1. Voltage regulators – April 2 nd 2. Layout of the pipework for the solenoid valves– April 6 th 3. Prototype complete –April 15 th
Citation preview
Ladon
STATUS REPORT # 5Wildlife deterrent and monitoring system
Team 12Team Members:
Andres Valdez @00838352Alim Kuychiyev @01182936
Andre Rice @00662925John H. Vargas Jr. @01145168
March 31st, 2014
Monitoring system that will make gardening easier and more bountiful
GOALS TO HELP THE HOME GARDENERS GET BACK THAT WHICH IS LOST TO
WILDLIFE AND BE MORE BOUNTIFUL, COME HARVEST TIME.
1. Voltage regulators – April 2nd
2. Layout of the pipework for the solenoid valves– April 6th
3. Prototype complete –April 15th
Recent Tasks
Testing of the codes to work simultaneously
Testing of mechanical relay vs. transistor switch
Talked to Z-bolt about the laser Choosing the right amount of voltage
Ongoing Tasks Troubleshooting
Making do with the solenoid valves received Testing Bluetooth with the EC-shield to send
data Designing a website Finish writing the first draft of the final
report
Upcoming Tasks
Writing of the code for the EC-shield and speaker
Assembling of the probe for the EC- shield
Soldering of the voltage regulators to the protoboard
Functional Block Diagram
Schedule