34
Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Why Major Projects Fail and What We Can Do About It

MARK JERGEAS P. ENG, PMP

PMI

PMI-SAC Conference

November 2019

Calgary

Page 2: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Mark Jergeas P. Eng, PMP

• President of iProjects – PM Consulting Firm

• Mechanical Engineer (P. Eng.) – U of C 2004

• Project Management Professional (PMP) - 2010

• Experience working for engineering, construction,

and owner organizations (TC Energy, Spectra,

AltaGas, Bantrel/Bechtel)

• Project Manager / Program Manager on 9 projects

throughout career ranging from $25 to $750 million

• Expertise in team alignment, risk management,

lessons learned, PM training, gated process,

project chartering, and project execution

planning

2

Page 3: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Purpose

The purpose of today is to:

1. Describe the characteristics, challenges, and complexities

of major/mega projects

2. Provide selected strategies that you can use to mitigate

these challenges

3

Page 4: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Characteristics of Major Projects

• Millions or billions in capital investment

• High risk and complexity

• Interface Management - Many players involved such as the

owner, engineers, contractors, suppliers and vendors

• Thousands of people involved

• Lack of predictability in cost and schedule

a. Systematically do not deliver on time and on budget

b. 50-100% cost overruns in budget is the norm

• Environmental, regulatory, and community impacts

• Labour availability and labour management issues

4

Page 5: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Characteristics of Major Projects

• High visibility and reputational risk

• Delivered by a network of private and public entities and

stakeholders

• The scope keeps evolving and can affect the overall cost

and schedule

• Success has been difficult to achieve despite industry best

efforts

• Increased risks to investors/clients

• Other problems; employee burn-out, blame game, litigation

5

Page 6: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

What does the research say?

6

Page 7: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

7

Page 8: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

8

Page 9: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary
Page 10: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary
Page 11: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

11

Page 12: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Focus of Today 12

Problem MitigationLack of scope definition and proper

front-end planning. Not following project delivery system (gated

process)

Conduct comprehensive front-end

planning. Develop Project Charter and PEP

Ensure project delivery system is in

place

Lack of alignment, collaboration, and

trust amongst the team

Increase alignment and collaboration

through Partnering

Lessons learned are repeated Institutionalize a proper lessons

learned program

Page 13: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Project Delivery System 13

Page 14: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

14

Page 15: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

What is Partnering?

• A structured management approach for transforming contractual

relationships into a cohesive, cooperative, team-based relationship

with common goals.

• Commitment between two or more organizations to facilitate

teamwork and is based on trust, dedication to common goals, and

understanding of each other’s individual expectations and values.

• Partnering and a “one-team” concept

• Facilitates open and honest communication

• Establish/improve working relationships amongst all players

• Forge common goals and objectives

15

Page 16: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

What is Partnering?

Youtube Video:

Title: Why do Major Projects Fail?

https://www.youtube.com/watch?v=-nOEKzUEnvM

16

Page 17: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

What is Partnering?

• Create mechanisms to not only build but to sustain collaboration

throughout the project

• Establishes frameworks for resolving issues or disputes in a timely

manner

• Not a legal agreement, nor does it replace contractual agreements

• Create an environment of trust and teamwork

• Results of Partnering sessions form the Project Charter

• Partnering must be started early in the project

• Applies throughout the project lifecycle

17

Page 18: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Key Components of Partnering

Partnering entails developing the following:

• Challenges and expectations of team

• Team vision or goal statement

• Project objectives

• Success criteria

• Identification risks and stakeholders

• Organization structure and lines of communication

• Project health checks

• Dispute resolution mechanism

• Ground rules

18

Page 19: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Examples: Vision Statements

• We, the Project Team, commit to a collaboration and mutual success

• We, the Project Team commit to being a good neighbour and delivering the project as one collaborative team, to meet the following milestone dates:

• Start Date of June 1, 2019

• Traffic Availability by Oct.1, 2022

• Construction Completion by Oct. 1, 2023

19

Page 20: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Example: Stakeholder Management Plan 20

Stakeholder Objectives How They OperateWhat do they need? What do

they consider “wins”

How will we engage them to

increase their favorability

HSE Compliance with HOIMS

Regulate operations through legal

regulations, insuring compliance

with health, safety and environment

Zero lost time incidents

Considered in design, a focus in

construction and carried out

through operational lifetime

Operations Operability, Maintainability and

Reliability

Minimal downtime with ease of

operationThe best version of everything

Keep involved in the design phase,

model reviews and tollgates

Leadership Team Make money View projects on a return basis On time, on budgetAchieve project deadlines and stay

within budget PF=1

Regulatory /Surface

Land/Community/AR/

Aboriginal Affairs/

Community

Keep Husky compliantModerate and oversee

design/construction

Need to be informed and engaged,

need reassurance of compliance in

construction and after reclamation

Be very open with our design,

validate compliance at required

project stages

Internal Stakeholders

(SCM/Legal & Risk)

Compliance with Client’s

policies and procedures to

minimize liability

Focus on contract indemnification,

protection and maximized value

Use Client “paper”, zero risk,

maximum value

Early engagement, detailed vendor

spec, realistic timelines,

collaboration

EPC & other contracted

vendorsMake money

By working to the design basis and

SOW of the project to deliver the

product in a way that maximizes

rate of return

Deliver the project in a manner that

achieves their anticipated profit

margin

Clear SOW, design basis and

execution plan to minimize change

orders and maximize efficiency

Page 21: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Health Check ToolCOMMUNICATION

1 Communications are… difficult, 1 2 3 4 5 open

2 Information flow is… restricted 1 2 3 4 5 free, open

3 Timeliness of information late 1 2 3 4 5 on-time

WORKING RELATIONSHIPS

4 Cooperation bet. parties poor, 1 2 3 4 5 good,

5 Issues and concerns are ignored 1 2 3 4 5 dealt quickly

6 Responses to issues become

personal 1 2 3 4 5 project problems

7 Disputes are addressed ineffective 1 2 3 4 5 efficiently

8 Problems are resolved by senior mng. 1 2 3 4 5 lowest level

TECHNICAL REQUIREMENTS

9 Safety performance is… NA 1 2 3 4 5 acceptable

10

Overall quality is… NA 1 2 3 4 5 acceptable

11

Value for money is NA 1 2 3 4 5 acceptable

STAKEHOLDER & EXTERNAL ISSUES

12

Public complaints are… frequent 1 2 3 4 5 infrequent

21

Page 22: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

22

Team Self-Evaluation Results (Combined)

04-Dec-09

0.0

1.0

2.0

3.0

4.0

5.0

1

2

3

4

5

6

7

8

9

10

11

12

Team Alignment Overall

Problems, issues or concerns

1. Communications

2. The flow of information

4. Cooperation

5.

6. Responses to problems

7. Disputes/problems

8. Problems are resolved

3. The timeliness of information

9. Construction safety performance

10. Design and construction quality

11. Value for money

12. Public Complaints

Page 23: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

23Team Alignment by Company

0.0

1.0

2.0

3.0

4.0

5.01

2

3

4

5

6

7

8

9

10

11

12

Team Self-Evaluation Results (By Company)

cc

Problems, issues or concerns

1. Communications

2. The flow of information

4. Cooperation

5.

6. Responses to problems

7. Disputes/problems

8. Problems are resolved

3. The timeliness of information

9. Construction safety performance

10. Design and construction quality

11. Value for money

12. Public Complaints

Page 24: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

24Issue Resolution Mechanism

• Mechanism for resolving issues

• Resolve at the lowest/working level

• Escalated when appropriate to the next level of

management

• No action is not an option

Page 25: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

25

Corporate Level

1.

2.

Stage One

At Site Level

Names:

1. __________

2. __________

Stage Two

At Project Level

Names:

1. _________

2. _________

Stage Three

At PM Level

Names:

1. __________

2. __________

Issue Resolution Mechanism

Problem becomes

apparent

Solution to problem

offered by those who

are directly involved

with it

If problem not resolved,

go to stage two.

If solution agreed, do

not go to stage two. If

changes affect other

project parties, record

them into a form for

circulation.

Problem discussed at

progress meeting.

Solution to problem

offered by project team.

If solution to problem

cannot be agreed at

progress meeting, go to

stage three.

If solution agreed, do

not go to stage three.

Solution to problem

recorded in meeting

minutes.

A resolution committee

comprising a

representative from

each of the project

parties is formed.

Problem resolution

meeting called for

committee.

Mutual way forward for

project greed by

resolution committee.

Statement of way

forward recorded and

issued.

Finish FinishFinish

ADRLitigation

Problem

Identified

Failure!!!

Page 26: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

• Lessons Learned: Is the learning gained from the process of performing

the project – PMI, 2004, p. 363

• The objective is to to improve project performance over time by

communicating and institutionalizing: o Successes that should be repeated

o Opportunities for improvement that should not be repeated

• The vision of lessons learned is to build a culture of learning

Lessons Learned Process 26

Page 27: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

HISTORYHISTORYHISTORY

History Repeats Itself

27

Page 28: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

What is the Number 1 problem? 28

Page 29: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Lessons Learned Process

• Lessons need to be captured in a clear and detailed way

• Lessons must be transferable

• Lessons should be both successes and opportunities for improvement

• Should have both formal and informal elements

• May involve subcontractors or be internal to organization

Keep doing, Start doing, Stop doing

29

Page 30: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Keys to Success

• Lessons learned procedure should be simple

• The team is accountable to follow it

• Focus on significant lessons

• A searchable database is required

• Don’t wait until the end to collect data

• Provide solutions

• Institutionalize by changing policies,

standards, specifications, procedures, etc.

30

Page 31: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

iProjects

• iProjects is a project management consulting and advisory firm

• Our vision is to help our clients achieve predictability in cost and

schedule on major projects

• We have services in areas ranging from project governance, risk

management, training, facilitation, and general PM support

• A start-up based in Calgary

• Website: www.iprojectsinc.ca

31

Page 32: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

iProjects

GovernanceDeveloping or streamlining fit-for-

purpose project delivery or stage-gate systems to provide a structured project management execution model.

Creates governance structure to help organizations gain greater predictability and success on projects.

FacilitationConduct facilitation in:

• Partnering Sessions

• Alignment/Team Building sessions

• Strategic Planning

• Risk Management

• Lessons Learned

• Project Health Checks

• Project Performance Auditing

• Project Readiness Reviews

(PDRI)

• Process Simplification

Training & SupportCreating customized training

programs for organizations in areas such as project management, leadership, risk management, contract administration, etc.

One-on-one mentoring and coaching for project managers.

Development of key documents:

• Project Charter

• Project Execution Plan (PEP)

• PM Tools and Templates

32

Page 33: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

Thank you!

Contact Info:

[email protected]

Cell: (403) 805-8267

www.iprojectsinc.ca

33

Page 34: Why Major Projects Fail and What We Can Do About It€¦ · Why Major Projects Fail and What We Can Do About It MARK JERGEAS P. ENG, PMP PMI PMI-SAC Conference November 2019 Calgary

References• A Framework for Performance Based Competency Standards for Program Managers, Sydney: Global Alliance for

Project Performance Standards, GAPPS, 2011.

• A Guiding Framework for Project Sponsors, Sydney: Global Alliance for Project Performance Standards, GAPPS, 2015.

• Alberta Report II, COAA Major Projects Performance Assessment System, Project Performance Engineering Productivity Construction Productivity, June 2014.

• Alberta Report III, COAA Major Projects Performance Assessment System, Project Performance Engineering Productivity Construction Productivity: A Best Practice of the Construction Owners Association of Alberta, May 2019.

• Analysis of the Front-end Loading of Alberta Mega Oil Sands Projects”, Project Management Journal, Volume 39, Issue 4, December 2008, George Jergeas.

• Benevolent Dictatorship for Major Capital Projects, LearnAcademy, 2017, Amazon.ca, George Jergeas and Jim Lozon.

• Performance Challenges of Mega Capital Projects, a report to Productivity Alberta, Go Productivity, November 2014, Alberta, George Jergeas and Jim Lozon.

• How to Create Predictable Cost and Schedule Estimates, 58th Western Winter Workshop, San Francisco & Southern CA Sections of AACE International, March 21 – 24, 2019. Dr. Nick J. Lavingia.

• Project Risk and Opportunity Management, The Owner’s Perspective, Routledge, Taylor & Francis Group, 2019.

• Risk Navigation Strategies for Major Capital Projects: Beyond the Myth of Predictability, Springer, 2011 by Per Willy Hetland, George Jergeas, Asbjorn Rolstadas, Dick Westney.

• The Fast Track Manual: A Guide to Schedule Reduction for Clients and Contractors on Engineering and Construction Projects. Loughborough, UK: European Construction Institute, 2002, Eastham, G.

34