Upload
truongmien
View
223
Download
0
Embed Size (px)
Citation preview
Wetroom ConceptINS TALL ATION INS TRUCTIONS V I NY L
This information is subject to change (05/2007).
Wetroom Concept is a system for wet areas comprising floor and wall coverings, drains and accessories.
The guarantee is only valid if the whole room is treated with the recommended Tarkett coverings,
including drains and accessories, along with ancillary products recommended for installation.
All Tarkett resilient flooring products are composed of the highest quality raw materials available and
are manufactured under strict production control. They will meet the most exacting requirements of
architects, contractors, owners and users.
Top quality material is only half of the story: a floorcovering's beauty and serviceability is dependant
also on proper installation over a suitable subfloor. By carefully using these instructions, it should
be simple matter to make each installation a job of which all can be proud. Tarkett floor and wall
products are regularly subjected to testing by adhesive manufacturers to ensure their compatibility.
Any subsequent adhesive recommendations are the sole responsibility of the adhesive manufacturers.
BEFORE INSTALLATION
• Handling, storage and acclimatisation- Care should be taken when handling all types of floor and wall coverings to ensure that safety
procedures are followed and damage does not occur to the material.
- Check the material for visible defects and/or damage before and during installation.
- Use the same batch number for each continuous surface. Save the details for each roll until the
installation is completed.
- The rolls shall be stored in an upright position.
- It is important that the rolls are stored for 24-48 hours before installation at a minimum temperature
of 15°C (ideally around 18°C). The pieces of flooring shall be cut to the required lengths, leaving a few
centimetres more and stored in the room where they are to be installed. This temperature should be
maintained throughout the installation.
- The minimum temperature of the subfloor should be 15°C.
- The relative humidity inside the room should be 50-60%.
• Underfloor heatingIt is imperative that underfloor heating systems have been previously commissioned and found to be
functioning correctly prior to the installation of the floorcovering. Ensure that the underfloor heating
system is switched off 48 hours prior to the floorcovering installation commencing and remains off
for at least 48 hours after the installation is complete. During the period of decommissioning of
the underfloor heating system, an alternative heating source should be provided, if required, to ensure
that the area of installation is kept at a constant temperature of 15°C - 27°C. Gradually increase
the temperature over a number of days by only a few degrees per day until the desired room temperature
is reached. The temperature should never exceed the floorcovering industry agreed maximum of 27°C
at the underside of the floorcovering (the adhesive line).
Wetroom Concept - Installation instructions
2
3
• Preparation of the subfloorThe subfloor must be smooth, level, clean, dry, structurally sound, moderately absorbent and not
exposed to high humidity. The preparation/dryness of the subfloor and installation procedures should
all be as per the current relevant building standards within the country of use. The dryness of a solid
subfloor should be below the maximum moisture level permitted when tested in accordance with the
local building standards.
IMPORTANT: to allow perfect water drainage, the subfloor should be foreseen with a slope of at
least 1 cm per metre towards the drain.
- Use a water-resistant levelling compound when patching or filling in areas where wet conditions exist.
- Subfloors made of particle board shall be installed according to the respective manufacturer’s
directions.
- If the subfloor is painted, damp-proofed or non-absorbent, then you must allow the adhesive to
become "tacky" before installing the floor.
- Seams are not recommended within a 0.5 m radius of floor drains. Contact Tarkett if unsure about any
part of the installation.
- For specific subfloor types and preparation, please contact Tarkett technical services.
Note: although Tarkett may on occasion list a choice of adhesive and levelling compound manufacturers
and types, we do not however guarantee the products listed. The list of products and manufacturers are
not guaranteed complete or current. Tarkett would not accept any liability for any of these products
failing to perform in conjunction with any of their products. It is the responsibility of the adhesive
and levelling compound manufacturer and flooring contractor to ensure the products being used are
appropriate for use and applied in accordance with the manufacturers’ recommendations.
• AdhesivesPlease refer to the list of recommended adhesives on page 14. Take the climatic conditions of the
premises into consideration when allowing time for the adhesive to become tacky and the open time.
Tarkett regularly tests the main adhesives on the market to ascertain their compatibility with its products.
Maintaining the quality of these adhesives is the responsibility of the manufacturer. Using them
in accordance with the manufacturer’s instructions is the responsibility of the installer.
• Protection of installationIf building work is carried out after installation, the floor should be covered for protection. Masking tape
must not be stuck directly to the floor. If it is necessary to put the floorcovering to use at an early stage,
protect the installation with hardboard or plywood.
• Technical assistanceCompanies that have not had experience of using Wetroom Concept are invited to contact our Technical
Support Department for advice, recommendations and, if necessary, on-site assistance. Please contact
your usual Tarkett sales representative.
• Project ManagementThe reputation of Tarkett Wetroom Concept is based on more than 20 years of quality installation. We
advise project managers to ascertain the experience of the company bidding to install Wetroom Concept.
4
Start with the installation of a Purus drain and trap a minimum of
30 cm from the walls (measuring from the edge of the drain).
The flooring is coved to approximately 10 cm (about 4 in.) up the
wall. The wallcovering should then overlap the wall base by
at least 3 cm (about 1 in.). For best results, the top section of
the coved floor should be tapered off gradually to the wall using
a water-resistant levelling compound that you will sand to
achieve a smooth finish prior to installing the wallcovering.
Tarkett junction covings can also be used (see figure below).
To achieve a perfect watertight installation, all the floor and wall
sheets must be hot welded using Tarkett welding rods. For the
best result, use a speed welding nozzle. For removal of excess
welding rod use a special trimming knife or an equivalent tool.
lowtops and clamps ensure a watertight finish where
pipework penetrates the walls.
®
Quick overview
With junction coving and cove former
JUNCTION COVING
(OVERLAPPING)
COVE FORMER
With levelling compound and without cove former
LEVELLING COMPOUND
(OVERLAPPING)
5
ACCESSORIES FOR SIPHONS
The Purus knife will allow you to make a perfect hole in the flooring
material and hence ensure a perfect water-tight installation.
Other accessories and spare parts are available.
Please contact your Tarkett sales representative.
Installing the drain
ø 220
ø 150
ø 172
50
97
ø 50
ø 220ø 150
ø 50
ø 173
65
102
150
ø 220
138
ø 152
ø 175
ø 75
73
50
112
ø 173ø 132
ø 220
ø 150
ø 50
230
58
ø 173
ø 220
ø 150
ø 75
320
150
VERTICAL DRAIN
PURUS KNIFE
PURUS DUSCHBRUNN
Ref. 1416 001
Flow 2L/s
PURUS BRAGE 50
Ref. 1416 004
Flow 2,5L/s
PURUS BRAGE 75
Ref. 1416 005
Flow 3L/s
PURUS FREJA
Ref. 1416 002
Flow 2L/s
PURUS ODEN
Ref. 1416 003
Flow 3L/s
HORIZONTAL DRAIN
PURUS KNIFE
Ref. 1417 003
IMPORTANT: to allow perfect water drainage, the subfloor
should be foreseen with a slope of at least 1 cm per metre
towards the drain.
The drain must be located a minimum of 30 cm from the walls and
should be installed by a plumber in accordance with Tarkett
technical specifications and Purus technical specifications and
in accordance with the local standards.
6
MULTISAFE GRANIT
• Cutting the sheetsWhen cutting the sheets, make sure there is enough material for the coving (the sheets should be cut
longer than the room length). During the laying, the temperature of the subfloor and the room should
not be lower than 15°C. Pre-cut 24 hours before gluing and lay the flooring flat to allow the material to
relax and adapt to room temperature. This is especially important for long lengths.
When a sheet fits the width of the room, make a cross mark on the bottom of the material and the
subfloor to indicate the centre. This will help you place the sheet in its exact position. The cross marks
should coincide when placing the material.
When the width of the room exceeds the sheet width (more than one piece has to be installed to cover
the area), mark a line on the floor parallel to the longitudinal wall at a distance equivalent to 12 cm
(about 4.5 in.) less than the sheet width. Mark the room’s centre on this line. On the bottom of each
sheet, mark their centre. The cross marks on the subfloor and sheets shall coincide.
Sheets shall always be reversed to prevent shading effects.
Caution: all welded joints must be at least 30 cm from the drain.
• Tracing the covingUsing a straight edge and pencil, mark up to a height of about 10 cm (about 4 in.) all walls where the
flooring will be coved. When marking, only use a lead pencil. Wall scribers or Combi scribers (see page 14)
are also available.
Apply the adhesive on the walls up to the marked line, using a fine notched trowel. Spread some of the
adhesive out on to the floor.
Installing the floorcovering
d
dd
d >– 30 cm
7
• Drain pipes and floor drains
IMPORTANT: no glue around and inside the
drains!
Above drain pipes, fold the sheet against the
pipe and mark the center of the pipe on the back
of the floor.
Cut a hole about 25 mm smaller than the
diameter of the pipe. Cut the hole at the start of
the fold. Warm the sheet with a hot air gun and
press it over the pipe.
OR (recommended for a quick and perfectcut): cut the hole with the Purus knife (Order N°
1417003). Install the base of Purus knife on the
drain, then cover it with the flooring material. Make a small hole with a blade to install the Purus knife
on its base and cut the flooring material to make a perfect circle. When the hole is made, heat the sheet
vinyl and press it over the pipe.
When the hole is made and the floor material pressed into the pipe, install the clamp ring down into the
edge of the drain. When using an adjustable ring, make sure it fits tightly. Trim off excess material using
a knife with a hooked blade to avoid cutting through the wall of the plastic pipe. A layer of silicone is put
between the sheet at the edge of the ring for extra sealing. Finish the installation around the drain
according to the instructions of the respective floor drain manufacturer.
•Laying and covingIn areas where one sheet is sufficient to cover the floor, the adhesive can be applied over the entire
surface area before installing the sheet.
In areas where several sheets are necessary, fold back and loosen the sheets covering half of the floor
area. Apply the adhesive on the subfloor with a fine-notched trowel (300 to 350 g/m2). Use a soft
brush in hard-to-reach areas. Follow the respective manufacturer’s instructions for the adhesive you
have selected.
If you don’t install a cove former, use a corner roller to obtain smooth corners when coving (Order
N° 32951149). With the corner roller, press the material firmly into the juncture between the floor and wall.
Depending on maintenance constraints or a poor quality angle at the
floor/wall junction, coving on a PA 25 cove former (Order N° 1415001) or
PA 20 (Order N° 1414001) may be necessary in accordance with the local
building standards.
After waiting for the adhesive to become tacky, lay the first section of the
sheet (or sheets). Position carefully. Raise the second section of the sheet
or sheets and continue laying using the acrylic adhesive.
The coving must be fixed with double-gluing using a suitable adhesive
(adhesive applied using a brush on the substrate and the reverse), in
accordance with the time required for the adhesive to become tacky.
Note: for a perfect watertight overlap of the wallcovering on the coved
floorcovering, we recommend to cut the studs with an appropriate tool
(Seam plane).
Installing the floorcovering
8
• Corners
Inside cornerWhen fitting in-corners, make a cut in the excess material starting about 5 mm (about 1/4 in.) above the
floor in the corner. The material has to be heated before folding, heat the area between the sheet and
the wall. This provides better contact between the sheet and adhesive.
Press the material firmly into the corner with a corner roller.
The corner seam shall be placed on one of the walls at a 45° angle.
Outside cornerWhen fitting an out-corner. The sheet is folded against the corner
and cut about 5 mm (1/4 in.) from the floor. The guidelines in the
picture show the corner on the sheet and the position of the cut at
about a 45° angle. Then a diagonal cut is made as shown.
To adhere the triangle-shaped piece more simply and securely, cut
a groove on the back of the triangle with a corner knife. The depth
of the groove shall be no deeper than half of the sheet thickness.
The triangle can now be folded and placed on the corner. It will
overlap the coved floor. Cut through the overlapping material to
make a tight fit.
Glue the substrate and the
reverse of the flooring with a
suitable adhesive.
When the adhesive becomes
tacky, press the upturn against
the wall.
Installing the floorcovering
9
• Hot weldingImportant: always wait 24 or 48 hours after laying before welding the floor joint using the welding rod.
Do not start welding until the adhesive is completely dry.
All welding seams are grooved with a Grooving machine or a Seam grooving tool with a hardmetal blade.
Weld with a Hot air gun and Tarkett Speed welding nozzle (Order N° 32951179) or any suitable Speed
welding nozzle specially designed for welding vinyl floors. Then trim the welding rod with the special
Trimming knife (Order N° 32951172). If the raised parts of the embossed pattern are too close to the
seam, cut them off at the same time as you trim the welding thread (Seam plane).
CAUTION: welded seams must cool to room temperature before trimming. Start trimming where
you began welding. All trimming of welding rod is recommended in two steps: rough and fine trimming.
With a Trimming knife rough and fine trimming can be done by turning the knife. When fine trimming
welding rod, turn the grooved side up.
•PipeworksAs far as possible it is best to avoid pipework penetrating the floor by making the necessary
arrangements at design stage (grouping vertical outlets into a services conduit or siting them within
studwork partitions).
Around pipes by walls, cut the sheet and press it against the pipe to form a collar. In tight or cramped
areas between pipes and walls, cut as shown by the dotted line. If a cover is required, do the following:
if you make a cover out of floor material, fit it against the pipe with adhesive. Weld the seams together
using a repair gun.
Installing the floorcovering
10
• lowtops and clamps (watertight sleeves)However, it is possible to create a watertight finish for small diameter pipework.
Sufficient space must be provided (free space of 4 cm between and behind the
pipes), and special protection must be provided in the form of prefabricated covers
( sleeves) after laying the flooring. Before applying the sleeve, hot weld
the cuts made (floor and wall).
The illustrations opposite show the various phases of application:
1 - put the RADONIX membrane at the base of the pipe.
2 - after cutting the sleeve, apply the welding fluid (V1008) to the base.
3 - position the sleeve and weld the joint (V1008).
4 - adjust the ring clamp to hold the sleeve while the welding fluid dries.
5 - remove the ring.
Where a special diameter is used (without a equivalent), create a sleeve
using the flooring (welded at the base with the flooring, and welded vertically at
the junction).
•Cold welding - V1008 welding fluidV1008 cold welding fluid is used to weld watertight sleeves and thus ensure protection against water
penetration.
V1008 cold welding fluid is supplied in tubes with an applicator tip and is packed in boxes of 10 tubes
(Ref. 1419 001); its composition requires compliance with the instructions given on the packaging and
leaflets.
®
®
®
Installing the floorcovering
3
4
5GLUE
GLUE
2
GLUE
1
WATERTIGHT SLEEVESSTOT
DIAMETER* REFERENCE PACKAGING
8 - 12 mm 1420 001 24 sleeves + 12 clamps
11 - 15 mm 1420 002 24 sleeves + 12 clamps
15 - 19 mm 1420 003 24 sleeves + 12 clamps
18 - 22 mm 1420 004 24 sleeves + 12 clamps
21 - 26 mm 1420 005 24 sleeves + 12 clamps
26 - 31 mm 1420 006 24 sleeves + 12 clamps
30 - 35 mm 1420 007 24 sleeves + 12 clamps
35 - 42 mm 1420 008 6 sleeves + 3 clamps
100 - 127 mm 1420 009 1 sleeve
Adhesive for 1260 021 1 tube = 160 ml®
®
* The first figure indicates the diameter of the upper part; the second indicates the diameter at the groove.
11
PREPARATION OF THE WALLS
If necessary remove previous coverings. On a block or porous substrate, apply a suitable primer. Do not
use paint, even diluted.
• Installing the materialCut 24 hours before gluing. Minimum ambient temperature: + 15° C.
For a perfect overlapping (levelling compound or junctionprofile PJ 30)Before installing the wallcovering on the floorcovering, the upper
edge of the coved floor material should be filled in using a water-
resistant levelling compound that you will sand to achieve a smooth
juncture.
To compensate for the thickness of the coving, Tarkett junction covings PJ 30 (Order N° 1418001) can
also be used. Apply the PJ 30 junction profile by double-gluing using a suitable adhesive.
Note: for a perfect watertight overlap of the wallcovering on the coved floorcovering, we recommend to
cut the studs with an appropriate tool (Seam plane).
According to the quality of junction between walls and floors and with accordance to local building
standards, we may follow one of the two installation methods hereunder:
• CautionThe sheets must never be cut in the corners and joints must be located as far away from the wet area as
possible and at least 10 cm from a corner. Allow for an overlap of at least 3 cm over the floor coving.
Vertical installationThe sheets can be installed vertically and hung over the whole height of the room (sheets reversed).
Installing the wallcovering
PJ 30
With junction coving and cove former
JUNCTION COVING
(OVERLAPPING)
COVE FORMER
With levelling compound and without cove former
LEVELLING COMPOUND
(OVERLAPPING)
12
Horizontal installationAquarelle Wall HFS can also be installed horizontally, subject to the
use of the wall border (height 49 cm) to ensure perfect protection
from water over the whole height of the room. The wall border is
installed after the Aquarelle wallcovering, and should overlap its top
edge by at least 2 cm (use only acrylic adhesive).
• GluingCoat the wall over the width of a sheet down to the coved flooring with an acrylic adhesive recommended
by Tarkett, using a fine-notched trowel (220 to 250 g/m2) starting from the plumb line previously drawn
onto the wall.
Wait for the adhesive to become tacky, then offer up the first sheet in line with the plumb line. Position
very carefully.
Coat the substrate with adhesive and hang the second sheet, reversed, either by butting it up tight, edge
to edge (Important: first check the condition of the edges), or by overlapping the edges by about 3 cm.
In the overlapping case, to cut the joint, heat with the heat gun and cut with a straight blade or using
the Combined scriber (see page 14).
• Corners
Inside cornerTo create the corner, use the corner roller, while heating the covering with the heat gun.
Where the corner of the substrate is not straight, cut the covering vertically, at least 10 cm from the
corner and continue hanging.
Outside cornerHang by double-gluing using a suitable adhesive 5 cm each side of the corner.
In case of a non-vertical corner, cut at 10 cm from the corner and continue hanging.
•Overlapping the covingTrim the Aquarelle Wall HFS at a height of 7 cm (i.e. an overlap of
3 cm) using the Combined scriber, then glue with acrylic adhesive
or double-glue with a suitable adhesive.
Comment: the excess material in the inside corner will be
reabsorbed using the heat gun and the corner roller.
Installing the wallcovering
13
CAULKING AND THRESHOLD STRIPS
Our guarantee is maintained where our floor or wall coverings are
perforated provided watertight chemical plugs are used or the
inside of the plug is filled with a suitable watertight mastic (of
the polyurethane or MS polymer type) before fixing accessories
and sanitary equipment using screws. In addition, watertightmastic must be applied between the surfaces in contact.
For example: when installing a WC (with a wall-hung bowl for
preference), proceed as indicated above and in addition, use
watertight mastic under the bowl before installation.
Use a suitable mastic (acrylic, polyurethane or MS polymer type)
around door frames, at the base of the wall covering and around
any fixings installed after the Aquarelle Wall HFS is hung.
A wetroom threshold strip in grey rubber is also available:
10 cm wide and in 20 lm rolls.
The threshold strip (order number 1255 748) has a bellow seal
that creates an obstacle to water and compresses under pressure
from people and trolleys.
The threshold strip is glued to the subfloor using a suitable
adhesive and the flooring is laid either side on the tongue of the
threshold strip (1 cm) using acrylic adhesive.
After installation
•Hot welding the jointsThe joint is opened using a Grooving tool (Gouge for wall) supported by a Thick ruler.
Weld from top to bottom using the Speed nozzle.
Trim in two stages using the Trimming knife, pre-trimming using a Trimming guide and finishing with the
Trimming knife without the guide.
14
TOOLS
ADHESIVES
List of recommended tools and adhesives
DESIGNATION FLOOR WALL JANSER ROMUS1 Hot air gun X X 226 110 000 95 045
2 Pressure roller (corner roller) X X 224 400 123 95 135
3 Gouge for wall or X 95 125
Gouge with guide X 262 601 000 95 180
4 Thick ruler X 91 580
5 Triangular rapid nozzle (Speed weld nozzle) X X 224 700 300 95 030
or Universal nozzle X X 224 400 300 95038
6 Quarter moon knife (spatula knife) X X 262 621 000 95 140
7 Trimming guide (spatula guide) X X 262 625 000 95 150
8 Hot air welding gun X X 224 962 000 95 075
Hot air welding gun X X 224 818 000 95 080
Hot air welding gun for coving and finishing X 224 815 000 95 082
9 Seam plane (for studded floorcovering) or X X
Trimming tool (narrow trimmer) or X 262 609 100 95172
Trimming tool ("Slim" or "Trim") X 262 609 300 95182
10 Angle's template (flat) or X 95 445
Angle's template (folded at 45°) X 95 446
11 Wall scriber or X 222 430 000 95 430
Combi scriber X 262 130 000 93 355
12 Swan neck nozzle or X 224 810 040 95044
Angles finishing nozzle X 224 810 050 95 039
13 Trimming gouge X 262 610 000 95 160
14 Cork smoother X X 262 380 000 93 145
15 Smoother X 93 150
MANUFACTURER ACRYLIC
BOSTIK S.A. - MANG POLYMANG
BOSTIK S.A. - MIPLACOL MIPLAFIX 300
BOSTIK S.A. - SADER SADERTAC V3
CEGECOL SNC TRIFIX SUPER
HENKEL THOMSIT K188
UZIN KE 2000 S
IMPORTANT: This information is subject to change (published 05/2007).
15
• Before useClean with a neutral detergent (pH 6/8) and a bristle brush, followed by rinsing with clean water.
• Daily maintenanceWet brushing with neutral detergent (pH 6/8).
• Periodic maintenanceWet brushing (bristle brush) with alkaline detergent (pH 8/10).
Occasionally, it may also be necessary to use disinfectants, degreasing and/or descaling agents.
• RenovationNOT REQUIRED provided maintenance as described above is carried out correctly and regularly.
However, if renovation is required (very significant soiling), one of the following methods can be used:
• Maintenance of walls (monthly)Wash Aquarelle Wall HFS with a sponge (no abrasive pad) and using neutral detergent (pH 6/8), followed
by rinsing with clean water.
Wetroom Concept – Cleaning and maintenance
Washing using a single-brush cleaning machine or a combined equipped with a flexible nylon
brush + alkaline detergent (pH 8/10).
• Avoid the accumulation of dirty marks, splashes of maintenance products, soap or shampoo.
• In all cases, follow the instructions given by the manufacturers of the maintenance products(dilution rates, method of application, etc.).
• Avoid mixing products of different brands (risk of incompatibility).
MACHINE
Method identical to that used for periodic maintenance, the mechanical action being obtained
manually by the use of a bristle brush.
Rinse with clean water
MANUAL
TARKETT SALES COMPANIES www.tarkett-commercial.com
We
tro
om
co
nce
pt
bro
chu
re -
En
gli
sh -
39
42
351
70
5 -
05
/2
00
7 -
DB
A
Wetroom concept
DESCRIPTION
Granit Multisafe: homogeneous single layered vinyl flooring with studded surface for use in wetroom. In sheet form. Product standard: EN 649.
Aquarelle Wall HFS: compact printed vinyl wallcovering for use in wetroom. Fire treated Bs2. Sanitized(R) treatment. In sheet form. Product standard: EN 235.
The above information is subject to modification for the benefit of further improvement (05/07).
For more detailed technical information, please contact Tarkett.
Follow Tarkett's installation and maintenance instructions carefully. These instructions are available upon request.
EN 649Granit Multisafe
According to European Classification EN 685
IQUALITY SYSTEM
Technical data Standards Granit Multisafe Aquarelle Wall HFS
Classification EN 685EN 259UPEC
31
U4 P3 E2/3 C2Heavy duty
Total thickness EN 428 2.50 mm 0.92 mm
Wear layer thickness EN 429 2.00 mm 0.12 mm
Total weight EN 430 3 060 g/m2 1 500 g/m2
Abrasion group EN 660-1EN 660-1
Group P: ≤ 0.15 mmGroup P: ≤ 4.00 mm3
-
Static indentation EN 433 Approx 0.03 mm -
Dimensional stability EN 434 ≤ 0.40% Lengthwise : ≤ 0.60 mmWidthwise : ≤ 0.20 mm
Curl resultant to heat EN 434 - ≤ 0.8 %≤ 2 mm
Reaction to fire
Marine equipment
EN 13501-1
IMO FTPC Part 5 and 2IMO Res. A653
Bfl s1
0575
B-s2, d0 on gypsumplasterboard and on A1 or A2 substrate
Slip resistance DIN 51130EN 13893
R10µ ≥ 0.3
-
Bare foot test DIN 51097 Class C (27°) -
Seam strength (N/50 mm) EN 684 - ≥ 150
Electrical properties EN 1081EN 1815
approx 1010 ohms< 2 kV
-
Impact sound reduction EN ISO 140-8EN 717/2
∆Lw = approx. + 4 dB -
Acoustical absorption NF EN ISO 354 αw - 0.05 (H)
Light fastness EN ISO 105-B02 ≥ 6 ≥ 6
Chemical resistance EN 423 Good resistance Good resistance
Resistance to bacteria NF EN ISO 846 Does not favour growth Sanitized(R)
High fungi effect
Thermal resistanceUnderfloor heating
EN 12524 0.013 m2 K/WSuitable - max 27°C
0.01 m2 K/W
Colours 12 18 + 3 borders
Form of delivery EN 426EN 259
Rolls: 25 lm x 2 mRolls: 35 lm x 2 mBorders: 49 cm x 30-35 m
Aquarelle Wall HFSArt. code
Welding rods NCS codes
3942018 1292991 S 1010-B
3942019 1287260 S 1015-Y10R
3942020 1287261 S 1002-Y
3942021 1287262 S 2020-R90B
3942022 1287263 S 1510-R90B
3942023 1287264 S 1010-B70G
3942024 1287265 S 0907-B80G
3942025 1287266 S 1015-G60Y
3942026 1287267 S 1020-Y10R
3942027 1287268 S 1015-Y30R
3942028 1287269 S 1020-Y30R
3942029 1287270 S 2030-Y50R
3942030 1287271 S 1015-Y50R
3942031 1289514 S 1005-Y40R
3942032 1288123 S 0804-Y30R
3942033 1288126 S 1500-N
3942034 1292801 S 1000-N
3942035 1287272 S 1005-R20B
GranitMultisafeArt. code
Welding rods NCS codes
3476331 1287244 S 1010-B70G
3476332 1287245 S 1015-G60Y
3476333 1287246 S 1005-R20B
3476334 1287247 S 2030-Y50R
3476335 1287248 S 1020-Y30R
3476379 1292379 S 1510-R90B
3476383 1292383 S 0804-Y30R
3476770 1288255 S 1005-Y40R
3476772 1291772 S 1015-Y30R
3476776 1292656 S 2020-R90B
3476779 1292617 S 0907-B80G
3476782 1294680 S 1500-N
Australia: Tarkett Australia Pty Ltd – Tel. +61 2 96 34 73 73 > Austria: Tarkett Holding GmbH, Niederlassung Wien – Tel. +43 1 47 88 062 > Baltic States: Tarkett SAS -
Tel. +370 37 262 220 > Belgium: S.A. Tarkett NV – Tel. +32 2 520 04 67 > China: Tarkett Asia Pacific Limited Shanghai Representative Office – Tel. +86 (21) 62 88 15 38 > CzechRepublic: Tarkett SAS, org. slozka - Tel. +420-271 001 602 > Denmark: Tarkett A/S – Tel. +45 43 90 60 11 > Finland: Tarkett Oy – Tel. +358 9 5406 5870 > France: Tarkett SAS –
Tel. +33 1 41 20 42 49 > Germany: Tarkett Holding GmbH, Bereich Objekt – Tel. +49 6233 810 > Greece: Tarkett Monoprosopi Ltd – Tel. +30 2 10 576 3889 > Hong Kong: Tarkett Asia
Pacific Ltd. – Tel. +852 2511 8716 > Hungary: Tarkett SAS - Tel. +36 1 437-8150 > Italy: Tarkett S.p.A. – Tel. +39 02 893 411 > Luxembourg: Tel. +352 949 211 8804 > Middle East:
Tarkett Middle East – Tel. +961 1 75 2363/4 > Netherlands: Tarkett Benelux B.V. – Tel. +31 76 57 80 760 > Norway: Tarkett AS – Tel. +47 32 20 92 00 > Poland: Tarkett Komfort Sp. z o.o.
– Tel. +48 22 639 31 66 > Portugal: Tarkett SA – Tel. +351 21 427 64 20 > Russian Federation: Tarkett Russia – Tel. +7 4 95 777 69 83 > Slovakia: Tarkett SAS - Tel. +421 37 6515 404
> Singapore: Tarkett Far East – Tel. +65 67 43 53 84 > South East Europe: Tarkett Trade d.o.o. – Tel. +381 21 7557 649 • (44) 569 12 21 > Spain: Tarkett Floors S.L –
Tel. +34 91 358 00 35 > Sweden: Tarkett Sverige AB – Tel. +46 771 25 19 00 > Switzerland: Tarkett Holding GmbH, Bereich Objekt Schweiz – Tel. +41 043 233 79 24 > Ukraine: Tarkett
UA – Tel: +380380 (44) 569 12 21 > United Kingdom: Tarkett-Marley Floors Limited – Tel. +44 (0) 1622 854 040 > North America: Johnsonite – Tel. +1 440 543 8916
> Tarkett Inc. USA – Tel. +1 713 869 5811 > Tarkett International: Tel. +49 6233 811 755 – Tel. +33 1 41 20 41 01