19
Westside Treatment Plant Update May 14, 2018 Vancouver City Council Workshop Dan Swensen, Engineering and Construction Services Manager Frank Dick, Senior Civil Engineer

Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Westside Treatment Plant Update

May 14, 2018 Vancouver City Council Workshop

Dan Swensen, Engineering and Construction Services Manager

Frank Dick, Senior Civil Engineer

Page 2: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• Overview of Westside Wastewater Treatment Plant • Recap of events from Fall 2017 and progress since • Regulatory response to events • Influent Pumps Bypass Project • Other related Capital Improvement Projects (CIP) in process • Informational presentation – No action being requested

Presentation Overview

Westside Treatment Plant Update - 2

Page 3: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• Absolutely must work 24 / 7 / 365 • Treats 10 million gallons per day on average – 7000 GPM (gallons per minute)

• Westside handles the solids removed from the City’s two wastewater plants • Treatment theory is straight forward – Complexity comes from the high

volume required through these facilities and the need for process reliability. • Treatment relies heavily on electricity to move large amounts of water

through the treatment process.

Overview – Westside Treatment Plant

Westside Treatment Plant Update - 3

Page 4: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Five steps of treatment • Screening • Primary clarification • Biological treatment • Secondary clarification • Disinfection

Overview – Westside Treatment Plant continued

Westside Treatment Plant Update - 4

Page 5: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Screening

Westside Treatment Plant Update - 5

Page 6: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Primary Clarifiers

Westside Treatment Plant Update - 6

Page 7: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Biological Treatment

Westside Treatment Plant Update - 7

Page 8: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Secondary Clarifiers

Westside Treatment Plant Update - 8

Page 9: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Ultraviolet Light Disinfection

Westside Treatment Plant Update - 9

Page 10: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• September 30 event – Caused initially by a power interruption • October 25 event – During routine calibration of sensors • Causes of these two events were unrelated. • Steps taken since these events occurred

• Immediate actions • Some steps involve capital improvement projects

Events of Fall 2017

Westside Treatment Plant Update - 10

Page 11: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• Our regulator is Washington Department of Ecology (Ecology). • With our complete cooperation, Ecology is investigating. • To date: Waiting to hear back. No results yet communicated to

the City.

Regulatory Response

Westside Treatment Plant Update - 11

Page 12: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• “Bypass” is the ability to use an different route from influent control to treatment processes; bypassing influent pumps in the case of a power failure.

• Vulnerability was highlighted during operator contract procurement process. • Operator’s financial assistance was negotiated as part of the City contract. • Project design is moving toward 50 percent. • Creates an emergency pumping system independent of electric utility.

Bypass Project - Estimated $2 million

Westside Treatment Plant Update - 12

Page 13: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged
Page 14: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged
Page 15: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged
Page 16: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• Modernizing SCADA (System Control and Data Acquisition) - $12.5 M

• Electrical System Overhaul - $ 10 M (pre-design estimate) • Supply into the plant • Distribution throughout the plant • Emergency Switch Gear

Other Related Capital Projects

Westside Treatment Plant Update - 16

Page 17: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• Vancouver and CH2M take environmental protection and public trust in our wastewater treatment operations very seriously.

• Vancouver’s wastewater treatment processes function reliably to treat wastewater effectively.

• Vancouver’s treatment processes are highly regulated by the Washington State Department of Ecology.

• Vancouver’s two treatment plants are professionally run by a dedicated team of professional operators.

Takeaways

Westside Treatment Plant Update - 17

Page 18: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

• Our experience through these events highlights a much more engaged partnership with our operator.

• CH2M has demonstrated a high level of transparency within their operations.

• Events demonstrate the need for ongoing capital investment and reinvestment in our infrastructure.

Takeaways continued

Westside Treatment Plant Update - 18

Page 19: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged

Questions and Discussion

Dan Swensen, Engineering/Construction Services Manager (360)487-7750

Frank Dick, Senior Civil Engineer (360)487-7179

Westside Treatment Plant Update - 19