Wirebonding for TOB and TEC. Susanne Kyre University of California, Santa Barbara. Wirebonding. Equipment and Personnel Scale of the project Bonding times Bond quality TEC Outlook. Equipment and Personnel. Equipment: K&S 8090 wirebonder K&S 8060 wirebonder (receive end of January) - PowerPoint PPT Presentation

Citation preview

Page 1: Wirebonding for TOB and TEC

Slide 1Susanne KyreDOE review, January 20, 2004

Wirebonding for TOB and TEC

Susanne Kyre

University of California, Santa Barbara

Page 2: Wirebonding for TOB and TEC

Slide 2Susanne KyreDOE review, January 20, 2004

Wirebonding• Equipment and Personnel• Scale of the project• Bonding times• Bond quality• TEC• Outlook

Page 3: Wirebonding for TOB and TEC

Slide 3Susanne KyreDOE review, January 20, 2004

Equipment and Personnel

Equipment:• K&S 8090 wirebonder• K&S 8060 wirebonder (receive end

of January)• Dage 3000 pulltester• Stereo microscope• Precision measuring microscope

Personnel:• 1 main wirebond technician (Julie

Stoner)• 1 backup wirebond technician

(Andrea Allen)• In the process of hiring a second

wirebond technician• 1 support technician (David Staszak)

Page 4: Wirebonding for TOB and TEC

Slide 4Susanne KyreDOE review, January 20, 2004

Scale• UCSB will build ~4000 Modules with about 10 million wirebonds (that

is 3 times the amount of wirebonds done in all of CDF; All of UCSB’s wirebonding for BaBar was 150,000 bonds, we will do that in a week)

• Full production TEC and TOB: • 15 Modules per day• 30 Hybrids per day

Page 5: Wirebonding for TOB and TEC

Slide 5Susanne KyreDOE review, January 20, 2004

Bonding times

• Starting point: Bond centers had bonding times of up to 40 minutes with about 10 bonds that didn’t stick and needed to be rebonded

• Wirebond programs now bond an entire Module or Hybrid (previously had separate programs for each row of bonds), reduced bonding time by 50%

• Wirebond programs for all Module and Hybrid types now use pattern recognition (bonding time reduction by about 2-3 minutes)

• Pure bonding time for a module < 5min, for a hybrid < 4min (CMS record)

• Additional time (set up, database entry, pull testing):

~11min for a module, ~ 8min for a hybrid

• Total processing time can be reduce by using a support technician

• Actual bonding times during mini production run: • 2.5 hours for 10 modules (one technician)

Page 6: Wirebonding for TOB and TEC

Slide 6Susanne KyreDOE review, January 20, 2004

Bond quality• CMS wirebonding spec: pull strength > 6g• Extensive pull testing was done to determine a set of standard bonding

parameters for each bonding surface

Hybrids:• We pull test 10 bonds on a test area on each PA• Average pull strength: 10.0 g, std. Deviation: 0.6g

Page 7: Wirebonding for TOB and TEC

Slide 7Susanne KyreDOE review, January 20, 2004

Bond qualityModules:

• First 20 parts of each type, pull test every 50th bond

• PA to Sensor bonds: • Average pull strength: 9.9g, std. Deviation: 0.7g

• Sensor to Sensor bonds:• Average pull strength: 8.2g, std. Deviation: 0.8g

Page 8: Wirebonding for TOB and TEC

Slide 8Susanne KyreDOE review, January 20, 2004

Bond quality

• 79 Modules and 92 Hybrids bonded so far• Faults introduced during bonding:

• 1 pinhole (first TEC module) out of ~84000 bonds• Shorts: 1 repaired short on a hybrid• Open channels: 13 on modules, 5 on hybrids• Bad channels introduced in bonding: 0.034% for modules, 0.012% for

hybrids (historically 0.5% – 2%)

Page 9: Wirebonding for TOB and TEC

Slide 9Susanne KyreDOE review, January 20, 2004

TEC production

• We will do TEC Ring 5 and 6 Module production

• TEC Module and Hybrid wirebonding:• All fixtures for Rings 5 and 6 are designed • TEC Ring 6 module carrier and wirebond fixture were built and tested• Wrote program and wirebonded 4 Ring 6 modules• Wrote program and wirebonded 6 Ring 6 hybrids

Page 10: Wirebonding for TOB and TEC

Slide 10Susanne KyreDOE review, January 20, 2004

Future plans• Produce hybrid and module carriers and wirebond fixtures

in machine shop• Write remaining wirebond programs for TEC Modules

and Hybrids• Installation and set up of new 8060 Wirebonder (end

January)• Training of new wirebond technician (mid February)• Training of wirebond technician from Mexico• Mini production run

• 2 weeks at full production capacity of 15 Modules per day (start January 26)

• Production bonding!