What went wrong?. (1995) The Standish Group published a study “ CHAOS .” 365 information technology executive managers who managed over 8380 different information technology applications in U.S. are surveyed. In early 1990s, US companies spent more than $250 billion - PowerPoint PPT Presentation
Citation preview
2002年編寫 朝陽科技大學資管系 李麗華
What went wrong?
•(1995) The Standish Group published a study “CHAOS.”•365 information technology executive managers who managed
over 8380 different information technology applications in U.S.
are surveyed.•In early 1990s, US companies spent more than $250 billion
on 175,000 projects and the overall success rate of information
technology projects are only 16.2%.•The success is defined as meeting goals on time and on budget.
In 1995 over 31% of information technology projects
(over $81 billion) were canceled before completion.
2002年編寫 朝陽科技大學資管系 李麗華
Introduction to Project Management
• What is a project and what is not?• What is the characteristics of a project • What is the process of a project• What kind of project you had
involved?• What will be the problem when
conducting a project?Brain Storming
2002年編寫 朝陽科技大學資管系 李麗華
What is a project
• A project is a temporary endeavor undertaken to accomplish a unique purpose.
• Project normally involve several people performing interrelated activities, and the main sponsor for the project is often interested in the effective use of resources to complete the project in an efficient and timely manner.
• Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations.
2002年編寫 朝陽科技大學資管系 李麗華
Characteristics
ManagementProcess
Developmentprocess
How to be a Project Manager ?
What is a project?
講義引用自沈肇基老師之講義
2002年編寫 朝陽科技大學資管系 李麗華
Objective -performance specification -time schedule -cost budget
Resources -manpower and facility
Uniqueness -different customers,team members, time and/or methodology,….
Organization -Project and functional
Origin -Something not done before -must be one!(requirements)
Marketplace -Who is your boss
Product -Software and/or hardware
Size - scale
program, project, task
Characteristics of project
講義引用自沈肇基老師之講義
2002年編寫 朝陽科技大學資管系 李麗華
The project management process
• Defining: defining the project’s goal• Planning: planning how you and your team will satisfy
the Triple Constraint (performance specification, time schedule, and money budget.)
• Leading: managerial guidance to human resource, subordinates, and others(subcontractors)
• Monitoring: measuring the project work to find out how progress differs from plan in time to initiate corrective action
• Completing: making sure the job is done conforms to the current definition of what was to be done.
2002年編寫 朝陽科技大學資管系 李麗華
define
plan/replan
leadmonitor(metrics)
complete
Project Management Process
講義引用自沈肇基老師之講義
2002年編寫 朝陽科技大學資管系 李麗華
INITIALCONCEPT
REQUIREMENTANALYSIS
(USER NEED)
DESIGN
CODING
TESTING
OPERATION&MAINTENANCE
USERNEED
PROTOTYPING
CLASSIC
USERNEED
INITIALCONCEPT
CONCEPTPROTOTYPE
SOFTWAREPROTOTYPE
MODULESPROTOTYPE
OPERATIONALPROTOTYPE
RISKANALYSIS
BENCHMARKSDESIGNPHASES
時間
功能USER NEED
EPRTP理想WM
EvolutionaryPrototyping
Project Development process
講義引用自沈肇基老師之講義
2002年編寫 朝陽科技大學資管系 李麗華
SOCIETAL, POLITICAL AND ECONOMIC FORCES
CONTRACTOR
CUSTOMER
USER
YOUR ORGANIZTIONYOURBOSS
YOUR TEAMFULL TIME MEMBERS
YOUR TEAM PART TIME MEMBERS
YOU
If you are a project manager!
講義引用自沈肇基老師之講義
2002年編寫 朝陽科技大學資管系 李麗華
What went right?
•(1998) The follow-up study of Standish Group.
The cost of failed projects went down from $81 billion in
1995 to an estimated $75 billion in 1998.
Major decrease in cost overruns from the $59 billion spent in 1995
to the estimated $22 billion in 1998.
26% of information technology projects succeeded in meeting
scope, time, and cost goals.
2002年編寫 朝陽科技大學資管系 李麗華
•Egyptian pyramids(ancient)
•Great Wall of China(ancient)
•Military projects
•Manhattan project (modern) for atomic bomb
•1917 Gantt Chart developed by Henry Gantt
•1958 Pert Chart for the Navy Polaris missile/submarine project
•1970, military begun to use S/W to help manage large projects.
History