Upload
christian-hoover
View
218
Download
1
Tags:
Embed Size (px)
Citation preview
Workshop on Technology Development for reaching
250 MT (19-20)
Mahanadi Coalfields LimitedMahanadi Coalfields Limited
Trend and Coal production projection
0.00
50.00
100.00
150.00
200.00
250.00
300.00
in M
T
in MT 110.44 127.00 150.00 167.00 187.00 222.00 250.00
13-14 14-15 15-16 16-17 17-18 18-19 19-20
Estimated demand & Gap
Demand of coal IN MT (at 100% satisfaction level) as per FSA/LOA
Year 15-16 16-17 17-18 18-19 19-20
Demand 199.00 242.00 242.00 242.00 242.00
Prod 150.00 167.00 187.00 222.00 250.00
Gap 49.00 75.00 55.00 20.00 -8.00
Projected Coal production upto 2019-20
0.00
100.00
200.00
300.00
in M
T
On-Going 79.95 101.45 115.75 132.25 160.75 172.00
Completed+ existing 47.05 48.55 51.25 54.75 57.25 41.00
Future 0.00 0.00 0.00 0.00 4.00 37.00
TOTAL 127.00 150.00 167.00 187.00 222.00 250.00
14-15 15-16 16-17 17-18 18-19 19-20
Year 14-15 15-16 16-17 17-18 18-19 19-20
UG 1.50 1.50 1.50 1.50 1.50 1.50
OC 125.50 148.50 165.50 185.50 220.50 248.50
TOTAL 127.00 150.00 167.00 187.00 222.00 250.00
Coal production projection Year wise upto 2019-20Coal production projection Year wise upto 2019-20
Coal & OB Projection
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
400.00
Co
al-M
T, O
B-M
Cu
M
Coal 127.00 150.00 167.00 187.00 222.00 250.00
OB 94.00 177.00 202.00 231.00 275.00 351.00
14-15 15-16 16-17 17-18 18-19 19-20
Additional Shovel required to achieve 250 Mty by 2019-20
Capacity 15-16 16-17 17-18 18-19 19-20 Total
34 Cum 2 1 03
20-22 Cum 1 4 2 4 11
9-10 Cum 7 27 35 5 4 78
5-6.5 Cum 3 6 8 - - 17
2.5-4.3 Cum - 4 2 - - 6
Grand Total 115
Replacement of Shovel
Existing
14-15
15-16
16-17
17-18 18-19
19-20
Total
10 Cum 12 -
4.5 -6.5 Cum 40 2 2 4
2.5 to 4.3 Cum 37 2 4 5 2 1 14
Capacity 15-16 16-17 17-18 18-19 19-20 Total
35 T 7 8 31 - - 46
50/60 T 48 108 139 - - 295
85-100 T 63 229 328 55 53 728
190 T - 6 36 20 52 114
240 T - 20 20 - - 40
Total 1223
Additional Dumper required to achieve 250 Mty by 2019-20
Replacement of Dumper
Existing
14-15
15-16 16-17
17-18
18-19 19-20
Total
50/60 T 284 34 31 66 17 10 - 158
Additional Dozer required to achieve 250 Mty by 19-20
Capacity 15-16 16-17 17-18 18-19 19-20 Total
770-850 HP(with Ripper attachment) 4 17 9 5 3 38
410 HP 15 25 41 9 9 99
Replacement of Dozer
Existing 14-15 15-16 16-17 17-18 18-19 19-20
Total
410 HP 75 9 20 1 16 2 - 48
320 HP 31 - - 1 5 1 - 7
Additional Drill required to achieve 250 Mty by 2019-20
15-16 16-17 17-18 18-19 19-20 Total
250 mm 8 31 46 9 8 102
150-160 mm 12 26 30 4 5 77
Replacement of Drill
Existing
14-15 15-16 16-17 17-18 18-19 19-20 Total
250 mm 34 1 4 1 6
160 mm 55 7 6 1 3 2 19
Additional Surface Miner required to achieve 250 Mty by 2019-20
15-16 16-17 17-18 18-19 19-20 Total
3000-3800mm
3 8 14 3 4 32
Additional Loading machine (Pay loader) required to achieve 250 Mty by 2019-20
15-16 16-17 17-18 18-19 19-20 Total
>5 cum 5 11 13 - - 29
>10 cum - 1 4 3 4 12
Replacement Loading M/C(Pay loader)
Existing
14-15 15-16 16-17 17-18 18-19 19-20 Total
>5cum 10 4 1 5
Additional equipment required for UG upto 2019-20
Capacity Nos Existing Replacement
Continuous Miner
1.4 to 4.6 M 2
SDL 1 cum 9 18 18
Low HeightSDL
0.8 cum 6
Low HeightSDL
1 cum3
LHD 1.2 cum 2 29 20
LHD 2.7 cum 4
Roof Bolter Quad bolter 2
Shuttle Car 15 Te 6
Conveyor Belt Conveyor 11800 m
Roof Bolter 15
Tube/pipe conveyorRequirement/
Capacity
Hingula 5 Km
Bhubaneswari 3.5 km
Other P&M ( other than HEMM) requirement to achieve 250 MTOther P&M ( other than HEMM) requirement to achieve 250 MT
Washery
Jagannath washery 10 Mty
Hingula washery 10 Mty
Kulda washery 10 Mty
Basundhara washery 10 Mty
Siarmal washery 10 Mty X 4
Lakhanpur integrated 20 Mty & 10 Mty
Other P&M ( other than HEMM) requirement to achieve 250 MTOther P&M ( other than HEMM) requirement to achieve 250 MT
Kaniha/Gopalji SILO 30 Mty
Lingaraj SILO 16 Mty
Bhubaneswari SILO 20 Mty
Ananta SILO 15 Mty
Bharatpur SILO 15 Mty
Hingula SILO 15 Mty
Gopalprasad SILO 15 Mty
Talabira-II &III SILO 20 Mty
Lakhanpur SILO 30 Mty
Kulda SILO 10 Mty
Siarmal SILO 40Mty
Rapid Loading System including SILO requirement to achieve 250 MTRapid Loading System including SILO requirement to achieve 250 MT
Technological Development & Mechanization of Mines Proposed
Present technologyProduction level
in 19-20SDL/LHD with Bord & Pillar in UGMan-riding system in UG 1.5 MT
Dragline & Shovel-Dumper combination for OB removal , Loader-Tipper for coal production in OCSurface miner for blast free coal production in OC 248.5 MT OITDS, GPS for better monitoringFuture technologyContinuous miner in UGHigher capacity Shovels & DumpersPipe conveyor for coal transportationRipper dozer for blast free OB removal in OCRLS with SILO for faster loading of wagons
Award of Contracts
Sl Projects Key Contracts for EPC, OB removal, coal removal etc.
Timeline
1 Kaniha OCP Award of contract for MDO Sep-172 Siarmal OCP Award of contract for MDO Dec-16
Issues with BEML (A) Delay in supply of spare parts. Spare parts of a module is not
supplied in full rather it is supplied in piecemeal due to which repair of particular assembly and equipment is delayed.
(B) BE-1600 Hydraulic Excavator 9.5 cum. 06 nos. supplied to MCL
are going under frequent breakdown, due to Failure of engines, Hydraulic pumps & Hydraulic tubes, Cooling system and other components since its commissioning.
The performance of BEML :
Year 2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
% Availability
Model
Present
population
BE 1600 D 6 - 79 66 55 39 45 50
BE 1000 D 12 - 84 71 68 54 52 53
BE 1000 E 5 69 64 72 69 57 66 69
The performance of BEML :
Year 2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
% Breakdown
Model
Present
population
BE 1600 D 6 - 14 29 41 58 51 46
BE 1000 D 12 - 10 23 27 42 44 43
BE 1000 E 5 27 32 24 27 40 30 27
(C) The performance of BH-100 Ton Dumpers after warranty period is very poor due to failure of Engines, Transmission and other components. Performance is as below :
Year 2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
% Availability Present population 29 Model BH-100 (100T) - 63 76 61 55 34 38
(C) The performance of BH-100 Ton Dumpers after warranty period is very poor due to failure of Engines, Transmission and other components. Performance is as below :
Year 2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
% Breakdown Model Present
population
BH-100 (100T) 29 - 30 19 35 42 63 59
(D) Recently, supplied BH-60 Ton Dumpers are giving problems like Cabin Vibration, Regular failure of suspension, Air Conditioning compressor mounting bolt loosening problem, Sensors are not working, Camera monitoring foundation bracket failure & Transmission pump failure etc.
(E) Recently supplied BD-355 Dozers are also not performing to the mark and giving troubles like :
Automatic release of blades sometimes Misalignment of cabin Non functioning of Air Conditioner Fuel Injection Pumping problem Starting problem etc.
ISSUES WITH M/S.H.E.C., RANCHI
There is general delay in supply of equipment as well as spare parts.As HEC is facing financial constraints, they are demanding advance payment for supply of equipment for recently ordered 10 cum. Electric Rope Shovel
ISSUES WITH M/S. PROMTRACTOR (JSC), RUSSIAPerformance of 15 nos. 410 HP Dozers are very very poor due to abnormal failure of engine & transmission even in warranty period. The performance is as below :
M/s. Promtractor (JSC), Russia has no Indian service provider for supply of spare parts and maintenance and also not supporting well for supply of spare parts and services.
Year 2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
Company M/s. Promtractor (JSC), Russia
% Availability
Model Present Populat
ion
Promtractor T-25.01CB-1 15 - - 71 53 31 24 11
% Breakdown
Model
Promtractor T-25.01CB-1 - - 23 43 67 74 88
All HEMM should be supplied with Guaranteed Spare Parts Supply (GPS) or Maintenance and Repair Contract (MARC) for life time.
SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT
Guarantee for initial 2-3 years is meaningless as machine will perform initially better than when it gets older after 03 years. Hence, guarantee for later period is more important.
Cost of equipment quoted is very less but spare parts are very costly which ultimately result into higher cost of production. If life cycle cost is adopted this can be eliminated.
Buy back system is to be incorporated in case of spare parts which are not consumed during warranty period. Some manufacturers are reluctant for life time guarantee due to uncertainty in foreign currency fluctuation. This problem can be sorted out by incorporating currency escalation/de-escalation clause.
SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT
4-5 years satisfactory performance may be introduced instead of one year as per existing standard NIT.
At least 30-40% of the tendered quantity may be considered for meeting the prove ness criteria instead of at least one number as per existing standard NIT.
Tender finalization should be 60/40 basis as per earlier system to have a check on L-1 bidder both in price as well as performance.
The equipment which are not having base in India should not be given chance for participation in open tender as there is also problem of spare and service support because of non availability of India Agent. There should be a provision of consignment store having major population nearer to the project.
Modification in Proveness criteria