child health care, lab examination, ultrasonography, postpartum recovery, child
health care center, physical examination center, woman health care, perinatal health care
center, emergency department, radiology department, of stomatology department etc. (no
infectious disease department included). The major departments and its function are
presented in table 3-1 while the main components and contents detailed in table 3-2.
Table 3-1 The major departments for each floor and its function
No. Floor Indicator Layout of major departments and its functions
1 -2F 11879.05m2
Garage(with 324 parking lots), domestic water tank, pump
house, water tank for firefighting etc.
2 -1F 11879.05m2
Case file room, power distribution room, air-conditioner
machine room, central supply service room, laundry room,
canteen, storeroom, library for hospital staff, staff
activity room, X-ray room, radiography room and parking
lots (92 lots) .
3 1F 7980.4m2
emergency room , pediatrics department, gynaecology
department, new pediatric department, physical
6
examination center, TCM clinic, information center and
western medicine dispensary.
4 2F 6667.12m2
physical examination center (blood transfusion
department), pathology department, health care for VIP
and child, E.N.T. and ophthalmology and
otorhinolaryngology, stomatology team, child cognitive
team, child scene experience area, aseptic storeroom, baby
bathing room (nursing area in quarantine), therapy room,
nursing room for child suffering respiratory tract infection
and gastrointestinal disease, ICU, immature baby nursing
area, newly-born baby bathing room etc.
5 3F 6613.16m2
Postpartum recovery center, function examination area,
perinatal health care center, pregnant school, operation
room, central monitoring room.
6 4F 6661.84m2
Haifu postpartum recovery center, laparoscopic operation
room, outpatient operation room, family planning
operation area, women’s health care center, therapy center
of gynaecology, gynaecology clinic, assisted reproduction
center.
7 5F 3176.91m2
Pre-delivery area, isolated pre-delivery zone, buffering
zone, aseptic storeroom, therapy room, wards etc, with 34
beds
8 6F 1912.71m2 Wards with 61 beds
9 7 ~
13F 13482.67m
2 Wards, 405 beds
10 Top
floor 754.19m
2
Elevators machine room
Table 3-2 Project Components and Content
Components Contents
Main
Structure
Emergency
Dept.
With an area of 680 m2, located on 1st F in the northeast of
project site; east area of 1st F is designed for emergency
department, Pediatric clinic area, consulting room, infusion
area; south area of 1st F is for TMC clinic, healthcare center;
southeast area of 1st F is for entrance hall of inpatient
department; on the 2 sides of entrance hall is designed for fire
control room, infusion processing area; the emergency
department consists of consulting room, therapy room,
observation room, resuscitation room, registration window,
pricing window, on-call room, pharmacy and infusion hall.
Health Care &
Outpatient
With an area of 14152.06 m2, located in the northwest of
project site; 1st F is designed for entrance hall, pricing and
7
Dept. charging, medicine dispensing window, inquire desk; 2nd F is
for child healthcare center, physical checkup area, waiting
area, office area, special bathroom, dressing room, consulting
room; 3rd F is for women healthcare center; 4th F is designed
for perinatal healthcare; a corner in east of emergency
department is gateway f specially for patient who have fever
and intestinal tract department.
Medical
Technical Dept.
With an area of 10642.55 m2, includes 2 parts in total: 1)
functional area supporting outpatient service, such as medical
imaging center, physical examination center, function
checkup, type-B ultrasonic checks and pathology department,
and these sections are located at B1, 1st F, 2
nd F, and 3
rd F of
skirt building; 2) NICU operation room(birth-control operation
included) , central supply, central transfusion which are
located at B1, 1st F, 2nd F and 3rd F of inpatient department
area; 3rd F is where laminar flow operating room located; 4th
F is designed for doctor office and machine room.
Inpatient Dept.
Inpatient department is located in the southeast of project site,
with an area of 19636.17 m2, The layout of 1
st floor is:
entrance hall, dispensary and healthcare clinic and fire
control room; Ward area is from 5F to 13F of this building.
Administration
Dept.
Skirt building is located n the north of project site, with an area
of 19636.17 m2, one of the total 5 floors to be used as the
office area.
Logistical Dept. Logistical department and equipment house are at B1 and B2
of inpatient department.
Garage Garage located at B1(on floor next level of health care center,
inpatient and outpatient department), with 541 parking lots
Utility
work
Water supply
Domestic water supply network will be formed by laying a
pipe (DN200) to take water from the municipal water supply
trunk on the north of the hospital, with pressure of 0.35Mp and
backflow preventer to be installed on joint point.
Sewerage
Separate Sewer System is adopted ; wastewater and rainfall
will be separately collected by municipal water sewerage
network
Power supply
Double loop independent 10kv power source to be connected
with city power grid, one for daily use, another for standby.
10kv power source for each circuit can bear the whole load.
Diesel generator set with 800kw will be equipped as the third
power source. Transformer and distribution house is located at
Basement 1, transformer in-house with indicator of:
2×1600kVA+1×1250kva+1×500KVA;
Firefighting The fire-fighting water pipe network will be formed by laying
a pipe (DN200)(including the water meters) fromthe municipal
8
water supply network in the north of the hospital. Loop
pipe network will be formed by laying a pipe (DN150) from
the municipal water supply network in west of hospital.
Intelligent
system
Double circuit is proposed for machine room, with standby
power source of UPS; Precision air-conditioning system with
constant temperature and humidity will be equipped in
machine room; 24- hour monitoring will be carried out.
Computer network focus on network scale and security.
Network includes Intranet and internet; Intranet will function
as the core system for daily medical service (HIS, electronic
medical record, LIS, PACS systems etc.). Intranet is
characterized by stable operation, practical and safe in
utilization and able to be upgraded in the future; Internet
provided long-distance medical service and education, office
automation service and long-distance maintenance for medical
equipment.
Ventilation
system
Mechanical air supply device and natural ventilation are
adopted for underground garage and machine room. The
air-conditioning system consisting of two parts is applied: 1)
purifying zone such as operation room(OR) forms an
independent system; 2) the rest area except for purifying zone
is called general area will have another system. Cold and heat
sources are designed for OR; besides the special sources, pipes
will connect with central air-conditioning system, four-pipe
control is adopted with valves installed for switch. General
area is divided into 4 parts (emergency department, left & right
side of outpatient department and inpatient department) with 4
sub-systems; two-pipe control is adopted.
Environ-
ment
Engineeri
ng
Wastewater
treatment
station
The underground wastewater treatment station with design
treatment capacity 450m3/d will be built in the hospital, with
process of enhanced primary treatment + disinfection. The
wastewater will be collected by municipal wastewater network
in the south of hospital; accident tank to be built with design
capacity of 450m3.
Medical waste
The medical waste storage room is located in the south of the
Hospital. Special packages and containers used in medical
waste collection which will be transferred to the storage room
through dedicated passageway.
Domestic waste Dustbin will be put on each floor for garbage collection
Sludge 1 sludge disinfection tank and 1 concentration tank are to be
built
9
3.2 Utility Works
3.2.1 Water Supply System
Domestic water supply network will be formed by laying a pipe(DN200) to take water
from the municipal water supply trunk on the north of the hospital, with pressure of
0.35Mp and backflow preventer to be installed on joint point.
3.2.2 Wastewater Drainage System
The proposed project is located at Wanquan community in Shuanghekou of Wanzhou
District and within service scope of Mingjingtan WWTP. The design capacity of
Mingjingtan WWTP (phase I) is 30000m3/day with process of A2/O oxidation ditch
(anaerobic-anoxic-aerobic process, carrorsel oxidation ditch). Effluent quality satisfies
category B Class I of Discharge Standard of Pollutants for Municipal Wastewater
Treatment Plant (GB 18918-2002). This WWTP was completed in July 2003 and it’s under
stable operation with actual treatment capacity of 10,000m3/day, capable of receiving
wastewater generated by this Project.
The rainfall and sewage separation system is adopted. Underground WWTP with capacity
of 450m3/d will be built under this project. After reaching the pre-treatment standard
stipulated in table 2 of Discharge Standard of Water Pollutants for Medical
Organization (GB18466-2005) , the wastewater will be collected by urban wastewater
network and conveyed to Mingjingtan WWTP for treatment. Rainfall will be collected by
rainfall pipe then discharged into municipal rainfall pipe network.
3.2.3 Sanitary and Anti-epidemic System for Water Supply and Drainage
UV disinfection equipment will be installed at outlet of domestic water tank. As for the
rooms which require higher health condition will be equipped with quick opened and
sealed ground leakages. The water seal height shall be at least of 50mm for other ground
leakages. Infrared sensor taps or automatic switches are required for rinsing sink in asepsis
wards or isolated rooms preventing cross infection.
3.2.4 Power Supply System
Double loop independent 10kv power source will be provided by city power grid, one for
daily use and another for standby. 10kv power source for each circuit can bear the whole
load. Diesel generator with 800kw will be equipped as the third power source. Transformer
and distribution house is located at Basement 1, transformer in-house with indicator of:
2×1600kVA+1×1250kva+1×500KVA; diesel generator: 1×800KW.
3.2.5 Firefighting System
.
The fire-fighting water pipe network will be formed by laying a pipe (DN200)(including th
e water meters) from the municipal water supply network in the north of the Hospital. Lo
op pipe network will be formed by laying a pipe (DN150) from the municipal water supply
network on the west of hospital.
10
3.2.6 Intelligent System
① Double circuit is proposed for machine room, with standby power source of UPS. The
UPS power supply should continue for equal to or more than 4 hours when power
supply cuts.
② Precision air-conditioning system with constant temperature and humidity to be
equipped in machine room, where requires systems operate in a way of lower air
supply and upper air return.
③ Fresh air ventilation system is to provide fresh air to machine room, maintain the
positive pressure differential, and keep machine room clean and free of dust. The weak
current and heavy current shall be laid separately to avoid electromagnetic interference.
The general requirement for wiring is: heavy current laid underfloor with slot, weak
current laid upon ground with lifting metal bridge. Grounding for lightening system
shall be installed in machine room; gas fire extinguishing device to be installed; 24
hour monitoring and warning device shall be included establishing interactive
relationship with firefighting system of the hospital. Machine room surveillance will
provide 24 hour monitoring and record any problem happens.
④Computer Network
Intranet will function as the core system for daily medical service (HIS, electronic
medical record, LIS, PACS systems etc.). Intranet is characterized by stable operation,
practical and safe in utilization, high efficiency broadband with high volume and speed.
It shall be able to be upgraded in the future.
Internet is also called special line network which will support health insurance
settlement, bank card transaction, community service and receiving calls from first aide.
Internet will provide long-distance medical service and education, office automation
service within hospital area, long-distance maintenance for medical equipment.
3.2.7 Ventilation System
① Mechanical Ventilation
Mechanical ventilation and fume exhaust combined system will be adopted for for
underground garage. Mechanical ventilation is designed for underground equipment
house.
② Air-conditioning System
The air-conditioning system consisting of two parts is applied: 1) purifying zone such
as operation room(OR) forms an independent system; 2) the rest area except for
purifying zone is called general area will have another system. Cold and heat sources
are designed for OR; besides the special sources, pipes will be connected to central
air-conditioning system. Four-pipe control is adopted with valves installed for switch.
11
The normal area of the whole hospital is divided into 4 sub-systems (emergency
department, left & right side of outpatient department and inpatient department) , with
4 with two-pipe control adopted.
All- Air conditioning system is adopted for large space such as hospital entrance. Fan
coil combined with fresh air system is applied for wards and consulting rooms. As
required by fire protection zoning and different functions of hospital departments, the
air system consists of separated sub-systems.
4. GENERAL ENVIRONMENTAL SETTINGS
4.1 Natural Environment
4.1 .1 Geographical location
Wanzhou is located in the northeast edge of Chongqing, with the longitude from
107°55′22″E to 108°53′25″E, and the latitude from 30°24′00″N to 31°14′58″N.
4.1.2 Topography, geomorphology, and geology
Wanzhou is located at the eastern folded belt zone in Sichuan Basin, which is composed of
Jurassic sandstone and mudstone layers with unequal thickness, with Yangtze River across
its southern area and Fangdou Mountain at its southeastern comer. This parallel
ridge-valley region contains high mountains with steep hills as well as crossed ravines. In
general, the topography is varied and complicated.
Landslide, dangerous rock, collapse, debris flow, and other unfavorable geological
phenomenon were not found within the scope of this project site. The status of the slopes
along the riversides is stable. The ground bearing stratums are composed of mudstone and
sandstone with a shallow and stable distribution, which is suitable for project construction.
4.1.3 Meteorology
Wanzhou is situated in the region where the semi-tropical climate dominates. The climate
is warm and humid with large amount of precipitation. The annual temperature ranges
from -1.8 ℃ to 42.3 ℃ with an average of 18.1 ℃. The average annual frost-free period is
314.9 days with 30 to 40 fog days. The average annual precipitation is 1191.30 mm (the
highest precipitation was 1577.30 mm in 1993). The precipitation varies largely with
different months, with 70% being distributed in the rainy season from May to September
each year. The highest monthly precipitation was 711.9 mm (Jul 1982); the highest daily
precipitation was 175.00 mm; and the longest continues rainy period was 16 days.
4.1.4 Hydrology
12
The domain within Wanzhou contains abundant surface water resources, while the
groundwater is relatively deficient. The water area is 24.07 km2 and accounts for 10.1% of
the total area.The network of rivers is intricate and most rivers feed into Yangtze River.
The groundwater is in general fissure water or seepage water. According to the
precipitation brought by the subtropical monsoon, a clear trend of runoff adapt to the
precipitation exists. The seasonal distribution of the annual runoff is: 26.7% for spring;
40.2% for summer; 28% for autumn; and 5.1% for winter. Yangtze river travels across
Wanzhou from the southwest to the north through 17 towns and administrative offices with
the total length of 83 km. The average annual flow rate is 12913 m3/s; and the average
annual flow volume is 450 billion m3.
This report uses the monitoring data on Saiwangba Section of Changjiang River from
Wanzhou Environmental Monitoring Station on Sep 2012, which indicates that the index of
pH, COD, BOD5, NH3-N, petroleum, and fecal coliform is less than 1, which meets the
class III standard of Surface Water Quality Standard (GB3838-2002).
4.1.5 Acoustic environment
4 noise monitoring stations were set up in this project, and the results show that the
acoustic environment is in good condition, which satisfies the requirements of class 2
functional area.
4.1.6 Ecology
Wanzhou is located at the midwest valley area, where the climate is mild and the frost-free
period is long. Since the altitude is generally low, no clear zoning phenomena is found for
the plants. The type plants can be divided into: subtropical evergreen broad-leaved forest,
subtropical low mountain evergreen coniferous forest, broadleaved deciduous forest, and
bamboo forest. The major plants include: Masson pine, Chinese fir forest, azalea, cedar
wood, gleicheniaceae dicranopteris linearis community, coriaria, thatch, and others. Soil
types in Wanzhou are various, which can be divided into 8 categories, 13 subcategories, 46
genera and 138 species. The major soil types of parallel ridge-valley area are purple soil
and paddy soil; while the soil types of the mountain basin are mostly yellow soil, limestone
soil, yellow-brown soil and brown soil. The food crops are rape, legumes, citrus, tung oil,
broad bean, tobacco, etc.
This project is located at Wanquan community in Wanzhou district, of which the
environment is urban ecological environment. There is neither national protection zone of
rare wild animals and plants nor any nature scenic spot in the surrounding areas.
4.2 Social Environment
4.2.1 Administrative division
13
As a central city of the Three Gorges reservoir region, Wanzhou is the economic and
cultural center as well as the water route transportation hub. According to Wanzhou
statistical almanac in 2010, the area of Wanzhou is 3,457 km2 with the main urban area of
45.0 km2 and the rate of urbanization is 52.85%. There are 29 designated towns, 12
villages, 11 sub-district offices, and 184 residents committees. The total population is 1.73
million (registered population), which includes 5,461 nonagricultural population and 1.18
million agricultural population, with the population density of 500/ km2 and the natural
population growth rate of 6.65‰.
4.2.2 Social and economic structure
In 2011, the regional GDP increased 56 billion Yuan, which was 20.1% higher than the
previous year; the regional GDP per capita was 32,350 Yuan. The structural ratio of tertiary
industry was adjusted from 7.7:51.2:41.1 for the previous year to 6.8:54.7:38.5. The
proportion of GDP of the secondary industry was increased by 3.5% over the previous year.
The disposable income of urban residents per capita was 16,633 Yuan, increased 11.5%.
The net income of rural residents per capita was 5,332 Yuan, increased 19.3%, among
which the wage income per capita was 2,542 Yuan, increased 17.7%.
4.2.3 Transportation
The 3-dimentional traffic network of water, road, and air has been gradually formed. The
length of Wanzhou highway has reached over 1500 km (excluding the village road). The
Wanzhou Yangtze River Bridge and the Yangtze River Second Bridge have been built. The
construction of highway was completed and now only 3 hours are needed from Wanzhou
to Chongqing. The railway from Dazhou to Wanzhou has been constructed and opened for
freight and passenger transport. The special railway line from Hongxigou pier to Wanzhou
railway station has a transport capacity of 2 million t/a, which can connect the railway to
the water carriage once completed. Of molten iron transport can be realized. Wanzhou
Wuqiao airport has been open to air traffic in May 2003. One third of the construction of
the 15-million-ton port has been completed as planned. After the completion of the Three
Gorges project, ton class vessels and fleets can be directed into Wanzhou port. The
expressway from Wanzhou to Kaixian and Yunyang has been built and open for
transportation. With improving transport conditions, a network of convenient water, road
and air transportation will be formed with sound function and rational layout in Wanzhou.
4.2.4 Cultural relics
Wanzhou has many institutions to protect the cultural relics, including 56 first-group
district-level institutions, 20 second-group district-level institutions, 34 third-group
district-level institutions, and 17 forth-group district-level institutions. There is no
institution for cultural relics protection within 500 m of this project.
4.2.5 Urban planning
14
According to the document “A Decision by CPC and the Chongqing People’s Government
to Develop Wanzhou into One of the Second-largest Cities” (CMG [2010]16), Wanzhou is
one of the most important and largest cities to develop in Chongqing’s urban-rural
integration development project, and an important gateway for economic development in
northeastern Chongqing and three gorges reservoir area. It is also a barrier for stability and
ecological safety in the reservoir area.
By 2015, Wanzhou will be the central city in the three gorges reservoir area with an urban
area of 80 km2 and a population over 1 million. The regional GDP will be more than 100
billion and the average GDP per capita will be close to that of the main city. In the next
5-10 years, Wanzhou will see rapid development of urbanization.
5. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
5.1 Assessment Range
The assessment range of this project is determined according to the project characteristics,
regional environment characteristics and the requirements of the environmental impact
assessment technical guideline, as listed in Table 5-1.
Table 5-1 Assessment Level and Assessment Range
No. Environmental
Factor
Level Assessment Range
1 Air III An area taken the construction site as the
center and 500 m as the radius
2 Surface Water Below III Briefly explain the type and amount of the
contaminates discharged and the condition of
water supply and drainage. Conduct some
simple analysis of the environmental impact.
3 Acoustic
Environment
II An area within 200 m outside of the factory
4 Ecology III Within the scope of the factory
5.2 Environmental Impacts and Mitigation Measures
5.2.1 Environmental Impacts and Mitigation Measures in Construction Phase
① Air Pollution
The air pollution during the construction stage will be caused by the air-borne dust
generated from excavation, construction waste and material transportation, leading to
deterioration of air quality. Area affected by fugitive dust is within 150m of downwind
construction site when the wind speed is at 2.0m/s, which concludes the air pollution in
west and north of the project will be comparatively greater but to be eliminated when
project completed.
15
Air pollutant mixed by CO and NOx generated by fuel machine for excavation and fill,
transportation and construction will have minor impact because the fuel machine works
intermittently at night in earthwork excavation stage resulting in little discharge.
Pollution impact to be eliminated when work completed. Liquefied petroleum gas as
green energy to be used by workers has little impact on environment.
② Surface Water
The construction wastewater is mainly generated from domestic waste from works and
wastewater on site. Construction wastewater contains SS, petroleum element generated
by equipment maintenance, cleaning, and concrete curing.
Construction wastewater will be recycled after treatment though grease trap
sedimentation. The domestic wastewater will be collected then discharged into
municipal pipe network in the south of project site. The wastewater impact is
eliminated as work completed.
③ Noise
The primary noise source in construction phase is the operation of equipment, having
negative impact on the sensitive spots around of project site.
④ Solid Waste
Solid waste in construction phase is mainly generated by earth disposal, construction
waste and domestic waste from workers. It will have negative impact on cityscape and
sanitary condition if it’s not removed timely; it even will cause water and soil loss in
rainy day. The solid waste shall be firstly piled by sorting out then removed timely with
preventive measures taken so as to avoid water and soil loss. Construction waste shall
be moved to the designated spoil site, and domestic waste shall be moved to landfill
site.
⑤ Water and Soil loss
Earthwork excavation and ground leveling will loosen land surface to possibly cause
water and soil loss in raining day.
⑥ Transportation
As the construction site will have engineering vehicles access frequently (through
Longyuan Rd in northwest of site, and municipal road in south of site), the vehicles are
required to be washed before leaves, and no earth rock falling out as vehicles travels on
road. Solid waste transportation must follow “Notice on leak-proof transportation of
substances easily spilt in main city” and “Management Regulation on Construction
Waste Removal in Main Area of Chongqing”(No 93 document issued by CMG). These
measures will have effective control of pollution caused by solid waste transportation.
16
Table 5-2 Pollution Control Measurements during Construction
No. Contaminants Control Measurements
1
Dust Arrange reasonable work shift; operate with water spray when the
dust exists; pile up cement and other construction materials in the
warehouses and cover them; strengthen the supervision and
management od the waste residue, seal the supplies, clean and
maintenance the vehicles, and forbid taking overweight or over
height supplies or mud on the road; set separation barrier no less
than 1.8 m height at the construction site; speed up the construction
while assuring the quality.
Domestic fuel
emissions
Use clean energy such as liquefied gas.
Industrial fuel
emissions
Use advanced construction equipment with low- consumption,
low-pollution, and high-efficiency; strengthen the maintenance,
management, and reasonable arrangement of the equipment.
2
Domestic
wastewater
Toilet and septic-tank are set at the south of the construction site.
The sewage should be discharged to the municipal domestic water
network after septic-tank treatment.
Industrial
wastewater
Set grease trap sedimentation tank at lower-lying areas. Recycle
the treated wastewater.
3
Vehicle traffic
impact
Various types of vehicles enter and exit the construction site from
the west side of Saide international school on the Longyuan road;
avoid the vehicles to enter and exit the construction site at busy
school hours, to ensure the safety of the students; set slow-down
and silence identifications on Longyuan road and the south civil
road; set signs to prohibit irrelevant personnel in construction site
and start patrols.
污染物 防治措施
4
Construction
noise
(1) Construct strictly in accordance with the CMG's No. 126
document “Chongqing Environmental Noise Pollution Prevention
and Management Methods”. (2) The construction institution should
report to the local environmental protection bureau 15 days before
construction and release a statement to the public for
understanding. (3) Use low-noise construction equipment. (4) Use
commercial concrete. Concrete mixer that produces continuous
noise is strictly forbidden. (5) If 24-hour continuous operation is
required, the construction institution should report to the local
environmental protection bureau 4 days in advance and hang the
overnight construction permit to explain to the public. The
construction institution should also be responsible for reducing the
noises. (6) 15 days before and during the time of college or high
school entrance examination, the construction work at night is
forbidden (except for emergency or rescue operation). (7) Speed up
施工噪声
① 严格按照渝府令第 126号《重庆市环境噪声污染防治管理办
法》要求,文明施工。② 施工单位应在开工 15 日前向当地环
境保护局申报,得到环保局批准后,向施工区周边企业也发布
公告,以便得到公众的谅解。③ 采用先进的施工机械和技术,
选用低噪声作业机具。④ 采用商品混凝土,严禁用产生连续噪
声源的混凝土搅拌机等设备。⑤ 如因施工工艺需要,必须 24
小时连续作业时,施工单位应提前 4 日向当地环境保护局办理
夜间施工手续,并按要求认真实施降噪措施,将夜间施工审批
手续悬挂于工地显眼处,同时张贴告示,作好公众的宣传解释
工作,接受公众和环保执法人员的监督。
⑥ 高、中考前 15 日内以及高中考期间,禁止在噪声敏感建筑
物集中区域进行产生噪声污染的夜间施工作业(抢修、抢险作业
除外)。⑦ 加快施工进度,在不影响工程质量的前提下尽量缩
短工期。
17
the construction while assuring the quality.
5
Construction
wastes and
household
refuses
Classify the wastes and take actions to avoid dust and soil erosion
caused by rains. Transport the construction wastes to specified
dumping fields and the household refuses to the urban landfill
sites.
建筑垃圾
生活垃圾
分类堆积,并做好防护措施,避免扬尘和下雨时引发水土流失,
及时清运。建筑垃圾运往指定的渣场倾倒;生活垃圾及时运往
城市垃圾场卫生填埋
5.2.2 Environmental Impacts in Operation Phase
5.2.2 .1 Air Emission
① Emissions from Boilers
This project plans to set a gas-fired boiler to supply steam for the operating room,
laundry and other clean areas; and a gas vacuum hot water boiler for heating and hot
water.
Both boilers use gas and the combustion emissions should be merged and discharge
from a stack higher than 8 m. The limit for SO2 is 3.2 t/a, and the discharge
concentration should be lower than 51 mg/m3; the limit for NOX (converted to NO2) is
9.3 t/a, and the discharge concentration should be lower than 150 mg/m3; the limit for
dust and fume is 1.5 t/a, and the discharge concentration should be lower than 25
mg/m3, as required by “Air Pollution Emission Standards for Boilers”
((GB13271-2001)).
Since gas is a clean energy, the contaminate concentration is low and has minor
influence on the air.
② Cooking Oil Fume
The cooking oil fume from the canteens will bring negative impacts to the air, thus it is
necessary to purify the oil fume before discharging. Suppose the remove efficiency
reaches 85%, the oil fume concentration will be about 1.0 to 1.8 mg/m3, which meets
the requirement of “Emission Standard of Cooking Fume” (GB18483-2001) and has
minor influence on the air quality.
③ Wastewater Treatment Station Odor
This project plans to build a 450 m3/d wastewater treatment station at the south part,
which may produce odors by methane, ammonia, and hydrogen sulfide.
The assessment requires the station to be enclosed by cover plate with reserved
inlet/outlet. The collected odor should be treated with activated carbon and discharged
through specific pipelines to the green belt. The discharge outlet is 65 m away from the
Wanzhou No.3 People’s Hospital at Baolong, 55 m away from the southeastern
residential building, and 45 m away from the west residential building. The odor
influence will be reduced after the treatment.
18
④ Vehicle Exhaust
The vehicles can produce a certain amount of exhaust, thus it is necessary to set a
double-speed fan in the garage, of which the ventilation rate is no less than 6 times per
hour. The exhaust should be directed to the exhaust shafts and discharged at the roof.
The impact to the air quality is minor.
⑤ Backup Generator Exhaust
A mechanical discharge device is set up in the backup generator room. The exhaust
should be directed to the exhaust shafts (use refractory bricks for thermal insulation)
and discharged at the roof. The impact to the air quality is minor.
5.2.2.2 Surface Water
① Hospital Wastewater
According to the engineering analysis, the flow of the hospital wastewater is about
413.38 m3/d. The major components include: organics, SS, grease, pH, toxic chemicals,
pathogenic bacteria, viruses, and parasitic ovum, etc., thus it must be discharged after
sterilization and treatment.
A municipal pipe network (DN600mm) is set 160 m south from the site. The first phase
capacity of Minjingtan wastewater treatment plant was planned to be 30,000 m3/d,
using A2/O oxidation ditch process ((anaerobic-anoxic-aerobic carrorsel oxidation
ditch). The discharging water can meet the first level class B standard of “Urban
Wastewater Treatment Plant Pollutant Discharge Standard”. This plant was completed
on Jul 2003 and has been under stable operation. The actual capacity is about 10,000
m3/d, and can accept the wastewater of this project. Chongqing Yudong Water CO.
LTD has agreed to accept the wastewater after pretreatment of this project.
This project plans to build a wastewater treatment plant with the capacity of 450m3/d
and the treatment process of primary treatment + disinfection. After treatment, the
hospital wastewater will meet the primary treatment standard of “Water Pollutant
Discharge Standard for Medical Institutions” (GB18466-2005) and be discharged into
the Mingjingtan wastewater treatment plant through the municipal sewage network.
② Special Wastewater
This project adopts digital X-ray fluoroscopy devices. There is no photo development
room and liquid waste containing silver. According to related operation information, no
radioactive liquid waste is produced by the radiology department.
The silver amalgams used by the stomatology department are purchased and sealed in
19
capsules, thus will not generate wastewater containing heavy metals. The silver
mercury residues are stored by ground-glass stoppered flasks for manufacturers
recycling.
The wastewater of clinical laboratory may contain toxic substances such as chromium,
and cyanide with the amount about 0.5 m3/a. The amount of the special wastewater is
small, which is difficult for treatment and cost is high. The project incorporates the
waste water into the medical waste and uses special airtight container to collect the
pollutants for Wanzhou Senhao Pollutant Disposal Limited to dispose.
As long as this project can strengthen the operation and management of wastewater
treatment facilities and the workers’ environmental protection consciousness, and
ensure the reasonable management and control of special wastewater discharge, the
concentration of medical pollutants will be reduced and will not bring negative impacts
to the the Yangtze river.
5.2.2.3 Noise
The major sources of noise are pump house, cooling tower of air condition and fans,
backup generators, and vehicles. The equipment and intensity are listed in Table 5-3.
Table 5-3 Noise Equipment and Intensity
Source Vehicle Cooling
Tower
Pump House Fans Backup
Generator
Noise
Level
dB(A)
~70 ~80 ~80 ~85 ~90
Location The underground
garage and
courtyard
Roof The basement
equipment
room
The basement
equipment
room
The power
room in the
basement
The noise control measurements for various sources:
① Vehicles
The garage is in the two basement floors, thus the noise can be removed using its
location. The basement sound insulation capacity can reach to over 40 dB(A). After the
insulation, the basement garage sound insulation will not produce very large noises.
The garage on the ground can reduce the traffic noise by setting slow-down and silence
identifications. From these actions the traffic noise can be effectively controlled and
will not have great influence to the outside world.
② Cooling Tower
The noise produced by the cooling tower noise are mainly caused by the fan and
chimney, and the noise is about 80 dB(A). Noise reduction measures include: use a
shock absorber and rubber soft materials to reduce the effects of vibration; install a
20
muffler at the cooling tower inlet/outlet; use an anechoic water cushion and control
water muffler to control the noise; set up sound barriers outside the cooling tower.
③ Pump Room, Fan Room, and Power Room
Pump room, fan room, and power room are at the first level of the basement. From the
insulation of the walls, the noise can be reduced up to 40 dB(A), thus won’t influence
the environment.
5.2.2.4 Solid Waste Impact Analysis
① Medical Waste
The germs in medical waste are tens or even hundreds times more than the ordinary life
trash, and most dangerously, it is infectious.
Before taking the medical wastes, the packages or containers should be carefully
checked to be without damage, leakage, and other problems; it should also be
registered to prevent loss. The cultures for pathogens and bacteria, the specimen and
strains, the virus seed preserving liquid, and other medical wastes must be primarily
treated before transporting to the disposal institutions. The temporary storage facilities
and equipment regular cleaning and disinfection should meet the requirements of
“Hazardous Waste Storage and Pollution Control Standards” (GBl8597-2001) and
“Technical Specification FOR Medical Waste Centralized Disposal”.
The medical waste storage room is located at the south of this project, away from the
medical area, personnel activity area, and living area. The medical waste storage room
is separated from the domestic refuse temporary storage spot. The washing wastewater
of the medical waste storage room can be directly discharged into the wastewater
treatment plant. The medical waste on different floors can be collected by specified
containers and transported through specified channels to the storage room through the
south channel. The channels for waste transport are separated from the patients and
doctors. The medical wastes are collected, transported and disposed by Wanzhou
Senhao Pollutant Disposal Limited.
② Sludge from Wastewater Treatment Plant
This project intends to set up a sludge concentration pool and a disinfection pool. The
sludge that meets the requirements of "Water Pollutant Discharge Standard for Medical
Institution" (GB18466-2005) will be dealt with by Wanzhou Senhao Pollutant Disposal
Limited.
③ Household Refuse
The trash will be collected by class and transported to the municipal landfill sites.
④ Food Waste
The food waster will be dealt with by specified institutions with related certifications.
21
⑤ Special Wastewater
Clinical laboratory wastewater will be temporarily stored by specified airtight container
and sent to Wanzhou Senhao Pollutant Disposal Limited.
⑥ Waste Activated Carbon
The waste activated carbon that has absorbed the odor from the wastewater treatment
plant will be sent to Wanzhou Senhao Pollutant Disposal Limited.
5.2.2.5 Radiation Impact Analysis
According to the analysis, after the completion of the project, the annual effective
additional dose of the hospital radiation workers and the public are far less than the
limits of 6 mSv/a and 0.1 mSv/a, which meet the "Ionizing Radiation Protection and
Radiation Source Safety Standards" (GB18871-2002).
5.2.2.6 Social Impacts during Operation period
The increased traffic volume of current north, west and south municipal road is far
from its full load. The assessment reports show that the impacts to the current north,
west and south municipal road will be very little, and will not result in traffic jam, but
may have some negative impacts on the residents and students’ safety around
Longyuan Rd and the south municipal road. The prevention and control measures are:
Communicate with the management department, set school and hospital
identifications on the municipal road.
Set slow-down and silence identifications at the hospital entrances/exits.
6. ANALYSIS OF ALTERNATIVE PLAN
6.1 With or Without the Project
6.1.1 Without the Project
Three Gorges Reservoir Area is prone to epidemic disease and natural disaster, which leads
to difficult and arduous task of disease prevention and control. Currently the distribution of
medical resource in Wanzhou District is unbalanced. In the area where the head office of
Wanzhou Maternal and Child Hospital is located, the health care resources are concentrated,
which may lead to oversupply of the resources in a small area but insufficient in the whole
district.
If no further expansion of addition to the head office of Wanzhou Maternal and Child Hospital
(i.e. without the project), the current problem as regards medical resource in Wanzhou is to
worsen with ever increasing medical need of local people.
22
6.1.2 With the Project
The proposed project will :
① meet the needs of the Chongqing urban rural integration campaign;
② promote the development of medical health care in Wanzhou;
③ optimize the distribution of medical resources in Wanzhou District;
④ ensure that the public medical service of central cities in Three Gorge Reservoir will
be radiated to surrounding area;
⑤ ensure the health of local people.
The conclusion following the above comparison is that the proposed project will promote
the development of Wanzhou District medical service, ensure the medical service in
regional center be conveyed to surrounding area, improve the urban rural medical system
nd medical service, meet the needs of the people in Three Gorges Reservoir Area by
delivering safe, effective, convenient and local cost basic medical heath care service, and
ensure the health of local people. Therefore, the proposed project is necessary and urgent.
6.2 Site selection/ comparison
Three sites were proposed:
① Parcel C-01-33、C-01-10 included in the “Master Plan for Tiancheng Group I,II
Management Area(Tiangfang, Dongjia) ” located in Maogu Village 8 in Tiancheng
Town;
② Jianfengling of Wuqiao District;
③ Wanquan Community in Shuanghekou;
Based on the nature of the medical service to be delivered, the site condition and
environmental impact, Wanquan Community in Shuanghekou was selected as the best
project site.
6.3 Selection and Comparison of Disinfection Process
6.3 .1 Selection and Comparison of Disinfection Process
The following findings were made after comparison:
① For the method involving ozone generator and ultraviolet, one-off capital investment is
huge and operation management is complicated;
② For the method using bleaching powder concentrate, disinfectant and bleaching
powder, operation cost is too high;
③ For the method using liquid chlorine, the technique is mature and it is very effective,
but it is too dangerous and prone to leakage. In addition the one-off investment is no
less that of Chlorine Dioxide Generator method and toxic substance may be resulted
due to reaction with organics;
④ Sodium hypochlorite generator is bulky and its key components is easy to damage, the
23
electricity and salt consumption is high, and the operation is not convenient.
Currently Wanzhou Maternal and Child Hospital is a Category A of Class II hospital(with 500
hospital beds designed). The target of the proposed project is to upgrade it to a Category A
of Class III hospital(with more than 500 beds) integrating medical treatment and medical
care. The method of Chlorine Dioxide is proposed for disinfection.
6.3 .2 Selection and Comparison of Disinfectant Preparation
① Chlorine Dioxide Generator
Following comparison, NaCl diaphragm electrolysis method will be adopted, but it
must meet the requirement specified in ”Technical Specification of Environmental
Protection Product: electrolysis chlorine dioxide synergistic disinfectant generator”
(HJ/T257-2006).
② Alternative method in case of accident
In case of the breakage of disinfection equipment or other accident, the EIA requires that
all the medical wastewater be collected into the emergency tank, to be treated with
bleaching powder (sodium hypochlorite).
6.4 Comparison and Selection of Wastewater Treatment Process
The proposed site is in the service area of Mingjingtan WWTP and municipal wastewater
pipe has already been connected to the site. The wastewater from the project, which is to
be treated with enhanced primary treatment plus disinfection, will meet the requirement as
regards primary treatment specified in “Discharge standard of water pollutants for medical
organization (GB18466-2005)” , therefore the wastewater treatment proposal is feasible.
7. RESETTLEMENT PLAN
According to the field survey, there are no residential buildings within the project
construction area. The land-use right belongs to Wanzhou District Water Supply Company ,
Wanzhou Renyang Construction Material Shop, Wanzhou District Broadcasting Television
Station and Longbao Branch of Wanzhou District People’s Hospital. The project owner has
completed related land acquisition procedure. The Land Acquisition and Resettlement
Office under Wanzhou District Government will be responsible for the land acquisition and
resettlement. And the clean land will be handed over to Wanzhou Maternal and Child
Hospital. Therefore; there will be no land acquisition and resettlement under this Project.
8. ENVIRONMENT MANAGEMENT AND MONITORING PLAN
The environmental management specifications are detailed in Table 8-1; the environment
monitoring plan is detailed in Table 8-2. The summary of environmental protection
measures and the environmental protection investment estimation are detailed in Table 8-3.
24
Table 8-1 Environmental Management Specifications
Environmental
Problems Environmental Management Specifications
Implementing
Agency Supervision Agency
A. Design Phase
1. Location
and scale
Determine the hospital scale and site by comprehensively analysing the environmental
protection, social demand, technology economy and engineering aspects; Choose the optimal
scale and site selection plan to acquire the recognition of Wanzhou government and the project
owner;
Design
institution
EIA institution
CPMO, Wanzhou Health
Bureau, and Wanzhou DRC
2. Ecology
protection
Forbid to take over high quality farmland and forest in site selection; Set more green belts and
fences for climbing plants in the design and reduce the impact of hospital noise; Improve the
layout design of plants and flowers in the waiting area and inpatient building.
Design
institution
EIA institution
CPMO, Wanzhou DRC,
Wanzhou EPB, and CEPB,
etc.
3. Traffic noise
Improve and optimize hospital layout design and reduce the impact of traffic noise on hospital
operation; Hospital site selection should balance the service scope, convenient accessibility
and traffic noise prevention.
Design
institution
EIA institution
Wanzhou EPB
4. Surface
water
contamination
While meeting the process requirements, the site of medical wastewater treatment station
should consider making full use of the land; The design of water treatment process should try
to save energy and reduce consumption using the gravity flow; In addition, the designed
capability of the wastewater treatment station should balance the development and risks.
Design
institution
EIA institution
Wanzhou EPB
5. Air pollution
Strictly design gas deodorization control for the medical wastewater treatment station;
Optimize the designed layout and noise control for diesel generator; Optimize the ventilation
design of underground garage; Optimize the design of the oil fume and exhaust removal for
the dining room and boiler room.
Design
institution
EIA institution
Wanzhou EPB
6. Hospital
solid waste
Design flies, rodents, and cockroaches prevention measures for the temporary medical waste
storage; Make diversion design for medical waste collection and transport; Design clean and
conduct facilities for the temporary medical waste storage and collectors; Make anti-seepage
designs for the temporary medical waste storage.
Design
institution
EIA institution
Wanzhou EPB
25
7. Lighting,
ventilation and
natural scenery
Make full use of natural lighting and ventilation in the design; Make full use of local natural
landscape in the design of hospital.
EIA institution
Design
institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
8. Radiation
The layout and design for radiation protection should meet the national standards and the
requirements of "Medical diagnostic X-ray machine room sets must consider the safety of the
adjacent room and surrounding places" in "Health Protection Standards for Medical X-ray
Diagnosis" (GBZ130-2002).
EIA institution
Design
institution
CEPB, Wanzhou EPB, and
Wanzhou Health Bureau
9. Risk
prevention
Design facilities to prevent the risks and emergencies during the transport of chemicals and
wastes; Optimize the design of chlorine dioxide disinfection room and chlorine dioxide raw
material storage room, and set up mechanical ventilation facilities; Make sure that in case of
accidents, everyone could leave the disinfection room safely; Install automatic monitoring
alarm system in the disinfection room.
Design
institution
EIA institution
CPMO and Wanzhou DRC
10. Soil and
water
conservation
Optimize the design for temporary storage site and the dig-fill balance.
Design
institution
EIA institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
11. The
construction
campsites
Forbid set construction campsites close to the sensitive environmental acceptors; Use existing
roads or sites within the project scale; Keep the construction from residential areas and
schools.
Design
institution
EIA institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
12. Traffic
impact
Optimize the design of layout, entrance/exit, parking lot, and construction process to avoid the
impact of construction and operation on the urban traffic.
Design
institution
EIA institution
CPMO, Wanzhou DRC,
Wanzhou EPB, and Wanzhou
Transportation Bureau
13. Earthquake
resistance
The earthquake-resistance standards for the hospital should be one level higher than other
public buildings within the same district.
Design
institution
EIA institution
CPMO, Wanzhou DRC,
Wanzhou EPB, and Wanzhou
Health Bureau
B. Construction Phase
26
1. Ecology
protection
Add temporary drainage ditch and strengthen the bare ground to prevent the erosion of the
soil; Timely clean and backfill the wastes; Harden the road surface, plant trees in the open
space, and restore vegetation to assure the slope stability; Manage the working shift, avoid
large scale excavation work in the rain season.
Contractor
Supervising
institution
CPMO, Wanzhou DRC,
Wanzhou EPB, and Wanzhou
Health Bureau
2.Exhaust gas
Use of commodity concrete for site hardening; Timely remove the construction waste and
excess soil; Set washing and sedimentation facilities at entrance and exit for construction
vehicle; Regularly spray water to control the dust on site and the entrance and exit, keep the
site clean and tidy; No burning and melting asphalt; Construction site shall be enclosed in
accordance with the relevant provisions;
Contractor
Supervising
institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
3. Noise
The low-noise generating construction equipment and technology will be considered during
bid evaluation; The contractor shall bring related documents to the local environmental
protection department to declare "Construction Environmental Protection Approval Form"
15days before notice to commence .The work cannot be started without the approval; No
construction work which noise- generated are allowed during the period 12:00-14:00 and
22:00-7:00; For continuous concrete-casting work. The contractor should ask for approval
from related environmental protection department 3 days before work started.
Contractor
Supervising
institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
4. Wastewater
The domestic wastewater produced by working staff of the Contractor should be discharged to
urban wastewater network after treatment. To avoid foundation excavation during rainy
season.
Contractor
Supervising
institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
5. Construction
and domestic
Solid wastes
Use Waste soil shall be used for backfilling. Timely remove the construction solid waste from
the Site. The solid waste cannot be stored in site for long time, it should be cleaned daily. To
avoid solid waste falling down from the vehicle, it should be covered by felted fabrics.
Contractor
Supervising
institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
27
6. Traffic
Various types of vehicles enter and exit the construction site from the west side of Saide
international school on the Longyuan road; avoid the vehicles to enter and exit the
construction site at busy school hours and pay attention to and yield the students; set
slow-down and silence identifications on Longyuan road and the south civil road; set signs to
prohibit irrelevant personnel in construction site and start patrols.
Contractor
Supervising
institution
CPMO, Wanzhou EPB, and
Wanzhou Traffic
Administrative Department
7. Training The Employer is requested to provide training to construction staff of the Contractor on safety
and environment protection.
Contractor
Supervising
institution
CPMO, Wanzhou DRC, and
Wanzhou EPB
C. Operation Phase
1. Hospital
wastewater
The separated sewerage system will be adopted. The rainwater and sewerage will be collected
and discharged to the wastewater treatment station which will be built on the south side of
the project site with a capacity of 450m3/d. The treatment process is “Enhanced primary
treatment + Disinfection". Domestic wastewater and hospital wastewater will be discharged to
Mingjingtan Wastewater Treatment Plant through urban sewerage system after treatment in
hospital wastewater treatment station. The wastewater treated in the Station should reach the
discharge standard in the Table 2.of GB18466-2005. Emergency tanks will be built.
Wanzhou
Maternal and
Child Hospital
CEPB, Wanzhou EPB, and
Wanzhou Health Bureau
2.Exhaust gas
The odor will be collected and deodorized by active carbon, then discharge to green area
through special pipe; The exhaust gas of 2 boilers will be collected and discharged through one
exhaust cylinder not lower than 8m; The double speed fan will be set in the garage to enhance
ventilation. The ventilation frequency will not be less than 6 times /h. Automobile exhaust
will be discharged via dedicated exhaust shaft lead to roof high emissions; Mechanical
discharge device will be installed in the standby generator room. The exhaust gas will be led to
the roof by a special emission shaft (use refractory brick for heat treatment); The fume will be
led to the roof emission after treatment by oil fume purifier.
Wanzhou
Maternal and
Child Hospital
Wanzhou EPB
28
3. Hospital
solid waste
Hospital solid waste, sludge, and special wastewater will be transported and treated by
Wanzhou Senhao Pollutant Disposal Limited.; Wasted active carbon will be treated by
Wanzhou Senhao Pollutant Disposal Limited; Domestic solid waste will be collected by the
sanitation department and transported to county garbage disposal plant; Kitchen and food oil
wastes will be treated by organizations with related qualification.
Wanzhou
Maternal and
Child Hospital
and Medical
Waste Disposal
Institutions
CEPB, Wanzhou EPB, and
Wanzhou Health Bureau
4. Equipment
noise
Layout the major noise sources, like diesel generators, blowers, and air compressors, in the
basement or special equipment room; As for the roof cooling tower, adopt shock absorption
device, inlet/outlet silencer, or other sound insulation arrangements.
Wanzhou
Maternal and
Child Hospital
Wanzhou EPB
5. Traffic Set identifications for schools and hospitals; Set slow-down and silence identifications.
Wanzhou
Maternal and
Child Hospital
CEPB, Wanzhou EPB,
Wanzhou Health Bureau, and
Wanzhou Traffic
Administrative Department
6. Radiation Set radiation resistance walls, doors, and lead glass; Strengthen the management and training
for the technical personnel; Develop emergency plans.
Wanzhou
Maternal and
Child Hospital
CEPB, Wanzhou EPB, and
Wanzhou Health Bureau
7. Training Trainings about medical waste classification: colors of the medical waste classification boxes
(red for contagious wastes, yellow for infectious wastes, and green for injury wastes).
Wanzhou
Maternal and
Child Hospital
CPMO and Wanzhou EPB
D. Monitoring Conduct regularly environmental monitoring, as detailed in the monitoring plan.
Wanzhou
District
Environmental
Monitoring
Station
Wanzhou EPB
29
Table 8-2 Environment Monitoring Plan
Pollutant Monitoring
Parameters Monitoring Point Monitoring Frequency Responsible Organization Supervision Organization
Cost
(yuan/year)
Construction Phase
Air TSP site boundary 1time/quarter
Wanzhou Environment Supervision
Station
Wanzhou District
Environment Protection
Bureau
3288
Noise Leq(A) site boundary 1time/quarter
the Employer
2112
Solid waste Domestic solid waste / 1time/quarter 1920
Traffic
situation / / Random spot checks The Contractor and the Employer /
Subtotal 7320
Operation Phase
Exhaust
gas
Boiler Exhaust
gas(SO2,smoke and
dust ,NO2
1#Emission Cylinder 2 times
per year
Wanzhou Environment Supervision
Station
Wanzhou Environment Supervision
Station
Wanzhou Environment Supervision
Station
(Daily supervision be done by the
Hospital)
Wanzhou District
Environment Protection
Bureau
1644
Smell (odor
concentration,
ammonia, hydrogen
sulfide)
2# mission Cylinder 2 times
per year
3200
Oil fume Oil fume channel 2 times
per year
1794
Hospital
Wastewater
COD,BOD5,NH3-N,f
ecal coliform
Outfall of Wastewater
Treatment Station
Daily monitoring:
1) COD, BOD5, SS, NH3-N
1 time/ month;
2) fecal coliform bacteria
1 time/ two weeks.
3) Environmental monitoring: spot
checks
4) 1 times / half year
Wanzhou District
Environment Protection
Bureau and Wanzhou
District Health Bureau
2000
Noise
Boundary Noise Boundary
1time/quarter, daytime and night time .
One time when cooling tower put into
use.
The Employer , the Contractor and
Wanzhou Environment Supervision
Station
the Employer 2640
Traffic Noise Close to roadside 1time/quarter
Wanzhou Environment Supervision
Station
Wanzhou District
Environment Protection
Bureau
1056
30
Solid Waste
Medical Solid Waste Temporary Storage
Room
Check treatment sheet and agreement
one time per month;
Summarize medical waste transfer
amount every half an year The Hospital
Wanzhou District
Environment Protection
Bureau and Wanzhou
District Health Bureau
960 domestic Solid wastes /
Summarize the total treatment
amount every half year
Wasted Active Carbon / Check treatment sheet and agreement
one time per month;
Summarize medical waste transfer
amount every half an year
The Hospital Kitchen and Food Oil
Wastes /
Radiation
The accumulated
volume of personal
exposure dose
Check personal
dosimeter worn by
operator
Every 2 to 3 month The Hospital
Wanzhou District
Environment Protection
Bureau and Wanzhou
District Health Bureau
3194 the rate of kinetic
energy released in air
around working area
Around protection
Door and the gap,
entrances and exit of
cable ; operating room,
operation platform and
a room shielding walls
etc.
one time every half a year Chongqing Municipal Radiation
Technology Service Center
Subtotal 16488
Total 23808
Table 8-3 Summary of Environment Protection Measures and Related Investment
Pollutant Pollution Source Pollution Factor Mitigation Measures Investment
(million yuan )
Construction
Phase Exhaust gas Construction site Air-borne Dust
Regularly spray water to control the dust on site , build fence ,harden the
surface of the entrance and exit , wash the vehicle and tyre, cover the
construction material which easily borne dust, transport material with cover. 0.15
31
Wastewater
Construction
wastewater and
domestic
wastewater
SS , Oil
Water for equipment maintenance will be reused for controlling dust after
sediment treatment. Temporary septic tank and toilet will be built at the south
side of the Site. The domestic wastewater produced by working staff of the
Contractor should be discharged to urban wastewater network after
treatment in septic tank .
0.10
Solid Waste
Construction waste
and domestic Solid
wastes
Construction waste
and domestic Solid
wastes
Construction waste will be transported to appointed dumping site. Domestic
solid waste will be collected and treated by related sanitation department 0.12
Noise Construction Noise Noise
Ask for approval before work started; encourage to use new equipment and
technology, reasonably arrange working time, fence and enclosure are
requested. 0.20
Environment Management and Monitoring Cost during Construction Period 0.40
Subtotal : 0.97
Operation
Phase
Exhaust gas
Boiler SO2、NOX
、smoke and dust
The exhaust gas will be collected and discharged through one exhaust cylinder
with 15meter long 0.05
Kanteen Oil Fume The oil fume will be led to the roof emission after treatment by oil fume
purifier. 0.10
Wastewater
treatment station Odor
The odor will be collected and deodorized by active carbon , then discharge to
green area through special pipe. 0.07
Garage
NOX、HC
The double speed fan will be set in the garage to enhance ventilation.
Automobile exhaust via dedicated exhaust shaft lead to roof high emissions.. 0.06
Generator Room
Mechanical discharge device will be installed. The exhaust gas will be led to
the roof emission by a special emission shaft (use refractory brick for heat
treatment). 0.05
Wastewater
Hospital
Wastewater
COD、BOD5、SS、
NH3-N、
fecal coliform
Be discharged to urban sewerage system after pre-treatment in Wastewater
Treatment Station with "Enhanced primary treatment + Disinfection"
process , 450m3/d 2.50
Special wastewater With heavy metals, Treated as Hazardous waste ,be collected and transported to Wanzhou Senhao
Pollutant Disposal Limited. 0.08
Solid
Waste
Hospital Solid
Waste Hospital Solid Waste
Classified collection and package, be transported and treated by Wanzhou
Senhao Pollutant Disposal Limited. 0.50
Wastewater
treatment station
Sludge Wasted
Active Carbon
After concentration and disinfection, be transported and treated by Wanzhou
Senhao Pollutant Disposal Limited. 0.20
Domestic Solid Domestic Solid
Waste
Be collected by the sanitation department and transported to city solid waste
Landfill site. 0.10
32
Waste
Kitchen and Food,
Oil Wastes Be collected and treated by organizations with related qualification. 0.13
Noise Equipment Noise Noise sound barrier , noise elimination, sound insulation 0.09
Risk mitigation measures Disinfection measures for emergency discharge, medical solid waste
refrigeration measures; signs for leakage, rainwater and "hazardous waste", etc 0.20
Others Greening, Vegetation restoration, water and soil conservation 0.80
Final acceptance for environment protection, monitoring , environment management, training program etc. 0.10
subtotal 5.03
Total 2% of total investment 6.00
33
9. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
In accordance with the requirements of the China’s EA Law and Temporary Method
for Public Participation of China, as well as the Safeguard Policy of the WB, two
rounds of public consultation were conducted by the EIA team by the way of posting
notice in project area, network publicity, questionnaires, public meetings and so on to
solicit the concerns of the residents .
9.1 The way of public consultation
9.1.1 Notice Posting
A lot of investigation and coordination work has been done by Wanzhou Maternal and
Child Hospital before carrying out environmental impact assessment work . After
commissioned by the Hospital , Chongqing Dehe Environment Engineering Co.Ltd
has posted a notice on the east and south side of the Site, and at Saide International
School to provide the following information to the public: (1) the name and summary
of the project; (2) the name and contact way of the employer; (3)the name and contact
way of the company which works on environmental impact assessment; (4) work
procedure and main work of environmental impact assessment ; (5) main issues for
public opinion; (6) the main way of the public to express their opinions.
9.1.2 Information Disclosure on Internet
The first disclosure was done on the http://www.cqdhhb.com/Chinese/index.asp
website from November 5, 2012 to November 16th. The content includes: (1) brief
introduction of the project; (2) information related to the Evaluation Company; (3)
work procedure and main work of environmental impact assessment; (4) main issues
for public opinion; (5) the main ways to express public opinion.
The second disclosure of the whole report (first draft) was done on the
http://www.cqdhhb.com/Chinese/Index.asp web site from December 5, 2012 to
December 18th
. The report (draft) has been printed out and placed at the Yiwanshui
neighborhood committee office for public access of the EA documents.
9.1.3 Questionnaires
The employer has distributed "public participation investigation sheet" to surrounding
residents and Saide International School from December 20, 2012 to 25 , to seek
public opinion. Total 150 questionnaires were distributed ,147 valid questionnaires
were collected back, accounting for 98% of the total number of questionnaires. Of
which there are 140 people in favour of the project construction, 7 people think it does
not matter.
34
9.1.4 Public Meetings
To improve the public participation and opinion feedback, a public meeting attended
by PIU, local affected people and key stakeholder including Saide International
School and Yiwanshui Neighborhood Committee was held to discuss the main
environmental issues of public concern in the NC meeting room on December 12,
2012 . The agreements reached is recorded in a meeting summary given in Annex 11.
During the meeting, it was agreed that the construction of Wanzhou Maternal and
Child Hospital will further improve the regional health service quality, solve the
problem of “inaccessible of hospital” and “high cost of medical treatment”. It can also
improve the health service demand in the region. The participants have expressed
their support for the construction of the project. At the same time, the Hospital is
requested to pay great attention to prevention of noise during construction and make
sure the residents’ life are not disturbed by the construction.
9.2 Information Disclosure
9.2.1 Preparation Stage
In parallel with public participation, the information was disclosed by the hospital to
the public on the project progress and to seek public opinions.
From Nov 19 to Nov 30 2012, executive summary of EIA was placed at resident
committee of Yiwanshui community for easy access of project information, work
procedure and content for environment impact assessment.
From Dec 5 to Dec 18 2012, EIA (opinions acquiring version) was placed at resident
committee of Yiwanshui community for publicizing the environment impact might be
occurred during project construction, proposed mitigation measure, and preliminary
conclusion drawn from EIA.
9.2.2 Information Disclosure for 2nd Round
From Dec 22 to Dec 31 2014, the revised executive summary with comments from
Consultants incorporated and concerns from the public included was placed at
resident committee of Yiwanshui community, for purpose of publicizing the proposed
mitigation measures and optimal option.
9.3 Public Participation and Opinions Feedback
In the period of notice posting and online publicity, no opinion proposed by residents
in project site.
(1) Questionnaire
35
Questionnaires are issued to the public for receiving opinions in an effective way.
Among the respondents, 107 people suggest enhancing pollution treatment, 97 people
recommend having the project layout reasonable, and 18 people think the greening
needs be strengthened.
Responding to the concern of “enhancing pollution treatment”, EIA gives justification
on “ the Three Wastes—industrial wastewater, waste gases and residues”generated in
construction and operation periods, as well as other environmental issues; and
corresponding measures are proposed also. See details in chapter 7, 6, 9, 10, 11 and
12.
As for the concern of “rationalization of project layout”, the opinions received were
sent to EIA preparation unit and project layout was improved. EIA gives rational
analysis in chapter 13.
For the concern of “greening issue”, the greening area in the project is 13507.98m2,
with greening rate of 39.24%, which meets the requirement of relevant laws and
regulations.
(2) Seminar
In the afternoon of Dec 12, 2012, the employer convened the seminar at conference
room in resident committee of Yiwanshui community, with participants from local
residents, Saide International School, resident committee and the masses. It’s agreed
the prevention and control of noise shall be strengthened during construction and
assuring no disturbance occurs to residents.
As for noise control in construction stage, EIA presents environment impact from
construction noise in detail, proposes corresponding mitigation measure to minimize
the negative impact and make sure no disturbance occurs residents. See details in
chapter 7.
9.4 Conclusion of Public Participation
The survey results show that 100% of respondents think the project site selection is
reasonable, 95% agree with the construction of the project, no objection is received.
Thus it can be seen that residents support the construction of the project. The Hospital
is requested to: strengthen environment management, strictly carry out pollution
control and mitigation measures specified in the EA report during construction period,
listen to the opinions and suggestions of residents and do what the Hospital can for
local residents to solve medical problems, and strive to create a harmonious social
environment. Environmental protection administrative department shall strictly
supervise the project construction; protect the public health and the environment.
36
Hope that the contractor input more investment in environmental protection, carry out
the various environmental protection measures, meet the requirement of pollutant
discharging standard, and protect the environment and the public interest.