60
Window Installation Guide Certificate Number CMA-CM40120

Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Window Installation Guide

Certificate Number CMA-CM40120

Page 2: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly
Page 3: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-i

REV: -

Contents

IN-01 IntroductionIN-02 IntroductionIN-03 Introduction

IN-04 System ComponentsIN-05 System Components

IN-06 Step 1 Preliminary check of trim openingIN-07 Step 2 Wall underlay preparationIN-08 Step 3 Position unit in openingIN-09 Step 4 Fix off unitIN-10 Step 4a Fix of unit continuedIN-11 Step 4b Fix of unit continuedIN-12 Step 5 Tape the fixing finIN-13 Step 6 Fix cavity battens (if required by cladding type)IN-14 Step 7 Fit Cladding (weatherboard shown, example)IN-15 Step 7a Fit cladding (masonry veneer above window shown, example)IN-16 Step 7b Fit Cladding (weatherboard shown, example)IN-17 Step 7c Fit Cladding (flat Sheet types shown, example)

IN-18 Head flashings and end treatmentsIN-19 Type AIN-20 Type BIN-21 Type C

IN-22 Masonry veneer beside and above window, with steel lintel angle in courseIN-23 Masonry veneer beside and above window, with steel lintel angle fixed to lintelIN-24 Masonry veneer beside window, other cladding above windowIN-25 Masonry veneer continued, common jamb detailIN-26 StuccoIN-27 Horizontal bevel-back weatherboardsIN-28 Weatherboards with facings, Head and sill with Smartfit head flashingIN-29 Weatherboards with facings, Jamb detail with Smartfit head flashing aboveIN-30 Rusticated weatherboardsIN-31 Fibre cement weatherboardsIN-32 Horizontal profiled metalIN-33 Fibre cement sheet and flush-finished fibre cementIN-34 Plywood sheet claddingIN-35 E.I.F.S, genericIN-36 E.I.F.S, generic, top corner sealing detailIN-37 Hebel with Smartfit head flashingIN-38 Rockcote INTEGRA with Smartfit head flashingIN-39 Rockcote INTEGRA Without Smartfit head flashingIN-40 Scyon Linea weatherboard - no facingsIN-41 Scyon Linea weatherboard - with facings head & sill detailIN-42 Scyon Linea weatherboard - with facings jamb detail

Rev. Rev.Date

Dwg.No.

Dwg. Description.

Page 4: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-ii

REV: -

Contents

IN-43 Additional Details - Soffit at window / door headIN-44 Additional Details - No Smartfit head flashing with claddings aboveIN-45 Additional Details - Soffit fitted after joinery - All framesIN-46 Additional Details - Soffit fitted after joinery - BifoldsIN-47 Additional Details - Soffit fitted after joinery - Sliders / stackersIN-48 Additional Details - Full height unit to enclosed decksIN-49 Additional Details - Full height unit to sump thresholdIN-50 Additional Details - Full height unit to floorIN-51 25mm reveals (shown with BB WB cladding)IN-52 Sliding door frames (shown with BB WB cladding)IN-53 Bifold frames, head fixing. Head flashing above and no head flashing optionsIN-54 Slider and stacker frames, head fixing. Head flashing above and no head

flashing options

IN-55 Code Compliance - Product substitutionIN-56 On-site application for minor variation to approved plans (example)

Rev. Rev.Date

Dwg.No.

Dwg. Description.

Page 5: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-01

REV: -

This guide details the preparation, sequence and methods of installation of the Smartfit window and door system intobuildings.This document should be read in conjunction with BRANZ appraisal No. 868 (2014) and CodeMark™ certificate (cert noCMA-CM40120), which are included in this guide.

Product Description.

The Smartfit Window and Door installation system is a variant of the Altus Pacific suite. While the internal componentsare common to the Altus Pacific Suite, the external frame comprises of specially designed extruded aluminium sectionsand reinforced nylon injection moulded components, pre assembled to form an integral, weatherproofed window or doorready for installation in prescribed cavity wall cladding situations. The window and door units are manufactured inapproved production facilities.

The Smartfit Window and Door system enables windows and doors to be attached to buildings and made weathertightusing methods that differ from conventional detailing as outlined in NZBC Acceptable solution E2/AS1 Third Edition,Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installationas a pre finished assembly complete with integral head and jamb flashings and sill support bar. The Smartfit windowand door system incorporates integral drainage mechanisms to receive, manage and discharge water safely from theinstallation to the exterior of the building. The window or door trim openings need no special preparation prior toinstalling units other than folding the building wall underlay inwards.

Introduction

Page 6: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-02

REV: -

The Smartfit installation System can be used with following cladding types on a drained and ventilated cavity only*;

a. Masonry Veneer with 40 to 50mm cavityb. Stucco, and similar proprietary systemsc. Horizontal Bevelback Timber weatherboardsd. Horizontal rebated Bevelback Timber weatherboardse. Horizontal Rusticated weatherboardsf. Fibre Cement weatherboardsg. Proprietary Fibre Cement weatherboard systemsh. Flat sheet type claddings (FC sheet and Plywood)i. E.I.F.S, and similar proprietary systemsj. Aerated Autoclaved Concrete Panel systems (AAC)*k. Other cladding systems covered by a valid BRANZ appraisal that specify a nominal 20mm (minimum 18mm)

drained and vented cavity; or systems covered by a valid Codemark Product Certificate that specify a nominal20mm (minimum 18mm) drained and vented cavity.

l. Other cladding types not covered by the above are on application - Please contact Altus.

*May also be used in AAC panel systems that are closed cavity.

The Smartfit window or door frame outer facing is set at a fixed distance from the wall framing.Thinner cladding types will leave a larger gap to finish between cladding face and window facing.This can be overcome by selecting a larger cavity size than 20mm.Cavities larger than 20mm nominal (excluding masonry veneer) are outside the scope of the BRANZ appraisal andCodemark certification.Larger cavity sizes or variations away from the Smartfit detailing must be approved by the BCA prior to construction.

The Smartfit system can be used with any wall framing dimension depth and any thickness or type of rigid air barrier.

Special requirements

1. Wall Framing must at least protrude over slab edge2. Windows and doors are installed prior to any cladding fixing3. Wall underlay's must be either BRANZ appraised or CodeMark™ certified and be used within the limitations as stated by the manufacturer.4. Flashing tapes must be Smartfit branded tapes as supplied by the joinery manufacturer.

Introduction

Page 7: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-03

REV: -

Features of the system

The Smartfit system improves weathertightness by reducing complexity and risk and simplifies the installation ofwindows and doors into buildings. The key feature of the Smartfit system is the relocation of the weatherline and airsealaround windows and doors out to the wall underlay line, or outer framing line. Current practice as described in E2 AS1shows the weatherline reaching all the way back to the internal wall lining, which consequently requires the buildingframing in this area to be protected by waterproof tapes in case of window or installation failure. The relocation of theweatherline and airseal line is possible by moving the at risk parts of the window or door frame out into the cavity andcladding space. This places less emphasis on window and door frame joints having to perform faultlessly over theirlifetime and eliminates the need for any protective taping measures in the trim opening and air seals back at the internalwall lining line. The window or door trim space around the reveal now becomes part of the internal wall space ratherthan an external weathering area.Other benefits of the Smartfit system are improved productivity on the building site and less materials required duringinstallation. The window or door comes as a complete ready to install package with no loose parts requiring separatefitting at the building site. The window or door is simply lifted into the opening and fixed. The installation is thencompleted by taping the joinery unit to the wall underlay to create a continuation of the wall underlay weatherline.Subsequent cladding can then be applied around the unit without the need for complex cladding cuts and critical sealingdetails around flashings.

The Smartfit installation system improves the current situation and better addresses adjacent wall systemweathertightness failure with water management features at all points of the connection between a window and thecladding.The Smartfit installation system is closely aligned with E2 AS1in terms of how windows connect to claddings and howfailure water from the installation or other areas is managed. Each Smartfit detail can trace a clear path back to theequivalent E2 AS1 detail but with the Smartfit advantages added.

Key Features;

• No flexible flashing tapes required within the window or door trim opening.• Sill support bar is inclusive in the window or door sill ensuring total and permanent support.• Head flashing, head flashing end dams and cavity closer are inclusive in the window or door head.• Jamb flashings are inclusive in the window and door jambs.• Sill corner soakers and drainage blocks are inclusive with and solid fixed to window or door frames.• No cladding saw cuts are required around head flashing horns.• No P.E.F rod and expanding foam or sealant air seals required between reveal and trim opening.• Less reveal packing and fixing.• Window is taped directly to outside face of building wall underlay with Smartfit flashing tape.• Window to wall framing trim gaps are not critically sized and can be insulated.• Window and door frames are square cut for joint strength.• Windows and some door frames reside over cavity space.• Simplification removes quality and material issues and the subsequent long term risk.

Introduction

Page 8: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bottom corner soakercomplete with drainagefunction and outlet.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-04

REV: -

Window or door internal reveal

Head flashing horns for;• MV are flush with jamb facing• AAC are flush with jamb facing• EIFS are flush with jamb facing.

Masonry Veneer (MV) end dam.Fills the cavity space between headflashing horns and the backflashing.• Only required with Top hub

Window or door head(concealed under headflashing)

Window or door jamb

Window or door sill complete withintegrated support bar.

Top hub, complete with end dams.Top hub is not required when;• No head flashing is required

Window or door integraljamb flashing

Window or door fixingand taping fin - 4 sidesof unit.

Soaker drainage block out in cavityspace under mid framepenetrations (concealed)

System Components; • Masonry veneer (MV)• Aerated concrete panels (AAC)• E.I.F.S

Head flashing is integral to window ordoor unit. It is complete with drainedcavity closer.Head flashing is not required when;• Units finish hard up to soffit• Under a MV lintel angle (option)• One AAC head option is selected

Page 9: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bottom corner soakercomplete with drainagefunction and outlet.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-05

REV: -

Window or door internal reveal

Head flashing horns wraparound the front of thecladding a specifieddistance.

Scriber cap. Adjustable.Fills the space betweenhead flashing horns andface of cladding.Two sizes (depths).

Head flashing is integral to windowor door unit. It is complete withdrained cavity closer.Head flashing is not required when;• Units finish hard up to soffit

Window or door jamb

Window or door sill complete withintegrated support bar.

Top hub. Complete with end dams.Top hub is not required when;• No head flashing is required.

Window or door integraljamb flashing

Window or door fixingand taping flange - 4sides of unit.

Window or door head(concealed under headflashing)

• Weatherboard - horizontal bevelback• Weatherboard - horizontal rebated bevelback• Weatherboard - horizontal rusticated• Fibre cement weatherboards• Horizontal profiled metal• Fibre cement sheet• Plywood sheet• Stucco• Scyon Linea weatherboard

System Components;

Soaker drainage block out in cavityspace under mid framepenetrations (concealed)

Page 10: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-06

REV: -

1.2 Check trim opening for level, plumb,twist and squareness. Check outerwindow mounting surface is free from anyprotrusions and misaligned timber.

1.3 The trimmer must be fixed as such toresist torsional loads placed upon it fromthe weight of the installed and glazedwindow

1.4 Check concrete slab edge issmooth and even, devoid of spilland boxing ridges. Any substantialedge breakouts that could affectsill sealing must be reinstated

STEP 1 - Preliminary check of trim opening

1.1 IMPORTANT NOTE;The wall framing must at leastbe flush or protrude out overthe floor edge. 5mm nominal isideal.

5mm

Page 11: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-07

REV: -

Outside

Exterior line ofWall Underlay

Fix the wall underlay toframing using approvedfixings

Sill Detail (Jamb Similar)

Head Detail

STEP 2 - Wall underlay preparation

2.1 Cut the wall underlay at 45° away from each corner.2.2 Fold flaps tightly into opening and secure on all sides.2.3 Trim off excess after fixing.

The Smartfit window and door system can be used with rigidair barriers (RAB). The reveal depth is altered to suit andfixing screw length should be adjusted accordingly. No silltaping of the trim opening is required if using a RAB

External sheet bracing to wall framing must leave an evenmounting surface for the window or door to seat properly onall sides. This may require the sheet brace to run pastwindow openings or stop sufficiently short to allow for finfixing and taping to occur.

Wallunderlayfolded intoopening

Page 12: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 3 - Position unit in opening

3.1 Position unit into opening.

3.2 Push outer fixing flange hard against the framing ensuring it isevenly seated and devoid of twist. Minor shimming under outer fixingfin is permissible to eliminate twist or to position window accurately tothe reveal wall board groove or architrave.

3.4 Use full depth rectangular packers between framing and revealto level the unit if required. If the floor or trimmer is straight and level,the window or door may sit hard down.

3.5 Diagonally measure to check for square and pack reveals ifrequired.

3.6 Fix off unit as described in Step 4

3.7 Remove any packers from head reveal area

3.8 Cladding fixing starts after window install.

Note; The remaining trim gap dimension between reveal and framingis not important.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-08

REV: -

Page 13: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 4 - Fix off unit

4.2 Fixing requirements @Head & Jambs through outer fin;

10g x 32 SS screws @ 300 ctrs andnot more than 150mm fromcorners

Holes are pre machined in headand jambs for screw fixings.

4.3 Fixing requirements @ Sill.10g x 32 SS screws @ 300 ctrs notmore than 150mm from Corners.Holes are pre machined in sill forfixings. Refer to subsequent detailsfor timber or concrete sill fixing.

4.4 Reveal Fixing:The reveal is not the primary means for attaching thewindow to the building. The frequency of reveal fixingsand packers should follow good carpentry practice toprevent the reveal from being unduly flexible in service.Remove any head packers after fixing reveals.If no head flashing is present, reveal fixings at the headare required in accordance with 4.5.Sliding and hinged door jambs at lock points will requirea positive reveal fixing. Pack between reveal and houseframing and nail fix reveal to a suitable standard toresist jamb movement from potential lock loads.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-09

REV: -

4.5 Windows with head hard to soffit and no head flashingrequired (not shown);Fixings: 2 off 75mm Jolt Head Nails@ 450ctrs and not more than 150mm from each end throughreveal at head only. See IN-43 for example.

4.1 Do not fix through any plasticparts.

Note;Before attempting to install a Smartfit window unit,installers are advised to familiarise themselveswith the Smartfit window system componentsshown on Dwg. No's IN-04 and IN-05.

Page 14: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 4a - Fix off unit continued

4a.2 Fixing requirements @Head & Jambs through outer fin;

10g x 32 SS screws@ 300 ctrs and not more than 150mm fromCorners.

Holes are pre machined in head and jambsfor screw fixings.

Notes;Screw positions can be optimised at time ofmanufacture to suit window size andwindload. Screw fixing hole positions coulddiffer from those specified in this guide.

Sliding and hinged door jambs at lock pointswill require a positive reveal fixing. Packbetween reveal and house framing and nailfix reveal to a suitable standard to resistjamb movement from potential lock loads.

4a.3 Fixing requirements @ Sill.10g x 32 SS screws @ 300 ctrs notmore than 150mm from Corners.Holes are pre machined in sill forfixings. Refer to subsequent detailsfor timber or concrete sill fixing.In some case top fixing through revealor additional fixing tag up on top offloor will be required

4a.4 Reveal Fixing:The reveal is not the primary means for attaching the window to the building.The frequency of reveal fixings and packers should follow good carpentrypractice to prevent the reveal from being unduly flexible in service.Remove any head packers after fixing reveals.If no head flashing is present, reveal fixings at the head are required inaccordance with 4a.5.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-10

REV: -

4a.1 Do not fix through any plasticparts.

150mm Max 150mm Max300mm Max Ctrs

150mm Max300mm Max Ctrs150mm Max

150m

m M

ax15

0mm

Max

300m

m M

ax C

trs

Front elevation of window

4a.5 Windows with head hard to soffit and no head flashingrequired (not shown);Fixings: 2 off 75mm Jolt Head Nails@ 450ctrs and not more than 150mm from each end throughreveal at head only. See IN-43 for example.

Page 15: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 4b - Fix off unit continued

4b.4 FIXING REQUIREMENTS @Sill.10g x 32 SS screws @ 300 ctrs notmore than 150mm from Corners.

4b.2 Fixing requirements @Head &Jambs;10g x 32 SS screws @ 300 ctrs and notmore than 150mm from Corners.

4b.5 Reveal fixing:*See note 4.4 on sheet IN-09

4b.6 Fixing requirements @head & jambs.10g x 32 SS screws @ 300 ctrsnot more than 150mm from corners.

HEAD

SILL

JAMB

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-11

REV: -

Note: Use top row of holesfor fixing into timber, Usebottom row for fixing intoConcrete.

Packer

4b.3 Note: Window reveal to buildingframing trim clearances are notimportant. 5mm nominal shown allround to allow for squaring unit.

4b.1 For windows with head hard to soffitand no head flashing present (not shown);See specific detail on Dwg. No. IN-43.

NOTE: Heavy duty head flashing (shownN.T.S) is required for Bi-fold door units.See specific detail on Dwg. no. IN-53.

Minor shimming under outerfixing fin is permissible toeliminate twist or to positionwindow accurately to thereveal wall board groove orarchitrave.

Vertical and Horizontal cross section of unit

Page 16: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 5 - Tape the fixing fin

5.1 Smartfit flashing tape to be fitted before fixing the cavitybattens that are adjacent to the window.

5.2 Use only Smartfit 60mm wide flashing tape.

5.3 Half the tape (30mm ) to cover the fixing fin and half

(30mm )to cover the wall underlay. All fixings and unusedfixing holes must be covered by tape (except sill fixingholes into concrete slab ).

5.4 The ends of each preceding piece of tape should befully covered by the subsequent piece.

5.5 Start at the sill - then jambs and lastly the top strip overthe head flashing.

5.6 Additional wall underlay from overlap above lapped overhead flashing and flashing tape.

5.7 It is permissable to fill the trim cavity between thewindow reveal and house framing with insulation material.

Sill first

Jambs second

Head last

Tape order

Smartfit flashing tape

Smartfit Flashing tape

Smartfit Flashing tape

HEAD

SILL

JAMB

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-12

REV: -

50 min.

Additional wall underlay from overlap abovelapped over head flashing and flashing tape.

Page 17: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 6 - Fix cavity battens

6.2 Cavity battens,notch and run overhead flashing fin

6.1 Fix cavity battens in accordancewith E2/AS1 or proprietary claddingsystem suppliers requirements to suitcladding type

HEAD

SILL

JAMB

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-13

REV: -

6.3 Cavity battens,notch and run over sillfixing fin

6.4 Cavity battens on outer stud or as closeto the window trim opening as possible.It is possible to have a reduced cavity battenimmediately adjacent to window jamb on topof fixing fin.

(if required by cladding type)

Page 18: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 7 - Fit cladding

Bevel-back weatherboard

Cavity battens

HEAD

SILL

JAMB

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-14

REV: -

Bevel-backweatherboard

Cavity battens

Scriber

Bevel-backweatherboard

Min 8

Weatherboard shown, example

8 m

in c

ove

r

Claddingreferences top hub

Cant strip

Cavity battens

In all cases, cladding is fitted afterwindow installation. Sheet claddingproducts will need joins to allowcladding to be presented about awindow after the window is in position.

Page 19: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 7a - Fit cladding

Masonry veneer cavity enddam component to be trimmedto back of, or bent aroundbehind lintel angle as shown.Apply sealant to remaininggaps to form dam.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-15

REV: -

Masonry veneer lintelangle should reference thissurface of the plastic tophub but not bear loads on it

FRONT VIEW, FROM OUTSIDE, top left corner of window, cladding and framing not shown

Masonry veneer above window shown, example

Masonry veneer lintelangle in masonrycourse (other optionsavailable)

Internal timber reveal

Head flashing upstand

Top hub

Window jamb

No head flashing horns

Window jamb in Masonry veneer cavity

Internal timber reveal

This surface againstframing and wall underlay

This surface againstframing and wall underlay

REAR VIEW, FROM INSIDE, top left cornerof window, house framing not shown.

Page 20: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 7b - Fit cladding

Head Flashing

The head flashing horns run in front of thecladding face. There is no saw cut required tolet the head flashing horns into the cladding.

The scriber cap is loose and runs fore and aft ina track in the top hub. Once the weatherboardsare installed, apply sealant between the scribercap and weatherboard face prior to pushing thescriber cap home hard to the face of theweatherboard.

A small hanger coming out from under thescriber cap will rest on the face of theweatherboard. The finished scriber will trap thishanger in position. It is possible to trim thishanger back so as not to protrude out the sideof the finished scriber.

Scriber cap

Hanger

Weatherboards

The Weatherboard that is cut upand over the top hub must be aneat fit to the side of the top hubwith no more than 2mm side float.

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-16

REV: -

FRONT VIEW, FROM OUTSIDE, top leftcorner of window, before scriber fitted.

FRONT VIEW, FROM OUTSIDE, top leftcorner of window, after scriber fitted

Scriber cap (shownshortened in this view)

Window jamb

Finished scriber

Top hub

Window jamb

Head Flashing

Gap to scribe

Weatherboards

Window head

Window head

Top hub

Finish the scriber hard up under thetop hub / scriber cap and seal all gaprior to paint.

Weatherboard shown, example

Hanger, hidden behind scriber

Page 21: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

STEP 7c - Fit cladding

Scriber cap

Scriber cap

Hanger

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-17

REV: -

The head flashing horns run in front ofthe cladding face. There is no saw cutrequired to let the head flashing hornsinto the cladding.

The scriber cap is adjustable and runsfore and aft in a track in the top hub.Once the flat sheet cladding has beeninstalled, apply sealant between thescriber cap and cladding face prior topushing the scriber cap home hard tothe face of the cladding.

A small hanger coming out from underthe scriber cap will rest on the face ofthe cladding. The finished scriber willtrap this hanger in position. It ispossible to trim this hanger back so asnot to protrude out the side of thefinished scriber.

Flat sheet cladding

The flat sheet type cladding that iscut up and over the top hub mustbe a neat fit to the side of the tophub with no more than 2mm sidefloat.

In all cases, cladding is fitted afterwindow installation. Sheet claddingproducts will need joins to allowcladding to be presented about awindow after the window is inposition.

Window jamb

Head flashing

Window head

Gap to scribe - varies dependingon cladding thickness

Head Flashing

Window head

Finished scriber - varies dependingon cladding thickness

Top hub

Finish the scriber hard up under thetop hub / scriber cap and seal all gapprior to paint.

Flat sheet types shown, example

Flat sheet cladding

Hanger, hidden behind scriber

FRONT VIEW, FROM OUTSIDE, top leftcorner of window, after scriber fitted

FRONT VIEW, FROM OUTSIDE, top leftcorner of window, before scriber fitted.

Page 22: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Head flashings and end treatmentsScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-18

REV: -

There are three categories of claddings that will define the needfor a head flashing and the end treatment of the head flashing;

See Dwg. No's. 19, 20, 21 for Types A, B and C

There are many more methods available for joining claddings toSmartfit windows that are not detailed in this guide.

Please contact Altus for any requirements outside of the detailsshown.

Page 23: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

NTSMay 2015 N/A

-

IN-19

IN-19

Window and Door Installation

Head flashings and end treatments - TYPE AType A. - Masonry veneer beside window with other cladding type on battens above the window. - Bevel back weatherboards with additional wide facings top and sides and applied weatherhead above top facing- Hebel aerated concrete panels.- E.I.F.S. (Generic)- Proprietary systems may require different head flashing end treatment. Contact cladding manufacturer- Rockcote Integra with Smartfit head flashing.

A Smartfit head flashing is required.•The head flashing horns will be flush with the window jambs.•The top hub will have masonry veneer end dams fitted.•

This Drawing is Protected by Copyright © Altus NZ Ltd

Cad :Scale:Date: Updated:

REV:

Top hub79703 AW or

Head flashing

79710 HD

MV Steel lintel angleshould reference thissurface of the tophub but not to bear loadson it.

79707 MV end dam

Head Flashing hornscut flush to Window Jambs

Page 24: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Window and Door InstallationMay 2015

-

1:1 IN-20

IN-20

N/A

gap between window head and construction above (soffit, lintel angle etc.)

Head flashings and end treatments - TYPE BType B. - Masonry veneer with masonry veneer beside and above window on steel lintel angle.- Windows hard to soffit for all cladding types.- Scyon Linea weatherboard option - additional facings with separate head flashing above.- Rockcote Integra with no head flashing.

No Smartfit head flashing or top hub is required.•Inclusive soffit bar is an additional option instead of applying suitable trim (by others) to finish the

There is a further 'hard to soffit' option for pre-fabricated wall construction.See IN-45, IN-46 and IN-47.

This Drawing is Protected by Copyright © Altus NZ Ltd

Cad :Scale:Date: Updated:

REV:

Aluminium jamb section

79701 Soffit Seal

Aluminium head section(no head flashing required)

Page 25: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Window and Door InstallationN/A

-

1:1 IN-21

IN-21

May 2015

Head flashings and end treatments - TYPE C

Type C. - Weather boards of all types.- Flat sheet claddings of all types.- Horizontal profiled metal.- Stucco.- Scyon Linea weatherboard option - no additional facings.

ASmartfit head flashing is required complete with top hubs, scriber caps and head• flashing horns of a predetermined length.

This Drawing is Protected by Copyright © Altus NZ Ltd

Cad :Scale:Date: Updated:

REV:

79710 HD

Top Hub Cap79703 AW or

Scriber Cap

Min. dimensionis to cover scriber

Head flashing

Page 26: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Masonry veneer

Galvanised or stainlesssteel lintel. See furtherdetails for more linteloptions

Sealant to gap HEAD

SILL

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-22

REV: -

Flashing tape coveringfixings and unusedfixing holes. Tape outover sill flashing.

40-50

Masonry veneer beside and above window, with steel lintel angle embedded in course

Drainage holes inmasonry veneer

Additional layer of wallunderlay lapped overflashing.

Wall Underlay

Sill flashing with drip edge,extend 200mm each side ofwindow. Position sill flashingagainst trimmer prior to installingwindow. Sill support bar ofwindow runs over sill flashing.

H3.2 timber kick-out fillet

Temporary packers ifrequired are to be removedfrom head after fixing.

Fixings - see Step 4

Flashings around window openings in masonryveneer by others and in accordance with NZBCE2/AS1 Paragraph 9.2.4 and Fig. 73C

It is permissable to fill the trimcavity between the windowreveal and house framing withinsulation material.

Head flashing turned intoangle or flat steel lintel.Extend flashing 200mmeach side of opening

Reveal fixingswith no headflashing: ReferStep 4.5

See IN - 44 forhead taping detail

Follow NZBC E2/AS1 detailing for masonry veneer inthe areas adjacent to the window installation

Page 27: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Masonry veneer

Galvanised orstainless steel lintel

HEAD

SILL

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-23

REV: -

Flashing tape coveringfixings and unusedfixing holes

40-50

Masonry veneer beside and above window, with steel lintel angle fixed to timber lintel

Drainage holes inmasonry veneer

Additional layer of wallunderlay lapped overflashing and lintel angle

Wall Underlay

Temporary packers ifrequired are to be removedfrom head after fixing.

Fixings - see Step 4Soffit bar or suitabletrim to close gap

Flashings around window openings in masonryveneer by others and in accordance with NZBCE2/AS1 Paragraph 9.2.4 and Fig. 73C

It is permissable to fill the trimcavity between the windowreveal and house framing withinsulation material.

Head flashing turnedinto steel lintel. Extendflashing 200mm eachside of opening

Reveal fixingswith no headflashing: ReferStep 4.5

See IN- 44 for headtaping detail

Sill flashing with drip edge,extend 200mm each side ofwindow. Position sill flashingagainst trimmer prior to installingwindow. Sill support bar ofwindow runs over sill flashing.

H3.2 timber kick-out filletFollow NZBC E2/AS1 detailing for masonry veneer inthe areas adjacent to the window installation

Page 28: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Masonry veneer

HEAD

SILL

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-24

REV: -

Flashing tape coveringfixings and unusedfixing holes

End dam flap bent ortrimmed to back ofveneer or claddingabove window. Applysealant to remaininggaps to form dam.

Batten out asrequired

Cladding above windowto reference top hub.

Flashing tape coveringfixings and unusedfixing holes

Masonry veneer beside window and other cladding above window

Other claddingabove window

Fixings - see step 4

Temporary packers ifrequired are to be removedfrom head after fixing.

Wall underlay

Flashings around window openings in Masonryveneer by others and in accordance withNZBC E2/AS1 Paragraph 9.2.4 and Fig. 73C

Head flashing hornscut flush to windowjambs

Additional wallunderlay fromoverlap abovelapped over headflashing andflashing tape.

It is permissable to fill the trimcavity between the windowreveal and house framing withinsulation material.

Sill flashing with drip edge,extend 200mm each side ofwindow. Position sill flashingagainst trimmer prior to installingwindow. Sill support bar ofwindow runs over sill flashing.

H3.2 timber kick-out filletFollow NZBC E2/AS1 detailing for masonry veneer inthe areas adjacent to the window installation

Page 29: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Jamb flashing

200

Note:Grooved reveals shown on all details forconsistency only. All details may be used witharchitraved reveals. If specifying no reveal orreturned wallboard into window frame, pleaseconsult joinery manufacturer for additional detailsand trim options.

Line of head and sill flashingsextended 200mm each sideof opening (refer head andsill details for relevance ofadditional flashings in cavity).

Packers

Fixings - see Step 4

JAMB

Wall underlay

Masonry veneer continued.Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-25

REV: -

Line of window head flashingand MV end dam in cavityarea. (Refer to head and silldetails for relevance of headflashings and end dams in thisarea).

Flashing tape coveringfixings and any unusedfixing holes

Flashings around window openings in Masonryveneer by others and in accordance with NZBCE2/AS1 Paragraph 9.2.4 and Fig. 73C.

It is permissable to fill the trimcavity between the windowreveal and house framing withinsulation material.

Follow NZBC E2/AS1 detailing for masonry veneer inthe areas adjacent to the window installation

Common Jamb detail

Page 30: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-26

REV: -

Stucco40mm Cavity Battens

Head flashing

Line of headflashing above

Fixings - see Step 4 Temporary packers ifrequired are to be removedfrom head after fixing.

Wall underlay

SILL

Fixings - see Step 4

HEAD

Packers

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Head flashing horn. Make aseal between cladding andhead flashing horn. Min. 30mm

Flashing tape

Stucco above window toleave a minimum 5mm gapto head flashing.Make a seal aroundhead flashing horn.

Flashing tape coveringfixings and anyunused fixing holes

Stucco

40mm Cavity Battens, and additionalbatten adjacent to opening to supportjamb flashing if required.

Wall underlay

Line of jamb flashing.Finishes up under headflashing and down in frontof sill flashing upstand

Sill flashing with10° slope.

8 m

in c

ove

r35

min

cov

er

Cavity spacers asrequired forcladding fixing

5mm stop end

End dam flap bent or trimmedto back of cladding. Applysealant to remaining gaps toform dam.

Line of sillflashing. 5mmstop end required.

Sealant over bond breaker tape5

Tophat or Tee Jamb flashing

Suitable cavity base angle closer or similar for40mm cavity. Integral cavity closer on Smartfithead flashing is complete with drain slots.

10mm min. cover

Note;The installation detailing for Stuccocladding as drawn is outside the scope ofNZBC E2/AS1 and NZS 4251.1:2007 dueto the cavity depth and jamb flashingset-up. It is the responsibility of thedesigner to verify compliance with theNZBC for the Stucco cladding system.

Additional wall underlay fromoverlap above lapped overhead flashing and flashingtape.

Page 31: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bevel-back weatherboardcladding

Cavity battens, first battenaway from trim opening

Bevel-backweatherboards Wall

underlay

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-27

REV: -

Horizontal bevel-back weatherboards

Scriber fixed andSealed to face ofWeatherboards

8 m

in c

ove

r

Line of head flashing over

HEAD

SILL

JAMB

Flashing tape

8mmmin. cover

Packers

Trim under windowas necessary

Cavity battens

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

Flashing tape coveringfixings and anyunused fixing holes

Weatherboards above windowsit on top hub to enforce 5mmgap to head flashing.

Cavity battens

Scriber cap

The weatherboard that is cut up andover the window must be a neat fit tothe side of the top hub with no morethan 2mm of side float.The boards below require a front jambflange cover of 8mm minimum

Scriber cap sealed to faceof weatherboards

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Head flashing horn

Wall underlay dressedinto opening and stapled.

Hanger, trap betweencladding face andscriber

Min. dimension: must cover scriber

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Cant strip

Scriber, profile to finalshapes and seal tocladding

Additional reduced cavity battenadjacent to opening to receive scriberfixings if required (not shown).

Additional wall underlayfrom overlap above lappedover head flashing andflashing tape.

Page 32: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bevel-backweatherboards

Wallunderlay

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-28

REV: -

Weatherboards with facings

8 m

m m

in c

ove

r

HEAD

SILL

Flashing tape

Cavity battens

Flashing tape coveringfixings and anyunused fixing holes

Weatherboards abovewindow sit on top hubto enforce 5mm gapto head flashing.

Cavity battens

Temporary packers ifrequired are to be removedfrom head after fixing.

Fixings - see Step 4

Wall underlay dressedinto opening and stapled.

H3.1 planted sillprofile

H3.1 treated timberweather head, lapsjamb scribers

Jamb Facing

Head flashing horns,cut flush with windowjambs.

Facing board, maintain 5mm gapto top face of head flashing

79707 masonry veneerend dam in position (notshown). Flap trimmed toback of cladding to letweatherboards up andover top hub. Applysealant to remaining gapsto form dam.

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

H3.1 cant strip

Head and sill detail, with Smartfit head flashing

Additional wall underlayfrom overlap above lappedover head flashing andflashing tape.

There are many other different ways to those detailed toachieve wide facings around a Smartfit window or door.Contact FWDS for more information

Page 33: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bevel-backweatherboard

Cavitybattens, firstbatten awayfrom trimopening

JAMB

8mmmin cover

PackersFlashing tape coveringfixings and any unusedfixing holes

Wall underlay

Scriber to suit, fix andseal to face ofweatherboards, finishup under weather head

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-29

REV: -

Weatherboards with facings

Line of weatherhead over.Run 10mm min. past scriberLine of planted sill below

Line of Smartfit head flashingfinishes flush with jambs

The weatherboard that is cut up andover the window must be a neatnotched fit to the side of the tophub's masonry veneer end dam withno more than 2mm side float.The boards below require a frontjamb flange cover of 8mm minimum

Masonry veneer end dam inposition behind head flashing

Jamb Detail, with Smartfit head flashing above

Additional reduced cavity battenadjacent to opening to receive facingboard fixings if required (not shown).

There are many other different ways to those detailed toachieve wide facings around a Smartfit window or door.Contact FWDS for more information

Page 34: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Rusticated weatherboards

HEAD

SILL

Wallunderlay

Line of head flashing over

Wall underlay dressedinto opening and stapled

8mmmin. cover

Packers

Cavitybattens

Flashingtape

Rusticatedweatherboards

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-30

REV: -

Flashing tape

Cavity battens

Weatherboards abovewindow sit on top hubto enforce 5mm gapto head flashing.

Scriber cap

Scriber

8 m

in c

ove

r

Trim under windowas necessary.

Rusticated weatherboardsScriber fixed andSealed to face ofWeatherboards

JAMB

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

The Weatherboard that is cut up andover the window must be a neat fit tothe side of the top hub with no morethan 2mm side float.The boards below require a front jambflange cover of 8mm minimum

Scriber cap sealed to faceof weatherboards

Head flashing horn

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Hanger, trap betweencladding face andscriber

Cavity battens, first battenaway from trim opening

Min. dimension: must cover scriber

It is possible to fill thetrim cavity between thewindow reveal andhouse framing withinsulation material.

Additional reduced cavity battenadjacent to opening to receive scriberfixings if required (not shown).

Additional wall underlayfrom overlap abovelapped over headflashing and flashingtape.

Page 35: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Fibre cement weatherboards

Line of head flashing over8mmmin cover

Fibre cementweatherboards

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-31

REV: -

HEAD

SILL

Wallunderlay

Wall underlay dressedinto opening and stapled

Cavitybattens

Flashingtape

Flashing tape

Cavity battens

FC weatherboardsabove window sit ontop hub to enforce5mm gap to headflashing.

Scriber cap

Scriber

8 m

in c

ove

r

Trim under windowas necessary.

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Hanger, trap betweencladding face andscriber

Packers

Scriber fixed andSealed to face ofWeatherboards

JAMB

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

The weatherboard that is cut up andover the window must be a neat fit tothe side of the top hub with no morethan 2mm side float.The boards below require a front jamflange cover of 8mm minimum

Scriber cap sealed to faceof weatherboards

Head flashing horn

Cavity battens, first battenaway from trim opening

Min dimension: must cover scriber

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Additional reduced cavity battenadjacent to opening to receive scriberfixings if required (not shown).

Additional wall underlayfrom overlap above lappeover head flashing andflashing tape.

Page 36: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Horizontal profiled metalScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-32

REV: -

Line of Head Flashing over

Profiled metal Cladding

HEAD

SILL

WallUnderlay

Wall underlay dressedinto opening and stapled

CavityBattens

FlashingTape

Flashing tapeCavity battens

Jamb flashing, finishes up underhead flashing and scriber cap. Letcladding at lower cut line into jambflashing. Jamb flashing finishes downonto and in front of sill flashingupstand.

8 m

in c

ove

r

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Scriber cap (above) sealed toface of cladding

JAMBFlashing tape coveringfixings and any unusedfixing holes

Wall underlay

The profiled Metal cladding that is cutup and over the window head must becut to allow the cladding behind thescriber cap to run lower than the cutline above the window to give thescriber cap a surface to reference andbe sealed to. The cladding must becut neat down the sides of the top hubwith no more than 2mm side float.

Head flashing horn

Cavity battens, first battenaway from trim opening

Min dimension is to cover jamb flashing

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Line of Sill Flashing Under

End of Sill Flashing closedand scribed to cladding

Line of Sill Flashing Under

Line of Head Flashing over

Continuous compressiblefoam strip seal

Preformed jamb flashinglapping over sill flashing

Vertical compressible foam

Cladding cut line abovewindow to be 5mm off headflashing surface.

Cladding cut line immediatelybeside top hub directly behindscriber cap. Cladding cut mustbe below scriber cap top surface.

5Scriber cap pushed back andsealed to face of cladding

50 min.

5

10 min. cover

22

22

16

17

30

Front elevationcladding cut at top ofjamb LH

Cladding cut to sit on topof the top hubs - 5mm offhead flashing.

Cut to suit JambFlashing

17

Sealant

Cla

ddin

g C

ut

Additional wall underlayfrom overlap above lappeover head flashing andflashing tape.

Page 37: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Fibre cement sheet and flush-finished fibre cement

Line of head flashing over8mmmin cover

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-33

REV: -

FC sheet cladding

HEAD

SILL

Wallunderlay

Wall underlay dressedinto opening and stapled

Cavitybattens

Flashingtape

Flashing tape

Cavity battens

FC sheet abovewindow to sit on tophub to enforce 5mmgap to head flashing.

Scriber cap

Scriber

8 m

in c

ove

r

Trim under windowas necessary

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Hanger, trap betweencladding face and scriber

Packers

Scriber fixed andsealed to face of FCsheet.

JAMB

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

The FC sheet that is cut up and overthe window must be a neat fit to theside of the top hub with no more than2mm side float.The Sheet edges at window jambsrequire a front jamb flange cover of8mm minimum

Scriber cap sealed to faceof FC sheet

Head flashing horn

Cavity battens, first battenaway from trim opening

Min dimension: must cover scriber

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Cavity spacers, set to fall, whererequired for sheet fixing

Additional reduced cavity battenadjacent to opening to receivescriber fixings if required.

Additional wall underlayfrom overlap abovelapped over head flashingand flashing tape.

In all cases, cladding is fitted afterwindow installation. Sheet claddingproducts will need joins to allowcladding to be presented about awindow after the window is in position.

Page 38: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Plywood sheet claddingScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-34

REV: -

Line of head flashing over8mmmin cover

Plywood cladding

HEAD

SILL

Wall underlay

Cavitybattens

Flashingtape

Ply sheet abovewindow to sit on tophub to enforce 5mmgap to head flashing.

Scriber cap

Scriber

8 m

in c

ove

r

Trim under windowas necessary

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Hanger, trap betweencladding face andscriber

Packers

Scriber fixed and sealed to face of plysheet.

JAMB

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

The ply sheet that is cut up and overthe window must be a neat fit to theside of the top hub with no more than2mm side float.The Sheet edges at window jambsrequire a front jamb flange cover of8mm minimum

Scriber cap sealed to faceof plywood sheet

Head flashing horn

Cavity battens, first battenaway from trim opening

Min dimension: must cover scriber

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Wall underlay dressedinto opening and stapled.

Flashing tape

Cavity battens

Cavity spacers, set to fall, whererequired for sheet fixing

Additional reduced cavity battenadjacent to opening to receivescriber fixings if required.

Additional wall underlayfrom overlap abovelapped over headflashing and flashingtape.

In all cases, cladding is fitted afterwindow installation. Sheet claddingproducts will need joins to allowcladding to be presented about awindow after the window is in position.

Page 39: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

E.I.F.S

Wallunderlay

Line of Head Flashing over

JAMB

Wall underlay dressedinto opening and stapled.

Cavitybattens

Flashingtape

Notch jamb flashing return legunderneath Aluminium HeadFlashing

EIFS & coating

EIFS & coating

Flashing tapeCavity battens

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

First cavity batten awayfrom trim opening.Battens to be styrene

Packers

EIFS & coating

HEAD

SILL

Wall underlay dressedinto opening and stapled.

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-35

REV: -

EIFS above window toreference top hub to enforceminimum 5mm gap to headflashing. Seal between claddingsystem, top hub and headflashing at the ends. Continueseal down jambs.

10mmmin cover

EIFS sill flashing system over 3way corner flashing with 10° min.fall to exterior

8m

m M

inC

ove

r

Cavity spacers set to fall

Refer to E2 / AS1 foradditional information requiredto complete this detail

uPVC or metal trim

Sealant with bond breaker

Top hub with masonry veneer enddams fitted. Remove or bend flapsbehind EIFS.

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

The installation details as drawn areindicative only. Refer to the EIFS systemsupplier for proprietary flashing andinstallation details. Thicker cavity battenoptions will deliver a more recessed window.

Additional wall underlayfrom overlap above lappedover head flashing andflashing tape.

Generic

Page 40: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

E.I.F.S Top corner sealing detail

Run sealant up jamb, continuing uphead flashing slope to diminishedpoint at the head flashing / claddingtop corner junction.

Cladding

Head flashing

Cladding

HEAD DETAIL TOP LEFT CORNER

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-36

REV: -

Top hub has masonry veneer enddams present. Bend over or break offflaps behind EIFS

Page 41: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

HebelScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A NTS

IN-37

REV: -

Packers

Fixings - see Step 4

JAMB

Wall underlayFlashing tape coveringfixings and any unusedfixing holes

HEAD

Flashing Tape

Temporary packers ifrequired are to be removedfrom head after fixing.

24 o

r 35

Wall underlay

DPC jamb flashingInstalled after window.Fit tight to window jamb.

For more information see 'CSRhebel' window flashing details'www.csrhebel.co.nz'Hebel is a closed cavity system

Front part of top hubremoved to allow cavitybased failure water fromabove to exit off ends ofhead flashing

Sealant, covered witharcrylic coating. Seal upand over head flashingends to meet head seal.Ensure no gaps remain.

SILL

Damp proof coatingapplied to sill as permanufacturers literature.Min 15deg slope to sill

Drainage slots at ends ofsill to be left clear. Seeelevation detail at right.

HEBEL 50mm or75mm Powerpanel

DPC sill flashing to theback of the cladding.Fixed to face of silltrimmer before window isinstalled.

Reveal fixings:Refer step 4.5

15°

appr

ox

Sealant to 3 - 6mmgap to claddingmanufacturersspecifications

AAC panels, bottomedge cut to suit

Head flashing horns cutflush to window jambs

Win

dow

jam

b

Window sill

Front Elev. RH sill / Jambjunction (N.T.S)

Seal along sill and up jambsfully, but ensure drain slotoutlet remains open to front.

Sea

lant

at j

amb

Sealant at sill

Heb

el p

anel

Hebel panel

Additional wall underlayfrom overlap above lappedover head flashing andflashing tape.

Masonry veneer enddam in position.

Masonry veneer enddam in position.

With Smartfit head flashing

Page 42: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Rockcote INTEGRA

Wall underlay

Line of Head Flashing over

JAMB

Cavity battens

Flashing tape

*Sealant

*Proprietary trim

*Panel & Coating

*Panel & coating

Flashing tape

*40mm cavity battens

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

Packers

*Panel & coating

HEAD

SILL

Wall underlaydressed intoopening andstapled.

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see Step 4

*40

50*

40*

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-38

REV: -

Masonry veneer end dam inposition, flap bent back or trimmedto back of cladding. Apply sealantto remaining gaps to form dam.

*Rockcote system cavitybatten, first batten awayfrom trim opening

*For all final dimensions and detailing referto the current Rockcote technical detailsrelating to Smartfit windows

With Smartfit head flashing

Masonry veneer end dam inposition behind head flashing horn

Panel system to reference tophub to enforce 5mm gap abovehead flashing. Continue jambseal up and over head flashingto terminal point.

*Sealant, drain holes insill frame to remain clear

*Flashing

It is possible to use Rockcote Integra 20mmbattens. The window will not appear asrecessed

Additional wallunderlay fromoverlap abovelapped over headflashing and flashingtape.

Page 43: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Rockcote INTEGRA

Wall underlay

JAMB

Cavity battens

Flashing tape

*Resene edge seal head flashing

*Panel & coating

40*mm cavity battens

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

Packers

*Panel & coating

HEAD

SILL

Wall underlaydressed intoopening andstapled.

Temporary packers ifrequired are to be removedfrom head after fixing.

*40

50*

40*

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-39

REV: -

*Rockcote system cavitybatten, first batten awayfrom trim opening

Without Smartfit head flashing

*3M All Weather Flashing Tape8067 to be installed against jambbatten to form stopend

79701 Soffitseal, evenlyseated againstwall underlay

Reveal fixings withno head flashing:Refer step 4.5

*Panel & coating

*Sealant, drain holes insill frame to remain clear

*Flashing, notch clear of drainholes

*Sealant

*3M All Weather Flashing Tape8067 from wall underlay to headflashing.

See IN- 44 for headtaping detail

*For all final dimensions and detailing referto the current Rockcote technical detailsrelating to Smartfit windows

It is possible to use Rockcote Integra 20mmbattens. The window will not appear asrecessed

Page 44: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-40

REV: -

Scyon Linea weatherboard - no facingsH3.1 treated timber cant strip

Scyon Linea weatherboard

Cavity batten

Cavity batten

JAMB

HEAD

SILL

Fixings - see step 4

Temporary packers ifrequired are to be removedfrom head after fixing.

Wall underlay

8mmmin cover

The weatherboard that is cut up andover the window must be a neat fit tothe side of the top hub with no morethan 2mm side float.The boards below require a front jambflange cover of 8mm minimum

Scriber fixed andsealed to face ofweatherboards

Line of head flashing over

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

Scriber cap sealed to faceof weatherboards

Head flashing horn

10

mm

min

co

ver

Trim under windowas necessary

Weatherboards above windowsit on top hub to enforce 5mmgap to head flashing.Scriber cap

Hanger, trap betweencladding face andscriber

Scriber, profile to finalshapes around cap andhangar and fix and seal tocladding

Additional reduced cavity battenadjacent to opening to receivescriber fixings if required.

Min. dimension: must cover scriber

Flashing tape

It is possible to fill the trim cavitybetween the window reveal andhouse framing with insulationmaterial.

Wall underlay dressedinto opening and stapled.

Refer to the JamesHardie Scyon Lineaweatherboard technicalmanual for further details

Cavity batten

Linea weatherboard

Flashing tape coveringfixings and any unusedfixing holes

Additional wall underlay fromoverlap above lapped over headflashing and flashing tape.

Page 45: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-41

REV: -

Scyon Linea weatherboard - with facings

Cavity batten

HEAD

SILL

Temporary packers ifrequired are to be removedfrom head after fixing.

Wall underlay

10

mm

min

co

ver

Planted sill trimunder window asrequired

It is possible to fill the trimcavity between the windowreveal and house framingwith insulation material.

Wall underlay dressedinto opening and stapled.

Flashing tape coveringfixings and any unusedfixing holes

Jamb facing boardbeyond

H3.1 treated timber cant strip

Linea weatherboard

Cavity batten

Flashing tape or alternativelyadditional layer of wall underlayover head flashing

James Hardie uPVC vent strip

15

5

50mm strip of sealant atboth ends of headflashing

H3.1 packers to suit.Fix over window framehead seal.

79701 Soffit Seal,evenly seatedagainst wall underlay

Head and sill detail

5mm x 3mm inseal3109 to overlapoptional

Sealant must be installedbetween head flashingand trim in VH and EHwind zones

Reveal fixings withno head flashing:Refer Step 4.5

Head flashingwith 15° slope

10 m

in.

10 m

in.

20mm stop ends tohead flashing

Refer to the JamesHardie Scyon Lineaweatherboard technicalmanual for further details

See IN- 44 for headtaping detail

Page 46: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

JAMB

Scriber sized to suit.Fixed and sealed toface of weatherboards

Line of Head Flashing over, 10mm min. past scriber

Flashing tape coveringfixings and any unusedfixing holes

Wall underlay

Additional reduced cavity battenadjacent to opening to receivefixings if required.

Cavity batten

Linea weatherboard

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-42

REV: -

Scyon Linea weatherboard - with facings Jamb detail

H3.1 packers to suit.

Optional facing trim, fix inaccordance with James Hardieinstructions

10

5mm x 3mm inseal3109 to overlapoptional

Line of planted sill below

Refer to the JamesHardie Scyon Lineaweatherboard technicalmanual for further details

Page 47: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Additional Details - soffit at window / door head

Soffit lining

Notes;• No head flashing is required.• No top hubs are required.• No fin fixing available at head.• No continuous tape along head (where

soffit is immediately above).• Ensure rubber soffit seal contacts wall

underlay / soffit evenly.• Remove packers at head reveal once fixed.• Primary head fixing is through reveal.• Fix through front fin for the other three

sides of the unit.• Soffit may be sloping (down from wall).• Finished soffit is 15mm higher than

underside of lintel (Suitable for 19, 25mmreveals). 30mm reveals require a differentoffset. Agree offset with joinery supplier.

100mm Min to face of cladding

HEAD

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-43

REV: -

15m

m79701 Soffit Seal

Jamb

Head

TOP RIGHT CORNER DETAIL

Apply horizontal flashing tape strip to sill first (If not concrete).Run jamb flashing tape over sill strip and up jamb to the highestavailable point overlapping the ends of the rubber soffit seal.Then overlay a further horizontal tape patch making sure thatthe ends and sides of the rubber seal are covered. Additionally,this area can be further tape patched or stapled to hold downtape edges.

Jamb Tape

Head Tape Patch

79701 Soffit seal,evenly seated againstwall underlay

Temporary packers ifrequired are to be removedfrom head after fixing.

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Alternative finishing detail (NTS):Suitable trim or flashing to gap

Fixing requirements at head only;2 off 75mm Jolt head nails @ 450 ctrs andnot more than 150mm from each end. Seestep 4.5. All other fixings see Step 4.

Page 48: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Additional Details - no Smartfit head flashing

Notes;• No head flashing is required.• No top hubs are required.• No fin fixing available at head.• Tape is required along the head (where

there is not a soffit immediately above).• Ensure rubber soffit seal contacts wall

underlay / soffit evenly.• Remove packers at head reveal once fixed.• Primary head fixing is through reveal.• Fix through front flange for the other three

sides of the unit.

HEAD

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-44

REV: -

79701 Soffit seal under tape

Jamb

Head

TOP RIGHT CORNER DETAIL

Apply horizontal flashing tape strip to sill first (If not concrete).Run jamb flashing tape over sill strip and up jamb to overlap theends of the rubber soffit seal.Then overlay a further continuoushorizontal tape strip along the window frame head and rubberseal making sure that the ends and sides of the rubber seal arecovered. Additionally, further tape patches can be applied tohold down tape edges. Jamb tape

Head tape

Flashing tape continuousalong head, lapping overrubber soffit seal ends

Temporary packers ifrequired are to be removedfrom head after fixing.

Reveal fixingswith no headflashing: ReferStep 4.5

79701 Soffit seal,evenly seated againstwall underlay

Fixing requirements at head only;2 off 75mm Jolt Head Nails @ 450 ctrsand not more than 150mm from each end.All other fixings see Step 4.

Cladding abovefinishing direct towindow head

Page 49: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Additional Details - Soffit fitted after joineryScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-45

REV: -

Soffit lining

100mm Min to face of cladding

HEAD

15m

m

Temporary packers ifrequired are to be removedfrom head after fixing.

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Extra framing abovejoinery for soffit fixingafter windowinstallation

Apply horizontal flashing tape strip to sill first (If notconcrete). Run jamb flashing tape over sill strip and upjamb to overlap the ends of the rubber seal andcontinue to the top of the head fixing tab.Then overlaya further continuous horizontal tape strip along thewindow frame head fixing tab making sure that theends and sides of the rubber seal, head fixing tab andjamb are covered. Additionally, further tape patchescan be applied to hold down tape edges. Seal 79717

Jamb

Head

TOP RIGHT CORNER TAPING DETAIL

Jamb Tape

Head Fixing Tab

Head Tape

Flashing tapecontinuous along head

Note;This detail can be used when the joinery units are tofinish up to a soffit but there is no soffit constructionpresent at joinery installation time. This could occurwhere wall panels complete with joinery areprefabricated off site and soffit construction is addedlater. Full head taping of the unit is possible with thismethod. Apply further tape patches or wall underlayaprons above to prevent water ingress duringconstruction time if required. The reveal fixing is nolonger the primary structural fixing as described in step4.5 and detailed in IN-43 so can be unspecified.

All frames except bifoldand sliding / stacker

Adjustable soffit bar isoptional. Alternative istimber finishing bead orflashing

Page 50: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-46

REV: -

Additional Details - Soffit fitted after joinery

Soffit lining

100mm Min to face of cladding

HEAD

15m

m

Temporary packers ifrequired are to be removedfrom head after fixing.

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Extra framing abovejoinery for soffit fixingafter windowinstallation

Apply horizontal flashing tape strip to sill first (If notconcrete). Run jamb flashing tape over sill strip and upjamb to overlap the ends of the rubber seal andcontinue to the top of the head fixing tab.Then overlaya further continuous horizontal tape strip along thewindow frame head fixing tab making sure that theends and sides of the rubber seal, head fixing tab andjamb are covered. Additionally, further tape patchescan be applied to hold down tape edges. Seal 79717

Jamb

Head

TOP RIGHT CORNER TAPING DETAIL

Jamb Tape

Head Fixing Tab

Head Tape

Flashing tapecontinuous along head

Note;This detail can be used when the joinery units are tofinish up to a soffit but there is no soffit constructionpresent at joinery installation time. This could occurwhere wall panels complete with joinery areprefabricated off site and soffit construction is addedlater. Full head taping of the unit is possible with thismethod.

Bifold frames

10g x 65 SS screws @ 200 ctrs.Cluster 4 screws @ 50mm ctrswhere bifold wheel sets park whenclosed and stack when open

10g x 50 wood screws at 300 ctrs through reveal.Screw can be used to adjust pitch of headassembly in tandem with front adjuster screw

Don't push wallboardhard into reveal groove.

Optional soffit bar, set to allowframe to adjust up if needed.

Extra soffit noggingabove door to pickup head fixings

Page 51: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-47

REV: -

Additional Details - Soffit fitted after joinery

Soffit lining

100mm Min to face of cladding

HEAD

15m

m

Temporary packers ifrequired are to be removedfrom head after fixing.

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

Extra framing abovejoinery for soffit fixingafter windowinstallation

Apply horizontal flashing tape strip to sill first (If notconcrete). Run jamb flashing tape over sill strip and upjamb to overlap the ends of the rubber seal andcontinue to the top of the head fixing tab.Then overlaya further continuous horizontal tape strip along thewindow frame head fixing tab making sure that theends and sides of the rubber seal, head fixing tab andjamb are covered. Additionally, further tape patchescan be applied to hold down tape edges. Seal 79717

Jamb

Head

TOP RIGHT CORNER TAPING DETAIL

Jamb Tape

Head Fixing Tab

Head Tape

Flashing tapecontinuous along head

Slider / Stacker frames

Note;This detail can be used when the joinery units are tofinish up to a soffit but there is no soffit constructionpresent at joinery installation time. This could occurwhere wall panels complete with joinery areprefabricated off site and soffit construction is addedlater. Full head taping of the unit is possible with thismethod.

*Sliding door;1 off, 10g x 50 wood screw @450 ctrs through frame pocket

*Stacker door;2 off, 10g x 50 wood screws @450 ctrs through frame pockets.

*A Sliding or Stacker door frame head will need extra headfixing if it is spanning any significant distance betweenmullions and jambs unsupported. A Stacker door has noavailable reveal fixing room so frame fixings are necessary.

Adjustable soffit bar isoptional. Alternative is timberfinishing bead or flashing

Page 52: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-48

REV: -

Note;For full height joinery units finishingto floor, the wall framing must be atleast flush or protrude out beyondthe floor edge.

Note;It is not important to maintain a5mm nominal gap between revealand floor or framing. Provideappropriate separation between thereveal, any aluminum member andconcrete.

Fixing requirements at sill;10g x 32 SS screws (or longer if sill bar is packed offfloor edge) (if timber) @ 300 ctrs and not more than150mm from Corners.Note: Use bottom row of fixing holes for expansivetype fasteners. Pre fill fixing holes with sealant inaccordance with NZBC E2 AS/1 figure 17A. Analternative sill fixing detail is available on sheet IN-49

Fixing requirements at sill;10g x 50 SS screws (if timber)@ 300 ctrs and not more than150mm from each end. Packunit to level under reveal ifrequired.

SILL

Line of Cladding beyond

12

100

mm

min

Additional Details - full height unit to enclosed decks

5

Packer if required

Details to be read in conjunction with NZBC E2/AS1, Figure 17A "Level thresholds for enclosed decks".

79700 Sill Seal tobe evenly seatedalong floor edge.Run out ends andlap with jamb tape

Floor structure

Deck membrane continues up ontofloor and is turned up 100mm min. attrimmer studs.

Note;Check concrete slab edge (if concrete floor and deck) is smooth and even,devoid of spill and boxing ridges. Any substantial edge breakouts that couldaffect sill sealing must be reinstated. If the rubber seal is prevented frommaking a suitable seal against the edge of the slab, a wet seal may be usedbetween sill support bar vertical fin and slab edge. This includes situationswhere the use of a rigid air barrier effectively pushes the sill fixing fin furtherfrom the floor edge. Run the rubber sill seal out just beyond the furthermostedges of the support bar fin. Ensure the jamb flashing tapes lap the ends of thesill fin and seal. Deck membrane to be extended up under sill and sill reveal.

Operating gear for Bifold doors runs inthis gap. Sufficient clearance isrequired. Consult joinery supplier

Wall framing line

Enclosed deck structure

Page 53: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

SILL

10g x 50 SS screws into plugs@ 300 ctrs and not more than150mm from Corners.

Pre Fix angle to frameusing 2 off 8g Csk SSscrews @ 300 ctrs

12

75 x 50 x 3.0 thick Angle,continuous.

Compressible foam tape full length ofsill. Run out ends and lap with jambflashing tape. Foam tape must be of athickness to ensure full contact andsufficient compression between backof angle and floor edge.

Door unit

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-49

REV: -

Additional Details - full height unit to sump threshold

Details to be read in conjunction with NZBC E2/AS1, Figure 17B "Level thresholds for ground level".

Note;For full height joinery units finishing to floor, the wall framingmust be at least flush or protrude out beyond the floor edge.

Note;It is not important to maintain a 5mm nominal gap betweenreveal and floor or framing. Provide DPC or similarseparation between reveal, any aluminium member andconcrete.

There is no practical sill support bar fixing available throughthe front of the support bar as shown in Fig 17B of NZBCE2/AS1. Use additional angle fix method as shown. Airsealis completed using single sided compressible foam seal tapebehind the angle. Ensure a good seal is made.

Concrete slab

Establish support blocks under face ofangle to resist rotational sill loads if gapsare present between slab edge and angle.Fix blocks to angle during trial installation.

Provide appropriateseparation between reveal,any aluminum member andconcrete.

Wall framing line

Note;Check concrete slab edge is smooth and even, devoid ofspill and boxing ridges. Any substantial edge breakoutsthat could affect sill sealing must be reinstated. If therubber seal is prevented from making a suitable sealagainst the edge of the slab, a wet seal may be usedbetween sill support bar vertical fin and slab edge. Thisincludes situations where the use of a rigid air barriereffectively pushes the sill fixing fin further from the flooredge. Run the rubber sill seal out just beyond thefurthermost edges of the support bar fin. Ensure thejamb flashing tapes lap the ends of the sill fin and seal.

Operating gear for Bifold doors runs inthis gap. Sufficient clearance isrequired. Consult joinery supplier

Page 54: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Additional Details - full height unit to floorScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-50

REV: -

SILL

FIXING REQUIREMENTS @ Sill.10g x 50 SS screws @ 300 ctrsand not more than 150mm fromeach corner.

SILL

Flashing Tapecovering fixings andremaining fixing holes

Timber Reveal

Wall underlay

Cavity Batten

Cladding to suit

Details to be read in conjunction with NZBC E2/AS1, Figure 17C "Door sills for cavity construction".

79700 Sill Seal to be evenly seatedalong floor edge. Run out ends andlap with jamb tape

Use additional fixingtag if no sill reveal ispresent. Many typesavailable.

Concrete Slab

Timber subfloor

Fixing requirements at sill;10g x 32 SS screws (or longer if sill baris packed off floor edge) into plugs @300 ctrs and not more than 150mm fromCornersNote: Use bottom row of fixing holes forexpansive type fasteners.

Fixing requirements atsill;10g x 32 SS screws (orlonger) into plugs @300 ctrs and not morethan 150mm from eachend. Pack unit to levelunder fixing tag ifrequired.

Wall framing line

Note;For full height joinery units finishing toslab floor, the wall framing must be atleast flush or protrude out beyond thefloor edge.

Note;It is not important to maintain a 5mmnominal gap between reveal and flooror framing. Provide appropriateseparation between reveal, anyaluminum member and concrete.

Reveals may or may not be present.

Units may be rebated into floor edge

Provide appropriateseparation betweenreveal, any aluminummember and concrete.

Wall framing line

Note;Check concrete slab edge is smooth andeven, devoid of spill and boxing ridges. Anysubstantial edge breakouts that could affectsill sealing must be reinstated. If the rubberseal is prevented from making a suitableseal against the edge of the slab, a wet sealmay be used between sill support barvertical fin and slab edge. This includessituations where the use of a rigid air barriereffectively pushes the sill fixing fin furtherfrom the floor edge. Run the rubber sill sealout just beyond the furthermost edges of thesupport bar fin. Ensure the jamb flashingtapes lap the ends of the sill fin and seal.

Page 55: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bevel-back WeatherboardCladding

Cavity Battens, first battenaway from trim opening

Bevel-backWeatherboards Wall

Underlay

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-51

REV: -

25mm reveals (shown with BB WB cladding)

Scriber fixed andSealed to face ofWeatherboards

8 m

in c

ove

r

Line of Head Flashing over

HEAD

SILL

JAMB

Flashing Tape and extra underlay

8mmmin cover

Packers

Trim under windowas necessary.

Cavity Battens

Flashing Tape coveringfixings and any unusedfixing holes

Wall Underlay

Flashing Tapecovering fixings andany unused fixingholes

Weatherboards above windowsit on top hub to enforce 5mmgap to head flashing.

Cavity Battens

Scriber cap

The Weatherboard that is cut up andover the window must be a neat fit tothe side of the top hub with no morethan 2mm side float.Boards below require a front flangejamb cover of 8mm minimum

Scriber cap sealed to faceof weatherboards

Temporary packers ifrequired are to be removedfrom head after fixing.Fixings - see step 4

Head flashing horn

Wall underlay dressedinto opening and stapled

Hanger, trap betweencladding face andscriber

Min dimension is to cover scriber

Grooved, architraved or noreveals may be used.

Additional reduced Cavity Battenadjacent to opening to receive scriberfixings if required. (Not shown)

Scriber, profile to finalshapes and seal tocladding

Cant strip

It is permissable to fill thetrim cavity between thewindow reveal and houseframing with insulationmaterial.

30mm reveals similar

Page 56: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Bevel-back WeatherboardCladding

Cavity Battens, first battenaway from trim opening

Scale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-52

REV: -

Sliding door frames (shown with BB WB cladding)

Scriber fixed andSealed to face ofWeatherboards

Line of Head Flashing over

HEAD

SILL

JAMB

Flashing Tape and extra underlay

8mmmin cover

Packers

Flashing Tape coveringfixings and any unusedfixing holes

Wall Underlay

Weatherboards abovewindow sit on top hubto enforce 5mm gapto head flashing.

Cavity Battens

Scriber cap

Scriber

The Weatherboard that is cut up andover the door must be a neat fit to theside of the top hub with no more than2mm side float.Boards below require a front flangejamb cover of 8mm minimum

Scriber cap sealed to faceof weatherboards

Temporary packers ifrequired are to be removfrom head after fixing.

Fixings - see step 4

Head flashing horn

Wall underlay dressedinto opening and stapled

Hanger, trap betweencladding face andscriber

Min dimension is to cover scriber

Concrete Slab

79700 Sill Seal to be evenlyseated along floor edge. Runout ends and lap with jambtape

Use additional fixing tagwhen no sill reveal ispresent.

Fixing requirements at sill;10g x 32 SS screws (or longer)into plugs @ 300 ctrs and notmore than 150mm fromCornersNote: Use bottom row of fixingholes for expansive typefasteners.

Fixing requirements at sill;10g x 32 SS screws (orlonger) into plugs @ each endand @ 300 ctrs. Pack unit tolevel under fixing tag ifrequired.

IMPORTANT NOTE;For full height joinery units finishing toslab floor, the wall framing must be atleast flush or protrude out beyond thefloor edge.Note;It is not important to maintain a 5mmnominal gap between reveal and flooror framing. Provide appropriateseparation between reveal, anyaluminum member and concrete.

Reveals may or may not be present.

Units may be rebated into floor edge

Additional reduced Cavity Battenadjacent to opening to receive scriberfixings if required. (Not shown).

Provide appropriateseparation between reveal,any aluminum member andconcrete.

Cant strip

Page 57: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Heavy Duty Head Flashing is required forBi-Folds. Fix flashing to the lintel with 10gx 32 SS screws @ 200 Ctrs. Cluster 4screws @ 50mm ctrs where bifold wheelsets park when closed and where panelsstack when open

Bifold frames, head fixingScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-53

REV: -

HEAD, with head flashing

Head flashing above and no head flashing options

Soffit Lining

79701 Soffit Seal,evenly seated againstwall underlay

M6 Adjuster screws (suppliedfitted to unit). Install unit anduse adjusters if needed toraise, lower or straighten head.Range = +/- 3mm

10g x 50 wood screws at 300ctrs through reveal. Screw canbe used to adjust pitch of headassembly in tandem with frontadjuster screw

Extra soffit noggingabove door to pick uphead fixings

10g x 65 SS screws @ 200 ctrs. Cluster 4screws @ 50mm ctrs where bifold wheelsets park when closed and stack whenopen

10g x 50 wood screws at 300ctrs through reveal. Screw canbe used to adjust pitch of headassembly in tandem with frontadjuster screw

HEAD, hard to Soffit or no head flashing option

5 m

m m

in

No packers to head.

Suitable clearance isrequired for later adjustment

Don't push wallboardhard into groove.

No packers to head.

Suitable clearance isrequired for later adjustment

Don't push wallboardhard into groove.

5 m

m m

in

Optional soffit bar, set to allowframe to adjust up if needed.

See IN- 43 for additionalend taping detail of 79701

Page 58: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Slider and stacker frames, head fixingScale:Updated:

This Drawing is Protected by Copyright © Altus NZ Ltd.

Smartfit Window InstallationN/A 1:2

IN-54

REV: -

HEAD, with head flashing

No packers to head.

Head flashing above and no headflashing options (stacker shown).

Soffit Lining

79701 Soffit Seal,evenly seated againstwall underlay

*Sliding door;1 off, 10g x 50 wood screw @450 ctrs through frame pocket

*Stacker door;2 off, 10g x 50 wood screws @450 ctrs through frame pockets.

No packers to head.

HEAD, hard to soffit or no head flashing option

*A Sliding or Stacker door frame head may need extrafixing if it is spanning any significant distance betweenmullions and jambs unsupported. A Stacker door is unlikelyto have any available reveal fixing room.

10g x 32 SS screws @ 300 ctrs and notmore than 150mm from ends

*Sliding door;1 off, 10g x 50 wood screw @450 ctrs through frame pocket

*Stacker door;2 off, 10g x 50 wood screws @450 ctrs through frame pockets.

15m

m

Optional soffit bar

See IN- 43 for additionalend taping detail of 79701

Page 59: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly
Page 60: Window Installation Guide - Altus · Amendment 6 and the WANZ guide to Window Installation. The window or door is delivered to site ready for installation as a pre finished assembly

Page 1 of 1 October 2014 AC2131/SMARTFIT (v.1)

This application is to advise Auckland Council that the following minor variation is proposed to be undertaken on the building situated at the address listed below. It is the owner’s responsibility to notify Council of any changes to the approved plans; this document once signed by the owner serves as acknowledgement. The variation must be approved by the Building Inspector before work can proceed.

Building consent N

o:

Site address:

Agents name: Fletcher Window and Door Systems

Postal address:

Agents role in project: System Supplier / Manufacturer

Contact phone number:

The following documents must be provided with this application form:

Two copies of SMARTFIT window technology installation details; SMARTFIT CODEMARK and BRANZ appraisal certificates must accompany this application (must be handed to Inspector for inspection to proceed)

No changes to the size of the windows or doors are permitted (if sizes differ, a formal amendment must be sought)

Windows / doors must be fitted into a cavity system; direct fixed installations not permitted

SMARFIT windows and doors to replace existing joinery units

Owner’s name: Date:

Owner’s signature:

By signing this statement the owner gives the agent authority to act on their behalf

Council use only:

The variation is minor and does not materially affect compliance Yes No

Inspector’s signature: Date:

Inspector’s name:

THIS VARIATION IS NOT APPROVED UNTIL SIGNED AND APPROVED BY A COUNCIL BUILDING INSPECTOR

On-site application for minor variation to approved plans – SMARTFIT window & doors