Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
AGNICO-EAGLE MINES LIMITEDTechnical Update
December 17, 2009
With its emphasis on , an exceptional record of creating shareholder value, and one of the most robust profiles in the industry, Agnico-Eagle Mines Limited has emerged as the gold stock of choice.
quality
growth
Member of the World Gold Council www.gold.org Meadowbank, Canada
Forward Looking Statements
The information in this document has been prepared as at December 17, 2009. Certain statements contained in this document constitute “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward looking information under the provisions of Canadian provincial securities laws. When used in this document, the words “anticipate”, “expect”, “estimate”, “forecast”, “will”, “planned”, and similar expressions are intended to identify forward-looking statements or information.
Such statements include without limitation: statements regarding timing and amounts of capital expenditures and other assumptions; estimates of future reserves, resources, mineral production and sales; estimates of mine life; estimates of future internal rates of return, mining costs, cash costs, minesite costs and other expenses; estimates of future capital expenditures and other cash needs, and expectations as to the funding thereof; statements and information as to the projected development of certain ore deposits, including estimates of exploration, development and production and other capital costs, and estimates of the timing of such exploration, development and production or decisions with respect to such exploration, development and production; estimates of reserves and resources, and statements and information regarding anticipated future exploration; the anticipated timing of events with respect to the Company's minesites and statements and information regarding the sufficiency of the Company's cash resources. Such statements and information reflect the Company's views as at the date of this document and are subject to certain risks, uncertainties and assumptions, and undue reliance should not be placed on such statements and information. Many factors, known and unknown could cause the actual results to be materially different from those expressed or implied by such forward looking statements and information. Such risks include, but are not limited to: the volatility of prices of gold and other metals; uncertainty of mineral reserves, mineral resources, mineral grades and mineral recovery estimates; uncertainty of future production, capital expenditures, and other costs; currency fluctuations; financing of additional capital requirements; cost of exploration and development programs; mining risks; community protests; risks associated with foreign operations; governmental and environmental regulation; the volatility of the Company's stock price; and risks associated with the Company's byproduct metal derivative strategies. For a more detailed discussion of such risks and other factors that may affect the Company’s ability to achieve the expectations set forth in the forward-looking statements contained in this document, see the Company'sAnnual Report on Form 20-F for the year ended December 31, 2008, as well as the Company's other filings with the Canadian Securities Administrators and the U.S. Securities and Exchange Commission. The Company does not intend, and does not assume any obligation,to update these forward-looking statements and information. Marc Legault, a Qualified Person and the Company’s Vice-President, Project Development, reviewed the technical information disclosed herein. For a detailed breakdown of the Company’s reserve and resource position see the February 18, 2009 press release on the Company’s website. That press release also lists the Qualified Persons for each project.
2
Note To Investors
Note to Investors Regarding the Use of Non-GAAP Financial MeasuresThis document presents estimates of future "total cash cost per ounce" and "minesite cost per tonne" that are not recognized measures under United States generally accepted accounting principles ("US GAAP"). This data may not be comparable to data presented by other gold producers. These future estimates are based upon the total cash costs per ounce and minesite costs per tonne that the Company expects to incur to mine gold at the applicable projects and do not include production costs attributable to accretion expense and other asset retirement costs, which will vary over time as each project is developed and mined. It is therefore not practicable to reconcile these forward-looking non-GAAP financial measures to the most comparable GAAP measure. A reconciliation of the Company's total cash cost per ounce and minesite cost per tonne to the most comparable financial measures calculated and presented in accordance with US GAAP for the Company's historical results of operations is set forth in the notes to the financial statements included in the Company's Annual Information Form and Annual Report on Form 20-F, for the year ended December 31, 2008, as well as the Company's other filings with the Canadian Securities Administrators and the SEC.
3
Corporate Strategy
■ Increase gold production■ Targeting 2010 gold production of 1.0 – 1.1 million oz■ Internal expansions expected to contribute to steady
production growth through 2014
■ Grow gold reserves■ Record reserves of 18.1 million ounces*■ Four of six deposits may ultimately exceed 5 million oz
■ Acquire small, think big■ Continue with successful acquisition strategy
■ Be a low-cost leader■ Expect to remain below average total cash cost
producer long term
■ Maintain a solid financial profile■ Credit facilities of $900M with a large syndicate of
banks
* See attached reserve and resource tables
Strategy Remains Focused On Per Share Metrics
4
Status Update: Progressing As PlannedAll Q3 issues well under way to being resolved
5
Nov mill production rate –2,110 tpdNov. mill grade – 2.17 g/t AuNov. leach pad ore stacked –50.9 kt
Sept. mill production rate –893 tpdSept. mill grade – 1.41 g/t AuLeach pad ore stacked – 8.4kt
Longer than expected commissioning of tailings filter presses.
Pinos Altos
Nov prod. rate – 3,107 tpdNov Au prod. – 14,505 ozNov recovery rate – 76%
Q3 prod. rate – 1,956 tpdQ3 Au prod. – 18,284 ozQ3 recovery rate – 64%
Gold production below expectation due to low recovery rates; Cost high due to low tonnage milled
Kittila
Budgeting 50% dilution going forwardQTD recovery rate – 81%
Up to 75% dilutionQ3 recovery rate – 75%
Lower than expected production due to 57% ore dilution. Lower than expected mill recoveries
Lapa
QTD grade – 2.14 g/tQ3 avg. grade – 1.59 g/tMining lower grade ore from eastern mining blocks
Goldex
November production rate –7,070 tpd
Average production rate of 6,509 tpd
Lower production rate as a result of a longer than expected maintenance shutdown
LaRonde
Q4 to November 30September 30 – Q3IssueOperation
Industry Leading1 Gold Production Growth EstimatesStudies on three potential internal expansions underway
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
2009E 2010E 2011E 2012E 2013E 2014E$300
$320
$340
$360
$380
$400
$420
LaRonde Goldex Lapa KittilaPinos Altos Meadowbank Creston Mascota Total Cash Cost (US$/oz)
Payable Gold Production(ounces)
1 For an intermediate or senior gold producer
6
Consistent Focus On Per Share Production GrowthGold production (oz) / 1000 shares
7
0
1
2
3
4
5
6
7
8
9
10
2008A 2009E 2010E 2011E 2012E 2013E 2014E
■ Located in mining-friendly regions of low political risk■ 100% owned, with low total acquisition costs■ Each region has long-term mining camp potential
Operations At A GlanceFive mines now operating. One new gold mine nearing completion
LaRondeQUEBEC, CANADA
GoldexQUEBEC, CANADA
KittilaKITTILA, FINLAND
MeadowbankNUNAVUT, CANADA
Fraser Institute’s ranking 1 Fraser Institute’s
ranking 1 Fraser Institute’s ranking 14
Fraser Institute’s ranking 44
Fraser Institute’s 2008/2009 ranking of 71 mining jurisdictions
Fraser Institute’s ranking 1
LapaQUEBEC, CANADA
Fraser Institute’s ranking 28
Pinos AltosCHIHUAHUA, MEXICO
8
2010 - A Year of Transition
■ Increase gold production■ LaRonde continues to perform■ LaRonde Extension on time and budget■ Goldex has exceeded daily rates of 8,500 tpd■ Grades back to reserve estimates■ Record production at Kittila in November■ Grades improving at Lapa in December■ Pinos Altos ramping up■ Meadowbank start up in January
■Grow gold reserves■ Record reserves of 18.1 million ounces*■ Four of six deposits may ultimately exceed 5 million oz■ Over 300,000 metres of drilling planned in 2010
* See attached reserve and resource tables
9
LaRonde – Canada
■Operations ■ Steady state operations■ Averaging 7,070 tpd November■ Will achieve production targets
■ 2010 Exploration■ Focus on resource conversion, additional
potential at depth and to the East■ Drilling possible extension of Westwood zone on Ellison■ Drilling program at depth
Good production and cost performance continues
Au reserves (m oz) 5.0
Average reserve grade (g/t) 4.3
Measured & Indicated resource (m oz) 0.4
Inferred resource (m oz) 3.0
Estimated average production (k oz/yr) 320
Est. LOM (years) 13
2010 exploration budget $4M
10
LaRonde – Canada
■ LaRonde Extension■ Shaft sinking completed to a depth of 2,854 metres■ No ground control issues experienced■ Start of production from Extension expected in 2011.
On time, on budget■ Changeover on schedule
Au reserves (m oz) 5.0
Average reserve grade (g/t) 4.3
Measured & Indicated resource (m oz) 0.4
Inferred resource (m oz) 3.0
Estimated average production (k oz/yr) 320
Est. LOM (years) 13
2010 exploration budget $4M
11
2010 LaRonde Extension – Shaft Schedule
12
Last bench : Nov. 14th 2009
Changeover end : Jan. 23th 2010
Exploration Plan 2010-2014
Puits PennaPuits IPuits Bousquet IIPuits Bousquet I Puits II
LaRonde Operations Forecast
LaRonde Operations Summary 2010 2011 2012 2013 2014
Ore milled (000's tonnes) 2,592 2,580 2,428 2,373 2,300
Grade: Gold (g/tonne) 2.40 2.31 2.91 4.00 4.75 Silver (g/tonne) 58.35 66.65 51.17 31.29 21.30 Zinc 3.41% 3.04% 2.26% 0.92% 0.55% Copper 0.26% 0.29% 0.30% 0.34% 0.32%
Mill recovery: Gold 90% 90% 92% 93% 93% Silver 86% 85% 86% 85% 79% Zinc 89% 88% 85% 70% 66% Copper 81% 85% 85% 86% 86%
Payable metal produced: Gold (ozs) 179,700 172,100 208,200 283,100 328,600 Silver ('000 oz) 3,551 4,110 3,179 1,867 1,141 Zinc (tonnes) 67,133 58,576 41,861 12,925 7,111 Copper (tonnes) 5,056 5,693 6,130 6,476 5,979
Mining/Milling Costs (C$/tonne) $75 $75 $79 $79 $79
Total Cash Cost per ounce $220 $186 $289 $370 $359
LaRonde Challenges
■ 14.4 km of lateral development (waste handling)
■ Zone 21 - new zone - grade and continuity
■ Production below 215 = 44 % tonnes / 71% ounces of gold
■ Underhand mining
LaRonde Opportunities
■Mature and highly qualified workforce
■Qualified management
■ Higher metal prices than budgeted
■ LaRonde Extension is on plan and on budget
Goldex – Canada
Operations
■ Processed and hoisted more tonnage than budgeted (+100,000 tonnes)
■More tonnes drilled and blasted than plan
■Mill has achieved record of 8,500 tpd
■ Costs on plan
■Grade Q4 back to reserve levels – mining sequence issues have been resolved
Drilling and blasting approximately 1.5 years ahead of schedule
Au reserves (m oz) 1.6
Average reserve grade (g/t) 2.1
Measured & Indicated resource (m oz) 0.0
Inferred resource (m oz) 0.9
Estimated average production (k oz/yr) 175
Est. LOM (yrs) 8
2010 exploration budget $3M
17
Goldex – Canada
■ Project■ Increase production rate increase from 6,900 tpd to
8,000 tpd (an additional 20,000 oz/yr), starting in late-2011 on schedule
■ Crushing plant commissioned in January■ Capital cost approximately $10 million. Estimated
IRR 76%
■ 2010 Exploration■ Focus on resource conversion, exploration to west,
east and at depth
Drilling and blasting approximately 1.5 years ahead of schedule
Au reserves (m oz) 1.6
Average reserve grade (g/t) 2.1
Measured & Indicated resource (m oz) 0.0
Inferred resource (m oz) 0.9
Estimated average production (k oz/yr) 175
Est. LOM (yrs) 8
2010 exploration budget $3M
18
2010 Mining Plan
CentralWest East
66 level65 level
73 level 73 level
2010 Mining Plan
58 level55 level
76 level76 level
49 level
Production Longitudinal - Dec 31st, 2009
CentralWest East
66 level65 level
73 level 73 level
58 level55 level
76 level76 level
49 level
Production Longitudinal - Dec 31st, 2010
2010 Mining Plan
Goldex Operations Forecast
Goldex Operations Summary 2010 2011 2012 2013 2014
Ore milled (000's tonnes) 2,520 2,597 2,880 2,880 2,880
Grade: Gold (g/tonne) 2.20 2.18 2.07 2.00 1.94
Mill recovery: Gold 91% 92% 92% 92% 92%
Payable metal produced: Gold (ozs) 164,000 166,800 175,000 169,500 164,800
Mining/Milling Costs (C$/tonne) $23 $22 $22 $22 $21
Total Cash Cost per ounce $318 $307 $332 $342 $329
3 Year Exploration Plan
38 Level
73 Level
5000m to test the West area
(1 500 m per year for 150m spacing)
GEZ Deep
West of GEZ
EAST
Of
GEZ
Exploration Area for 3 years 60m to 90m spacing below GEZ and150m spacing West of GEZ
10 000m to test the eastern area
( 150m spacing)
View Looking North
R-Zone
Evaluation of the potential of the zone and drilling.
Drilling under GEZ DEEP to explore deeper
Continue to explore South Zones
Goldex Challenges
■Ground control management of three mining blocks■ potential impact on mucking and grade
■ Drilling and blasting schedules to maintain stope inventory – ground control
■ Vibration management■ community relations■ research & development with
explosive supplier
■ Surface crusher commissioning
■ LaRonde – concentrate circuit■ optimization still in progress
Goldex Opportunities
■ Potential increase in tonnage toward year’s end
■ Drilling and blasting 1.5 years ahead of schedule
■Mining of S zone with ramp to M Zone in vicinity
■ Smelting contract (higher recovery)
■ Experienced management & workforce
Lapa – Canada
■Operations■ Tonnage hoisted to date has exceeded plan■ Ore development according to plan■Grades have been reconciled with mill■Mill recoveries approaching design■ Still plagued by excessive dilution (50% – 65%)
Efforts focused on reducing mining cycle time
Au reserves (m oz) 1.1
Average reserve grade (g/t) 8.8
Measured & Indicated resource (m oz) 0.1
Inferred resource (m oz) 0.2
Estimated average production (k oz/yr) 115
Est. LOM (yrs) 6
2010 exploration budget $3M
26
Lapa – Canada
■ Dilution – potential solutions■ Reduce cycle time – two 6 yd scoops on order■ Improve ground support – two rock bolters■ Reduce stope size■ Improve blasting■ Increased dilution incorporated in mine plan – 50%
Efforts focused on reducing mining cycle time
Au reserves (m oz) 1.1
Average reserve grade (g/t) 8.8
Measured & Indicated resource (m oz) 0.1
Inferred resource (m oz) 0.2
Estimated average production (k oz/yr) 115
Est. LOM (yrs) 6
2010 exploration budget $3M
27
Lapa Operations Forecast
Lapa Operations Summary 2010 2011 2012 2013 2014
Ore milled (000's tonnes) 516 540 539 539 536
Grade: Gold (g/tonne) 8.13 7.88 7.91 7.90 8.05
Mill recovery: Gold 86% 87% 86% 85% 85%
Payable metal produced: Gold (ozs) 115,600 118,500 118,400 116,500 118,300
Mining/Milling Costs (C$/tonne) $125 $122 $123 $123 $123
Total Cash Cost per ounce $506 $515 $519 $525 $515
Proposed Exploration Program
Queenston
Maritime (option)
0.8 Km 2011
Sediment Contact Target
0.7 Km 2010
Zulapa Corridor Target
Lapa Challenges
■ Mill recovery lower than budgeted
■ Higher dilution than budgeted
■ Mining just-in-time, no flexibility
■ Lower Opex costs (more flexibility with ramps connected – May 2010)
■ Higher throughput
Lapa Opportunities
■ Potential flotation project
■ Lower dilution
■ Experienced management
Kittila – Finland
■Operations■Open pit has achieved targets last four months■Underground development on plan■First stope being blasted with positive results
■ Process Plant■Availability has improved – 94% in November■Record gold production of 14,504 ounces in November■Reserve model reconciles with mill
Overall mill recoveries now approaching 80%
Au reserves (m oz) 3.2
Average reserve grade (g/t) 4.7
Measured & Indicated resource (m oz) 0.3
Inferred resource (m oz) 2.5
Estimated average production (k oz/yr) 150
Est. LOM (yrs) 14
2010 exploration budget $16M
32
33
Kittila – Mill Optimization UnderwayGold production progressing as expected (Nov. 09 / Results)
10
20
30
40
50
60
70
80
90
J F M A M J J A S O N D0
2000
4000
6000
8000
10000
12000
14000
Gold Payable(ounces)
Forecasted / May 2009
Gold Recovery(%)
4,514 oz
13,771 oz23,000 oz
33,500 oz
RealisedAu Ounces :
Au Recovery : Realised Forecasted / May 2009
13,300 oz
18,284 oz
14504 oz
Estimate
34,900 oz E
Kittila Operations Forecast
Kittila Operations Summary 2010 2011 2012 2013 2014
Ore milled (000's tonnes) 1,034 1,030 1,045 1,100 1,100
Grade: Gold (g/tonne) 5.25 5.32 5.16 5.26 5.05
Mill recovery: Gold 84% 86% 88% 89% 89%
Payable metal produced: Gold (ozs) 147,100 151,500 153,200 166,100 159,500
Mining/Milling Costs (EUR/tonne) € 49 € 55 € 52 € 52 € 53
Total Cash Cost per ounce $502 $541 $515 $497 $525
Kittila – Expansion Opportunity
■ Studying production rate of 300,000 ounces per year
■ Examining underground mining via shaft access
■Orebody remains open at depth and along strike
■ Eleven drills currently operating
Examining large capacity increase. Potential reserve increases at depth
Mineral Resource
Probable Reserve
Latest Drill Holes
Open Pit Outline 0 1000
metres
Section 36940N
35
2010 Minesite Exploration
36
37
Mine
Reduced flexibility as the pit matures
Underground preproduction for 2011
Mill –reliable operation
Improvements in recoveries
Maintenance
Improve maintenance of fleet and process plant
Training, education and communication
Tailings
Management – water balance
Cost control
Kittila Challenges
38
Kittila Opportunities
Maintenance
Better control on maintenance and potential cost reduction
Human resources –most senior positions have been filled
Employees are becoming more confident – young crew
Cost control - with stable operations, cost reduction opportunities exist
Exploration upside
091123 – 125kg – 3880 oz
Mine – underground and open pit are operating according to plan
Mill – potential to increase tonnage – 3,700 tpd already achieved
Pinos Altos – MexicoPlant commissioning in progress. Commercial production Q4 2009
■Operations■Open pit and underground - according to plan■ Plant undergoing commissioning and ramp up■ Issue with pressure filter commissioning and capacity■ Has negatively impacted mill availability■ Reserve model not yet reconciled■ Development of Mascota has started
■2009 Exploration ■ Potential to develop additional satellite
deposits (Cubiro, Sinter, San Eligio)■ Focus on resource conversion, expansion of
Pinos Altos zones, Reyna de Plata, Creston Mascota
Au reserves (m oz) 3.6
Average reserve grade (g/t) 2.7
Measured & Indicated resource (m oz) 0.4
Inferred resource (m oz) 0.2
Estimated average production (k oz/yr) 165
Est. LOM (yrs) 20
2010 exploration budget $4M
39
Pinos Altos Operations Forecast
* Assumes slower than expected ramp-up to full production levels.
Pinos Altos Operations Summary 2010* 2011 2012 2013 2014
Heap Leach: Treated tonnes (000's) 765 898 842 798 707
Gold grade (g/tonne) 0.96 1.38 1.58 1.42 1.40 Silver grade (g/tonne) 30.32 47.32 51.22 53.05 61.08
Gold recovery (%) 52% 68% 68% 68% 68% Silver recovery (%) 7% 12% 12% 12% 12%
Gold production (ozs) 12,500 27,100 29,000 24,800 21,600 Silver production ('000 oz) 52 164 166 163 167
Mill: Treated tonnes (000's) 1,212 1,525 1,525 1,525 1,525
Gold grade (g/tonne) 3.67 3.78 4.16 3.75 3.85 Silver grade (g/tonne) 75.56 108.79 145.75 91.52 87.60
Gold recovery (%) 96% 97% 97% 97% 97% Silver recovery (%) 52% 54% 55% 53% 53%
Gold production (ozs) 138,400 178,900 197,000 177,300 182,100 Silver production ('000 oz) 1,542 2,854 3,899 2,373 2,266
Total Payable Production: Gold production (ozs) 150,900 206,000 226,000 202,100 203,700 Silver production ('000 oz) 1,594 3,018 4,066 2,536 2,432
Mining/Milling Costs (US$/tonne) $42 $39 $40 $40 $40
Total Cash Cost per ounce $401 $272 $188 $299 $294
41
Indicated DDHAu Oz 33,000
ResourceAu Oz 41,000
ResourceAu Oz 38,000
Pinos Altos
■ Stabilizing filter operation
■ Short term mine planning
■ Underground production - learning curve
■Maintaining community relations
■Grade reconciliation
Challenges
Opportunities
■Open Pit Optimization
■ Accelerate Underground Production
■ Increase Heap Leach Tonnage and efficiency
■ Accelerate development of satellite zones – ie El Sinter
■ Evaluate potential expansion
■ Experienced management and work force
Pinos Altos Opportunities & Challenges
Meadowbank – CanadaPlant start-up on schedule for Q1 2010
Construction
■ Project currently one month away from start up
■ Performance in the pit has been better than plan
■Over 600,000 tonnes of ore stockpiled Dec 31st
■ All necessary supplies and consumables for project operation on site
■ Power plant completed
■ Plant commissioning has started
Au reserves (m oz) 3.6
Average reserve grade (g/t) 3.5
Measured & Indicated resource (m oz) 1.5
Inferred resource (m oz) 0.4
Estimated average production (k oz/yr) 350
Est. LOM (yrs) 10
2010 exploration budget $6M
44
Meadowbank
45
■ Dewatering of Portage Lake according to plan
■ Required operating labour force hired and on site
■ Plant commissioning has started
■ Dike construction on schedule
■ Capex has been a challenge
Meadowbank Operations Forecast
* Assumes commissioning phase extended by three months.
Meadowbank Operations Summary 2010* 2011 2012 2013 2014
Ore milled (000's tonnes) 2,235 3,037 3,103 3,103 3,103
Grade: Gold (g/tonne) 4.47 3.78 4.16 4.60 4.79
Mill recovery: Gold 93% 94% 94% 94% 95%
Payable metal produced: Gold (ozs) 299,900 347,300 390,400 433,300 455,600
Mining/Milling Costs (C$/tonne) $68 $67 $65 $64 $64
Total Cash Cost per ounce $460 $534 $469 $414 $399
■ 2009 Exploration■ Focus on resource conversion and expansion of Vault,
Goose South and Portage
2010 Minesite Drilling
2010 Minesite Drilling
Sealift 2009
Power Plant
Process Plant
Mining Equipment
Mining Equipment
■ Process plant ramp-up with tail end construction … -45C…
■ Process plant capacity - 8 500 tpd
■ Stockpile management vs frozen stockpile
■ Reserve reconciliation
■ Narrow mining widths with large equipment – dilution?
Meadowbank Challenges
Meadowbank Opportunities
■ Block model confirmed
■ Potential increase in tonnage through mill – under evaluation
■ Potential higher production rate due to revised mine plan
■ Reserve reconciliation - potential grade upgrade
■ Experienced management team
■Qualified workforce
Estimated Production & Cash Costs
Estimated Payable Gold Production and Total Cash Costs per Ounce 2010 2011 2012 2013 2014
Payable Gold ProductionLaRonde 179,700 172,100 208,200 283,100 328,600Meadowbank 299,900 347,300 390,400 433,300 455,600Goldex 164,000 166,800 175,000 169,500 164,800Lapa 115,600 118,500 118,400 116,500 118,300Kittila 147,100 151,500 153,200 166,100 159,500Pinos Altos 150,900 206,000 226,000 202,100 203,700Pinos Altos - Creston Mascota - 60,700 52,300 40,900 36,100
1,057,200 1,222,900 1,323,500 1,411,500 1,466,600Total cash costs per ounceLaRonde $220 $186 $289 $370 $359Meadowbank 460 534 469 414 399Goldex 318 307 332 342 329Lapa 506 515 519 525 515Kittila 502 541 515 497 525Pinos Altos 401 272 188 299 294Pinos Altos - Creston Mascota - 322 344 423 493
$399 $398 $379 $399 $393
Estimated Capital Expenditures
Capital Expenditures ($ 000's) 2010 2011 2012 2013 2014
Sustaining Capital 259,881$ 178,020$ 100,000$ 100,000$ 100,000$ LaRonde Depth Extension 64,872 - - - Creston Mascota 51,715 - - -
Total Project Capital Expenditures 376,468 178,020 100,000 100,000 100,000
Capitalized Commissioning Costs 50,000 - - - - Capitalized Exploration 36,076 - - - -
Total Capital Expenditures 462,544$ 178,020$ 100,000$ 100,000$ 100,000$
2010 Operating & Capital Budget
Meadowbank50,000Capitalized Commissioning Costs
UG development37,267Pinos Altos
Construction51,715Creston Mascota
Tailings, development64,872LaRonde Extension
UG development, mill57,315Kittila
301,231 metres*36,076Exploration
462,544Total:
Dikes, fuel farm95,300Meadowbank
Development, NH328,175Lapa
M Zone development13,785Goldex
NH3 plant28,039LaRonde
StatusCostOperation
Capital Expenditures
* Total drilling including mine sites
■ Complete “Clean up residual construction”■Meadowbank, Pinos Altos, Kittila
■Optimize operations – cost control■ Lapa, Kittila, Pinos Altos,
Meadowbank
■Maintain consistency at LaRonde, Goldex
■ Focus on internal growth opportunities■ Sinter, Mascota, Kittila, Goldex
Meadowbank
■ Focus on regional exploration
■ Competitive environment
■ Focus on employees – our strength
2010 Operating Strategy
60
Exploration Overview &
2010 Budget
Agnico-Eagle Mines Limited
2010 Exploration Budget
■ 2009 exploration budget was $54M■ Targeted 3.0 to 3.5 million ounces of gold discovered, including
1.0 to 1.5 million ounces of reserves - $30 to $35 per ounce
■ 2010 exploration budget is $75M■ Targeting 3.0 million ounces of gold discovered, including 1.0
million ounces of reserves
■ 2010 emphasis on resource exploration (discovery) & conversion (grow reserves)
■ 297 kilometres of exploration drilling planned in 2010
■Objective 20 Moz to 21 Moz reserves by end of 2010
61
“Our experience has demonstrated that the lowest cost ounces are added by the drill bit” - Ebe
62
$7M (16.5 km)W. Canada
Grassroots Exploration
Quebec $5M (26.5 km)
Mexico $8M (21.0 km)
Finland $7M (20.0 km)
Nunavut $5M (16.0 km)
Nevada $7M (15.9 km)
Total $39M (115.9 km)
$6M (25.4 km)Meadowbank
Mine Site Exploration
Kittila $16M (80.6 km)
Goldex $3M (28.2 km)
Pinos Altos $4M (19.4 km)
LaRonde $4M (19.3 km)
Lapa $3M (8.0 km)
Total $36M (180.9 km)
2010 Exploration Budget
2010 Exploration Budget - Finland
63
SUURIKUUSIKKO REGIONAL
Target: Suurikuusikko and Suurikuusikko West structures
HAKO, RETU, KETOLA,KARHU, KORPI and UKKO
Planned drilling 18,000 mResource estimate = HAKO and RETUDeveloping 3D Model for Suurikuusikko structure
CENTRAL LAPLAND AND OIJÄRVIGrassroot projects- geochemical targeting/ structuresPlanned drilling 2,000 mGround geophysics
20,000 metres, $7 million
Kittila Mine
2010 Exploration Budget - Finland
64
20,000 metres, $7 million
Kittila Mine
2010 Exploration Budget - Kittila
Mineral Resource
Probable ReserveSignificant Drillholes
Open Pit Outline
0 1000
metres
Section37270N
4.8730.7Central lensSUU-09-005E
5.244.0East lensSUU-09-005D
8.284.2East lens #2and
4.7910.5East lens #1SUU-08-001F
10.325.8EastSUU-08-001E
7.2112.0CentralSUU-09-005C
6.106.5Roura EastROU-08-003C
Gold (g/t)True Width(metres)LensDrill Hole
9.625.5East lensSUU-09-006C
8.880.9Ketolaand
4.133.7KetolaKET-09-004
6.115.9East lens #2and
4.984.7East lens #1SUU-09-006B
4.147.12Centraland
7.865.6East SUU-08-001G
Gold (g/t)True Width(metres)LensDrill Hole
Suuri Inferred Resource at Depth1.4 Moz, 7.8 Mt@ 5.6 g/t
Roura Resource Potential at Depth
Kittila Longsection - Suuri & Roura Open at Depth (November 2009 Results)
Mineral Resource
2010 Exploration Budget - Kittila
400 m
East OPEN
OPEN
Open Pit Outline
Probable Reserve
Mineralization
Central
3.3 g/t Au / 3.2 m
6.1 g/t Au / 6.5 m
New Resource Potentialat Depth New Roura East Lens
Central RouraPit Outline
Central Roura Cross Section 37270N (November 2009 Results)
2009 exploration results
suggest:
Suuri and Roura zones link
and are open to north and at
depth
A new lens at Roura
2010 Exploration Budget - Kittila
67
■ Resource to Reserve conversion program■ 25 km drilling■ Suuri South, Rimpi, Ketola
80,600 metres, $16 million
Ketola Etela Suuri Roura Rimpi
OPENOPEN
OPENOPEN
OPENOPEN
OPENOPEN
2010 Exploration Budget - Kittila
68
Resource exploration■ 56 km drilling■ Roura Deep, Rimpi, Ketola and Suuri at depth ■ Directional drilling
80,600 metres, $16 million
OPENOPEN
OPENOPEN
OPENOPEN
OPENOPEN
Ketola Etela Suuri Roura Rimpi
2010 Exploration Budget - Mexico
69
$MillionsDDH km2010 BudgetMine Site 19.4 4Regional 21 8
Total 2010 40.4 12
2010 Exploration Budget - Pinos Altos Regional
Cerro ColoradoCerro Colorado
Santo NiSanto NiññooOberonOberon de Weberde Weber
El ApacheEl Apache
de Plata Fault
Santo Niño Fault
Reyna
Mine Mine SiteSite
Cubiro Cubiro
CrestonCrestonMascotaMascota
SinterSinter
San Eligio San Eligio Cerro de PlataCerro de Plata
RefugioRefugio
21,000 metres, $8 Million
2010 Exploration Budget - Pinos Altos Regional
Section 763904 E3132000N
SIN-09-0102.1 g/t Au / 7.8 m
SIN-09-0113.3 g/t Au / 17.6 m
SIN-09-0261.7 g/t Au / 18.2 m
SIN-09-0071.1 g/t Au / 24.4 m
SIN-09-0061.1 g/t Au / 27.5 m
SIN-09-0431.4 g/t Au / 15.7 m
SIN-09-0502.9 g/t Au / 5.2 m
SIN-09-0531.8 g/t Au / 6.2 m SIN-09-036
1.2 g/t Au / 29.6 m
SIN-09-0581.0 g/t Au / 31.5 m
SIN-09-0511.3 g/t Au / 6.3 m
Significant Drillholes
Previously Released DrillholesDrillhole Intercepts
■ 2010 study heap leach satellite mining potential
■Open along strike East and West
21,000 metres, $8 Million
Sinter Longitudinal Section
2010 Exploration Budget - Pinos Altos Regional
Reyna de Plata Structure
SIN-09-0361.2 g/t Au, 20.4 g/t Ag / 29.6 m
SIN-09-0261.7 g/t Au, 20.5 g/t Ag / 18.2 m
Longsection763904E3132000N
Significant DrillholesPreviously Released Drillholes
■ 2010 study heap leach satellite mining potential
21,000 metres, $8 Million
Sinter Cross Section
2010 Exploration Budget - Pinos Altos Regional
CB-09-0092.3 g/t Au / 16.9 m
CB-09-0152.4 g/t Au / 26.2 m
CB-09-0163.7 g/t Au / 6.4 m
CB-09-0131.8 g/t Au / 21.4 m
CB-09-0071.6 g/t Au / 18.9 m
Section758413 E313659 N
CB-09-0201.2 g/t Au / 12.9 m
CB-09-0192.5 g/t Au / 4.5 m
CB-09-0252.2 g/t Au / 12.0 m
CB-09-0237.6 g/t Au / 10.5 m
Significant Drillholes
Previously Released DrillholesDrillhole Intercepts
■ 2010 study heap leach satellite mining potential■Open on strike to the East and West
Cubiro Longsection
21,000 metres, $8 Million
2010 Exploration Budget - Pinos Altos Regional
CB-09-0237.6 g/t Au, 28.1 g/t Ag / 10.5 m
CB-09-0131.8 g/t Au, 21.4 g/tAg / 21.4 m
CB-09-0252.2 g/t Au, 6.9 g/tAg / 12.0 m
Longsection758378E3136626N
CB-09-0092.3 g/t Au, 17.5 g/t Ag / 16.9 m
Significant Drillholes
Previously Released Drillholes
■ 2010 study heap leach
satellite mining potential
Cubiro Cross Section
21,000 metres, $8 Million
Cerro Colorado
Santo Nino San Eligio Oberon de Weber El Apache
exploration upside
300 m
Probable Reserve Indicated& Inferred Resource
75
Resource Conversion
San Eligio & Santo Nino UG
San Eligio & Creston MascotaDescriptionDDH km2010 Budget
Exploration 8.7
Conversion 10.7
Total 19.4
2010 Exploration Budget - Pinos Altos Minesite19,400 metres, $4 million
exploration upside
exploration upside
2010 Exploration Budget - Pinos Altos Minesite
Sect
ion
485
0E
0 200
Mineral Resource
Probable Underground Reserve
Latest Drill Holes
Current Open Pit Reserve Outline
metres
San Eligio Longsection
■ 2010 resource conversion & resource exploration at depth
19,400 metres, $4 Million
2010 Exploration Budget - Pinos Altos
2.49 g/t Au / 4.0 m
San Eligio Cross Section 4850E
■ 2010 resource conversion &
resource exploration at depth
19,400 metres, $4 Million
Quartzite
Lakes
Coordinate system UTM NAD 83 Zone 15
Gold Reserves & Resources
0 10
kilometres
VaultVault
PortagePortage
Goose IslandGoose Island
Goose SouthGoose South
Open Pit outline
PDFPDF
Granite
Volcanic
Mine Site
Mine Site Aerial View
GoslingGosling
2010 Exploration Budget - Meadowbank Minesite25,400 metres, $6 Million
Mineral Resource
Significant Drill Holes
Open Pit Outline
0 500
metres
Section 4300N
12.1Conversion
25.4
13.3
DDH km2010 Budget
Exploration
Total $6M
2010 Exploration Budget - Meadowbank Minesite
Exploration Target
Exploration Target
Conversion TargetFa
ult
Faul
t
25,400 metres, $6 Million
2010 Exploration Budget - Meadowbank Minesite
G09-143.89g/t Au / 7.0 m
G09-118.87 g/t Au / 3.0 m
■ Evaluating underground ramp exploration in 2010
Goose South Cross Section 4300N
25,400 metres, $6 Million
2010 Exploration Budget - Meadowbank Minesite
Vault Cross Section 4675N
Vault Plan map
■Open pit likely to expand to the north and east (Vault South)
25,400 metres, $6 Million
OPENOPEN
OPENOPEN
10.0 g/t / 4.5 m7.4 g/t / 3.7 m
VLT09-2756.6 g/t Au / 8 m
2010 Exploration Budget - Meadowbank Minesite
Vault Cross Section 4675N
25,400 metres, $6 Million
2010 Exploration Budget - Regional & Nunavut
Quartzite Lakes
Coordinate system UTM NAD 83 Zone 15
Gold Reserves & Resources
0 10
kilometres
Open Pit outlineGranite Volcanic
VaultVault
PortagePortage
Goose IslandGoose Island
Goose SouthGoose South
Mine Site
83
14RegionalDDH km2010 Budget
Nunavut 2Total 16
16,000 metres, $5.4 Million
PDFPDF
ShebaSheba
2010 Exploration Budget - Quebec26,500 metres, $5 Million
James Bay
Chibougamau
Abitibi
ABITIBI REGION
Ellison, Lapa trend, Casa Berardi & Blake River
20.5 km of DDH
CHIBOUGAMAU, JAMES BAY
Grassroot exploration 6 km of DDH
2010 Exploration Budget - Quebec
EllisonBo
usqu
etRi
ver F
ault
Westwood Project - 3.4 Moz
Zone 5
85
Untested
2009 Iamgold DDH confirms Westwood extension onto AEM’sEllison (2.3/19.2 incl. 4.6/6.7)
1000 m
2000 m
3000 m
1000 m
2000 m
OPE
NO
PEN
OPE
NO
PEN
Westwood extension target
1,500 m in 2010
Doyon - LaRonde Mine Trend
18 Moz of historical production and reserves
3,000 metre drillhole in progress testing for extension of Westwood onto Ellison
Puits PennaPuits IPuits Bousquet IIPuits Bousquet I Puits II
5 600m
7 500m
6 200m
2010 Exploration Budget - LaRonde19,300 metres , $4 Million
LARONDE - 19,300 metres of drilling $4 million
2010 Exploration Budget - Goldex
38 Level
73 Level
GEZ Deep18,290 m
West of GEZ
1,955 m
EAST ofGEZ
3,820 m
View Looking North
R-Zone(Compilation)
410 m to explore South Zones
28,200 metres , $3 Million
E-Zone
3,731 m
-500 m
-1,000 m
-500 m
-1,000 m
500 m
1,000 m
1,500 m
0.3 / 2.8 9.3 / 0.5
0.2 / 2.8
LV
0.3 / 2.8
19.4 / 0.4
2.1 / 0.5
0.1 / 3.1LV
LV
5.6 / 0.8
2010 Exploration Budget - Lapa8,000 metres, $3Million
700 metres drift in 2010
800 metres drift in 2011
1,900 metresconversion
6,100 metres
exploration in 2010
Level 101 exploration
drift opens new
potential along Lapa
gold trend at depth and
to east
Queenston
Maritime (option)
0.8 Km 2011
Sediment Contact Target
0.7 Km 2010
Zulapa Corridor Target
2010 Exploration Budget - Lapa8,000 metres , $3 Million
Level 101 Exploration Drift
2010 Exploration Budget - Nevada15,900 metres, $7 Million
Nevada Strategy 2010 Generate exploration property in USA and
South America Project evaluations in South America Advance West Pequop project, Nevada Joint venture in Santa Cruz, Argentina
90Total
ArgentinaUSA
2010 Budget615.9$ MillionsDDH km
115.9 7
Nevada
Santa Cruz JV
2010 Exploration Budget - Western Canada
Jennings
Jennings Property - Yukon / BC Jennings property in Yukon/BC hosts a
potentially large W-Mo skarn porphyry (200 - 400 Mt)
Jennings Target is a Logtung (Northern Dancer: the 6th largest W resource in the world with 168 Mt @0.13% WO3, 0.052% MoS2 )
2010 program: sufficient info to estimate inferred
resource scoping study to determine economic
potential baseline environmental study evaluate next step (sale, option, spin-off)
16,500 metres, $7 Million
Vancouver Strategy 2010 Generate exploration property in
Western Canada and Northern USA Project evaluations in Americas Establish links with Vancouver juniors Advance Jennings project
LaRonde site, Canada
Appendix
92
Operating Mines With Reserves Over 5M oz, Grading Over 2g/t Au
Kittila, Meadowbank and Pinos Altos have the potential to join this group of top-tier world class operating assets
93
Property Name CountryLocation Ranking*
Reserves Grade
Reserves - Contained
Total Cash Costs $/oz
Prod'n (000's oz)
(100% basis)
% Owned Operator/Significant Owner
1 Turquoise Ridge (Getchell) United States - Nevada 3 15.58 g/t 5,313,000 oz $515 165 75% Barrick Gold Corporation (Operator)2 Moab Khotsong Gold Mine South Africa 49 10.86 g/t 7,320,000 oz $379 192 100% AngloGold Ashanti Limited3 Mponeng Gold Mine South Africa 49 10.69 g/t 13,000,000 oz $249 600 100% AngloGold Ashanti Limited4 Bulyanhulu Gold Operation Tanzania 48 9.86 g/t 11,977,000 oz $620 200 100% Barrick Gold Corporation (Operator)5 Phakisa Gold Mine South Africa 49 8.05 g/t 5,300,000 oz $555 22 100% Harmony Gold Mining Company Limited6 Driefontein Gold Mine South Africa 49 7.50 g/t 18,200,000 oz $448 830 100% Gold Fields Limited (Operator)7 Obuasi Gold Mine Ghana 35 7.50 g/t 9,660,000 oz $633 357 100% AngloGold Ashanti Limited8 Evander Gold Mine South Africa 49 7.26 g/t 13,800,000 oz $572 190 100% Harmony Gold Mining Company9 Kloof Gold Mine South Africa 49 6.20 g/t 10,521,000 oz $552 643 100% Gold Fields Limited (Operator)
10 Elandsrand Gold Mine South Africa 49 6.20 g/t 7,500,000 oz $660 174 100% Harmony Gold Mining Company11 South Deep Gold Mine South Africa 49 6.10 g/t 29,486,000 oz $717 175 100% Gold Fields Limited (Operator)12 Beatrix Gold Mine South Africa 49 5.00 g/t 6,450,000 oz $507 391 100% Gold Fields Limited (Operator)13 Loulo Gold Operation Mali 33 4.90 g/t 7,400,992 oz $511 258 80% Randgold Resources Limited14 LaRonde Gold/Base Metals Mine Canada - Quebec 1 4.32 g/t 5,000,000 oz $106 216 100% Agnico-Eagle Mines Limited15 Carlin Gold Mine United States - Nevada 3 3.80 g/t 12,709,380 oz na na 100% Newmont Mining Corporation16 Olimpiada Gold Operation Russia 53 3.75 g/t 15,385,265 oz na 854 100% OJSC Polyus Gold (Operator)17 Betze-Post Gold Mine - Open Pit United States - Nevada 3 3.70 g/t 10,294,000 oz $452 1,706 100% Barrick Gold Corporation (Operator)18 Porgera Gold Operation Papua New Guinea 61 3.08 g/t 8,240,000 oz $417 660 95% Barrick Gold Corporation (Operator)19 Geita Gold Mine Tanzania 48 2.93 g/t 5,140,000 oz $728 264 100% AngloGold Ashanti Limited20 Lihir Gold Mine Papua New Guinea 61 2.83 g/t 21,778,721 oz $406 771 100% Lihir Gold Limited (Operator)21 Aksu Gold Mine Kazakhstan 56 2.55 g/t 5,796,297 oz na na 100% KazakhGold Group Limited22 Ahafo Gold Operation Ghana 35 2.33 g/t 9,380,000 oz $408 521 100% Newmont Mining Corporation
Lapa Canada - Quebec 1 8.80 g/t 1,061,000 oz na na 100% Agnico-Eagle Mines LimitedKittila Gold Mine Finland 14 4.69 g/t 3,224,000 oz na na 100% Agnico-Eagle Mines LimitedPinos Altos Mexico 28 2.68 g/t 3,593,000 oz na na 100% Agnico-Eagle Mines LimitedMeadowbank Gold Mine Canada - Nunavut 44 3.45 g/t 3,638,000 oz na na 100% Agnico-Eagle Mines LimitedGoldex Canada - Quebec 1 2.05 g/t 1,571,000 oz $419 57 100% Agnico-Eagle Mines Limited
Notes: *2008/09 Fraser Institute study ranked 71 mining jurisdictions
Source: Intierra, Fraser Institute, company websites -- March 2009
Au
min
es w
ith
rese
rves
>5m
oz,
grad
ing
>2 g
/t
Gold and Silver Reserves and Resources
Tonnes (000’s)
Gold (g/t)
Gold(ounces)
(000’s)
Proven 4,828 2.77 430
Probable 154,469 3.55 17,631
Total Reserves 159,297 3.53 18,061
Indicated 47,569 2.07 3,173
Inferred 46,603 3.84 5,760
Tonnes (000’s)
Silver(g/t)*
Silver(ounces)
(000’s)
Proven 4,172 66.74 8,952
Probable 73,404 55.83 131,759
Total 77,576 56.42 140,711
Indicated 18,817 26.31 15,919
Inferred 8,937 28.32 8,138
*Calculated grades
94
Copper, Zinc and Lead Reserves and Resources
Tonnes (000’s)
Copper(%)*
Copper(tonnes)
Proven 4,075 0.33 13,370
Probable 31,735 0.28 89,961
Total 35,810 0.29 103,331
Indicated 6,349 0.15 9,399
Inferred 4,937 0.44 21,515
Tonnes (000’s)
Zinc(%)*
Zinc(tonnes)
Proven 4,075 3.27 133,442
Probable 31,735 1.42 450,246
Total 35,810 1.63 583,688
Indicated 6,349 1.55 98,124
Inferred 4,937 0.77 38,068
Tonnes (000’s)
Lead(%)*
Lead(tonnes)
Proven 4,075 0.37 15,146
Probable 31,735 0.12 38,769
Total 35,810 0.15 53,915
Indicated 6,349 0.16 10,235
Inferred 4,937 0.08 3,946
*Calculated grades
95
Executive and Registered Office:145 King Street East, Suite 400Toronto, Ontario, Canada, M5C 2Y7Tel: 416-947-1212Toll-Free: 888-822-6714 Fax: 416-367-4681
www.agnico-eagle.com
Trading Symbol: AEM on TSX & NYSE
Sean BoydVice Chairman and Chief Executive Officer Ebe ScherkusPresident and Chief Operating OfficerDavid GarofaloSenior Vice President, Finance and Chief Financial Officer
Investor Relations:[email protected]
A solid financial position, low-cost structure, well-funded growth projects in regions of low political risk, and a focused, consistent strategy put Agnico-Eagle in a strong position to continue creating exceptional per share value.
Member of the World Gold Council www.gold.com96