WFO Planning Tool RFC & FCT. STMicroelectronics Wafer Foundry Outsourcing. Team Members & Roles. Business Objective. Need for medium term forecast of the demand and supply to plan business growth. - PowerPoint PPT Presentation
Citation preview
STMicroelectronics Wafer Foundry Outsourcing
1
Team Members & Roles
Matric No
Name Role
A0066009J
Chetan Krishna Dhulipalla
Project Manager
A0065625A
Swetha Vardharajan B.A/Project Lead
A0065775R
Rama Rao Dutta Technical Lead
A0065875N
Kyaw Lwin Phyo Quality Manager/ DB Admin
A0066010Y
Venkatakrishnan Kambarajan
Test Lead
Business ObjectiveNeed for medium term forecast of the
demand and supply to plan business growth. Improve the correctness in the decision
making process of WFO planning team and ST management, by providing the pattern of the demand and supply from ST customers and ST foundries respectively on a one year scale.
Improve the productivity and effectiveness of the WFO Planners.
3
ScopeWFO Planning Tool assists WFO planner in
bridging Supply demand.Developing a medium term forecast module
(FCT) for analyzing the business of the company for future plans and also to enhance the functionality of the current short term forecast module (RFC).
Based on the data from FCT, implement the enhancement in the RFC module.
4
Business FlowST Group AProduct 1
ST Group B(Product 3
WFO Planning
Team
Foundry A(China)
Foundry B(Malaysia)
Needs/Request
Needs/ Request
Commit
Commit
Request
Request
5
Required System
ST Group AProduct 1
ST Group BProduct 3
WFO Planning
Team
Foundry A(China)Cap-50
Foundry B(Malaysia)
Cap-50
Needs -80
Commit-80
Needs -80
Request - 80
+ Cap-30
Request - 50
Request - 50
Commit-50
Commit-50
Request - 50
Request - 50
Capacity- 50
Request - 80
Capacity- 50Capacity- 80
6
STM WFO FDY Planning Process –Requirements of RFC and FCT
Commit
By PN
AllocCommit by
Area / MP / Group
Request
by PN
Forecast
By Area / Capa
Confirmation
By Area / Capa
FCT
Tool
Monthly Visibility 12 Months
horizon
Request
By PN
Real demand by PN & Capacity Limitation by Area / MP / Group / W
RFC
Manualentry
CCP WFO
Commit
By PN
Constrained order
by PN
I2 / MPS
Monthly CRP Request
CRP Com & CCAR
Weekly orders 17weeks horizon
7
Development StrategyPhase-1, Phase-2 activity of project is performed
in waterfall model.Phase-3 is developed using SCRUM methodology.Total Number of Sprints – 5.Life time of Sprint – 1 Week.Developed in Client location, as the tool is tightly
integrated with STMicroelectronics internal OrgSec tool.
Client suggested iterative incremental model, as parallel work is being done on the same tool.
Reasons for Choosing SCRUMClient need to integrate continuously with
the current system.As parallel development work is occurring
team expected last minute change requests.SCRUM provides easy feedback system from
client, as client is closely involved in the project progress – vital to project success.
UCMS for FCT
10
UCMS for RFC
11
System Architecture
12
Physical Architecture overview
13
14
15
Technical Issues During Phase 3Issue with design of RFC – In the current application
the complete logic is performed in Week17Page.
Issue with setting up Configuration Management System – The clearcase on the system could not be configured.
Issue with Database – Parallel usage of DB led to ‘Lock of the DB Procedures’.
16
Solution for Technical IssuesIssue with design of RFC – We designed and
implemented the enhancement based on the existing structure/design for RFC.
Issue with setting up Configuration Management System – The entire application was divided into modules and split the work individually and integrated using the common shares folder at the end of each day.
Issue with Database – Cleared the issue by defining separate schema for our project, there by ensuring the DB lock do not occur.
Demonstration Video
17
18
Acceptance ProcedureAs part of SCRUM Methodology, team delivered the
components/deliverables on sprint (week) basis.
The Customer would examine the deliverable and share the feedback with the team.
At the end of project, after the system testing is performed by the team, User performs official Acceptance Testing before the sign off.
19
Customer FeedbackAs the development was performed on client location,
the user had a closer view on the daily activity of the team.
The customer identified an issue with deliverable of sprint 1, he raised it during the sprint 3 process. Team rectified the issue during the sprint 4.
User reviewed the team’s System test log, bug tracking system, and performed an informal acceptance testing before signing off the Project Acceptance.
Project Progress – Planned / Actual
20
Project Progress – Planned / Actual
Project Progress – Planned / Actual
Project Progress – Planned / Actual
Project Progress – Planned / Actual
Project Progress – Planned/ Actual Effort (Man Days)
Management Problems – Phase 3Tasks from Planned Phase 2 – Detailed
DesignDetailed design and system test plan were
finished and finalized before the start of coding phase.
Delay in start of Phase 3 – Started on 17/1/2011 but planned to start on 10/1/2011.Addressed with contingency. Prepared System
Test Plan during this period.
Late notice of unavailability of QM.Cancelled Sprint 2 re-planned the sprints,
Additional Sprint.
Management Problems – Phase 3
Unexpected leaves at the end of January.Cancelled Sprint 2.
Closure of ST for Chinese New Year (Forced Vacation)The schedule was delayed. But, have sufficient
contingency.
Unavailability of systems at STMicroelectronics.Two heads on same code, increased effectiveness
and reduced the number of bugs in coding phase.
What’s Next??? The next milestones for WFOPT are envisioned as:
Additional Features on Medium Term Forecast Module.
The next stage of WFOPT would be to develop Long term forecast tool which would be on 2 years to 5 years period on quarters scale.
Similar to the request restriction in RFC based on the capacity value from FCT. The content in FCT could be controlled based on the data from long term forecast tool which would make the tool even more effective.
Lessons LearntResource Planning (Back up)
No Back up for the activities performed by a single assigned resource.
Faced few issues due to sudden unavailability of quality manager.
Customise Process to suit your project. Implemented SCRUM for the coding phase alone. Enabled to identify defects early. Simplified the Integration and User Acceptance activities.
Code Walk Through and Resource Management Due to constraint in system availability, team engaged two heads
on single code. This reduced defects in coding, thus reduced rework.
29
Plan for Implementation Phase - SCRUM
Client Proposal – Iterative Incremental Development.
Team’s Proposal – SCRUM.Product Backlog:
RFC Functionality. FCT Functionality. Data Transfer between RFC & FCT. Validation/Approval in FCT. Download/Upload data in FCT.
Sprint Duration – 1 week.Number of Sprints – 4.
32
Sprint Release PlanningSprint-1 Backlogs
RFC Functionality New Parameters for a particular product. Capacity validation using M-FEG data from DB
Sprint-2 BacklogsFCT Functionality & Integrate RFC & FCT
Attributes for a product to be added. Change in attribute should reflect in RFC.
Sprint-3 BacklogsValidate functionality in FCT & Upload, Download
Functionality. Validate functionality similar to RFC. Upload and download the data of the particular product from
DB.Sprint-4 Backlogs
System Testing & Contingency System Testing and test documentation and results. Rectification activity. Contingency.
Product Backlog