Upload
ko-ranmarwadi
View
5
Download
0
Embed Size (px)
DESCRIPTION
Managing Project Delay : Choosing the right activity for acceleration.
Citation preview
Managing Acceleration Original Schedule Before Project Start
Project Status as of 22 Nov 2014
Owner has directed the Contractor to accelerate the works so as to finish according to Project Completion ( 30 Dec 2014)
3 days reduction in Activity G
Is it possible to accelerate on Activity C??
Activity Cost per Day vs Possible Days to be accelerated ABCDEFGHI
Activity Cost per day$5K$10K$6K$500 $5K$2K$1K$500 $2K
Estimated day to accelerate222221322
Question: Identify the activities for the most cost effective way to accelerate works.