53
Why Grade? Because the Best Can Do This? Important Note: Notice the graceful transition from the building pad to the public walk in the right of way. Extremely thoughtful & skilled work demonstrated in setting the building pad elevation. 1 Tuesday, October 26, 2010

Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Why Grade? Because the Best Can Do This?

Important Note: Notice the graceful transition from the building pad to the public walk in the right of way.

Extremely thoughtful & skilled work demonstrated in setting the building pad elevation.

1Tuesday, October 26, 2010

Page 2: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

But Why Roads?

To get you from the grace & comfort of home here....

2Tuesday, October 26, 2010

Page 3: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

To Here

Road design is complicated technically and specialist road engineers and high end software are involved

LA’s work with Engineers in Corridor Planning & Scenic Byway Design

Generally LA’s design minor drives & and almost always in conjunction with a qualified engineer

3Tuesday, October 26, 2010

Page 4: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Basic Geometry of a Simple Circular Curve

Two fundamental elements are the curve that connects two tangents

Tangents are straight lines

The radius of the Curve is the same radius as the radius of the circle that the Curve is a portion of

Curve RadiusTangent

Tangent

4Tuesday, October 26, 2010

Page 5: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Types of Circular Curves: Reverse Curve

Reverse Curve: Two curves moving in opposite direction linked by a tangent

Note: The radii of the two curves need not be the same

The radius of any curve must meet the minimum dimension for the design speed of the road being designed

Tangent Linking Curves

5Tuesday, October 26, 2010

Page 6: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Curve Radii for Design Speeds

Note, higher design speeds require larger minimum radii for safety

Your assignment is a simple two lane drive with an intentionally slow design speed

6Tuesday, October 26, 2010

Page 7: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Types of Circular Curves: Compound Curves

Compound Curves: A single continuous flowing curve with two (or more) radii

Note how the Center of Curve (O) falls on the radius of the larger radius curve

Note that the difference in radii between the two curves should not be more than 50%

O

7Tuesday, October 26, 2010

Page 8: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Nautilus

Growth in a compound curve the radii of which are in proportion to one another using the golden ratio

8Tuesday, October 26, 2010

Page 9: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Types of Circular Curves: Broken Back Curves

Broken Back Curves: Two curves moving in the same direction separated generally by a short tangent

Can be awkward to maneuver through, breaks rhythm of movement. can present sight line problems, only for very slow speeds

9Tuesday, October 26, 2010

Page 10: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Circular Curve Elements: Point of Curvature (PC)

The Point of Curvature (PC) is the point where the curve begins at the end of the entering tangent

10Tuesday, October 26, 2010

Page 11: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Circular Curve Elements: Point of Tangency (PT)

The Point of Tangency (PT) is the point where the curve ends at the outgoing tangent

Note: Stationing is a standard means of horizontally locating critical points along the centerline of a road’s horizontal profile

We will use stationing for this assignment

Entering Tangent

11Tuesday, October 26, 2010

Page 12: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Circular Curve Elements: Point of Intersection (PI)

The Point of Intersection (PI) is the point where the extension of the entering and exiting tangents intersect

Important Note: The tangent line between the PC & PI will always be the same length as the tangent line between the PI and the PT

Exiting Tangent

12Tuesday, October 26, 2010

Page 13: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Radii Characteristics

Important Notes: Other than for Compound Curves, the dimension of the radius for any specific curve remains constant

The radius of a curve is described by a line perpendicular to the entering tangent and the outgoing tangent at the PC & PT respectively

13Tuesday, October 26, 2010

Page 14: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

The Center of Curve (0)

The Center of Curve (O) is the point created by the intersection of the radius lines extended down perpendicular from the tangents at the PC & PT.

You insert your compass point in O to ‘swing’ your radius

14Tuesday, October 26, 2010

Page 15: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Tangents Entering & Leaving the Curve

For our assignment we will consider the first entering tangent the first tangent entering the first curve from the left of the sheet ~ Point A

Tangent Entering the curve

Tangent Leaving the curve

15Tuesday, October 26, 2010

Page 16: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Included Angle (I)

The Included Angel I (I) is the angle created by the intersection of the extended tangents

Note: I also is equal to the angle described by the intersection of radii extended from the PC & PT

16Tuesday, October 26, 2010

Page 17: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Straight Curb ~ No Gutter Pan

17Tuesday, October 26, 2010

Page 18: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Straight Curb ~ No Gutter Pan

Typical Section of a Straight Curb w/o gutter pan.

17Tuesday, October 26, 2010

Page 19: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Straight Curb ~ No Gutter Pan

Typical Section of a Straight Curb w/o gutter pan.

Road surface abuts vertical face of the curb.

17Tuesday, October 26, 2010

Page 20: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Poured in Place Concrete Curbs w/Gutter Pan

18Tuesday, October 26, 2010

Page 21: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Poured in Place Concrete Curbs w/Gutter Pan

Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

18Tuesday, October 26, 2010

Page 22: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Poured in Place Concrete Curbs w/Gutter Pan

Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Gutter pan sloped either toward curb or away from curb depending on drainage needs. The lower gutter pan slopes to the curb

18Tuesday, October 26, 2010

Page 23: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Poured in Place Concrete Curbs w/Gutter Pan

Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Gutter pan sloped either toward curb or away from curb depending on drainage needs. The lower gutter pan slopes to the curb

Which of these would we use for our road project & why?

18Tuesday, October 26, 2010

Page 24: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Drain Inlet

Drain Inlets have only an outlet pipe. They have no inlet pipe.

Drain Inlets have no Sump below the outlet pipe

Note “Bumble Bee” Grate

19Tuesday, October 26, 2010

Page 25: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Catch Basin (CB) Characteristics

Note Sump: Volume of space below pipes entering & leaving for debris & sediment to settle & Collect

Note Pipe entering & leaving.

Catch Basins have a pipe in & out

For our project, the outlet pipe shall have an invert@ the CB 2” lower than the invert of the pipe coming into the CB where it enters

20Tuesday, October 26, 2010

Page 26: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Catch Basin Installation

Note Concrete Structure on Top of CB below with Iron Inlet secured in concrete

CB & Inlet installed prior to placement of road compacted aggregate sub-base and finish surface

CB Inlet must be precisely set to proper Rim Elevation as indicated on Grading & Drainage Plan

21Tuesday, October 26, 2010

Page 27: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

22Tuesday, October 26, 2010

Page 28: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Invert Elevation (INV. IN, INV. OUT.) Invert refers to the Elevation of the Bottom of the Pipe

22Tuesday, October 26, 2010

Page 29: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Invert Elevation (INV. IN, INV. OUT.) Invert refers to the Elevation of the Bottom of the Pipe

INV. EL @ CL of road must be 2’-3” above top of pipe directly below it to achieve a minimum of 2 FT of cover over the top of the pipe.

22Tuesday, October 26, 2010

Page 30: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Invert Elevation (INV. IN, INV. OUT.) Invert refers to the Elevation of the Bottom of the Pipe

INV. EL @ CL of road must be 2’-3” above top of pipe directly below it to achieve a minimum of 2 FT of cover over the top of the pipe.

Note interaction of contours with head wall

22Tuesday, October 26, 2010

Page 31: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Invert Elevation (INV. IN, INV. OUT.) Invert refers to the Elevation of the Bottom of the Pipe

INV. EL @ CL of road must be 2’-3” above top of pipe directly below it to achieve a minimum of 2 FT of cover over the top of the pipe.

Note drafting of head wall beyond in concept section

Note interaction of contours with head wall

22Tuesday, October 26, 2010

Page 32: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

23Tuesday, October 26, 2010

Page 33: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Note location of Catch Basins or either side of road against the curb

23Tuesday, October 26, 2010

Page 34: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Note location of Catch Basins or either side of road against the curb

Note longitudinal flow pattern of road

23Tuesday, October 26, 2010

Page 35: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Note location of Catch Basins or either side of road against the curb

Note longitudinal flow pattern of road

Note flow pattern resulting from cross slope from crown of road to face of curb

23Tuesday, October 26, 2010

Page 36: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Basics

Note location of Catch Basins or either side of road against the curb

Note longitudinal flow pattern of road

Note flow pattern resulting from cross slope from crown of road to face of curb

Note flow pattern from low point on road center line to the catch basins

23Tuesday, October 26, 2010

Page 37: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Gentle Swale Flowing to Culvert w/Headwall

This Culvert Runs beneath the entry drive to this park

It likely connects with what appears to be a ‘natural’ vegetated swale on the other side of the road

Note the simple yet elegant curved headwall

24Tuesday, October 26, 2010

Page 38: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Contract Document Plan & Section of Culvert Outlet

25Tuesday, October 26, 2010

Page 39: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Contract Document Plan & Section of Culvert Outlet

Note washed cobble at outlet to absorb energy of water flow at outlet to prevent erosion

25Tuesday, October 26, 2010

Page 40: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Contract Document Plan & Section of Culvert Outlet

Note washed cobble at outlet to absorb energy of water flow at outlet to prevent erosion

Note reinforcing filter fabric beneath end of pipe and cobble to prevent erosion

25Tuesday, October 26, 2010

Page 41: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Contract Document Plan & Section of Culvert Outlet

Note washed cobble at outlet to absorb energy of water flow at outlet to prevent erosion

Note reinforcing filter fabric beneath end of pipe and cobble to prevent erosion

• Note slope on pipe. Our culvert pipe shall have a minimum slope of 1% & maximum slope of 2%

25Tuesday, October 26, 2010

Page 42: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Concept Alternate Outlet for Culvert

26Tuesday, October 26, 2010

Page 43: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Concept Alternate Outlet for Culvert

Prepared Soil & Root Zone for bio-physical treatment of pollutants in runoff

26Tuesday, October 26, 2010

Page 44: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Concept Alternate Outlet for Culvert

Prepared Soil & Root Zone for bio-physical treatment of pollutants in runoff

Reinforcing Stone inter-planted w/flowering plants

26Tuesday, October 26, 2010

Page 45: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Concept Alternate Outlet for Culvert

Prepared Soil & Root Zone for bio-physical treatment of pollutants in runoff

Reinforcing Stone inter-planted w/flowering plants

Scarify subsoil to promote infiltration

26Tuesday, October 26, 2010

Page 46: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Concept Culvert Outlet Plan

Concept Plant of Culvert Outlet

Cobble 4” to 8” dia. to absorb energy of outflow and not get washed away

27Tuesday, October 26, 2010

Page 47: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Head Wall & Larger Scale Culvert Pipe

28Tuesday, October 26, 2010

Page 48: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Head Wall & Larger Scale Culvert Pipe

Note Contours on Headwall

28Tuesday, October 26, 2010

Page 49: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Head Wall & Larger Scale Culvert Pipe

Note Contours on Headwall

Note Contours on Side Slope of swale, 3:1 max, 4:1 a better maximum side slope

28Tuesday, October 26, 2010

Page 50: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Head Wall & Larger Scale Culvert Pipe

Note Contours on Headwall

Note Contours on Side Slope of swale, 3:1 max, 4:1 a better maximum side slope

Note Swale Signature at bottom of swale

28Tuesday, October 26, 2010

Page 51: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Head Wall & Larger Scale Culvert Pipe

Note Culvert is beneath road & top of pipe has soil cover

Note Contours on Headwall

Note Contours on Side Slope of swale, 3:1 max, 4:1 a better maximum side slope

Note Swale Signature at bottom of swale

28Tuesday, October 26, 2010

Page 52: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

Culvert Outlet w/No Reinforcement of Land Surface

This condition on a slope will eventually lead to accelerating erosion of the slope which will continue until actions arrest and repair the damage made

29Tuesday, October 26, 2010

Page 53: Why Grade? Because the Best Can Do This? · Poured in Place Concrete Curbs w/Gutter Pan Note direction horizontal face of gutter pan slopes. This gutter pan slopes away from the curb

The Immediate Process ~ Stay Tuned for Step 2

Analyze existing conditions, vegetation, natural features, views, built structures, topography, high points, low points, water conveyance patterns etc.

Read & understand the structure of the existing land form. What does it suggest for a road alignment.

Rough out a free hand alignment with design speed criteria in mind for minimum radii

Begin to formalize horizontal curve layout geometry

Engage the iterative process and be willing to explore & change options

Draft the preferred option with the curb line, the shoulders and walk

30Tuesday, October 26, 2010