73
Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-48320 IDA-50020 IDA-H3390 IDA-H6290) ON A CREDIT IN THE AMOUNT OF SDR 65.9 MILLION (US$ 96.3 MILLION EQUIVALENT) AND GRANT IN THE AMOUNT OF SDR 44.8 MILLION (US$69.4 MILLION EQUIVALENT) TO THE GOVERNMENT OF NEPAL FOR A ROAD SECTOR DEVELOPMENT PROJECT December 22, 2016 Transport and ICT Global Practice Nepal Country Unit South Asia Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

Document of

The World Bank

Report No: ICR00003916

IMPLEMENTATION COMPLETION AND RESULTS REPORT

(IDA-48320 IDA-50020 IDA-H3390 IDA-H6290)

ON A

CREDIT

IN THE AMOUNT OF SDR 65.9 MILLION

(US$ 96.3 MILLION EQUIVALENT)

AND

GRANT

IN THE AMOUNT OF SDR 44.8 MILLION

(US$69.4 MILLION EQUIVALENT)

TO THE

GOVERNMENT OF NEPAL

FOR A

ROAD SECTOR DEVELOPMENT PROJECT

December 22, 2016

Transport and ICT Global Practice

Nepal Country Unit

South Asia Region

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

i

CURRENCY EQUIVALENTS

(Exchange Rate Effective October 24, 2016)

Currency Unit = Nepalese Rupee

US$ 1.0 = NPR 107

US$ 0.009346 = NPR 1.0

FISCAL YEAR

July 16 – July 15

ABBREVIATIONS AND ACRONYMS AADT Annual Average Daily Traffic MIS Management Information Systems

ADB Asian Development Bank MOF Ministry of Finance

AF Additional Financing MOPIT Ministry of Physical Infrastructure and

Transport

CMS Content Management System MPPW Ministry of Physical Planning and Works

CPA Comprehensive Peace Accord MTR Mid Term Review

CPI Consumer Price Index NPR Nepali Rupee

CPN-M Communist Part of Nepal – Maoists NPV Net Percent Value

DFID Department for International Development PAD Project Appraisal Document

DOR Department of Roads PAF Project Affected Families

EIRR Economic Internal Rate of Return PCU Program Coordination Unit

EMAP Environmental Monitoring and Assessment

Program

PDO Project Development Objective

EoP End of Project PIP Priority Investment Plan

ESMF Environmental and Social Management

Framework

RAIDP Rural Access Improvement

Decentralization Program

FMIS Financial Management Information System RAP Resettlement Action Plan

GESU Geo-environmental and Social Unit RBN Roads Board Nepal

GDP Gross Domestic Product RMDP Road Maintenance Development Project

GRM Grievance Redress Mechanism RSDP Road Sector Development Project

GoN Government of Nepal SDR Special Drawing Rights

HR Human Resources SFC Standard Conversion Factors

HRD Human Resources Development SRN Strategic Road Network

ICT Information and Communications

Technology

SWAP Sector Wide Approach

ICR Implementation Completion and Results

Report

UN United Nations

IDA International Development Association USD United States Dollar

ISN Interim Strategy Note VOC Vehicle Operating Cost

ISR Implementation Status Report VoT Time Saving Benefits

IT Information Technology WAN Wide Area Network

JICA Japanese International Cooperation Agency WP With Project

M&E Monitoring and Evaluation XDR Special Drawing Rights

Senior Global Practice Director: Jose Luis Irigoyen

Country Director:

Country Manager:

Practice Manager:

Qimiao Fan

Takuya Kamata

Karla Gonzalez Carvajal

Project Team Leader: A.K. Farhad Ahmed

ICR Team Leader: Justin Runji / Sri Kumar Tadimalla

Page 3: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

ii

NEPAL

Road Sector Development Project (RSDP)

CONTENTS

Data Sheet

A. Basic Information

B. Key Dates

C. Ratings Summary

D. Sector and Theme Codes

E. Bank Staff

F. Results Framework Analysis

G. Ratings of Project Performance in ISRs

H. Restructuring

I. Disbursement Graph

1. Project Context, Development Objectives and Design ........................................................... 1

2. Key Factors Affecting Implementation and Outcomes ........................................................... 8

3. Assessment of Outcomes ...................................................................................................... 15

4. Assessment of Risk to Development Outcome ..................................................................... 22

5. Assessment of Bank and Borrower Performance .................................................................. 23

6. Lessons Learned .................................................................................................................... 25

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ....................... 27

Annex 1. Project Costs and Financing by Component.............................................................. 29

Annex 2. Outcomes and Outputs by Component ...................................................................... 31

Annex 3. Economic and Financial Analysis ............................................................................. 36

Annex 4. Bank Lending and Implementation Support/Supervision Processes ......................... 42

Annex 5. Beneficiary Survey Results ....................................................................................... 44

Annex 6. Stakeholder Workshop Report and Results ............................................................... 45

Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ................................. 46

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ................................... 51

Annex 9. List of Supporting Documents ................................................................................... 52

Annex 10. Notes on Accessibility, Time Savings, and Employment Impacts of the Project ... 53

MAP .......................................................................................................................................... 56

Page 4: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

iii

Data Sheet

A. Basic Information

Country: Nepal Project Name: Road Sector

Development Project

Project ID: P095977 L/C/TF Number(s):

IDA-48320, IDA-

50020, IDA-58650,

IDA-H3390, IDA-

H6290

ICR Date: 10/21/2016 ICR Type: Core ICR

Lending Instrument: SIL Borrower: GOVERNMENT OF

NEPAL, MOF

Original Total

Commitment: XDR 27.80M Disbursed Amount: XDR 64.71M

Revised Amount: XDR 110.73M

Environmental Category: B

Implementing Agencies:

Department of Roads

Cofinanciers and Other External Partners:

B. Key Dates

Process Date Process Original Date Revised / Actual

Date(s)

Concept Review: 03/19/2007 Effectiveness: 02/21/2008 02/21/2008

Appraisal: 09/10/2007 Restructuring(s):

09/06/2010

06/30/2011

06/27/2012

01/21/2015

06/18/2015

02/03/2016

06/15/2016

Approval: 12/06/2007 Mid-term Review: 08/30/2010

Closing: 06/30/2012 07/15/2019

C. Ratings Summary

C.1 Performance Rating by ICR

Outcomes: Moderately Satisfactory

Risk to Development Outcome: Significant

Bank Performance: Moderately Satisfactory

Borrower Performance: Moderately Satisfactory

Page 5: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

iv

C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

Bank Ratings Borrower Ratings

Quality at Entry: Moderately Satisfactory Government: Moderately Satisfactory

Quality of Supervision: Moderately Satisfactory Implementing

Agency/Agencies: Moderately Satisfactory

Overall Bank

Performance: Moderately Satisfactory

Overall Borrower

Performance: Moderately Satisfactory

C.3 Quality at Entry and Implementation Performance Indicators

Implementation

Performance Indicators

QAG Assessments

(if any) Rating

Potential Problem

Project at any time

(Yes/No):

Yes Quality at Entry

(QEA): None

Problem Project at any

time (Yes/No): Yes

Quality of

Supervision (QSA): None

DO rating before

Closing/Inactive status:

Moderately

Satisfactory

D. Sector and Theme Codes

Original Actual

Sector Code (as % of total Bank financing)

Central government administration 10 10

Rural and Inter-Urban Roads and Highways 90 90

Theme Code (as % of total Bank financing)

Infrastructure services for private sector development 67 67

Rural services and infrastructure 33 33

E. Bank Staff

Positions At ICR At Approval

Vice President: Annette Dixon Praful C. Patel

Country Director: Qimiao Fan Susan G. Goldmark

Practice

Manager/Manager: Karla Gonzalez Carvajal Guang Zhe Chen

Project Team Leader: A.K. Farhad Ahmed Marianne Kilpatrick

ICR Team Leader: Justin Runji / Sri Kumar Tadimalla --

ICR Primary Author: Paul J. Kaiser --

Page 6: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

v

F. Results Framework Analysis

Project Development Objectives (from Project Appraisal Document)

The PDO is for the residents of beneficiary districts to have all-season road access

thereby reducing travel time. This will help improve access to economic centers and

social services. The project targets five hill districts which currently lack all-season road

access and will improve access to one other district. The achievement of the project will

be monitored by the following outcome indicators:

i. 6 percent increase in the number of people with all-season road access in the project

districts (20 minutes walking or 2 km);

ii. 35 percent decrease in travel time for target population to reach key economic centers

and social services;

iii. DoR to provide effective road infrastructure services to users (measured through user

satisfaction survey);

iv. Roads Board is fully functional and provides effective and sustainable funding for

road maintenance (undertaking at least 500 kms of periodic maintenance of the SRN

annually and over 1,000 km of backlog periodic maintenance within the project period).

Revised Project Development Objectives (as approved by original approving authority)

The PDO was not revised. However, for better reporting on the PDO, some indicators

and targets were revised. Other indicators were added to reflect the scaling up of the

operation. A summary of the changes made to the indicators and targets at the time of the

first Additional Financing (AF) is provided in Table 1 of the main text.

(a) PDO Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Percent increase in population in project districts with all season road

access within 20 minutes walking distance (Original).

Value

quantitative or

Qualitative)

8% 14% - 15%

Date achieved 06/25/2007 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target of 14% was achieved and marginally exceeded by 7%.

The original target was not revised and there is evidence that at the time of

the main restructuring in Sep. 2010, this indicator had progressed

satisfactorily.

Source: SRDP Accessibility Study Report of Sep. 2014, based on a GIS

analysis

Indicator 2 : Percent decrease in journey times in the project area (Original).

Page 7: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

vi

Value

quantitative or

Qualitative)

n/a 35% -- 53%

Date achieved 06/25/2007 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target, which also remained unchanged, was exceeded

significantly – by 51%. The report makes reference to markets and district

headquarters as economic centers, whereas social services centers include

schools, colleges, and hospitals. Although the original target was not

revised, there is evidence that at the time of the main restructuring in Sep.

2010, this indicator had progressed satisfactorily well. Refer to more

details on journey times in Annex 10

Source: GoN 2016 Impact Study on Project Roads1.

Indicator 3 : Decrease in journey times in the project area to key economic centers.

Value

quantitative or

Qualitative)

4 hours -- 2.6 hours 1.9 hours

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

Target was exceeded by 56%. As against the original target of 35%

decrease, journey time to key economic centers decreased by 53%, to

below half of the baseline of 4 hours. Refer to more details in Annex 10

Source: GoN 2016 Impact Study on Project Roads.

Indicator 4 : Decrease in journey times in the project area to key social service centers.

Value

quantitative or

Qualitative)

4 hours -- 3 hours 1.2 hours

Date achieved 06/25/2007 1/21/2015 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

Target was substantially exceeded, by 60%. As against the original target

of 25% decrease, journey time to social service centers decreased to below

one-third of the baseline duration of 4 hours. Refer to more details in

Annex 10 Source: GoN 2016 Impact Study on Project Roads.

Indicator 5 : Direct project beneficiaries within 4 hours walking distance.

Value

quantitative or

Qualitative)

200,000 -- 800,000 752,000

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was underachieved, falling short marginally, by 6%. This

indicator was added during the first AF. The underachievement can be

explained by the slightly fewer-than-planned length of roads upgraded or

rehabilitated. The reason for the slightly fewer roads appears justified as

mentioned in the comment on Intermediate Indicator 4 below.

1 Summary of the document is filed

Page 8: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

vii

Source: ISR of June 2, 2016 and GoN study based on GIS analysis.

Indicator 6 : Female beneficiaries

Value

quantitative or

Qualitative)

0 -- -- 53%

Date achieved 06/30/2016

Comments

(incl. %

achievement)

This indicator captures the disaggregation of data from PDO Indicator 5

above. It is based on the 2011 Population Census which reports the female

proportion in the project area as 53%.

Source: ISR of June 2, 2016 and GoN study based on GIS analysis

Indicator 7 : Employment generated

Value

quantitative or

Qualitative)

0 -- 2.5 million

person days

6.68 million

person days

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

Target was substantially exceeded by 170%. Employment as an indicator

was introduced during the AF. Against the target of 2.5 million person-

days, the project generated employment of 6.68 million person-days. This

employment refers to direct engagement of people on road sites by

contractors during the life of the project. The relevance or importance of

this indicator is not elaborated in the project paper. Additional details are

provided in Annex 10

Source: ISRs with inputs from GoN based on Contractors’ Reports.

Indicator 8 : Employment generated - male

Value

quantitative or

Qualitative)

0 -- -- 6,017,663

Date achieved 06/25/2007 06/30/2016

Comments

(incl. %

achievement)

This indicator primarily reports disaggregated information on employment

(Indicator 7 above). Additional details are provided in Annex 10

Source: ISRs with inputs from GoN based on Contractors’ Reports.

Indicator 9 : Employment generated - Female

Value

quantitative or

Qualitative)

0 -- -- 663,211 person

days

Date achieved 06/25/2007 06/30/2016

Comments

(incl. %

achievement)

This indicator primarily reports disaggregated information on employment

(Indicator 7 above). Additional details are provided in Annex 10

Source: ISRs with inputs from GoN based on Contractors’ Reports.

Indicator 10 : Employment generated - Dalit

Value

quantitative or

Qualitative)

0 -- -- 280,907 person

days

Date achieved 06/25/2007 06/30/2016

Page 9: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

viii

Comments

(incl. %

achievement)

This indicator primarily reports disaggregated information on employment

(Indicator 7 above). Additional details are provided in Annex 10

Source: ISRs with inputs from GoN based on Contractors’ Reports.

Indicator 11 : Employment created - Janajatis

Value

quantitative or

Qualitative)

0 -- -- 3.28 million

person days

Date achieved 06/25/2007 06/30/2016

Comments

(incl. %

achievement)

This indicator primarily reports disaggregated information on employment

(Indicator 7 above). Additional details are provided in Annex 10

Source: ISRs with inputs from GoN based on Contractors’ Reports.

Indicator 12 : Reduced percentage of blacktop Strategic Road Network (SRN) in poor

condition to 15% (Original).

Value

quantitative or

Qualitative)

18% 10% 15% 11.27%

Date achieved 06/25/2007 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target was underachieved by 12.7% but the revised target of

15% was overachieved by 25%. The revision of the original target at

restructuring (in effect downwards) was therefore based on realistic

projections.

Source: ISR of June 2, 2016

(b) Intermediate Outcome Indicator(s)

Indicator Baseline Value

Original Target

Values (from

approval

documents)

Formally

Revised

Target

Values

Actual Value

Achieved at

Completion or

Target Years

Indicator 1 : Roads Board Act amended and more training and logistics provided

(Original).

Value

(quantitative

or Qualitative)

RBN Act amendment

bill in the Parliament

RBN Act

amended and

more training

and logistics

provided;

Human resource

development

(HRD) plan.

Draft

amendment

to RBN Act

finalized and

submitted to

Parliament

for

consideration

The draft RBN

Act has been

submitted to

Parliament and is

under discussion.

Training

completed.

Date achieved 06/25/2007 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target was partly achieved with regard to the training aspect

while the revised (downgraded) target was fully achieved. The draft Act is

still in Parliament. The restructuring of January 25, 2015 was a proactive

and commendable realization that the original target was overambitious.

Indicator 2 : Government decision to benchmark RBN staff salaries to market rates.

Page 10: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

ix

Value

(quantitative

or Qualitative)

-- --

Government

decision to

benchmark

RBN staff

salaries to

market rates

RBN Staff

salaries are paid

on a competitive

basis

Date achieved 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The indicator and target (introduced in the AF) were partially met. While

RBN Staff salaries are reportedly being made comparable to other

autonomous bodies, it is not clear how they compare with market rates.

Also, the indicator was introduced disregarding attribution difficulties.

Indicator 3 : Human Resources Development Plan (Original).

Value

(quantitative

or Qualitative)

--

Human resource

development

(HRD) plan

RBN’s 5 year

business plan

(2012-2017)

incorporates

Human

Resource

Development

(HRD) Plan

RBN has prepared

5-year business

plan (2012-2017)

and submitted to

the Board. Board

is reviewing the

plan

Date achieved 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target on the HRD plan was fully achieved. In addition, the

revised broader target, with a 5-year plan was also achieved.

Indicator 4 : Roads rehabilitated non-rural (km)

Value

(quantitative

or Qualitative)

297 705 680

Date achieved 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target of 297 km was achieved and exceeded by nearly

130%, the revised target of 705 km was slightly underachieved by 4%.

The marginal underachievement was due to justifiable omission of road

sections with peculiar technical challenges. Specifically the road sections

had unstable slopes and would have required more resources to construct,

thus reducing the achievable road length with the same amount of funding

even further. These omitted sections have commendably been included as

part of Second AF. Source: ISR of June 2, 2016 and Aide memoirs

Indicator 5 : Share of rural population with access to an all-season road

Value

(quantitative

or Qualitative)

7.6%

--

14%

15%

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was marginally overachieved, by 7%. This indicator is an

amplification of PDO Indicator 1 and was not appropriate as an

Intermediate Outcome Indicator

Page 11: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

x

Indicator 6 : Number of rural people with access to an all-season road

Value

(quantitative

or Qualitative)

71,500 -- 131,000 328,144

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was exceeded by 150%.

Source: ISR of June 2, 2016; SRDP’s Accessibility Paper of Sep. 2014

Indicator 7 : Roads in good and fair condition as a share of total classified roads

Value

(quantitative

or Qualitative)

82% 90% 85% 88.7%

Date achieved 06/25/2007 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

While the original target of 90% was marginally underachieved by 1%,

the revised target of 85% was marginally overachieved by 4% to 88.7%.

The downsized target commendably reflected the realization that the

original target was overambitious.

Indicator 8 : Size of total classified roads

Value

(quantitative

or Qualitative)

9,399 -- -- 10,835

Date achieved 06/25/2007 06/30/2016

Comments

(incl. %

achievement)

This indicator is supplemental to Indicator 7 above. It is also needed for

assessing the relative significance of other indicators (e.g., share of poor

roads). It was not to be affected by the project. As such it did not have any

pre-specified targets.

Indicator 9 : 700 km target roads received upgrading works (Original).

Value

(quantitative

or Qualitative)

0 297 705 680

Date achieved 06/25/2007 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

This indicator is similar to Indicator 4 above. It should have been deleted

Indicator 10 : 2,550 km of highways received periodic maintenance (Original).

Value

(quantitative

or Qualitative)

0

450

2,550 2,595

Date achieved 06/25/2007 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target ws overachieved significantly, by 477%. The revised

target was also overachieved, albeit marginally by 2%. A total of 2,595

km road length (Out of which 450 km was funded from original

financing; 1,728km from AF and 417km by GoN) had been completed as

of end-June, 2015.

Page 12: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

xi

Source: Aide Memoires and ISRs.

Indicator 11 : Road safety action plan and physical works (Original).

Value

(quantitative

or Qualitative)

No plan

--

Road Safety

Action Plan

implemented

and physical

works carried

out.

Road safety

action plan

developed and

approved and

physical works

carried out.

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was achieved. Road safety action plan was developed and

approved, and is under implementation. All the physical works executed

through 9 contracts have been completed.

Indicator 12 : Periodic maintenance of targeted highways and feeder roads backlog

executed (Original).

Value

(quantitative

or Qualitative)

0 1,000 1,000 1,692

Date achieved 06/25/2007 11/30/2010 1/21/2015 06/30/2016

Comments

(incl. %

achievement)

The data is not well supported. Actual GoN funding dropped from

US$58.5 million as planned to US$24.5 million. It is therefore unclear

how the target would have been exceeded. Besides, the indicator seems to

partly measure outputs related to Indicator 10 above. Indeed government

did finance several periodic maintenance contracts (dubbed Year 1, Year

2, Year 3 etc.) but the monitoring thereof was not well documented. Based

on the annual work reports, a total of 690 km appear to have received

periodic maintenance: Year 1- 182 km; Year 2 and 3 - 268 km; and Year 4

– 244 km.

Indicator 13 : Capacity building in geotechnical, environmental and social aspects, and

awareness creation on HIV /AIDS

Value

(quantitative

or Qualitative)

0

--

Capacity

building in

geotechnical,

environmenta

l and social

aspects, and

awareness

creation on

HIV /AIDS

and planned

activities

carried out

a) Geotechnical

assessments

carried out

b) Site specific

EMAP and RAP

monitoring

being done

periodically

c) Creating

awareness among

project

construction

workers and road

users on

HIV/AIDS is

ongoing

Page 13: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

xii

Date achieved 06/25/2007 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was fully achieved. All the listed sub-activities have been

completed.

Indicator 14 : DoR IT based Management Information Systems (MIS) operational

Value

(quantitative

or Qualitative)

WAN installed in DoR

offices in Kathmandu

Additional IT

inputs to enhance

IT based

management

system in DoR.

Web based

system

adopted for

FMIS, GRM,

CMS

Web based

system being

adopted for FMIS

GRM and CMS

Date achieved 11/30/2010 11/30/2010 01/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target (which was rather broad) was not achieved but the

revised narrower, and more specific target was achieved. The

implementation team also paid due attention to the emerging

technological changes and adopted appropriate changes to the strategy.

Indicator 15 :

Road asset management tools used for prioritization of road maintenance

and upgrading works

Value

(quantitative

or Qualitative)

-

HDM4 used for

bi annual road

condition asset

and preparation

of annual

maintenance plan

Annual

maintenance

plan prepared

using

objective

methods;

Road

inventory

prepared for

a portion of

the network

and data

model

developed in

order to roll

out the

methods to

the whole

network

Objective method

has been used in

the preparation of

the annual road

maintenance plan.

Design of a road

inventory

software and the

collection of basic

road inventory

data along a

selected road

corridor was

completed.

Date achieved 11/30/2010 01/21/2015 06/30/2016

Comments

(incl. %

achievement)

The original target to use HDM4 was too ambitious and was also not

achieved. The revised target, which aimed at more objective methods, was

achieved albeit partly. The extent to which road inventory for a portion of

the network was prepared, as part of the target, could not be ascertained.

Indicator 16 : Improved quality assurance

Value

(quantitative

-

--

Quarterly

monitoring

Central Road Lab

has been carrying

Page 14: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

xiii

or Qualitative) plan prepared

each year and

quality audit

carried out

by Central

Road Lab

out internal

quality road

audits of the

selected roads.

Quality assurance

has been

monitored

Date achieved 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was achieved. The Central Road Lab is reportedly carrying out

quality audits and monitoring quality assurance. The scope and

periodicity of such activities, however, is not clear.

Indicator 17 : Third party technical audit

Value

(quantitative

or Qualitative)

-

Third party

technical

audit carried

out for 20%

of the project

works each

year

Third party

technical audit of

upgrading and

periodic

maintenance

works under

RSDP has been

carried out on

selected contracts

Date achieved 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was achieved. Third party technical audit of upgrading and

periodic maintenance works under RSDP has been carried out on 20% of

the project works.

Indicator 18 : Improve staff capacity within DoR

Value

(quantitative

or Qualitative)

-

--

HR policy

updated and

3-year

training plan

finalized

HR policy

updated and 3-

year training plan

finalized.

Domestic and

international

training provided

for DoR staff as

per policy and

plan

Date achieved 11/30/2010 06/30/2016

Comments

(incl. %

achievement)

The target was achieved. HR policy updated and 3-year training plan

finalized. Domestic and international training provided for DoR staff as

per policy and plan.

Page 15: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

xiv

G. Ratings of Project Performance in ISRs

No. Date ISR

Archived DO IP

Actual

Disbursements

(USD millions)

1 06/03/2008 Satisfactory Satisfactory 3.00

2 12/31/2008 Satisfactory Satisfactory 11.46

3 05/27/2009 Satisfactory Satisfactory 21.45

4 08/04/2009 Satisfactory Satisfactory 21.45

5 02/08/2010 Satisfactory Satisfactory 21.45

6 12/12/2010 Satisfactory Satisfactory 32.25

7 07/13/2011 Satisfactory Satisfactory 53.32

8 01/25/2012 Moderately Satisfactory Moderately Satisfactory 53.32

9 10/17/2012 Moderately Satisfactory Satisfactory 71.94

10 06/01/2013 Moderately Satisfactory Moderately

Unsatisfactory 71.94

11 12/07/2013 Moderately Satisfactory Moderately

Unsatisfactory 89.32

12 05/18/2014 Moderately Satisfactory Moderately Satisfactory 89.32

13 12/19/2014 Moderately Satisfactory Moderately Satisfactory 98.01

14 05/14/2015 Moderately Satisfactory Moderately Satisfactory 98.01

15 11/10/2015 Moderately Satisfactory Moderately Satisfactory 98.46

16 06/02/2016 Moderately Satisfactory Satisfactory 98.23

H. Restructuring (if any)

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring &

Key Changes Made DO IP

09/06/2010 S S 30.06

Extension of closing date

to December 31, 2013

Approval of first AF

Revision of Results

Monitoring Framework

06/30/2011 S S 53.32

Cancellation and

recommitment of

undisbursed grant amount of

SDR 17.5 million

(US$ 27.5 million) under

the AF

Page 16: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

xv

Restructuring

Date(s)

Board

Approved

PDO Change

ISR Ratings at

Restructuring

Amount

Disbursed at

Restructuring

in USD

millions

Reason for Restructuring &

Key Changes Made DO IP

06/27/2012 MS MS 71.94

Extension for 18 months

mainly to utilize about US$7

million balance.

01/21/2015 MS MS 98.01

Marginal reallocation of

funds across categories;

Cancellation of savings

of about US$ 7million due

to NPR depreciation; and

Revision of targets for a

few intermediate result

indicators.

06/18/2015 MS MS 98.01

Extension of closing date

from June 30, 2015 to June

30, 2016 due to the

earthquake of April 2015

02/03/2016 MS S 98.46

Reallocation of funds

between components and

sub-components with more

funding for institutional

strengthening

06/15/2016 MS S 99.10

Second AF

Extension of closing date

of the project to June 30,

2017.

I. Disbursement Profile

Page 17: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

xvi

Page 18: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

1

1. Project Context, Development Objectives and Design

1.1 Context at Appraisal

Country Background

1. At the time of appraisal in 2007, Nepal was the poorest country in South Asia with

an average per capita Gross Domestic Product (GDP) of US$270 (2005) and also slowest

growing economy, with growth rates of around two percent, compared to the regional

average of eight percent. Recovering from a ten year insurgency, the government

prioritized increased access to basic public services for those impacted by and residing in

these security-affected areas. The project thus was prepared at a time of significant political

fluidity and unpredictability.

Sector Background

2. Severe slowdown in capacity expansion: In the 1990s, the road network in Nepal

expanded by about seven percent a year, mainly due to concerted efforts of donors and

government to fund rehabilitation works, with the objective of overcoming the effects of

inadequate and irregular maintenance exacerbated by the insurgency. This expansion

however significantly slowed down thereafter to less than one percent a year from 2001 to

the time of appraisal. Insecurity adversely impacted Government of Nepal’s (GoN) ability

to undertake road works but also created resource constraints (the allocation of resources

to the road sector declined from about ten percent of total GoN budget in the 1990s to five

percent in 2001). As a result, 55 percent of Nepal’s total road stock of 33,280 km still

remained as dry-season fair-weather-tracks.

3. Lack or inadequate access to all-season roads: Even within the Strategic Road

Network (SRN) – that is, 7,535 km out of the 17,280 km of the main road network

comprising highways and feeder roads connecting districts – the proportion of roads in

good and fair condition, which increased from less than 50 percent in 1992 to 90 percent

in 2001, declined to 82 percent in 2006. At the time of appraisal, 12 of the 75 administrative

districts in Nepal were not yet connected by road and another fourteen were linked with

seasonal tracks or dirt roads. Residents of Nepal’s hill districts, excluding the Kathmandu

Valley, walked an average five hours to reach an all-season road, and residents of the

mountain districts walked over fifteen hours. Access to all-season roads was identified as

a critical measure of development potential in Nepal, especially because monsoon rains

made - and continue to make - earthen roads impassable for many months at a time.

4. Inadequate funds for periodic maintenance: Toward the end of the insurgency, as

the donor programs shifted towards new construction and rural access infrastructure, GoN

established a Roads Board with the goal of linking road sector funding to road use and

improving the level of domestic funding for road maintenance. The Roads Board of Nepal

(RBN) was instrumental in generating partial maintenance resources through road user

charges, allocating timely resources to road agencies based on priority annual maintenance

Page 19: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

2

plans, and monitoring effectiveness of maintenance works carried out by the road agencies.

Even so, at the time of appraisal, funding for maintenance remained at about half of the

requirement estimated at NRs. 2 billion per year (US$30,000,000), and the issue of backlog

for periodic maintenance continues to remain a challenge.

Rationale for Bank Assistance

5. The Bank had established strong working relationships with the GoN and donor

stakeholders in the transport sector in the years leading up to the appraisal. The successful

implementation of the World Bank-funded Road Maintenance and Development Project

(RMDP IDA Credit 3293 - NEP), which closed on June 30, 2007, supported the GoN’s

Priority Investment Plan (PIP-1997) for the transport sector and updating of the same for

2007-2016. The updated PIP highlighted the importance of improving accessibility to the

SRN, by specifically bringing the population within two hours walk in the Terai and four

hours walk in the hill districts,2 to an all-season road. It identified SRN roads for investment

on the basis of their social and economic benefits and was essentially a road master plan

that formed a basis for the selection of road projects for the 11th and 12th national plans.

The Road Sector Development Project (RSDP, P095977) directly responded to this priority.

1.2 Original Project Development Objectives (PDO) and Key Indicators

6. The original Project Development Objective was for the residents of beneficiary

districts to have all-season road access thereby reducing travel time. This, in turn, was

envisaged to improve access to economic centers and social services. The project targeted

five hill districts (Darchula, Baitadi, Dailekh Surkhet and Darchula) which lacked all-

season road access and one other district (Bajhang) for which linkage to the other districts

was critical. The achievement of the PDO was to be measured through the following key

outcome indicators:

i. 6 percent increase in the number of people with all-season road access in the

project districts (20 minutes walking or 2 km);

ii. 35 percent decrease in travel time to key economic centers and social services;

iii. DoR to provide effective road infrastructure services to users (measured

through user satisfaction survey)3;

iv. The Roads Board becoming fully functional and providing effective and

sustainable funding for road maintenance, as to be measured through (a)

undertaking at least 500 kms of periodic maintenance of SRN annually and over

2 The Terai is the southern plains that border India and the hill districts are to the north of the

Terai, just south of the Himalayan mountain range.

3 This indicator does not appear in the Results Framework and Monitoring. It was not directly

measured or reported on. It could however be argued that effective road infrastructure services

constituted road rehabilitation, maintenance and road safety interventions – all of which had

monitored targets

Page 20: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

3

1,000 kms of backlog periodic maintenance within the project period; and (b)

reduction in percentage of black top SRN in poor condition to about 10 percent.

1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and

Reasons/Justification

7. Since its inception, the project was restructured seven times, which included two

AF credits. Through these changes, the PDO remained the same. However, some PDO and

Intermediate level indicators were revised or added at the time of the first AF. The notable

changes to the indicators are detailed below:

Table1: Modifications to the Indicators

PDO and Intermediate Indicators Before and After Additional Financing

PDO Indicators

Original Project Changes at AF

6 percent increase in population with all

season access to economic centers and

social services (in five project districts)

Revised: 6 percent increase in population in

project districts to have all season road access

within 20 minutes walking distance (in eight

project districts)

35 percent decrease in journey times to key

economic centers in the project area

Retained: 35 percent decrease in journey

times to key economic centers in the project

area

Added: 25 percent decrease in journey times

to key social services in the project area

Reduce the percentage of black top SRN in

poor condition to about 10 percent

Revised: Reduce the percentage of black top

SRN in poor condition to 15 percent

Intermediate Outcome Indicators

Original Project prior to AF4 Changes at AF

100 percent of 297 km of target roads

received upgrading works

Added: An additional 408 km of target

roads received upgrading works

100 percent of 100 km of highways and

350 km of targeted roads received

periodic maintenance

At least 500 km of SRN receives

periodic maintenance works annually

and over 1000 km of backlog periodic

maintenance addressed during the

project period

Added: An additional 2100 km of strategic

roads received periodic maintenance

Revised: No backlog periodic

maintenance within the project period.

Publication of Road Safety Action Plan

and implementation of actions

Retained: Same as in original project

4 Some changes to the original six Intermediate Outcome Indicators took place at other Level 2

restructuring before the AF. The original six are those in bold

Page 21: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

4

HR policy updated and 3 year training

plan finalized. Domestic and

international training provided for DoR

staff as per policy and plan

Retained: Same as in original project

Completion of Geo-technical

assessments, EMAP and RAP

compliance monitoring and

performance in creating awareness

among project construction workers

and road users on HIV/AIDS

Added

Completion of pilot installation of

wide area network (WAN) in DoR

division offices in Kathmandu and

satisfactory operation and

maintenance of IT based management

system

Added: Additional IT inputs to enhance

IT based management system in DoR

including fully operational e-procurement

system

HDM4 used for bi annual road condition

assessment and preparation of annual

maintenance plan

Revised: Simple road asset management software

operationalized to use HDM4 for annual

road condition assessment and preparation of

annual maintenance plan

Quality monitoring plan prepared each year

and quality audit carried out by Central

Road Lab

Added

RBN Act amended and more training

and logistics provided Government

decision to benchmark salaries to

market rates

Retained: Same as in original project

Human resource development (HRD)

plan

Third party technical audit carried out for

20 percent of the project works each year Added

8. All the revisions to indicators and targets were essentially to: (i) reflect the scaling

up of the project scope (e.g., km of roads to upgraded, from 297 to 705); (ii) capture the

project’s impact in certain key areas (e.g., number of beneficiaries and employment

generated); and (iii) fine-tune monitoring data sets in line with the implementation

challenges and realities (e.g., moving IT systems from WAN-based to cloud-based

computing, avoiding HDM4 as an analytical option based on technical assessment of its

unsuitability for targeted network).

1.4 Main Beneficiaries

9. The main beneficiaries of the project included: (i) communities – in particular

women, and two historically disadvantaged groups, the Dalits, and Janajatis – living along

the roads upgraded and periodically maintained in the project districts; (ii) government

organizations and the staff involved in development and management of SRN – namely,

Page 22: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

5

the Ministry of Physical Infrastructure and Transport (MOPIT), Roads Board of Nepal

(RBN) and the Department of Roads (DoR). The latter had its capacity enhanced through

experience acquired in implementation of various civil works, institutional strengthening

and policy reform component covering several key areas5; and (iii) local contractors who

were accorded ample opportunity to bid and work on road upgrading, thus building the

experience and capacity of Nepal’s nascent construction industry.

1.5 Original and Revised Components

10. The project had two components throughout its life: Road Development; and

Institutional Strengthening and Policy Reform. The main focus of the original project was

to improve connectivity in six hill districts6 (Darchula, Baitadi, and Bajhang in the Far

Western Region and Kalikot, Dailekh, and Surkhet in the Mid Western Region), by

upgrading and rehabilitating selected roads. Other infrastructure related interventions were

countrywide periodic road maintenance program, and road safety. These three categories

of road related activities constituted the first component.

11. The institutional strengthening and policy reform focused on providing support to

DoR, RBN, and MOPPW, by building on support provided under the previous project –

the Road Maintenance and Development Project. The areas of support included general

skills development, enhancement of selected specialized competencies (e.g. in geo-

environmental and related safeguards, financial management, quality assurance, and

technical audits). The support also covered strategic and reform activities such as the

revision of RBN legislation.

12. The first AF in 2010 scaled up the two components by supporting: (i) additional

length of roads for upgrading and rehabilitation in the original six project districts and

introduction of similar works in two new districts (Jajarkot and Rukum in the Mid Western

Region); (ii) additional length of periodic road maintenance; and (iii) introduction of

additional institutional strengthening under the second component. The same components

were maintained in the Second AF approved on August 25, 2016.

Component 1: Road Development (US$ 149 million, IDA: US$93.5 million).

13. Sub-Component A: Road Upgrading (USUS$ 84.1 million, IDA Financing: 100%):

This sub-component originally aimed at improving connectivity to six districts - Darchula,

Baitadi, Kalikot, Bajhang Dailekh, and Surkhet through upgrading of about 297 km of

5 These included Human Resource Development (HRD); Geo-technical, Environment and Social

Development; IT and MIS Development; Road Asset Management; Road Safety; Effective Quality

Assurance; Mechanical Training; Technical Audit; Equipment and Logistics; and preparation of a

follow up project.

6 To be read with the original Project Development Objective Statement (par. 6), which lists five

plus one districts

Page 23: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

6

existing dry-season road-tracks that were selected from a pool of more than 1000 km of

prioritized roads, based on the feasibility studies under the 2007 Priority Investment Plan.

Specifically, these roads were to be upgraded to all-season standards with low cost sealed

gravel (Otta Seal) pavements, at an estimated cost of US$30.9 million.

14. As part of the first AF, the scope of this component was scaled up to include

upgrading of a further 227 km of roads within four of the original project districts in order

to provide connectivity to respective district headquarters and an additional 181 km to

improve all-weather connectivity in two new districts (Jajarkot and Rukum), at an

estimated cost of US$53.2 million. In effect the output of this subcomponent was scaled

up to nearly three times of the original plan, and the number of project districts rose to

eight.

15. Sub-Component B: Periodic Maintenance (US$ 63.7 million, IDA Financing:

US$8.7 million): This sub-component originally supported periodic maintenance of about

450 km of SRN prioritized in the 2007 PIP (from 5,300 km of black top surfaced highways

and feeder roads). Specifically, about 100 km of the two lane highways with high traffic

was targeted for premix asphalt overlay and 350 km of other single/two lane SRN was

targeted for surface seal coats, at an estimated cost of US$11.42 million, 30% of which

was to be supported through IDA financing.

16. As part of the AF, the scope of this component was expanded to support periodic

maintenance of an additional 2,100 km, based on maintenance priority established in the

PIP and annual road condition survey, at an estimated cost of US$47.5 million. To support

GoN’s efforts in coping with the damage caused by the 2009 monsoon floods, provisions

were made to finance emergency maintenance such as slope protection and pavement

works, at an estimated cost of US$4.75 million. In order to meet the costs of all the

maintenance works, the share of GoN financing was increased from 70% to 90%.

17. Sub-Component C: Road Safety (USUS$ 1.5 million, IDA Financing:US$0.7

million): This component was envisaged to support Road Safety Audit of SRN based on

accident prone sections, and physical works to improve the black spots identified through

the audit. Originally, an allocation of US$0.59 million was made with 100% IDA financing.

A further US$1 million was availed as part of the AF.

Component 2: Institutional Strengthening & Policy Reform (USUS$19.4 million, 100%

IDA Financing)

Page 24: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

7

18. This component was to provide support to DoR,7 RBN, and MoPIT8 to sustain and

deepen previous institutional and policy development activities started in RMDP as well

as support new ones identified by the GoN. Based on the proposed plan, the project

envisaged to provide assistance for (a) Human Resource Development (HRD); (b) Geo-

technical, Environment and Social Development; (c) IT and MIS Development; (d) Road

Asset Management; (e) Preparation of a Road Safety Action Plan; (f) Effective Quality

Assurance; (g) A Mechanical Training Centre; (h) Strengthening of Roads Board

operations; (i) Technical Audit; (j) Equipment and Logistics; and (k) Preparation of a

follow up project.

19. When the project was restructured to include the AF, support for DoR and RBN

under this component was to be continued and deepened, with particular focus on training,

expansion of IT based MIS/Financial Management Information System (FMIS) and road

asset management system, technical assistance and equipment, and undertaking three

studies covering Construction Industry, Bridges and improvement of the Thankot-

Mugling-Birgunj Corridor. Assistance was also to be provided for the National Vigilance

Centre for the technical audit of RSDP roads. In keeping with the scaled scope of the

component, the original allocation of US$6.57 million IDA financing was augmented with

an additional US$12.8 million.

1.6 Other significant changes

20. On June 30, 2011, an undisbursed amount of SDR 17.5 million (US$ 27.5 million)

under the AF Grant (No. H629-NP) was cancelled and the same amount of funds were

recommitted as new credit (No. 5002-NP). This constituted the second restructuring.

21. In addition to the AF and the cancellation of undisbursed amounts mentioned above,

the other five restructurings were as follows:

On June 27, 2012, the closing date of the original IDA Grant was extended by 18

months from June 30, 2012 to December 31, 2013;

On January 21, 2015 a marginal reallocation of funds across categories was

effected. In addition there was a cancellation of “savings” amounting to US$ 6.98

million due to depreciation of the Nepalese Rupee and a revision of targets for

some intermediate result indicators;

7 Within DoR, the Institutional Strengthening Component directly supported the following Units:

Mechanical Training Center, Mechanical Branch, Road and Traffic Unit, Central Road Laboratory,

Geo-Environmental and Social Development Unit, Road Sector Skill Development Unit, and the

Management and Information Systems Unit.

8 Ministry of Physical Infrastructure and Transport (earlier known as Ministry of Physical

Planning and Works, MoPPW).

Page 25: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

8

On June 18, 2015 the project closing date was extended to June 30, 2016. The

extension would enable GoN to cope with the disruptions and delays caused by

the devastating earthquake in April 2015, unofficial trade blockades at borders

with India, and also resolve technical challenge involving the design of arch

bridges on major highways;

On February 3, 2016 a reallocation of funds between components and sub-

components with more funding for institutional strengthening was effected; and

On June 15, 2016 the second AF of USUS$ 75 million was agreed to, together

with an extension of project closing date from June 30, 2016 to June 30, 2017.

2. Key Factors Affecting Implementation and Outcomes

2.1 Project Preparation, Design and Quality at Entry

22. Alignment with the Client Needs and Bank’s Strategy: Following the Road

Maintenance and Development Project (RMDP) that closed in 2007, the Bank prepared the

Road Sector Development Project (RSDP) on a “fast track” basis. The project design was

based on an appreciation of how the long period of insurgency had led to significant decline

in road funding, and how particular emphasis on maintenance in the previous years had

slowed down the capacity expansion. Accordingly, the project was pivoted on the objective

of improving all-season road access. This objective was in full alignment with Nepal’s

Poverty Reduction Strategy (PRD)/Tenth Plan (2002-07), which placed improving

transport access among the top priorities, and also the Bank’s Interim Strategy Note (ISN,

February 2007), which proposed that the emerging development agenda should focus on

public investment for the remote areas in order to increase inclusion.

23. Salient design features: The design placed emphasis on increased flow of funds

into the roads sector, and especially to districts with poor access to all-weather roads,

through the Road Development Component. The component singled out upgrading,

periodic maintenance, and road safety, each respectively accounting for 73%, 8% and 1%

of the IDA support to the project. The tracks/roads for upgrading and periodic maintenance

were selected: (a) based on the Priority Investment Plan (PIP, 2007-16), which was

prepared in alignment with the GoN’s goal of improving accessibility to the Strategic Road

Network (SRN); and (b) at locations and regions where the Bank had previously directed

its efforts. The project also sought to increase the flow of government’s own funds into the

periodic maintenance, by requiring GoN to share 70% of the corresponding costs, which

was further raised to 90% as part of the AF in 2011. The latter was intended to deepen the

institutionalization of road maintenance.

24. Institutional Strengthening: The project focused on ensuring implementation

capacity and future sustainability by providing support to key institutions in the road sector

and by deepening previous institutional and policy reforms. The design of this component

Page 26: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

9

however seems to have been ambitious in the range of activities it sought to support

(Human Resources, IT, Road Asset Management, Road Safety, Road Board, Equipment,

etc.) but lacking a coherent strategy or prioritization, say, in terms of why these activities

were important and how they were going to impact the capacity and efficiency of the target

organizations. Lack of such analysis seems even more conspicuous given that about 15%

of the IDA Grant amount was allocated for this component.

25. Use of lessons learned and effective assessment and mitigation of risks: Drawing

upon the lessons from RMDP, the project design recognized that: (a) PDO needed to be

realistic in light of several external factors beyond the control of GoN in general and

implementation agencies in particular; and (b) due diligence and improved supervision

from both the Client and the Bank to ensure better performance by contractors and

consultants was essential. In terms of risks, the design accurately identified most key risks

(Technical Design, Implementation Capacity & Sustainability and Conflict in Project

Areas are rated as “Substantial”) and proposed reasonable measures to mitigate them, for

instance, through increased monitoring, enhanced support & dialogue with the client, and

keeping the technical designs flexible.

2.2 Implementation

26. While it is appreciated that the project was implemented within a fragile post-

conflict environment, some of the necessary implementation underpinnings do not appear

to have been sufficiently robust. The project commenced its operation in 2008, in the early

years after Nepal emerged from a decade-long ‘people’s war’ that formally ended

following a ceasefire agreement in 2006. Since then, the project operated against a

checkered backdrop comprising instability with frequent strikes (or “bandh”) called by

different political and ethnic groups, two major earthquakes, floods and an unofficial trade

blockade at the Indian border. For instance, during the 30 months from project

commencement to the time of Mid-Term Review (MTR), there were three changes in

government, which affected staff continuity and GoN decision-making.

27. Despite this, the project made notable progress, especially with regard to the Road

Development Component. By the time of MTR in October 2010, physical progress stood

at 82% of the planned activities, with 230 km of road upgrading completed (against the

EoP target of 297 km) and periodic maintenance of 322 km ongoing (against the MTR

target of 125 km). Spurred by this progress, GoN and the Bank sought to continue the

momentum by agreeing to an AF in order to improve accessibility within four of the

original districts and in an additional two. The civil works envisaged under the original and

the first AF were mostly completed within one year after their scheduled completion dates.

Yet another noteworthy aspect of implementation was the introduction of e-bidding system

and the application of contractual remedies against poorly performing contractors. The

implementation of the Road Development Component during the AF progressed smoothly,

except for a few instances of poor- or non-performance by some contractors which were

effectively dealt with by DoR in consultation with the Bank team.

28. The implementation of the Institutional Strengthening & Policy Reform component,

however, was uneven. The project made reasonably smooth progress in areas such as

Page 27: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

10

Training, Geo-environmental and Social Studies, quality assurance and third-party

technical audits. It however lagged in the areas of road asset management, mainstreaming

of IT based systems and a technical study on bridges. The approach in dealing with the

shortcomings seems to have been progressive recalibration of the targets downwards

through various restructurings. The project made little headway in its aspirations for

strengthening the Road Board of Nepal (RBN), as the amendments to the RBN Act are still

under consideration and so is the target of benchmarking the salaries of RBN staff to market

rates. This is perhaps understandable given that the backdrop of political instability may

not have been conducive for expediting such major decisions. Even so, the overall progress

of various activities under this component suggest little proactive action to redefine the

strategy or goals for this strategically significant components with sizeable allocation

(about 15%) of the Bank support to the project. For these reason, the second aspect of the

project was a significant contributor to the final Moderately Satisfactory rating of the

project.

29. The reasons for the project performance are not well documented. It was however

understood that a combination of factors ranging from project design, capacity of

implementing agencies, Bank supervision, to country level circumstances affected the

delivery of the project. The design of the project had placed high emphasis on the

infrastructure component and this bias was reflected in the client’s project implementation

structures. The DoR, is a technical establishment that understood the various project

implementation aspects well. Technical designs and procurement of road construction and

supervision services were executed with relative ease. The decision to break contracts into

reasonably small sizes in order to attract local construction industry yielded dividends in

terms of competition and speed of execution of works. The Bank supervision team on its

part, recognized the project implementation challenges associated with post-conflict and

intensified supervision. In addition to regular consultations between the team and the client,

there were 17 formal missions over the eight year period (from June 2008 – September

2016). The team further supported the use of additional technical capacity through

engagement of individual consultants both on the client and on its side.

30. A few challenges affected the implementation of the roads component. Initially

only the DoR Regional offices were tasked with the overall project oversight function,

leaving out the DoR establishment in the District. This created operational tension between

the two layers and affected supervision and progress on the road sites. The arrangement

was however addressed by involving the Division Road offices. Other notable contributors

to low performance on the roads component were the disruptions and delays caused by the

devastating earthquake of April 2015, and unofficial trade blockades at borders with India.

31. Regarding the institutional capacity building component, the long list and diverse

assortment of activities to be supported, and the lack of a prior strategic assessment of the

key areas of support led to implementation difficulties. The project design appeared to have

been overambitious in terms of what was doable under the prevailing political environment.

The lack of amendment of the RBN Act was a good example of the policy level challenges.

In a way, this could have accounted for the inability to introduce more robust planning

Page 28: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

11

tools such as HDM4. An internal environment that would demand and appreciate more

strategic investment processes was missing.

2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

32. M&E Design: M&E has emerged as a notable aspect of project weakness especially

in its design and implementation and a specific contributor toward the overall Moderately

Satisfactory rating of the project. The choice of the primary PDO indicators, which in turn

influenced the design of the monitoring framework, was essentially focused but had

elements of over-ambition, and was also partly disconnected from the PDO. Two of the

key outcome indicators – namely, percentage increase in population in project district with

all-season road access within 20 minutes walking distance and percent decrease in journey

times to key economic centers, were well linked to the PDO. The third key indicator – DoR

to provide effective road infrastructure services to users, measured through user

satisfaction, was however neither directly measured nor reported on. The fourth indicator,

envisaging a fully functional Roads Board, was the only allusion to institutional

strengthening, which was not a stated PDO.

33. The number of indicators is considered high, and some could have been avoided.

While the original results framework comprised three PDO indicators and six Intermediate

Outcome indicators (Ref. Project Appraisal Document) the revised framework arising from

the AF and other restructuring increased the number of indicators significantly. According

to the list in Section F of the Data Sheet (Results Framework analysis) above, at the end of

the ICR review period, the project was monitoring twelve PDO level indicators and

eighteen Intermediate Outcome indicators. The choice of these indictors does not seem to

have strictly focused on the PDO. Employment creation for instance, was not an explicit

objective yet four PDO indicators are dedicated to it.

34. Many of the Intermediate Outcome indicators were relevant but further

rationalization is considered to have been necessary. Indicator 5 for instance – Share of

rural population with access to all-season roads, belongs to PDO level category. Indicator

7 - Roads in good and fair condition as a share of the total classified road, would also be

viewed as a measure of project impact on institutional aspects. Furthermore, monitoring

and reporting on the periodic maintenance backlog (Indicator 12) appears to have been

complicated by the apparent lack of clarity on the target boundaries since Indicator 10 also

measures performance on periodic maintenance. Indicators for institutional capacity

building were particularly many, and some needed clarity to facilitate monitoring.

Indicators 13 on “Capacity building in geotechnical, environmental and social aspects and

awareness creation in HIV/AIDS”, as an example, was too broad.

35. M&E Implementation & Utilization: Internal efforts by DoR to implement an

effective M&E system were adversely affected by public service processes outside their

control. The DoR developed an annual M&E work plan that was approved by the National

Planning Commission. Project monitoring was carried out at different levels of government,

depending on the activity (Ministry, Department, Project Implementing Unit, DoR

Branches, Units, Project Offices, and Divisions). Supervision consultants assigned to

manage road upgrading and maintenance contracts were also to collect some data. However

Page 29: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

12

a review of the data entry into the ISRs reveals lack of comprehensiveness and continuity

in the process. Except for the information found in the Aide Memoires, there is little

evidence of an organized data management system to enable regular updating of data for

each indicator. Not all indicators were reported on diligently and there were delays in

updating some data. As also stated in the Borrower’s completion report, this situation was

a manifestation of inadequacies in the DoR’s M&E system. But the aspect that aggravated

the situation was the high staff turnover. Frequent ministerial transfers of both junior and

senior staff out of the project and their replacement with new personnel, not conversant

with the M&E, introduced continuous weaknesses in the process.

36. It was reported that the National Vigilance Center, used the data collected as part

of the M&E to identify and carry out technical audits on civil works contracts. The data

was also used as a progress management tool, especially in making implementation

adjustments to some components. Other than this limited project-specific use of the M&E

outputs, there is no evidence that the project’s M&E framework or data itself would be of

used beyond the project life. 2.4 Safeguard and Fiduciary Compliance

37. There were no significant safeguard or fiduciary compliance issues that affected

project implementation. Compliance of social and environmental safeguards were

regularly monitored by DoR and Geo-Environmental and Social Development Unit

(GESU) and documented in project documents for response when needed. Environmental

and social safeguard experts were hired by GESU to ensure for proper monitoring and

reporting.

38. The following social safeguard issues were clearly documented in the Aide

Memoires, and brought to the attention of GoN from the early stages of implementation.

These issues were summarized in the MTR.

Delayed compensation payments to Project Affected Families (PAFs);

Limited knowledge of Environmental and Social Management Framework (ESMF)

social safeguard requirements among key project stakeholders;

Unclear understanding of child labor requirements;

Need to follow-up on land ownership to the DoR along select road upgrading sites

in close coordination with Land Revenue Offices; and

Coordination lapses between the Program Coordination Unit (PCU) and Geo-

environmental and Social Unit (GESU).

39. Good practices were noted, for example, where a simple Nepali language version

of the ESMF was prepared and posted on the DoR website so that project stakeholders

could easily access and better understand ESMF compliance requirements. RSDP also

organized 65 HIV/AIDS awareness training programs (25 in the Far-Western Region and

40 in the Mid-Western Region) which involved 4,247 participants, including

representatives from local businesses, contractors, civil servants, drivers, teachers, students,

and farmers. These efforts facilitated project implementation.

40. The environmental management system used in RSDP was defined in the ESMF

prepared by the GoN at the time of appraisal with support from the Bank. Based on project

Page 30: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

13

documentation, including Aide Memoires and other project reporting, during the early

stages of implementation there were delays in carrying out some ESMF requirements,

including preparedness checks and other monitoring activities. This improved over time

as GESU staff, project staff, and the contractors were sensitized on Bank environmental

management expectations and compliance requirements. In addition, the project supported

the recruitment of additional GESU staff along with improved coordination among project

management, GESU staff, supervision consultants, on-site staff, and communities along

road sections being upgraded. Some of the initial challenges that were addressed included

the inappropriate disposal of spoil, poor labor-camp and occupational health and safety

facilities, and the location and operation of crusher plants as well as quarry sites. Project

staff effectively addressed these challenges to ensure for environmental safeguard

compliance.

41. Procurement: At the time of appraisal of original Grant, the team recognized

procurement as a notable risk especially in terms of staffing continuity, corruption and

collusion among the bidders. The project sought to mitigate these risks and ensure

compliance of procurement requirements during the implementation mainly through

adopting a disclosure policy and complaint redressal mechanisms and e-procurement. The

DoR successfully harnessed e-procurement and established itself as a leader in

implementing e-bidding in the GoN, which faced – and continues to face – intimidation

and collusion among bidders in public procurement in other parts of government.

42. During the course of the implementation, the project encountered some challenges

related to non-performing and slow-performing road upgrading and maintenance contracts

in 2012-13. The GoN and Bank worked together to effectively address these challenges.

GoN dealt with the non-performing and slow-moving contracts for upgrading and periodic

maintenance by applying suitable contractual remedies, including forfeiting of Bank

Guarantees against mobilization advances and/or termination. As of September 2016, all

contracts were successfully procured with no outstanding issues requiring resolution.

43. Financial Management: Financial management was the responsibility of the

Deputy Director General of the DoR’s Foreign Cooperation Branch, assisted by the RSDP

Project Coordinator, Senior Accountant and additional DoR staff as needed. At the time of

MTR, the Bank team recommended that DoR authorities: (i) review the Financial

Management Information System supported by the project in advance of AF; (ii) prioritize

monitoring of project outputs and expenditures to ensure that physical and financial

progress reconciled; and (iii) improve internal control systems to track eligible

expenditures and ensure that the GoN’s financial procedures were properly followed.

Since then, no other major issues were raised and the project maintained the required

ledgers and summaries of expenditures. In particular, the DoR recognized and addressed

the following financial management challenges during implementation, viz., slow

utilization of available resources, authorization delays in releasing expenditures, and the

timely submission of regular reporting. There is currently a Financial Management and

Information System (FMIS) in place, with all ledgers and accounts information included.

Page 31: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

14

44. Throughout the life of the project, the GoN worked closely and effectively with the

Bank to resolve issues related to social and environmental safeguard, financial

management, and procurement compliance.

2.5 Post-completion Operation/Next Phase

Post Completion Operation and Maintenance Operations

45. Notable strides have been made linking the target districts, but renewed political

commitment to road maintenance is needed. During the field visits9 to some of the roads

upgraded with the project support, ICR Team noticed that quite a few of them had not

received maintenance attention that was commensurate with the harsh terrain and weather

conditions. Wash-aways, potholes, and unattended landslides were common. Accordingly,

the sustainability of this project, especially related to the works completed, will require

sufficient annual budget allocations, continued investment in maintaining and deepening

the institutional capacity of the DoR, and meaningful reform of the RBN.

46. Nepal’s transport needs have changed. The result is that many RSDP roads require

enhancements to keep pace with both greater traffic volumes and the development that road

access has brought to remote areas. The AF also mentions about supporting such

enhancements, the design and investments under its civil works oriented components

appears to be primarily focused on bridges. Accordingly, the roads supported under the

project seem to be quite vulnerable to the risk of inadequacy of funds for their regular and

periodic maintenance.

Sustainability of Institutional Reforms and Capacity

47. RSDP made notable and laudable progress in institutionalizing a variety of best

practices in the DoR, including the development and adoption of an e-bidding system that

serves as a model for other government departments. It also strengthened capacity of key

branches of the DoR, including the GESU, IT and MIS Department, Road Traffic Unit,

Central Road Lab, Mechanical Training Center and Human Resource Development. Even

so, the endeavor of capacity building of DoR and its staff appears to be far from over as it

finds prominent place in the recently approved Second AF.

48. The project supported the drafting of a Roads Board Act Amendment that would

strengthen the RBN’s operations and independence, but this Amendment is still awaiting

approval. Proactive GoN commitment to pass this Amendment and fully reform the RBN

remains a crucial element of a fully functioning and sustainable road maintenance regime.

9 ICR Team visited the Surket-Khidkijyula and Tallodhungeswor-Dailekh Roads (Parent

Project) and Chhinchu-Jajarkot Road (Additional Financing) on September 6-7, 2016.

Page 32: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

15

49. Clearly, sustaining the institutional reforms and capacity is a major challenge

considering the context of frequent instability and various other challenges. Yet, it is

important to take note that both GoN and Bank recognize this challenge and attempting to

continue to place these among areas for continued support in future.

Proposed Follow-up Operation

50. The GoN requested a Second Additional Finance of USUS$ 55.0 million. The need

for the AF was triggered by the 2015 earthquakes that affected the road network adversely

and in particular compromised the integrity of some drainage structures. The Second AF

is intended to support the following:

Road and bridge works (including road safety enhancements);

Post-earthquake reconstruction and resilience enhancements to Nepal’s SRN; and

Technical assistance to improve investment planning and implementation capacity

within the institutions that manage the SRN.

51. The GoN would contribute US$10.0 million, thus bringing the total AF project size

to US$ 65.0 million. This scope of work for the proposed Second AF constitutes a scale-

up of the project activities and a restructuring of components to include the post-earthquake

needs, further capacity development, and resilience enhancements. In line with this, the

Second AF is aimed to achieving three key outcomes that support the PDO, viz., reduced

bridge vulnerability, enhanced resilience of RSDP roads, and enhanced access as reported

by beneficiaries. The results framework of the parent operation, too, has been modified,

reportedly to better reflect attributable outcomes from project interventions, employing

lessons learned from the results frameworks that guided the RSDP original PAD and AF.

3. Assessment of Outcomes

52. This ICR is prepared prior to the final completion of the project in accordance with

Bank Policy (BP) 10.00 because the second AF would extend the project implementation

by more than ten years. It therefore assesses the project performance over the period up to

August 31, 2016, a date after the approval of the Second AF10. The subsequent project

period would be covered in the next ICR. The still-ongoing project Credit (No. 5002-NP)

closes on June 30, 2017 while the Second AF Credit will close on July 15, 2019.

3.1 Relevance of Objectives, Design and Implementation

Rating: Substantial before and after restructuring11

53. Relevance of Objective - High before and after restructuring: The objective has

remained well aligned to the past and present focus of GoN, to increase road access,

promote economic growth, and reduce poverty in Nepal, particularly in rural and isolated

parts of the country. It is also still in sync with the Bank’s aim of increasing inclusion

10 The Second additional Financing was approved on August 25, 2016. 11 While the project underwent seven Level 2 restructurings, it is the changes at the AF of September 2010

that are considered most significant. Refer to Para. 71 for more details.

Page 33: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

16

through facilitating public investment in the remote areas according to the Bank’s current

Country Partnership Strategy (2014-2018). Pillar 1 of this strategy, “Increasing Economic

Growth and Competitiveness” includes an outcome (1.2) that explicitly focuses on

improved transport connectivity by improving access to markets for the poor and

facilitating national and regional integration. This outcome also focuses on improving the

maintenance, safety and quality of transport infrastructure and services while helping to

strengthen key institutions in the transport sector hampered by overlapping institutional

roles and mandates.

54. Relevance of Design and Implementation - Modest before and after restructuring:

A follow-up operation would most likely comprise similar road infrastructure and apply

the same technical interventions, but some significant adjustments within the components,

M&E design and implementation, and the reporting lines affecting the project

implementation unit, would be necessary. According to the latest rural accessibility

review12 Nepal’s classified road density is relatively low by regional standards, at 9.3 km

per 100 km2 of land. Most roads lie along Nepal’s southern border with India. In the more

rugged northern sections, where the project resources were mainly directed, lack of road

infrastructure and poor quality of roads continue to greatly impede the delivery of goods

and services. Support to the country, aimed at improving accessibility would therefore first

focus on the northern hilly districts.

55. However, the project would be less complete without the inclusion of structural

resilience and stability interventions for the road infrastructure, especially in view of the

country circumstances. The case of the omitted road sections due to slope instability is

compelling and a project located in the northern hilly parts of Nepal cannot ignore the

technical vulnerabilities of the road infrastructure. Regarding periodic road maintenance,

RSDP activities were “sporadically” spread across the entire country, thus involving many

administrative divisions, some without the necessary capacity. It would be necessary to

focus periodic road maintenance on well selected regions for better management, impact,

and monitoring.

56. On the second component (Institutional capacity building), the choice of the aspects

to be supported under institutional capacity strengthening would require prior analytical

work. This would be particularly so in areas that are reliant on policy decisions outside of

the project influence.

57. The design of the M&E system would require modifications including better

linkage between the PDO and its indicators, as well as the number, clarity, and

measurability of indicators. A more robust data collection system would be required. A

sub-component to support the implementation agency specifically in the area of M&E

would also be necessary.

12 Measuring Rural Access Using new technologies: UKaid, ReCAP, World Bank 2016

Page 34: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

17

58. Implementation would benefit to some extent from the experience gained through

RSDP, but significant changes especially at the level of the implementation agency would

be required. While the project has augmented DoR’s skills in the implementation of this

type of a project, DoR’s effectiveness was affected by the institutional linkage to the

ministry. Its inability to fully retain project staff was a major drawback. The frequent staff

transfers at the ministerial level would affect not just the M&E, as noted above, but also

other aspects of the project, including financial management, procurement, and safeguards.

Future success of a similar operation would therefore be predicated upon an undertaking

by the ministry to ensure continuity of project staff within the DoR. Also important would

be an undertaking by the ministry to facilitate policy level outputs of the project.

3.2 Achievement of Project Development Objectives

Rating: Substantial before and Modest after restructuring

59. The assessment is based on the combined pre- and post-restructuring achievements

of the project and the details are provided in Table 2 of Annex 2. Without the restructuring,

the PDO achievement is considered to have been Substantial. Two of the original three

PDO indicators (Indicator Nos. 1, 2, and 12, marked as such in Table 2 of Annex 2) were

overachieved. These were indicators No.1 - Percentage increase in population with all

season road access; and No. 2 - Decrease in journey times. However, one of the three

original PDO indictors (No. 12 - Reduction of blacktop roads in poor condition) was

underachieved. Similarly, without the restructuring, only one out of the six original

intermediate indicators (No.1-Roads Board Act Amended) was underachieved. Under-

achievement of one out of three original PDO indicators and one out of six original

intermediate indicators is considered as minor shortcoming in the operation’s achievement

of its objectives – before restructuring. Hence the Substantial pre-restructuring rating.

60. With the restructuring, performance is rated as Modest. There was only one revision

to the three original PDO indicator targets (Percentage of black top roads in poor condition),

and the revised target itself was exceeded. However, the number of PDO indicators was

increased from three to twelve, four of the new indicators having no clear targets. As a

result, only three out of the nine new PDO indicators could be assessed as having been

exceeded. Furthermore, restructuring resulted in an increase of intermediate indicators

from six to eighteen. Out of the twelve new intermediate indictors, eight were either

achieved or exceeded i.e. four of the twelve new intermediate indicators were

underachieved. In summary, two-thirds of the new PDO indictors were not achieved and

one third of the new intermediate indicators were also not achieved. This post-restructuring

performance is considered modest.

61. In addition to the above assessment, a detailed review of the project performance

towards realization of the PDO’s does reveal a counter-effect of the restructuring. The main

drivers of the restructuring included the need to reflect realism especially where original

targets were considered ambitious (e.g. on policy reforms) or due to availability of

additional resources, to highlight additional outcomes (e.g. employment generation), and

to amplify some of the outcomes (e.g. on time savings). However this resulted in a

multiplicity of indicators many of which were without targets and a few could not be

Page 35: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

18

comprehensively monitored. Examples of poorly monitored or reported indictors include

RBN staff remuneration relative to market salaries, and the impact of periodic maintenance

efforts on the maintenance backlog (intermediate indicators Nos. 3 and 12).

62. Direct assessment of the institutional strengthening aspect of the PDO seems to

have been low keyed. The outcome on institutional strengthening was, surprisingly, only

monitored through one out of twelve indicators i.e. Reduction in the percentage of blacktop

SRN in poor condition (Indicator 12). This was an indirect assessment of changes towards

more institutionalization of road maintenance – the ability of the project to make positive

impact beyond the project, by promoting an increase in road maintenance resources.

Fortunately the revised target was overachieved by 25%. Without restructuring, this

particular indicator would have significantly lowered the PDO rating.

63. The Intermediate outcomes of the infrastructure component made significant

contribution towards the PDO before and after restructuring. This was not unexpected,

considering that over 70% of the credit, in both instances, was dedicated to infrastructure.

A total length of 680km of roads were upgraded resulting in a marginal underachievement

of 4% below the 705 km target. This was mainly due to a justifiable technical and financial

consideration i.e. the need to avoid unstable slope areas. These areas would have required

more funding which in turn would have reduced the eventual upgraded length. Furthermore

the unstable sections have been included as part of second AF. Roads in good and fair

condition went up slightly above the target. The length of highways under periodic

maintenance was also marginally overachieved. A concern though, on the road related

outputs was the lack of clarity on the extent to which periodic maintenance backlog was

addressed or forestalled. This is mainly due to the lack of initial clarity in the choice of the

indicator, its definition, and the absence of due diligence in its measurement and reporting.

This matter could have been addressed through restructuring.

64. It could be argued that any of the project’s impact in terms of institutional

strengthening and policy reforms was, in fact, an outcome outside of the stated project

objective and that it was a substantial bonus to the project. Deliberate omission of the

institutional aspects in the PDO, although not discussed as such in the project documents,

may have been to provide sharpness in the project focus i.e. the emphasis was going to be

on physical infrastructure. However institutional strengthening was always part of the

project and indeed one of the upfront indicators (Roads Board is fully functional and

provides effective and sustainable funding for road maintenance …) pointed to the capacity

enhancements. The PDO could have been reworked for clarity, to reflect the institutional

strengthening aspect of the outcomes that the operation already supported.

3.3 Efficiency

Rating: Substantial before and after restructuring

65. Economic analysis was performed to assess whether the economic benefits of the

investments in upgrading projects – which accounted for about 70% of the overall Bank

support and about 92% of the Bank support to civil works – were higher than their

respective economic costs and whether these benefits were similar to those estimated at the

appraisal stage. The economic benefits of improved roads are assumed to stem from four

Page 36: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

19

sources: (1) time savings benefits (VoT), (2) reduction in vehicle operating costs (VOC),

(3) prevented road closures (only for AF), and (4) modal shift benefits.

66. Cost-benefit analysis indicates that the project achieved a favorable economic

internal rate of return (EIRR) at completion. The overall EIRR for the upgradation

contracts supported under the Original Grant is 41.1%, which is well above not only the

12% threshold but also the estimated EIRR of 29.4% at project appraisal. The EIRR for

the AF road sections is 29.4%, which is also well-above the 12% threshold and above the

estimated EIRR of 23.4% at project appraisal. The minimum EIRR for any of the road

section is 13.8% (see annex 3 for details). The NPV for parent project roads is estimated

to be USD 63.7 million in terms of 2011 prices and the NPV for the AF project is USD

49.3 million in terms of 2016 prices. These results were also tested for their robustness

with a sensitivity analysis comprising three scenarios: a 20% increase in cost, a 20%

reduction in benefits, and a 20% increase in costs plus a 20% reduction in benefits. In all

three scenarios, the EIRR stayed above the 12% threshold. For the Original Grant roads

the EIRR varies from 21.6% to 34.3% and for the AF roads varies from 15.7% to 24.8%.

Table 3: Upgrading Contracts

Net Present Value and Economic Internal Rate of Return

Road Sections

NPV at ICR

(in USD)

EIRR at

ICR

EIRR at

Appraisal

Original Grant 63.7 41.1% 29.4%

Additional Finance 49.3 29.4% 23.4%

67. Cost Estimates vs. Contract Prices and Forex Variations and Savings: An

analysis of the estimated costs and contract prices indicates that the prices of upgrading

contracts are, on an average, about 8% lower than the estimated costs. These figures,

coupled with the significant depreciation of Nepalese Rupee against the USUS$ (from 65.8

at the time of original Grant and 71.18 at AF, to 107 at present), suggest that the project

should have had substantial savings. Indeed, a comparison of actual expenditure to-date on

Roads Development Component (mainly comprising of upgradation and periodic

maintenance contracts) with the estimate/allocation at the time of appraisal suggests a

savings to the tune of 32% (see Project Component by Cost Table in Annex 1). It is also

noteworthy that these savings are not even across the upgrading and periodic maintenance

activities mainly because the actual expenditure by GoN on periodic maintenance under

the project was only US$28.3 million, that is, about 42% of the estimate at the time of

appraisal. While part of this is attributable to forex variations, it would still be interesting

to note that the variation of actual expenditure to costs estimated at the time of appraisal

are significantly different between the upgradation contracts (completely funded through

Bank-financing) and periodic maintenance contracts (envisaged to be funded with majority

contribution from GoN).

68. Two points are worth noting: (i) besides the physical works for which economic

benefits are readily quantifiable, the project did generate substantial non quantifiable

benefits including improved accessibility for beneficiary communities, employment

creation, better road safety environment; institutional capacity enhancement. The

Page 37: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

20

Substantial assessment of the efficiency criteria has a direct impact on the overall

justification of the outcomes, but it’s influence on the disbursement-weighted split rating

is remote.

69. In summary, while the economic analysis clearly points out to some weaknesses in

capturing and reporting on: (a) the extent of savings on account of variation in foreign

exchange rates (which turned out to be rather significant); and (b) the variations in the

ratios of GoN:Bank cost-sharing envisaged vis-à-vis the actual in the case of the Periodic

Maintenance activity it strongly reveals that the project supported investments have yielded

positive NPV and EIRRs well-above the threshold levels. Accordingly, the Efficiency

aspect is rated as Substantial.

3.4 Justification of Overall Outcome Rating

Rating: Moderately Satisfactory

70. The project is overall evaluated as having achieved the PDO Moderately

Satisfactorily. The combined rating before restructuring for the primary criteria i.e.

Relevance, Efficacy, and Efficiency is Satisfactory. After restructuring, Efficacy is rated

as Modest while the other two are rated Substantial thus making the combined rating

Moderately Unsatisfactory (MS). After assigning the appropriate values13 (Ref. Appendix

B of the ICR Guidelines) to the before and after restructuring ratings, and applying the

disbursement-weighted split rating method discussed below, the overall outcome rating is

Moderately Satisfactory.

71. The project PDO remained unchanged but the assessment of the outcomes has taken

due cognizance of the significant scale-up of the scope of outcome targets arising from the

AF of September 2010. At the restructuring for the AF, physical scope increased, new

districts were added, and notable changes were made to the results framework. While there

were other six restructurings, the September 2010 restructuring is considered as the

project’s main point of inflexion. The PDO ratings have therefore been assessed separately

for the periods before and after the September 2010 restructuring. Table 2 of Annex 2 is

particularly relevant in this regard. Thereafter, the disbursement-weighted split rating

method has been used to combine the ratings. At the time of the AF, disbursement stood at

US$ 30.1 million while it was US$ 99.1 million on August 31, 2016. The ratio (or split) of

the disbursements that is applied to weight the ratings is therefore 3:7. In other words, the

Satisfactory performance prior to restructuring is effectively counterbalanced by the

Moderately Satisfactory performance after the restructuring.

3.5 Overarching Themes, Other Outcomes and Impacts

(a) Poverty Impacts, Gender Aspects, and Social Development

13 The assigned values for Satisfactory and Moderately Unsatisfactory ratings are 6 and 3 respectively. The

assigned value for Moderately Unsatisfactory rating is 4.

Page 38: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

21

72. RSDP beneficiaries are based in Nepal’s Mid-Western and Far-Western Regions.

These regions have the highest overall rates of poverty in Nepal (32% and 46%,

respectively). The districts that benefitted from the project are home to approximately two

million people, roughly 8% of Nepal’s overall population. Just over half of the people

living in these districts were poor according to the Association’s Small Area Poverty

Assessment conducted in 2011. Three of RSDP’s original target districts (Kalikot, Bajhang,

and Jumla) were considered to be the second, third, and sixth poorest districts in Nepal,

with estimated poverty rates in 2011 of 58%, 56%, and 49%, respectively. Project

beneficiaries included women and members of two historically disadvantaged groups:

Dalits and Janajatis. The ICR Team had the opportunity to informally interview some

beneficiaries along project-supported roads; they emphasized how these roads had

improved access to government services and provided increased access to transport

services.

(b) Institutional Change/Strengthening

73. The Institutional Strengthening and Policy Reform Component focused on

improving processes and building the longer-capacity of key branches of the DoR, and in

the RBN. Both institutions are essential for maintaining RSDP upgraded roads and

ensuring continued maintenance of the SRN more generally. The DoR benefitted from

local and international training opportunities for senior staff and technical experts that built

capacity and expertise in information technology, environmental and social safeguards,

human resource development, road asset management, road safety, quality assurance of

upgraded works, auditing, and logistics. On the other hand, the project’s endeavor to

improve and mainstream the road asset management and IT-based systems, strengthening

RBN and further stepping up the capacity of DoR, remains an unfinished agenda, slated

for support under the Second AF.

(c) Other Unintended Outcomes and Impacts (positive or negative)

74. Development of New Construction Material: The upgrading of roads in remote

districts in the Mid-Western and Far-Western regions of the country was intended to

improve access to economic and social centers for isolated communities. The remoteness

of these regions, along with the difficult physical environments, presented engineering and

logistical challenges for the construction firms contracted to upgrade sections of non-

engineered roads. This influenced the choice of upgrading materials and technologies used.

Based on past pilot projects, RSDP roads utilized a unique, low-cost design comprised of

a particular river bed gravel size sourced from the immediate vicinities of project sites and

protected by thin coating of Otta Seal to prevent gravel erosion, run-off, and unhealthy dust

during the dry season.

75. Flexible Response: a present and ongoing engagement with GoN through RSDP

was found to be quite useful in mobilizing quick, relevant and just-in-time support to Nepal

especially when faced with emergency situations such as floods and earthquake. For

example, the first AF helped make funds quickly available for emergency maintenance to

mitigate the damage caused by floods. In a similar vein, the project could extend swift

support to DoR in undertaking a rapid assessment of the condition of 389 bridges in the

Page 39: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

22

Central and Western Development Regions in the aftermath of the earthquake, and identify

the extent of damages and options for remediation.

3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshop

n/a

4. Assessment of Risk to Development Outcome Rating: Significant

76. The risk to the development outcome is considered significant, based on the

magnitude and likelihood of risks in the areas of Politics, Government Ownership,

Institutional Support, Technical and Governance, as explained below.

Maintenance of SRN (Government Ownership/Commitment Risk – Significant):

The sustainability of project assets – including roads that were upgraded and others

that benefitted from periodic maintenance – will be at risk if the GoN does not

proactively maintain them in accordance with routine and periodic maintenance

requirements based on local, regional, and, where appropriate, international,

lessons learned and best practices. The DoR currently has a bottom-up prioritization

process in place, but the continued efficacy of this process will be limited without

reforms to the RBN.

Institutional Strengthening at DoR (Institutional Support Risk – Significant): DoR

has established itself as a capable implementing institution, but capacity remains

limited due to multiple demands and a limited number of experienced engineers

who are able to plan and manage works effectively. The DoR also continues to

recover from the April/May 2015 earthquakes which forced its staff to relocate

different Kathmandu-based units in a dispersed fashion in response to safety

concerns at DoR's damaged headquarters building.

Reform of Roads Board (Political, Institutional Support Risk – Significant):

Although a majority of the road maintenance budget allocated directly by the

government is provided through the consolidated budget line of the RBN, the DoR

continues to get a separate maintenance budget from the government and local

bodies get separate unconditional grants that they may use for local maintenance.

This practice has diminished the role and effectiveness of RBN, and also provides

opportunities for non-prioritized ad hoc maintenance works.

Build and Maintain Bridges that Connect Upgraded Roads (Technical Risk –

Moderate): The DoR has initiated the construction of bridges that connect RSDP

upgraded roads. To ensure that these roads provide all season access to economic

centers and social services, especially during the annual monsoon season, the DoR

needs to build bridges where needed, and complete those currently under

construction. This risk is, however, considered to moderate considering the

emphasis being placed on bridges in the Second AF.

Fiduciary Transparency (Governance Risk – Moderate): Government programs in

Nepal remain vulnerable to fiduciary risks. Irregularities may still occur despite

financial controls, procurement oversight, regular financial auditing, regular

Page 40: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

23

reporting, and other controls. While the introduction of e-bidding and general

improvements in DoR's fiduciary systems have resulted improvements in

procurement and contracting, residual risk remains.

5. Assessment of Bank and Borrower Performance

5.1 Bank Performance

(a) Bank Performance in Ensuring Quality at Entry

Rating: Moderately Satisfactory

77. At the time of preparation, the Bank team had taken good advantage of its earlier

engagement in the Nepal Road Sector – through the RMDP – to pinpoint the proximate

challenges facing the sector, namely, lack of access due to systemic decline in capacity

expansion investment owing both to insurgency and the particular focus of GoN and donors

on routine maintenance. This understanding has been harnessed well to (a) define a PDO

that is fully aligned with the sector needs, country priorities and the Bank’s engagement

strategy; (b) design components that respectively focused on enhancing access in the

targeted districts with acute deficiencies in access, through upgrading and periodic

maintenance investments and strengthening of policies and key institutions engaged in

planning and management of roads; and (c) prepare the project on “fast track” basis duly

taking advantage of the Environmental and Social Management Frameworks developed as

part of the earlier project.

78. The preparation also ensured that the design and quality at entry were robust with

respect to the Road Development Component, in terms of its alignment with the client

priorities and Bank strategy, logical and prioritized selection of investment interventions,

use of lessons from previous operations, identification & mitigation of risks and allocation

of adequate funds to meet the envisaged outputs and outcomes. In comparison, the design

of the Institutional Strengthening & Policy Reform Component, though appeared to have

been ambitious in terms of range of activities it sought to support, it lacked clear espousal

how and to what extent various activities under this component would strengthen the target

institutions. In particular, the team appears to have underestimated the challenges they are

likely to face in more complex areas such as mainstreaming of road asset management

system and strengthening of RBN. For example, the PAD explicitly identified the

“consolidation of road maintenance funding through RBN” as a Covenant applicable to

project implementation. While the RBN Act Amendment was developed and submitted to

the Constituent Assembly for action, this Covenant was yet to be met.

79. The aforementioned limitations in the design of the Institutional Strengthening and

Policy Reform component are considered as moderate as the team could not have envisaged

the prolonged period instability and other disturbances that ensued, and, accordingly, the

Bank’s performance in ensuring quality at entry is rated as Moderately Satisfactory.

(b) Quality of Supervision Rating: Moderately Satisfactory

Page 41: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

24

80. As envisaged at the time of appraisal, the team relied on continuous supervision to

ensure smooth implementation of the project. The team conducted a total of 17 formal

missions over an eight year period (from June 2008 – September 2016). The ISRs, Aide

Memoires and Management Letters provided regular and appropriate oversight of the

project, with the later Aide Memoire’s providing more detailed data and analysis. The

generation of these documents also provided useful ways for the Bank to maintain regular

communication with the GoN on implementation challenges and successes. These efforts

have enabled the team to identify operational problems (e.g., poor- or non-performing

contracts) as well as need/scope for AFs, restructurings and cancellations, early on, and

initiate appropriate remedial actions. Overall, project oversight improved over time, with

the most noticeable and positive changes beginning in 2012, when the Aide-Memoires

became far more detailed and systematically presented. The Aide-Memoires identified

implementation challenges at the sub-component level, and described actionable, time-

bound responses to these challenges.

81. The team, however, seemed to have not been equally effective in its pursuit of

complex challenges on the Institutional Strengthening and Policy Reform agenda.

Admittedly, much of the lack of the traction on this front is perhaps attributable to the

prevailing environment of political uncertainty. Yet, the team seems to have responded to

this constraint mainly through progressive downward revision/recalibration of its

expectations rather than identifying and pursuing alternative avenues for furthering the

reform agenda. Also, a quick review of the Aide Memoires and ISRs suggests little or no

analysis as to how the substantial changes in exchange rate have been impacting project

funds and the likelihood of savings. Keeping in view these shortcomings, the performance

of the Bank on Quality of Supervision is rated as Moderately Satisfactory.

(c) Justification of Rating for Overall Bank Performance

Rating: Moderately Satisfactory

82. Considering that the Bank’s performance in ensuring quality at entry and in quality

of supervision are rated as Moderately Satisfactory and Satisfactory respectively the overall

rating for Overall Bank Performance is rated as Moderately Satisfactory.

5.2 Borrower Performance

(a) Government Performance

Rating: Moderately Satisfactory

83. The project received continuous support of the GoN, which helped it sustain the

project efforts and momentum, despite the highly challenging context in which the project

was conceived and implemented. Continuity of staff was a challenge, but not surprising

given the protracted political transition that resulted in multiple governments, and the two

earthquakes that required emergency response to damaged roads. The government met all

the covenants except four. Of these, three Covenants on continuity of staff, ensuring for

adequate funding for road maintenance of back-logged periodic maintenance, and human

resource development, were partially met, and the one related to consolidation of road

maintenance funding for both local and strategic roads through the RBN starting in

Page 42: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

25

FY2008/09 was not met. The Roads Board Act Amendment, which would reform the RBN

structure, accounting systems, authority to collect and cause to collect Road User’s Charges,

and provide specific authorities for the Chairman and Executive Director – and thereby

significantly enhance the sustainability of funds flow to the critical area of maintenance –

is still under consideration of the Constituent Assembly. The Borrower Performance is

rated as Moderately Satisfactory.

(b) Implementing Agency or Agencies Performance Rating: Moderately Satisfactory

84. The DoR was the agency for implementing this project in fairly complex and

challenging environment. The international and local training for technical staff and

management, including capacity building in geo-technical, environmental, and social

aspects of road building, upgrading and maintenance, did contribute to the performance of

DoR in project implementation. However, frequent staff rotation affected implementation

continuity and delayed decision-making. In addition, operational issues at the outset slowed

implementation, especially related to road upgrading and addressing the road maintenance

backlog.

85. DoR, however, overcame these issues over time and eventually was able to

successfully meet upgrading and periodic maintenance targets. The agency also managed

to improve systems and process across its many administrative, operational and technical

branches. Continued commitment to institutional strengthening and managing

construction work in the immediate aftermath of the April/May earthquakes, when office

units were disbursed across Kathmandu due to safety concerns at DoR’s damaged

headquarters, is particularly noteworthy. Keeping these in view, performance of the

Implementing Agency is rated as Moderately Satisfactory.

(c) Justification of Rating for Overall Borrower Performance Rating: Moderately Satisfactory

86. Considering that the performance of the Borrower as well as the Implementing

Agency are rated as Moderately Satisfactory, the Overall Borrower Performance has been

rated as Moderately Satisfactory.

6. Lessons Learned

87. The development and implementation of RSDP during a period of political

transition and environmental challenge (including two earthquakes and devastating

flooding and mudslides due to a harsh monsoon season in 2013) provides the opportunity

to reflect on lessons learned that can inform future partnerships between the Bank and the

GoN, and also inform Bank work more generally in road transport.

88. Robust understanding of the needs and simple design to meet them: Perhaps the

most important lesson of the Bank’s engagement in RSDP is the way it analyzed the sector

context to understand how declining focus on capacity expansion has been progressively

Page 43: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

26

hampering access especially in poor and remote districts, and then put together a project

that squarely targeted this need by channelizing investments towards upgradation and

periodic maintenance of prioritized roads in selected districts. The Institutional

Strengthening and Policy Reform, on the other hand, comprised many but mostly disparate

activities with no coherent strategy and, accordingly, achieved mixed results.

89. There are advantages in having an ongoing engagement…but. Clearly, the

present and active engagement of the Bank in the sector proved to be invaluable in quickly

mobilizing additional support in the aftermath of natural calamities including earthquakes

and floods. At the same time, prolonging an engagement over a period of more than 10

years, with little or no variation in design seems to suggest that the Bank might have missed

an opportunity to look at the sector challenges and structure solutions from a fresh

perspective. To its credit, the recent Second AF, with its focus on bridges, climate

resilience, etc., seems to be attempting to break new ground but the way forward envisaged

on the Institutional Strengthening & Policy Reform front suggests serious need for

reworking the approach.

90. Support for innovative approaches to the development and use of local materials

in road construction can be cost effective, environmentally friendly, and promote local

entrepreneurship. When upgrading or building new roads in geographically isolated areas

with challenging environmental terrain, the Bank can incentivize the creative use of local

materials to build or upgrade low traffic roads at a lower cost and with a minimal carbon

footprint.

91. “Soft” investments are harder to implement, monitor and evaluate. The mixed

results on the Institutional Strengthening & Policy Reform component underscore the need

to pay more attention to duly integrating/reflecting it in the PDOs, and the results

framework with a logical chain of attribution. Furthermore, the opportunities to

restructuring should be fully harnessed to seek alternative solutions rather than simply

revising the expectations downwards and aligning the targets to whatever was possible.

92. Important to nurture innovations, as they can yield big dividends, even beyond

the remit of project and sector. The e-bidding system that was developed and supported

by RSDP is currently being rolled out to other GoN entities. The Bank and Borrower

should explicitly identify activities that support project goals and that have the potential to

impact other sectors and more generally improve government performance.

93. Project opportunities in difficult environments are rare and hence, interventions

should be more comprehensive and also cater to future needs. As indicated by GoN in

their project completion report, road construction in high mountains is a challenging and

cumbersome job. Also, as recognizes in the recent AF Paper, the travel needs on the project

roads are already changing, signifying the importance of addressing aspects such as bridges,

slope stabilization, road safety, etc. This aspect may be given due attention in future

projects in similar challenging contexts/areas.

Page 44: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

27

94. Road investments have the potential to contribute to post-conflict challenges.

Besides providing better living conditions and opportunities for post conflict communities,

road investments can contribute towards enhancement of cohesion and inclusion. This

would be particularly so if choice of interventions are guided by prior diagnostic work.

95. Institutional development component would have benefitted from prior

diagnostics. The institutional strengthening and reforms component was well funded and

continues to be part of the second AF. Its importance therefore cannot be overemphasized.

However, the wide scoped support for this component seems to have yielded mixed results

due the absence of prior in-depth sector needs assessment. In this regard, the 50 percent

increase in the original amount for capacity building (from US$8.0 million to US$12

million) required the backing of a robust situation analysis.

96. A technical department with a dedicated project implementation unit cab be

significantly advantageous. The performance of DoR with regard to the infrastructure

deliverables was notably effective. The department was in a position to mobilize a

dedicated project implementation unit as well as its regional and district units to deliver the

roads component. The department, based on its appreciation of national level challenges,

for instance, took the decision to package contracts into sizes that met the needs of the local

construction industry and advised the units accordingly. This improved competition, speed

of implementation and also contributed towards growth of the local construction industry.

DoR was able to implement this aspect of the project relatively well notwithstanding the

fragile country environment.

97. Overall project cost increase can yield corresponding outputs. For RSDP, the final

total expenditure of US$ 120 million was more than twice the original all-inclusive project

cost estimate of US$ 50 million. Similarly the 680 km of roads finally rehabilitated were

more than twice the initial estimate of 297 km. The main driver of the cost increase was

the need to scale-up the physical outputs and this was achieved. Of the US$ 120 million,

US$101 (83% of the project cost) was used to improve road accessibility. An analysis of

the road contract prices indicates that they were, on an average, about 8% lower than the

estimated costs. RSDP’s cost increase therefore translated directly into corresponding

physical outputs. This achievement was further augmented by the support towards the

Borrower’s institutional capacity.

7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

(a) Borrower/implementing agencies

n/a

(b) Cofinanciers

n/a

(c) Other partners and stakeholders

Page 45: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

28

n/a

Page 46: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

29

Annex 1. Project Costs and Financing by Component

(a) Project Cost by Component (in USD Million equivalent)

Component

Original Estimate at the time

of Appraisal

Actual/Latest Estimate

of Expenditure* % of

Appraisal Origina

l Grant

Addl.

Fin. Total

Original

Grant

Addl.

Fin. Total

in USUS$ million

Component 1: Road

Development Component 42.9 101.3 144.2 40.8 60.2 104.4 72%

1.1 Road Upgrading 30.9 53.2 84.1 30.5 43.4 75.9 90%

1.2 Periodic Maintenance 12.0 48.1 60.1 10.3 16.8 28.5 47%

1.3 Road Safety (in 1.1

above)

Component 2:

Institutional

Strengthening and Policy

Reform 6.6 18.0 24.6 9.3 7.1 16.4 67%

PPF 1.0 0.0 1.0 0.5 0.0 0.5 52%

Operating Cost 0.1 6.3 6.4 1.2 1.2 2.3 36%

TOTAL 50.6 125.6 176.2 51.8 68.5 123.6 70%

in SDR million

Component 1: Road

Development Component 27.9 65.3 93.2 26.5 41.8 68.4 73%

1.1 Road Upgrading 20.2 34.3 54.4 19.7 30.5 49.8 92%

1.2 Periodic Maintenance 7.7 31.0 38.8 6.8 11.3 18.6 48%

1.3 Road Safety (in 1.1

above)

Component 2:

Institutional

Strengthening and Policy

Reform 4.3 11.6 15.9 6.1 4.7 10.8 68%

PPF 0.7 0.0 0.7 0.3 0.0 0.3 43%

Operating Cost 0.1 4.1 4.1 0.0 0.8 0.8 20%

TOTAL 33.0 80.9 113.9 32.9 47.3 80.3 71%

Source: Department of Roads, Government of Nepal

Notes: (i) In June 2011, an undisbursed amount of SDR 17.5 million under the AF Grant was cancelled

and the same amount of funds were recommitted as new credit; (ii) ~US$7 million cancelled in January

2015 restructuring; and (iii) As of October 22, 2016, under the Original Grant and the first AF: Net

commitment - US$110.62 million; Disbursed - US$99.1 million; and Undisbursed - US$9.37 million

Page 47: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

30

(b) Project Costs and Financing by Source of Funding

Source of

Funds

Type of

Cofinancing

Appraisal Estimate Actual/Latest Estimate

of Expenditure* % of

Appraisal Original

Addl.

Fin. Total Original

Addl.

Fin. Total

in USUS$ million

Borrower - 8.0 50.5 58.5 9.0 15.5 24.5 42%

IDA Grant - 42.6 33.7 76.3 42.8 6.6 49.4 65%

IDA Credit - 0.0 41.3 41.3 0.0 49.8 49.8 120%

TOTAL - 50.6 125.5 176.1 51.8 68.5 123.6 70%

in SDR million

Borrower - 5.2 32.6 37.8 5.2 10.4 15.6 41%

IDA Grant - 27.8 21.7 49.5 27.8 4.4 32.2 65%

IDA Credit - 0.0 26.6 26.6 0.00 32.5 32.5 122%

TOTAL - 33.0 80.9 113.9 33.0 47.3 80.3 71%

Source: Department of Roads, Government of Nepal and Project P095977 Portal (IBRD)

Notes:

(i) Approval of the Second AF on August 25, 2016, committed an additional IDA amount of SDR 39.3

million (US$ 55.0 million). The credit is not yet effective.

(ii) Level 2 restructuring of January 21, 2015 resulted in the cancellation of SDR 4.67 million (US$6.98

million).

(iii) Total IDA funding is SDR 110.73 million (27.8+21.7+26.6+39.3-4.67)

(iv) The equivalent amount is US$ 165.62million (42.6+33.7+41.3+55.0-6.98)

(v) As at August 31, 2016: Net commitment - US$110.62 million; Disbursed – SDR 64.71 million (US$99.1

million); and Undisbursed - US$9.37 million, excluding Second AF.

Page 48: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

31

Annex 2. Outcomes and Outputs by Component

The Project had two main components and the outputs of each are listed in Table 1 below.

The outcome ratings with and without restructuring are shown in Table 2.

Table 1: Output and their indicators

Component /

Activity

Description

Key Performance Indicators

End of Project Target Achievement/Remarks

Component 1: Road Development Component

Overall 6 percent increase in

population in project

districts to have all

season road access within

20 minutes walking

distance (in eight project

districts)

Target marginally exceeded.

The percentage of population with all season

road access within 20 minutes walking

distance increased from 8% to 15%, as against

the target of 14%. Source: GoN study based

on a GIS analysis.

35 percent decrease in

journey times to key

economic centers in the

project area

Target exceeded.

Journey time to economic centers decreased

by 53% (from 4 hours to 2.6 hours)

25 percent decrease in

journey times to social

services in the project

area

Target exceeded.

Journey time to social centers decreased by

70% (from 4 hours to 1.2 hours)

Reduce the percentage of

black-top SRN in poor

condition to 15 percent

Target exceeded.

The percentage of blacktop Strategic Road

Network (SRN) in poor condition reduced to

11.27% as against the revised target of 15%

(original: 10%).

Periodic maintenance of

targeted highways and

feeder roads backlog

executed

Not clear. The target of backlog periodic

maintenance of 1,000 km was eschewed in

AF. No data on the other part of the indicator,

that is, at least 500 km of periodic

maintenance works annually.

1.1: Road

Upgrading,

Resettlement &

Rehabilitation

100 percent of 705 km

(Original: 297 km; Addl.

Financing: 408 km) of

target roads receiving

upgrading works

Substantially achieved.

As against the target of rehabilitating 705 km,

the project completed upgradation of 680 km.

1.2: Periodic

Maintenance

100 percent of 2550 km

(Original: 450 km; Addl. Achieved A total of 2,595km road length (Out of which

450 km of original financing; 1,728km of AF

Page 49: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

32

Financing: 2100 km) of

highways received

periodic maintenance

and 417km of GoN funding) has been

completed as of end-June, 2015.

1.3: Road Safety

Action Plan and

Physical Works

Road Safety Action Plan

implemented and

physical works carried

out.

Achieved.

Road safety action plan, developed and

approved, and is under implementation. All

the physical works spanning 9 contracts being

supported under the project have been

completed.

Component 2: Institutional Strengthening and Policy Reform

2.1 Improved

effectiveness of

Roads Board

Nepal

Draft RBN Act

(Amendment) finalized

and submitted to the

Parliament for

consideration

Revised target achieved.

The draft amendment to the Act finalized and

submitted to the Parliament.

Government decision to

benchmark RBN staff

salaries to market rates

Difficult to conclude.

While RBN Staff salaries are reportedly being

made comparable to other autonomous bodies

but not clear as to how they compare with

market rates. Also, the indicator was

eschewed in the recent AF citing difficult in

its attribution to project.

An RBN 5 year business

plan (2012-2017)

prepared that incorporates

Human Resource

Development (HRD) Plan

Revised target achieved.

5-year business plan prepared for RBN.

2.2 Improved

staff

capacity within

DOR

HR policy updated and 3-

year training plan

finalized

Achieved.

HR policy updated and 3-year training plan

finalized. Domestic and international training

provided for DoR staff as per policy and plan.

Capacity building in

Geotechnical,

Environmental and Social

Unit

Achieved.

Geotechnical assessments carried out and site

specific EMAP and RAP monitoring

being done periodically

Awareness creation on

HIV /AIDS and planned

activities carried out

Achieved.

Creating awareness among project

construction workers and road users on

HIV/AIDS is ongoing

2.3 DoR IT based

MIS operational

Web based system

adopted for FMIS, GRM,

CMS

Achieved. The implementation team also paid due

attention to the emerging technological

changes and adopted appropriate changes to

the strategy.

Page 50: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

33

2.4 Road asset

management

tools used for

prioritization of

road

maintenance and

upgrading works

Annual maintenance plan

prepared using objective

methods;

Road inventory prepared

for a portion of the

network and data model

developed in order to roll

out the methods to the

whole network

Revised target achieved.

The ICR team has not ascertained the efficacy

of the reported Objective method being use in

the preparation of the annual road

maintenance plan.

2.5 Improved

quality assurance

Quality monitoring plan

prepared each year and

quality audit carried out

by Central Road Lab

Achieved.

The Central Road Lab is reportedly carrying

out quality audits and monitoring quality

assurance. The scope and periodicity of such

activities, however, is not clear.

2.6 Third party

technical audit

Third party technical

audit carried out for 20%

of the project works each

year

Achieved. Third party technical audit of upgrading and

periodic maintenance works under RSDP has

been carried out on 20% of the project works.

Table 2: Outcome ratings with and without restructuring

Baseline Revised Target % achieved of

revised target

Original Target % achieved of

original target

PDO INDICATORS

1. Percent increase in pop. in project districts with all season road access within 20 minutes

(Original).

8% n/a n/a 14% 107%

2. Percent decrease in journey times in the project area (Original).

4hrs n/a n/a 35% 151%

3. Decrease in journey times in the project area to key economic centers

n/a 2.6 hrs. 137% n/a n/a*

4. Decrease in journey times in the project area to key social service centers.

n/a 3.0 hrs. 250% n/a n/a*

5. Direct project beneficiaries within 4 hours walking distance.

200,000 800,000 94% n/a n/a

6. Female beneficiaries

n/a n/a n/a n/a n/a

7. Employment generated

n/a 2.5 million 267% n/a n/a

8. Employment generated – male

n/a n/a n/a n/a n/a

9. Employment generated – Female

n/a n/a n/a n/a n/a

10. Employment generated – Dalit

Page 51: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

34

n/a n/a n/a n/a n/a

11. Employment created – Janajatis

n/a n/a n/a n/a n/a

12. Reduced % of blacktop Strategic Road Network in poor condition to 15% (Original).

18% 15% 133% 10% 75%

INTERMEDIATE OUTCOME INDICATORS

1. Roads Board Act amended and more training and logistics provided (Original).

0 Submission of

Act 100% Amend. of Act 50%

2. Government decision to benchmark RBN staff salaries to market rates.

n/a Market rates 50% n/a 50%

3. Human Resources Development Plan (Original).

n/a n/a n/a As indicator 100%

4. Roads rehabilitated non-rural (km)

0 705 96% 297 229%

5. Share of rural population with access to an all-season road

n/a 14% 107% n/a n/a

6. Number of rural people with access to an all-season road

n/a 131,000 250% n/a n/a

7. Roads in good and fair condition as a share of total classified roads

n/a 85% 104% 90% 99%

8. Size of total classified roads

n/a n/a n/a n/a n/a

9. 700 km target roads received upgrading works (Original).

0 705 96% 297 229%

10. 2,550 km of highways received periodic maintenance (Original).

2550 102% 450 577%

11. Road safety action plan and physical works (Original).

n/a n/a n/a As indicator 100%

12. Periodic maint. of targeted highways and feeder roads backlog executed (Original)**.

450 n/a n/a 1,000 Data unavailable

13. Capacity building in geot. env. and social aspects, and awareness creation on HIV /AIDS

0 As indicator 100% n/a n/a

14. DoR IT based Management Information Systems (MIS) operational

n/a Web based 100% IT based 50%

15. Road asset management tools used for prioritization of road maint. & upgrading works

n/a Annual plans 100% As indicator 50%

16. Improved quality assurance

n/a Annual reports 50% n/a n/a

17. Third party technical audit

n/a Audit 20% 100% n/a n/a

18. Improve staff capacity within DoR

n/a HR policy 100% n/a n/a

*The indicator was not part of the original three PDO indictors. It was introduced to amplify

the targets of the time-savings indicator

Page 52: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

35

** The indicator was not well monitored or reported on

Page 53: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

36

Annex 3. Economic and Financial Analysis

1. Economic analysis is performed to assess whether the economic benefits of the project

are higher than its economic cost and whether these benefits are similar to those

estimated at the appraisal stage. We accomplish this by first assessing whether the

economic internal rate of return (EIRR14) is greater than 12% and then comparing it to

the EIRR estimated at the appraisal stage. The same methodology as that used at project

appraisal is used to conduct the economic analysis at ICR stage.

Framework:

2. Assumptions: The following general assumptions are made when performing the

economic analysis:

The analysis is performed for a 16 year period – 1 year for civil works and 15 years

of benefits.

Project discount rate is assumed to be 12%. For the conversion rate it is assumed that 1 USD is equivalent to NPR 72 for the

parent project and NPR 106 for the AF. 15

A standard conversion factors (SCF) of 0.92 is used to convert financial (market)

prices to economic costs in road construction.

3. Costs: Actual costs, including supervision costs of implementation of the selected

roads are presented in the table below. In order to compare real costs, the estimated

costs at appraisal of the parent project (in terms of 2007 prices) are rescaled using CPI

to 2011 price level. Similarly, the estimated costs at appraisal of the AF (in terms of

2011 prices) are rescaled using CPI to 2016 price level. The currency conversion rates

provided above are used to convert costs to USD at implementation. A comparison of

the rescaled estimated cost and actual cost reveals that the actual costs of all but one

road section was lower than the estimated costs.

14 EIRR is the discount rate that equates the discounted stream of benefits and costs.

15 These are the currency conversion rates for January 2011 and January 2016, respectively.

Page 54: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

37

Table 1: Cost Comparison

Estimated Cost/Km (in 1000s

NRP)

Actual Cost/Km of

Implementation

Road Section Original

At Adjusted

Price Level

(in 1000s

NRP)

(in 1000s

USD)

Parent Project:

Khodpe-Kalinga Bridge 7,030 9,210 8,850 123

Satbanjh-Gokuleshwar 7,660 10,040 9,500 132

Satbanjh-Tripurasundari 6,720 8,810 6,150 85

Surkhet-Khidkijhyula 3,620 4,750 5,750 80

Tallodungeshwar-

Dailekh 7,840 10,280 8,810 122

AF:

Khidkijyula-Manma 12,500 18,760 10,340 98

Thaktoli-Darchula 8,380 12,570 7,850 74

Kalangagad bridge-

Chainpur 7,790 11,690 8,930 84

Gokuleshwaor-Thaktholi 7,820 11,740 8,430 80

Chhinchu-Jajarkot 7,580 11,380 7,050 67

Sittalpati-Musikot 6,360 9,550 7,210 68

Manma-Jumla 11,440 17,170 15,000 142

4. The economic benefits of improved roads are assumed to stem from four sources: (1)

time savings benefits (VoT), (2) reduction in vehicle operating costs (VOC), (3)

prevented road closures (only for AF) 16, and (4) modal shift benefits. These benefits

are estimated based on updated traffic surveys.

5. Traffic Data: For road sections covered under the parent project, traffic estimates from

2007 (for each road section) are projected to 2011 levels using annual growth rates of

7% for passengers, 5% for freight, and 1.5% for non-motorized traffic. These

projections are compared with actual traffic levels collected from roads during 2011.

Similarly, for road sections covered under AF, traffic estimates from 2010-11 (for each

road section) are projected to 2016 levels using annual growth rates of 8% for

motorized traffic and 1.5% non-motorized traffic. These projections are compared with

actual traffic levels collected from roads during 2011. In both cases, the difference in

the traffic volumes of every type of vehicles are considered to be traffic generated as a

result of the project implementations. Average annual daily traffic (AADT) with and

without project are presented below.

16 This is because for the parent project discussions in 2007 with a number of local residents

established that the project roads were not closed during monsoon times.

Page 55: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

38

Table 2: Average Annual Daily Traffic Without Project and Generated by Project

Road Section Scenario Mo

torc

ycl

e

Tra

cto

r

Bu

s la

rge

Bu

s m

ediu

m

Bu

s m

icro

Tru

ck h

eav

y

Tru

ck l

igh

t

Uti

lity

4 W

hee

l D

riv

e

Ca

r/T

ax

i/J

eep

Ped

estr

ian

s

Po

rter

Pa

ren

t P

roje

ct

Khodpe-Kalinga

Bridge

Without project 4 10 557 346

Generated 29 4 26 24 42 18 31 75

Satbanjh-

Gokuleshwar

Without project 3 1 3 390 673

Generated 10 5 19 10 30 7 17 29

Satbanjh-

Tripurasundari

Without project 3 1 3 168 290

Generated 8 4 14 8 22 5 13 22

Surkhet-

Khidkijhyula

Without project 11 6 8 5 10 5 7 8 3

Generated 1524 116 51 24 34 56 33 49 76 47

Tallodungeshwar-

Dailekh

Without project 8 4 16 2 5 527

Generated 23 2 3 5 6 6 1

AF

Khidkijyula-

Manma

Without project 13 113 3 18 12 15 9 3 830 16

Generated 23 10 4 30 7 4

Thaktoli-

Darchula

Without project 7 1 4 1 1 7 3 32 40 177 150

Generated 2 3

Kalangagad

bridge-Chainpur

Without project 7 15 24 4 4 3 510 25

Generated 40 4 10 9 6 8 10 39 1

Gokuleshwaor-

Thaktholi

Without project 7 1 0 15 3 7 15 435 161

Generated 13 2 4 8 3 2

Chhinchu-

Jajarkot

Without project 75 60 24 1 0 24 10 15 3 1045 22

Generated 238 2 27 29 12

Sittalpati-Musikot

Without project 87 54 41 26 41 25 24 9 1 998

Generated 3 1

Manma-Jumla

Without project 12 125 1 15 1 3 9 3 98 4

Generated 82 32 10 11 13 25 91 23 10

6. VOC Benefits: To estimate VOC benefits, the vehicle operating costs for each vehicle

type are obtained from the World Bank RED-VOC model according to the surface

types and condition. Without the project the IRI of the roads is 22 while with the project

the IRI of the roads is 5. This difference in road condition results in a VOC reductions

of 27% to 44% for each road section.

7. VoT Benefits: Time saving benefits—value of time (VoT)—are calculated on the basis

of the opportunity cost of time by using the hourly wage rate. The hourly wage rate is

estimated to be USD 0.76 (NPR 55) for the parent project (based on 2011 prices) and

USD 0.73 (NPR 106) for the additional finance roads (based on 2016 prices).

Page 56: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

39

Table 3: Travel Time Savings With and Without Project

Speed Without

Project

Speed With

Project Time Savings

per km

(in minutes) Vehicle type (km/h) (km/h)

Bus Light 20.0 34.6 1.3

Bus Medium 20.0 29.4 1.0

Bus Heavy 20.0 30.2 1.0

Car Medium 20.0 34.2 1.2

Motorcycle 20.0 32.1 1.1

8. Benefits from preventing road closures: Based on surveys at the start of the project,

it was established that the additional finance project roads were closed for an average

of approximately 45 days a year due to landslides and flooding during monsoon

season.17

The annual output of economic services from any road is given by: Money value

of output = [daily number of vehicles*unit vehicle operation cost/km*length of

road*365]

The annual loss of output from road closures is equal to: Annual benefit from

improvement = [money value of output per day * no. of days closed per year]

In the ‘with project’ (WP) paved road case, it is anticipated that, given suitable road

maintenance, the number of closed days will be reduced by a year-in year-out

average of 75 percent, Thus the annual economic benefit is calculated as:

AADT*45 days*75%*unit cost/km VOC*road length km.

9. Benefits from modal shift: Benefits from modal shift are estimated for freight and

passengers as explained below.

Freight: It is assumed that road improvements will result in a switch from using

mules and porters to trucks. The assumptions about average load and distance

travelled per day are the same as those made at the project appraisal stage and the

estimation methodology is also the same. The net economic cost savings from

modal shift to trucks, from either porter or mule transport mode, is estimated to be

USD 3.65 (NPR 263) per tonne-km for the parent project roads and USD 3.55 (NPR

376) per tonne-km for the AF project roads.

Passenger: With a marked improvement to the road, if pedestrians begin to take bus

trips instead of walking, then the economic benefit—to each passenger—would be

at least equal to the amount they pay for the bus ride. Additionally, people might

begin to take much longer trips. To estimate benefits from passenger modal shift

the same assumptions as at project appraisal are made regarding the fraction of

17 For the parent projects, a similar survey established that the project roads were not closed during

monsoon times. Thus, benefits from reduced road closures for the parent project roads are assumed

to be zero.

Page 57: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

40

pedestrians who switch to taking buses—this percentage varies from 20% for some

road sections to 40% for other road sections.

Results:

10. Cost benefit analysis indicates that the project achieved a favorable economic internal

rate of return (EIRR) at completion. The overall EIRR for the parent project roads is

41.1%. This is not only well-above the 12% threshold but also above the EIRR of

29.4% which was estimated at project appraisal. The EIRR for the AF road sections is

29.4%. This is also well-above the 12% threshold and above the EIRR of 23.4% which

was estimated at project appraisal. As shown in the table below the minimum EIRR for

any of the road section is 13.8%.18 The NPV for parent project roads is estimated to be

USD 63.7 million in terms of 2011 prices and the NPV for the AF project is USD 49.3

million.

Table 4: Net Present Value and Economic Internal Rate of Return

Road Sections

NPV at ICR(in

Millions of USD)

EIRR at

ICR

EIRR at

Appraisal

Parent Project:

Khodpe-Kalinga Bridge 6.8 24.6% 15.9%

Satbanjh-Gokuleshwar 13.0 35.6% 21.6%

Satbanjh-Tripurasundari 5.5 38.2% 12.2%

Surkhet-Khidkijhyula 27.2 61.7% 59.6%

Tallodungeshwar-Dailekh 11.1 45.9% 20.0%

Sub-Total: 63.7 41.1% 29.4%

AF:

Khidkijyula-Manma 2.5 23.7% 17.7%

Thaktoli-Darchula 4.9 32.0% 24.3%

Kalangagad bridge-Chainpur 2.7 21.2% 15.4%

Gokuleshwaor-Thaktholi 5.1 36.5% 26.4%

Chhinchu-Jajarkot 10.9 35.3% 26.7%

Sittalpati-Musikot 21.8 51.2% 39.9%

Manma-Jumla 1.3 13.8% 15.1%

Sub-Total: 49.3 29.4% 23.4%

11. Sensitivity analysis is performed to test the robustness of the results. In order to do so,

three scenarios are considered: a 20% increase in cost, a 20% reduction in benefits, and

a 20% increase in costs plus a 20% reduction in benefits. In all three scenarios the EIRR

18 EIRR at ICR is significantly higher than the EIRR at appraisal for some of the road sections in

the parent projects. This wedge is largely driven by freight modal shift benefits. It is unclear

whether modal shift benefits were included for the parent project at appraisal.

Page 58: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

41

stays above the 12% threshold. For the parent project roads the EIRR varies from

21.6% to 34.3% and for the additional finance roads varies from 15.7% to 24.8%.

Table 5: Sensitivity Analysis

Sensitivity

NPV (in Millions

of USD) EIRR

Parent Project:

+20% Cost 57.5 34.3%

-20% Benefit 44.7 32.9%

-20% Benefit & + 20% Cost 23.3 21.6%

AF:

+20% Cost 42.0 24.8%

-20% Benefit 32.1 23.8%

-20% Benefit & + 20% Cost 11.1 15.7%

Page 59: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

42

Annex 4. Bank Lending and Implementation Support/Supervision Processes

(a) Task Team members

Names Title Unit Responsibility/

Specialty

Lending

Kiran Ranjan Baral Consultant GSURR Consultant

Gizella Diaz Munoz Program Assistant GFA12 Team Assistant

Drona Raj Ghimire Senior Environmental Specialist GEN06 Environment

Sunita Gurung Program Assistant SACNP Team Assistant

Ernst-August Huning Consultant GTIDR Consultant

Surendra Govinda Joshi Consultant GSURR Consultant

Zarafshan H. Khawaja Manager OPSPF Sector lead

Marianne Kilpatrick Sr Transport. Spec. SASDT - HIS Task Team Leader

Nations Msowoya Voice Secondee TWITR - HIS Team Member

Bigyan B. Pradhan Senior Financial Management

Specialist SARFM Team Member

Binyam Reja Lead Transport Specialist GTI10 Economist

Narayan D. Sharma Procurement Specialist SARPS - HIS Procurement

Supervision/ICR

A. K. Farhad Ahmed Senior Transport Specialist GT107 Task Team Leader

Shambhu Prasad Uprety Procurement Specialist GGO06 Procurement

Olivier Le Ber Lead Transport Specialist GT107 Task Team Leader

Surendra Govida Joshi Senior Transport Specialist GTI07 Task Team Leader

Marianne Kilpatric Senior Transport Specialist GTI07 Task Team Leader

Yogesh Bom Malla Financial Management Specialist GGO24 Fiduciary

Ashok Kumar Team Member GTI06 Team Assistant

Deepak Man Singh Shrestha Peer Reviewer GTI06 Reviewer

Drona Raj Ghimre Safeguards Specialist GEB06 Safeguards

Shubu Thapa Consultant GT106 Consultant

Fabio Pittaluga Safeguards Specialist GSU04 Safeguards

Ishwor Neupane Safeguards Specialist GSURR Safeguards

Kiran Ranjan Baral Team Member GSURR Team Member

Shubu Thapa Team Member GTI06 Team Assistant

Zarafshan H. Khawaja Safeguards Specialist OPSPF Safeguards

Sunita Gurung Program Assistant SACNP Team Assistant

Satya N. Mishra Social Development Specialist GSU06 Safeguards

Nagendra Nakarmi Senior Program Assistant SACNP Team Assistant

Bigyan B. Pradhan Senior Financial Management

Specialist SARFM Team Member

Nastu Prasad Sharma Public Health Spec. SASHN- HIS Team Member

Neena Shrestha Procurement Assistant GGO06 Procurement

Silva Shrestha Water & Sanitation Specialist GWA06 Team Member

Paul Kaiser ICR Consultant GTI07 Consultant

Justin Runji Senior Tran. Spec./ ICR TTL GTI07 ICR TTL

Sri Kumar Tadimalla Senior Tran. Spec./ ICR TTL GTI06 ICR Co-TTL

Page 60: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

43

(b) Staff Time and Cost

Stage of Project Cycle Staff Time and Cost (Bank Budget Only)

No. of Staff Weeks

US$, Thousands

(Including Travel and

Consultant Costs)

Lending

FY06 2 10,868.04

FY07 16.37 82,325.67

FY08 0.00 0.00

FY09 0.00 0.00

FY10 0.00 0.00

FY11 0.00 0.00

FY12 0.00 0.00

FY13 0.00 0.00

FY14 0.00 0.00

FY15 0.00 0.00

FY16 0.00 0.00

FY17 0.00 0.00

Total: 18.37 93,193.71

Supervision/ ICR

FY06 0.00 0.00

FY07 0.00 0.00

FY08 48.97 151,434.91

FY09 38.88 133,056.42

FY10 41.2 119,419.77

FY11 50.58 179,844.42

FY12 36.96 118,181.41

FY13 33.71 105,944.49

FY14 28.11 128,817.6

FY15 21.46 126,862.5

FY16 9.86 78,182.19

FY17 3.49 81,068.4

Total: 313.22 1,222,812.09

Page 61: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

44

Annex 5. Beneficiary Survey Results

n/a

Page 62: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

45

Annex 6. Stakeholder Workshop Report and Results

n/a

Page 63: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

46

Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR

The GoN submitted a detailed ICR with updated data and information that will be included

in the main body and annexes of this ICR. Below are three sections of the GoN ICR that

provide a concise overview of Bank and Borrower performance, lessons learned, and

overall observations of RSPD

Performance of the Borrower and the Bank

Performance of Government

Government as per its road transport policy has approved RSDP as a key infrastructure

development project for mid-western and far-western development regions of the country.

The main responsibility of the government is to ensure adequate annual budget for the

project and to create conducive environment at project site and in project management

offices for smooth implementation of the project activities. Likewise the government plays

a vital role in coordinating inter-ministerial, inter-departmental and inter-agencies for

resolving project issues and problems related to them.

In most cases government has extended maximum support to the project and encouraged

for speedy implementation. Allocation of overall annual budget and government

counterpart fund was never a problem. However delayed approval of budget and release of

budget seldom affect the project activities.

Amendment of Road Board Act is one of the project output indicators, which has yet not

been achieved. The Government has already tabled the act in the parliament, but it is still

under discussion process in parliament sub-committee.

In overall performance of the government towards the execution Road Sector Development

Project is always positive, encouraging and sensitive.

Performance of Executive Agency

Ministry of Physical Infrastructure and Transport (MOPIT) as an executive agency plays a

pivotal role in implementing the project in smooth manner. Guidance and instruction from

MOPIT were always found to be very fruitful and constructive. It has provided important

support to prepare annual work program, financing plans and other policy level activities.

Deputation of required project staffs is also done by the ministry. MOPIT carries out

monitoring and evaluation of the project in regular basis. Since MOPIT being a line

ministry all important communication between project and government are done through

this office.

Monitoring and evaluation mechanism adopted by the ministry is not adequate and it needs

basic improvement for better feedbacks to the project.

Frequent transfer of project staffs in different levels has hampered the project progress in

many occasions. This has been mentioned in Bank’s aide memoires several times. Project

staffs should be designated for fixed time period so that the activities can run in systematic

manner.

Performance of Implementing Agency

Page 64: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

47

Implementing agency has established a separate project coordination team at Foreign

Cooperation Branch. Deputy Director General is responsible for the overall coordination

and monitoring of the project. Senior Divisional Engineer is the Project Coordinator for

RSDP. The team is supported by the subordinate staffs and equipped all logistic facilities.

During the period of project duration team’s effort to make project a success is very

commendable. However the team has been disturbed repeatedly by discontinuity of

supporting staffs, less experience in donor funded projects and even frequent transfer of

higher authorities within the Department. This has resulted in delayed preparation of

implementation progress reports, audit reports and other technical and financial reports.

Periodic maintenance works are sporadically spread out all over the country and those were

managed by various division offices. Due to lack of well experienced staffs financial

management and even other works management had been cumbersome job and reporting

system was occasionally late and incomplete. Monitoring of such activities was a problem.

Likewise institutional strengthening component activities are also managed by respective

branches and units of the Department and structured monitoring is lacking. Department has

to improve the monitoring and evaluation mechanism in order to streamline wide spread

activities and to achieve the project goal.

Performance of the Bank

The World Bank is always supportive to the RSDP project and has provided necessary

assistance to make the project success. Bank’s persistent and continuous effort has helped

to resolve many issues and problems raised during the implementation. Particularly

safeguard compliance issues were minutely addressed by Bank mission team while visiting

the site and discussing with concerned authorities. The monitoring work carried out by the

Bank is commendable. Comments, remarks, advices and recommendations provided in

aide memoire after each mission were very fruitful for solving issues, expediting project

works and streamlining the outstanding problems and lagging behind activities. Bank’s

endeavor for maintaining the technical, financial, institutional, social and environmental

discipline as agreed in PAD and grant/credit agreements has established definite norms and

motivated the project staffs including consultants and contractors. As a result despite of

various impediments project objectives have been achieved to great extent. All the time

missions’ attitude and their suggestions were within the agreed standards and norms and

were directed to the success of the project.

Lessons Learnt

Road Sector Development Project is being implemented since eight years and it covers

remote hilly areas of Mid-western and Far-western Development Regions of Nepal. Its

scope of works includes almost all activities for which the Department of Roads is

responsible. Road upgrading, periodic maintenance, road safety works and institutional

strengthening and policy reform are dynamic activities DoR is striving to improve and

continue for long period. Lots of feedback was received from RSDP for continuing the

institutional endeavor. Likewise national construction industry has also gained substantial

experiences and opportunities for enhancing its capacity and capabilities. Some of the

major lessons learnt from the project are as follows:

a. Project development objective adopted by RSDP is very relevant for providing

reliable and safe all weather access to poor people from remote hilly areas of the

Page 65: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

48

country. Similar objectives have to be continued in future as well by the

government policies and departmental targets.

b. Road construction in high mountains is a challenging and cumbersome job which

needs lots of technical and financial resources and takes long time for completion.

Unpaved roads are not sustainable and high standard roads are not feasible. But

RSDP has shown that upgrading the recently build tracks to all weather road

standards with moderate standard of pavement is cost effective and efficient in

service delivery to the people of remote areas.

c. Well-constructed Otta Seal pavement is cost effective particularly in low volume

traffic roads. Construction materials are easily available and construction

technology is very simple. However certain technical parameters have to be

maintained strictly which is yet to be disseminated to all stakeholders. Some study,

research and investigations have to be carried out on Otta Seal pavement based on

the already constructed such pavement in different environments of hill and Terai

of Nepal. Result of such studies shall develop technical papers, guidelines and

manuals. Technical training on Otta Seal construction should be organized for all

levels of technicians from government offices, consultants and contractors.

d. Road maintenance is still not getting sufficient priority and pace of deterioration of

existing roads is very high. RSDP has given great emphasis on the periodic

maintenance as a result condition of road in strategic road network has improved

substantially. DoR should continuously emphasize on the maintenance and it

should be planned and executed in a systematic manner. Sufficient budget should

be allocated for maintenance annually.

e. Road safety component should be included in all roads more aggressively so that

accident rate could be minimized. It should be integrated with safety awareness

programmes to be conducted in different levels and groups.

f. Construction and maintenance of bridges were not the part of original RSDP, which

seems to be a bit departure from the project objective of providing all weather roads

to people from remote areas. Bridges and other cross drainage structure should

always be entailed in project component.

g. Slope stabilization activities also received less attention in RSDP. Particularly in

hill roads slope stabilization is one of the main concerns which should be dealt very

sensitively. Landslide, road blockage, accidents etc. could be substantially reduced

if slope stabilization issues are addressed in time.

h. Small size civil contracts have attracted many national contractors, where as it

failed to attract international contractors. Contracts involving international

contractors can help to develop national construction industry through transfer of

knowledge in terms of project management, site management, resource

management and technology transfer.

i. Joint venture provision in civil contract should be elaborated in the sense that

capable and lead partner manages the contract at site. Otherwise, in many occasion

it was found that the inferior/junior partner handles the contract and lots of

Page 66: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

49

problems and issues crop up due to lack of experience and competency resulting

delay in completion and even termination of the contract.

j. Coordination with all stakeholders including road users, road neighbors,

government offices, private agencies and other public institution is very essential

for the success of project. Project information should be transparently disseminated

to all stakeholders in every stage of project so that they can understand the project

objectives and accordingly contribute their effort for the success of project.

k. Acquisition of land, public and private properties required for the project is very

difficult task, which needs lots of coordination and cooperation among various

agencies. Concerned district administration office, land revenue office, district

survey office, forest office, project affected persons and local consultative forums

should be made aware of all project objective, construction activities, schedules and

plans for carrying out the project works. They should be convinced that without

successful completion of land acquisition and resettlement action plan construction

work cannot be implemented.

l. For the smooth implementation of any donor assisted construction project it is very

essential that the concerned government offices such as Ministry of Finance,

Finance Comptroller Office, and Auditor’s General Office etc. are aware of project

details including grant/loan agreements and their conditions.

m. Programme approach for the implementation of the project will help to solve many

issues developed during the project period. Institutional commitment from

concerned agencies shall be assured so that implementation process can be

expedited.

n. There are many incidents which affected the implementation of project such as

adverse weather condition, strike/bandh called by different local and national

groups, shortage of construction materials including fuel due to various reasons and

even unforeseen site conditions. Conditions of contract of civil works should

explicitly spell out the provisions and solutions for such incidents so that the issues

could be resolved without losing the time.

Conclusion

Implementation of Road Sector Development Project has revealed that such infrastructure

development project can deliver lots of benefits to the people of remote hilly areas of Nepal.

Government should encourage preparing such infrastructure development projects in

cooperation with bi-lateral and multi-lateral donor agencies so that more and more all

weather, safe and locally sustainable road access will be available for poor people from

remote areas.

However such project should always entail cross drainages including bridges, slope

stabilization works, road safety measures and have very effective social and environmental

safeguard activities including transparent resettlement and rehabilitation action plan and

environmental management plan.

Page 67: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

50

The World Bank as an important and major development partner should continue to work

together with the government in such types of vital projects which will support to alleviate

poverty in remote rural areas and help to promote the overall social and economic

development of the area.

Page 68: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

51

Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders

n/a

Page 69: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

52

Annex 9. List of Supporting Documents

Aide Memoires

February 25-March 22 2007

June 3-12 2007

September 10-18 2007

March 9-13 2008

October 15-23 2009

March 12-19 2010

August 30-September 6 2010

December 19-28 2010

July 16-26 2011

July 23-27 2012

February 4-8 2013

August 26-September 4 2013

March 20-31 2014

September 16-26 2014

January 19-28 2015

July 29-August 6 2015

February 29-March 4 2016

September 1-9 2016

Country Partnership Strategy for Nepal, FY 2014-18, Report No. 83148-NP

Financing Agreements – Road Sector Development Project

January 31, 2008, Grant No. H339-NEP

March 4, 2011, Grant No. H629-NP, Credit No. 4832-NP, (AF)

Implementation Status and Results (ISR) Reports

Sequence 1-15

Interim Strategy Note for Nepal, January 22, 2007, Report No. 38119-NEP

Ministry of Physical Infrastructure and Transport, Department of Roads, Road Sector

Development Project, Second Trimester Report of FY 2015-16

Nepal Road Sector Assessment Report, 2014

Nepal: Transport Sector Policy Note, March 31, 2014

Project Appraisal Document on a Proposed Grant in the Amount of SDR 27.8 Million

(USUS$42.6 Million Equivalent) To Nepal. For a Road Sector Development

Project, Sustainable Development Department South Asia Region, Report No.

40698 – NP, November 6, 2007

Project Paper on a Proposed Additional Credit in the Amount of SDR 26.60 Million

(USUS$41.26 Million Equivalent) and Proposed Additional Grant in the Amount

of SDR 21.70 Million (USUS$33.74 Million Equivalent) to the Government of

Nepal for a Road Sector Development Project, Sustainable Development Unit,

Nepal Country Unit, South Asia Region, Report No: 57154-NP, October 27, 2010

Page 70: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

53

Annex 10. Notes on Accessibility, Time Savings, and Employment Impacts of the

Project

A) Beneficiary Accessibility to RSPD Upgraded Roads

1. The GoN, in September 2014, commissioned the Accessibility Study. The approach

was to use a Geographic Information Systems (GIS)-based tool to measure the accessibility

of beneficiary district residents to roads supported by RSDP. The tool was developed

during the preparation of the GoN’s 2007-16 Priority Investment Plan, and was based

primarily on terrain and population models using DoR, census, and GIS data,

complemented by research and analysis in a project-focused Accessibility Study Report.

More specifically:

Baseline road network data of project districts was taken from the database of

Strategic Road Network (SRN) of DOR’s statistics 2011/12;

2011 population census data (with a projection for 2015 population level) and 2001

population census data (with a projection for 2008 population level) were used in

respectively used for the ex-ante and ex-post population estimates; and

A project-based terrain model established 20-minute and 4-hour accessibility

profiles used to inform relevant PDO indicators.

2. The following table summarizes the results of the Accessibility Study Report:

Time

Band

Estimated Road Accessible Population

Without

RSDP

With

RSDP

Additional

Population

Percentage

Increase (%)

Female

Beneficiary

Population

20

minute

195,730 (9%) 328,144

(15%)

132,414 6 70,179 (53%)

4 hours 1,103,810

(51%)

1,655,347

(76%)

551,537 25 292,314 (53%)

B) Time Savings and Economic and Social Centers in Project Districts

3. In addition to the Accessibility Study Report described above, the GoN

commissioned a project-focused Socio-economic Impact Study to identify the socio-

economic status of the households within “zones of influence” of upgraded roads,

specifically focusing on travel time, cost saving, and access to social services. Overall,

Page 71: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

54

1,914 sample households were surveyed, with a total population of 11,781, (52.5% male;

47.5% female).

4. This study presented the following findings which informed PDO indicators:

Travel distance to all-weather road decreased from 42.2 km to 1.5 km (96.4%

decrease);

Travel time to all weather road decreased from 561 to 17 minutes (96.9%

decrease);

Travel time to social services decreased 51.4% (educational services by 60.8;

hospital by 58%; market centers by 56%; district headquarters by 46.5);

Travel time to economic centers decreased from 225 to 112.5 minutes (1.9 hours;

50% decrease);

Travel time to market centers decreased from approximately 170 minutes to 75

minutes, to district headquarters from 280 to 150 minutes after road upgrades.);

and

Travel time to key social centers decreased from 154.5 to 73.5 minutes (1.2 hours;

52% decrease).

5. The following tables summarize the results – by upgraded road section, of the

Accessibility Study Report:

S.N. Road Section

Secondary

School

College/

Campus HP/SHP Hospital

Market

Centers

District

Headquarters

Before After Before After Before After Before After Before After Before After

1. Satbanjh-Tripurasundari 22 21 78 47 34 23 93 43 66 32 102 53

2. Satbanjh-Gokuleshwor 31 29 213 100 35 34 319 154 85 47 313 154

3. Khodpe-Kalangagad 55 38 147 84 52 42 303 149 41 28 342 204

4. Tallodungeshwor-Dailekh 54 44 119 62 58 55 175 62 64 45 149 47

5. Surkhet-Khidkijyula 86 73 574 290 71 65 566 300 558 294 539 305

Average: Original Financing 50 42 239 122 50 45 301 147 182 99 296 156

6. Gokuleshwor-Darchula 50 42 120 58 109 89 311 135 86 62 264 166

7. Kalangagad-Chainpur 44 29 67 45 44 36 497 141 272 96 254 120

8. Chhinchu-Jajarkot 129 61 273 63 74 55 146 109 100 60 478 263

9. Sitalpati-Musikot 37 31 76 70 85 82 194 87 147 88 209 140

10. Khidkijyula-Jumla 69 33 300 46 83 31 256 68 209 53 247 64

Average: Additional Financing 62 39 193 55 79 58 275 101 163 60 269 146

Aggregate Average 58 40 212 83 62 51 286 120 170 75 280 150

Page 72: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

55

S.N. Road Section

Secondary

School

College/

Campus HP/SHP Hospital

Market

Centers

District

Headquarters

Before After Before After Before After Before After Before After Before After

Note: Average of travel time to social service center computed based on the total travel time to household and

total number of household travelled to visit service center.

C) Employment creation

6. Although not discussed in the project documents, employment creation was listed

among the PDO indicators of the project. The employment refers to direct engagement of

people on road construction and maintenance sites by contractors during the life of the

project. PDO Indicator No. 7 measures the combined number of persons employed while

PDO Indicators 8 to 11 disaggregate the numbers into various categories of beneficiaries:

Male, Female, Dalit and Janajatis. The employment target were substantially exceeded. As

against the original target of generating 2.5 million person-days, the project generated

employment of 6.68 million person-days.

7. The reported numbers appear sufficiently credible. DoR has submitted a

comprehensive set of spread sheets that summarize several aspects of the employment,

including the DoR labor utilization norms, labor cost analysis, labor-based road work

activities and labor utilization summary along the various roads. The employment data

reported by DoR is summarized in the table below.

Employ

ment

generat

ed

(person

days)/N

PRm

Employ

ment

generate

d

(person

days)/$

m

Employ

ment

generat

ed

(person

days)/k

m

Total

Employment

generated

(person days)

Employ

ment

generate

d

(person

days)/N

PRm

Employment

generated

(person

days)/$m

Employm

ent

generated

(person

days)/km

Total

Employment

generated

(person days)

Caste 81.57 8,157 445 682,519 172 17,175 1,627 1,437,155 2,119,674

Ethnic 126.23 12,623 688 1,056,229 266 26,580 2,517 2,224,063 3,280,293

Dalit 49.29 4,929 269 412,442 104 10,379 983 868,465 1,280,907

Local 94.20 9,420 513 788,246 198 19,836 1,879 1,659,782 2,448,028

Non-Local 162.89 16,289 888 1,362,944 343 34,298 3,248 2,869,902 4,232,845

Male 231.57 23,157 1,262 1,937,642 488 48,760 4,618 4,080,021 6,017,663

Female 25.52 2,552 139 213,549 54 5,374 509 449,662 663,211

Total 257.09 25,709 1,401 2,151,190 541 54,134.41 - 4,529,683 6,680,874

RSDP Summary of employment data

Upgrading works

Total

Employment

generated

(person days)

Ethnicity

Origin

Gender

Periodic Maintenance

Category Sub-category

Page 73: World Bank Documentdocuments.worldbank.org/curated/en/304061483126953394/...2016/12/22  · Document of The World Bank Report No: ICR00003916 IMPLEMENTATION COMPLETION AND RESULTS

56

MAP