Upload
kamin
View
74
Download
0
Embed Size (px)
DESCRIPTION
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation. Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings Group (VSC). Topics. Typical Vacuum Instrumentation Cold & RT beam vacuum Cryostat insulation vacuum LHC & LEP inputs - PowerPoint PPT Presentation
Citation preview
Workshop on cryogenic & vacuum sectorisation of the SPL
Vacuum Sectorisation
Paul Cruikshank, CERN
Technology Department (TE)Vacuum Surfaces & Coatings Group (VSC)
Topics
· Typical Vacuum Instrumentation
· Cold & RT beam vacuum
· Cryostat insulation vacuum
· LHC & LEP inputs· LHC Vacuum sectorisation · LEP cavity experience
· Sectorisation Variants for SPL· Advantages / Disadvantages
09-11-092Vacuum Sectorisation
Typical Beam Vac Config
09/11/09Vacuum Sectorisation 3
Typical Insulation Vac Config
·
09/11/09Vacuum Sectorisation 4
LHC; Arcs and LSS
Arcs: - 8 x 2.8 km = 22.4 km - cryomagnets in a continuous cryostat
LHC arcLHC LSS
LSS (Long Straight Sections): - up- and downstream of the experiments - 8 x 2 x 250 m = 4 km - room temp and standalone cryo-magnets
Cryogenic distribution line QRL
LHC Vacuum Overview
6
IP7IP8
LHC b
ARC IR8 LDS DS ARCIR8 RDSIR7 R
TI8
2456 m 170 m 269 m
beam 2
beam 1
> 300 beam subsectors
LHC Vacuum Overview
• A few numbers….
Characteristic Quantity for LHC machine & distribution line (QRL)
Insulation vacuum system length 22,4 km & 25 km
Welds ~ 250 000 (90 000 in-situ)
Weld length ~ 100 000 m
Elastomer joints ~ 18000
Elastomer joint length ~ 22 000 m
Multi-layer insulation ~ 9 000 000 m2 or 200 m2/m of cryostat
Vacuum subsectors 234
Vacuum subsector length 214 m (machine) & 428 m (QRL)
Vacuum subsector volume ~ 80 m3
Fixed turbo pumps 178
Nominal turbo pumping speed 0,25 l/s/m of cryostat
Fixed vacuum gauges 974
Mobile turbo pumping groups 36
Mobile primary pumping groups 36
LHC Vacuum Sectorisation
· LHC Sectorisation Working Group setup in 1995· Consider beam vacuum, insulation vacuum, cryogenic
layout· Increased flexibility ?· Reduce down-time ?· Analyse types of intervention
· Short – diode replacement, weld repair,instrument repair· Long – change of cryomagnet
· Additional equipment required?· Implementation Cost ?
· LHC Project Report #60 – September 1996· Quantifications, recommendations, (dis)advantages,
costs 09/11/09Vacuum sectorisation 8
LHC Sectorisation
· Long Straight sections· Low density of cold magnets (30+20+10+10m cryostats
in 250m) & lots of RT equipment – needed helium distribution line
· Beam vacuum sectorisation at each cold warm transition (CWT)
· Arc· Coherent vacuum & cryogenic subsectors to allow local
warm-up of 2.8 km continuous cryostat· Vacuum barriers and helium plugs every 214 metres -
compromise between staged installation, leak localisation, partial warm-up, additional heat inleaks, limit degraded vacuum
· No beam vacuum sectorisation in 2.8 km continuous cryostat
· QRL· Separation of QRL vacuum from magnet vacuum to
allow staged reception and leak localisation in long cryostats
09/11/09Vacuum sectorisation 9
Insulation vacuum sectorisation
LHC ARC: CRYOGENIC AND INSULATION VACUUM BASELINE DESIGN
Q7R Q9R Q11R Q13R Q15R Q17R Q19R Q21R Q23R Q25R Q27R Q29R Q31R Q33R Q33L Q31L Q29L Q27L Q25L Q23L Q21L Q19L Q17L Q15L Q13L Q11L Q9L Q7L
A B A B A B A B A B A C D A B A B A B A B A B A B A
Insulation Vacuum sectorization:
Magnet vacuum barriers Jumper vacuum barriers Cryogenic line vacuum barriers
Cold-mass sectorization:
Bus-bar plugs Safety relief valves Cooldown and fill valves
QRL vacuum jacket
Magnet vacuum vesselQ7R Q9R Q11R Q13R Q15R Q17R Q19R Q21R Q23R Q25R Q27R Q29R Q31R Q33R Q33L Q31L Q29L Q27L Q25L Q23L Q21L Q19L Q17L Q15L Q13L Q11L Q9L
Insulation Vacuum (3)
11
FBDC
KC'XYLE
V1V2
W
Z
LHCmagnetcryostat
QRLcryostat
Jumpers Vacuumbarriers
Baseline ‘short interventions’in insulation vacuum subsectors
• Scenario from LHC Project Report 60• Vacuum barriers every 214m
• n-2…. floating, cold, under vacuum• n-1 thermal buffer, RT, under vacuum• n intervention, RT, vented, W opened• n+1 thermal buffer, RT, under vacuum• n+2…. floating, cold, under vacuum
• With subsector length of 214m, it is necessary to warm-up 642m of the 2.8 km continuous cryostat
nn-1
Eg repairs on diode, busbar, line Y, helium leak….but no intervention on beam vac
n-2 n+1 n+2
Sectorisation of LEP RF CavitiesBeam Vacuum
• Commissioning and installation• During the installation and commissioning, the RF cavities
shall stay under vacuum to:• Limit the contamination by dusts
– Without any sectorisation, several venting will be required, increasing the risk of dust contamination.
• Preserve the RF commissioning on surface– Venting always implies repeating partly the RF commissioning
• During the pre-commissioning on the surface, absorber blocks have to be installed on the other side of the sector valves to absorb the accelerated electrons emitted by field emission. Once installed in the LEP tunnel, the sector valves were the absorbers.
• Modules were warmed individually to change tuners or couplers.
Sectorisation of LEP RF CavitiesBeam Vacuum
• RF processing is required to increase the accelerating field above 6 MV/m• Injection of helium (5.10-6 mbar, reading on the gauge) onto
the cold (4.5 K) RF cavity.
• Sequence is as follow:• Installation of a pumping group with an helium injection line (4 h)• Bake out (24 h)• Helium injection (3 h)…RF processing…• Helium pump down (10 h minimum) needs a partial warm-up to
release the condensed helium
Need that each module is sectorised to allow for an RF processing
SPL Sectorisation Variants
09/11/09Vacuum sectorisation 15
Continuous
SegmentedOption B
SegmentedOption A
Typical Insulation Vac Config
· Cost for vacuum system:
· Draft estimate from S. Calatroni
· Includes instrumentation, controls, cabling, in-situ leak test
· Insulation vacuum subsector ~ 90 kCHF
· Beam vacuum ‘cell’ ~ 90kCHF (cold) + 90kCHF (RT with valves)
09/11/09Vacuum sectorisation 16
SPL Sectorisation Variants
Volume types Max ‘Segmented’ Max ‘Continuous’
Insulation vacuum volumes - cryomodule
35((10+5)+6+(12+2))
3200m+90m+212 m
Beam vacuum volumes- cryomodule + intermodule
7135+35+1
73+3+1
Insulation vacuum volumes- helium distribution line
5 ?106m*5
0 or 1530m
Total vacuum volumes 111 10
09-11-09Vacuum sectorisation 17
Design aspects – vacuum
· Advantages· More modular design· Minimise cold equipment –
access, alignment, repairs, upgrades, unecessary outgassing, leaks, etc
· Modules are complete & tested before installation
· Disadvantages· More vacuum equipment
eg cold to warm transitions, intermodules
· More vacuum instrumentation
· Advantages· Compact longitudinal
layout – fewer CWT, fewer RF contacts
· Helium transfer line can be integrated – less vac systems
· Disadvantages· Beam vacuum sectors
long- cold sector valves don’t exist!
· Some sensitive equipment is imprisoned in cryostat - needs vacuum compatibility and validation
09-11-09Vacuum Sectorisation 18
Segmented Continuous
Installation aspects – vacuum
· Advantages· Minimise tunnel work and
problems - modules are complete and tested before installation
· Fewer problems treated on-line
· Staged acceptance tests· Decoupling of problems
· Disadvantages· Beam and insulation
vacuum systems are exposed to tunnel environment – dust contamination?
09-11-09Vacuum sectorisation 19
Segmented Continuous
Repair aspects – vacuum
· Advantages· Reduced search zone· Decoupling of repair and
other activities · Limit zones of warm-up
and opening of vacuum system – cost & downtime
· Disadvantages· Difficult access at cold to
warm transitions – not std interconnect design
· Advantages· Less tasks for systematic
repairs on modules – venting, repumping..
· Disadvantages· Equipment will see more
thermal cycles – create leaks?
09-11-09Vacuum Sectorisation 20
Segmented Continuous
Commissioning aspects – vacuum
· Advantages· Precommissioning before
installation· Staged tests – smoothing
of resources, earlier identification of problems
· Decoupling of problems· Recommissioning of
‘weak’ module possible· Disadvantages
· More volumes to commission
· Disadvantages· Cavities need to be
recommissioned if vented· RF processing with helium
required for field above < 6 MV/m – complicated
· Movable blocks or valves to absorb field emission electrons?
09-11-09Vacuum Sectorisation 21
Segmented Continuous
Operational aspects – vacuum
· Advantages· Limit zone of degraded ins
vacuum (helium leak)· Easier diagnosis of
problems· Disadvantages
· More equipment (fixed pumping systems & valves)
· More interlocks· More risk of equipment
failure· More maintenance
· Advantages· Simpler controls· Redundancy in fixed
pumping systems· Disadvantages
· MCI would affect more equipment
09-11-09Vacuum Sectorisation 22
Segmented Continuous
SPL Vac Sectorisation – next steps
· Which sectorisation variants are not possible?
· Strong vacuum constraints need to be identified & investigated – eg can we expose cavity to tunnel air, etc.
· Constraints for other technologies to be confirmed
· For retained variants, advantages and disadvantages presently expressed qualitatively, now need to be quantified in time, manpower and expenditure.
· Are there other vacuum aspects to add?
· Continue to get feedback from other operational machines 09-11-09Vacuum Sectorisation 23
Last Slide
Thanks for your attention
09-11-09Vacuum Sectorisation 24
ITER/CERN Collaboration - LHC Insulation Vacuum - Paul Cruikshank - 25 June 2009
Semi-standalone cryo-magnet- typical installation and leak test sequence -
HELIUM CIRCUIT
JUMPER
CRYO-MAGNET
CRYOGENIC DISTRIBUTION LINE (QRL)
CRYO-MAGNET
BEAM VACUUM TUBES
PUMP + DETECTOR
PUMP +
DETECTOR DETECTOR DETECTOR