Welding of Duplex Stainless Steel Pipelines

  • Upload
    alaa

  • View
    237

  • Download
    3

Embed Size (px)

Citation preview

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    1/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    Contents

    1.  Introduction ..................................................... ........................................................... ......... 1 1.1 Purpose................................................................ ......................................................... .... 1 1.2 Changes to the Specification................ ...................................................................... ...... 1 1.3 Effective Period .............................................................. ................................................. 1

    1.4 Review and Improvement........................................................... ..................................... 1 1.5 Process Owner's Responsibility ............................................................. .......................... 1 

    2.  Specification for Welding Duplex Stainless Steel.............................................................. 2 2.1 Specification Requirements ........................................................ ..................................... 2 2.2 Process Deliverables ........................................................... ............................................. 2 2.3 Performance Levels / Indicators ............................................................ .......................... 2 2.4 Performance Monitoring ............................................................ ...................................... 2 

    Appendix A Glossary of Definitions, Terms and Abbreviations........... ............................... 3 

    Appendix B Amendments/Supplements to ASME B31.3 ..................................................... 6 

    Chapter V Fabrication, Assembly and Erection ................................................................. .. 6 

    328  Welding ....................................................... ................................................................ .... 6 328.2  Welding Qualifications...................................................................... ................... 6 

    328.2.1  Qualification Requirements............................................................................. 6 328.2.1.1  General......................................... ........................................................ 6 328.2.1.2  Welding Procedure Specification ........................................................ 6 328.2.1.3  Essential Variables......................................... ...................................... 7 328.2.1.4  Test Welding................ ................................................................ ........ 8 328.2.1.5  Examination of the Test Weld ........................................................... 10 328.2.1.6  Destructive Testing of the Test Weld ................................................ 10 328.2.1.7  Retests.................................................................. .............................. 13 328.2.1.8  Approval of the WPS..................... .................................................... 13 328.2.1.9  Performance Qualification ................................................................. 13 

    328.2.2  Procedure Qualification by Others...... .......................................................... 14 328.2.3  Performance Qualification by Others............................................................ 14 328.2.4  Qualification Records............................................................................. ....... 14 

    328.3  Welding Materials ................................................................ .............................. 15 328.3.1  Filller Metal...................................................... ............................................. 15 

    328.3.1.1  Storage and Handling of Filler Metals and Fluxes ............................ 15 328.3.1.2  Shielding Gases......................................................................... ......... 16 

    328.3.2  Weld Backing Material .................................................................. ............... 16 328.3.3  Consumable Inserts .............................................................. ......................... 16 

    328.4 

    Preparation for Welding ............................................................ ......................... 16 328.4.1  Cleaning ......................................................... ............................................... 16 

    328.4.2  End Preparation......................... ........................................................... ......... 16 328.4.3  Alignment................................................................... ................................... 17 

    328.5  Welding Requirements ........................................................... ............................ 18 328.5.1  General.................................................... ...................................................... 18 328.5.2  Fillet and Socket Welds ........................................................ ........................ 20 328.5.4  Welded Branch Connections..................... .................................................... 21 

    328.6  Weld Repair ......................................................... ............................................... 21 328.6.1  General.................................................... ...................................................... 21 328.6.2  Welding of Test Repair Welds...................................................................... 22 328.6.3  Testing of Repair Welds ................................................................ ............... 22 

    330  Preheating.............................................................. ....................................................... 22 330.1  General.......................................................... ...................................................... 22 

    December 2004 SP-1096  ii 

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    2/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    330.1.1  Requirements and Recommendations............................................................22 330.1.

    330

    330.2.4  Interrupted Welding ........................................................ .............................. 23 

    331  Heat Treatment ........................................................ .................................................... 23 

    332 di

    332.1  General................................................................................................................23  

    333  Brazing and Soldering..................................................................................................23 

    336 ndl

    336.3  Pipe Handling......................................................................................................24 

    Chapter VI Inspection, Examination and Testing............................................................... 25 

    340 pec

    340.4  Qualifications of the Owner’s Inspector ............. Error! Bookmark not defined. 

    341 m

    341

    .3.

    341

    341.4.1  Examination Normally Required...................................................................25 

    342 m

    342.1  Personnel Qualification and Certification ........................................................... 26 

    343  Examination Procedures..............................................................................................26 

    344 es

    344

    .2.

    344

    .5.

    344.6  Ultrasonic Examination.......................................................................................28 

    345 tin345.1  Required Leak Test ......................................................... .................................... 28 

    346 or

    346.1  Documentation............................................................ ........................................ 28 

    4  Preheat Zone..................................................................................................22 .2  Specific Requirements ................................................................ ........................23 

    Ben ng and Forming ..................................................................................................23 

    Ha ing and Storage ..................................................................................................23 336.1  General................................................................................................................23  336.2  Storage .................................................... ............................................................ 24 

    Ins tion.......................................................................... Error! Bookmark not defined. 

    Exa ination..................................................................................................................25 341.2  Responsibility for Examination...........................................................................25 

    .3  Examination Requirements .................................................................... .............25 341.3.1  General ........................................................ .................................................. 25 341 2  Acceptance Criteria ................................................................ ....................... 25 .4  Extent of Required Examination.........................................................................25 

    Exa ination Personnel ................................................................................................26 

    Typ of Examination ..................................................................................................27 .2  Visual Examination.............................................................................................27 344 2  Method...........................................................................................................27  

    344.3  Magnetic Particle Examination .............................................................. .............27 344.4  Liquid Penetrant Examination.............................................................................27 

    .5  Radiographic Examination..................................................................................27 344 3  Method...........................................................................................................27  

    Tes g ...........................................................................................................................28 

    Rec ds..........................................................................................................................28 

    iii 

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    3/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    347  Certificate of Conformity ........................................................ .................................... 29 

    Table 1 Extent of Non-Destructive Testing for Welds ........................................................ 30 

    Figure 1  Hardness Indent Locations .................................................................. ............ 32 

    Figure 2  Orientation and Location of Charpy Impact Specimens .............................. 33 

    Appendix C References.............................................................................. ............................ 34 

    Appendix D Determination of the Volume Fraction of Ferrite in Duplex Stainless Steel by

    Systematic Point Count ......................................................... ............................................ 36 

    Appendix E Certificate of Compliance.............. ................................................................ ... 40 

    User Comment Form ....................................................... ....................................................... 41 

    iv 

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    4/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    1. Introduction

    1.1 Purpose

    This specification is a revision of SP-1096 version 1.0, Specification for Welding of Duplex

    Stainless Steel Piping, issued in July 1999. The purpose of this document is to define theminimum technical requirements for the welding of duplex stainless steel (DSS) pipework.

    This specification is intended to be used where the applicable code has been designated by

    the Company as ASME B31.3, 2002. Chemical Plant and Petroleum Company Piping,

    (normally on-plot locations).

    This document is not applicable to the welding of DSS pipelines, where the applicable code

    has been designated as ASME B31.4 or ASME B31.8 (off-plot locations) or to the

    manufacture of welded DSS pipe

    1.2 Changes to the Specification

    This Specification shall not be changed without approval from the Custodian, the Material

    and Corrosion Functional Discipline Head (CFDH) who owns this Specification. If youthink the Specification is not correct, write your comments on a copy of the User Comments

    Form. The form is included as the last page of this Specification. Send the copy with your

    comments and personal details to DCS.

    1.3 Effective Period

    The requirements of this specification shall remain in force indefinitely unless superseded by

    an authorised revision.

    1.4 Review and Improvement

    This specification will be reviewed and updated once every three years. The review authoritywill be CFDH Materials and Corrosion. 

    1.5 Process Owner's Responsibility

    The owner of this specification is CFDH Materials and Corrosion, is responsible for

    authorising all proposed deviations or amendments to the specification and for the instigation

    of periodic reviews and updates in accordance with Clauses 1.2 and 1.4. 

    Page 1

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    5/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    2. Specification for Welding Duplex Stainless Steel

    This specification gives the minimum requirements for the welding, fabrication and

    inspection of duplex stainless steel on-plot pipework. The scope is intended to cover all

    commercially available compositions (MESC), including 22Cr and 25Cr duplex/superduplex

    grades. The specification is restricted to piping for service in non-sour environments where

    the applicable Code for pressure piping is designated by the Company as ASME B31.3,

    Chemical Plant and Petroleum Refinery Piping. The use of duplex stainless materials in

    environments containing H2S shall be subject to approval by the Company.

    2.1 Specification Requirements

    Welding, fabrication and inspection shall be in accordance with the requirements of ASME

    B31.3, 2002 Edition, as amended and supplemented by Appendix B of this specification.

    The amendments and supplements given in Appendix B are considered necessary to ensure

    integrity of the fabricated pipework in accordance with PDO and Shell Group requirements.

    The Clause numbering in Appendix B follows that of ASME B31.3. Where clauses of 

    ASME B31.3 are not amended or supplemented by Appendix B, they shall apply in their entirety.

    2.2 Process Deliverables

    Process deliverables comprise shop or field welded duplex stainless steel pipework and

    related welded fabrications designed to ASME B31.3 and normally intended for on-plot oil,

    gas or water service.

    2.3 Performance Levels / Indicators

    See relevant ASME B31.3 weld inspection and testing acceptance criteria and the

    amendments given in Appendix B of this specification.

    2.4 Performance Monitoring

    Requirements for monitoring welding process variables, welder performance and weld

    quality are detailed in relevant sections of ASME B31.3/ASME IX as amended by Appendix

    B of this specification.

    December 2004 Page 2 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    6/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    Appendix A Glossary of Definitions, Terms and Abbreviations

    Certain terms and abbreviations used in this document are defined below. The listed

    definitions shall be considered to supplement those given in ASME B31.3.

    General Definitions

    Contractor The party which carries out all or part of the design,

    engineering, procurement, construction, commissioning or

    management of a project, or operation or maintenance of a

    facility. The Company may undertake all or part of the duties of

    the Contractor.

    Manufacturer/ The party ch manufactures or supplies equipment and

    Company etroleum Developmant Oman LLC. The Company will

    y may

    User he Company, Consultant or Contractor who uses this

    Corporate Functional he person within the Company responsible for the discipline to

    shall dicates a requirement. Any deviation to a requirement shall be

    should dicates a recommendation. A deviation to a recommendation

    may dicates a possible course of action.

    Specific Definitions

    Batch or Lot

    8.3.1) 

    As defined in AWS A5.01, Clause 5 (Classification) and

    Duplex Stainless Steel chromium-nickel-molybdenum stainless steel containing a

    Nominal Thickness ominal thickness t shall have the following meanings:

     butt joint; parent metal thickness, which for joints between

    etween

     pe.

    Owner erm used in ASME B31.3 that shall be understood to mean

    Supplier

    whi

    services to perform the duties specified by the Contractor.

    P

    generally specify the technical requirements. The Compan

    also include an agent or consultant authorised to act for, and on

     behalf of, the Company.

    T

    document.

    Discipline Head

    T

    which the standard belongs.

    In

    approved by the CFDH.

    In

    shall be approved by the welding (TA-2).

    In

    (see App. B, 32 Clause 6 (Testing)

    A

     balance of austenite and ferrite stabilising alloying elements

    such that the microstructure at room temperature consists of

    approximately equal proportions of austenite and ferrite.

     N

    -

    dissimilar thicknesses is that of the thinner material.

    - fillet weld; parent metal thickness, which for joints b

      dissimilar thicknesses is that of the thicker material.

    - set-on branch connection; thickness of branch pipe

    - set-through branch connection; thickness of main pi

    T

    the Company.

    December 2004 Page 3 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    7/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    Verified copy A photocopy of an original document which has been re-

    endorsed and signed by the organisation producing the

     photocopy to verify that none of the information has been

    adulterated.

    Welding Co-ordinator The Contractor nominated authority on the quality aspects of

    welding. The Welding co-ordinator shall be a Welding

    Engineer meeting the recommendations for EuropeanWelding Engineer (refer ISO 14731). However, other

    national/ international qualifications may be considered at the

    discretion of the Company. The Welding Co-ordinator shall

     be approved by the Company TA-2 (Welding).

    Abbreviations

    a Throat Thickness of Fillet Weld

    ASNT American Society for Non-destructive Testing

    CFDH Corporate Functional Discipline Head

    AWS American Welding Society

    CSWIP  Certification Scheme for Welding Inspection Personnel

    D   Nominal Outside Diameter

    DSS Duplex Stainless Steel

    DNV  Det Norske Veritas

    GTAW  Gas Tungsten Arc Welding

    IQI Image Quality Indicator

    HAZ  Heat Affected Zone

    HV  Vickers Hardness

    NDE   Non-destructive Examination

    PAMS  Portable arc monitoring system

    PQR   Procedure Qualification Record

    PRE Pitting Resistance Equivalent

    PT Penetrant Testing

    PWHT  Post Weld Heat Treatment

    RT  Radiographic Testing

    SAW  Submerged Arc Welding

    SMAW  Shielded Metal Arc Welding

    December 2004 Page 4 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    8/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    T   Nominal Thickness

    TA Technical Authority, as defined in ERD-00-02 and PDO GU-272.

    TWI The Welding Institute

    WPS Welding Procedure Specification

    WFS Wire Feed Speed

    December 2004 Page 5 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    9/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    Appendix B Amendments/Supplements to ASME B31.3

    Chapter V Fabrication, Assembly and Erection

    328 Welding

     Delete introductory paragraph and replace as follows:

    Welding shall be performed in accordance with the requirements of ASME B31.3 and the

    amendments and additions of this specification. The work shall be undertaken only by

    Contractors that have been approved by the Company specifically for the on-plot welding of

    duplex stainless steel, (Work Category CE6421). Approval of Contractors shall be based on

    Company document GU-225.

    The welding Contractor shall maintain and operate a quality system that shall be in

    accordance with ISO 9001:2000, and SP-1171. A quality system based on alternative

    standards to of ISO 9001 may be considered for agreement by the Company. All welding

    and related activities shall satisfy the requirements of ISO 3834-2. It is recommended tofollow the guidelines given in PD CR 13576.

    328.2 Welding Qualifications

    328.2.1 Qualification Requirements

     Delete entire section and replace as follows:

    328.2.1.1 General 

    Where the Contractor is unable to provide satisfactory records to demonstrate the suitability

    of the proposed welding procedure specification and compliance with ASME B31.3 and this

    specification, welding procedure qualification shall be undertaken prior to the

    commencement of production welding.

    The Contractor shall submit WPS proposals to the Company for review and approval a

    minimum of two weeks prior to undertaking qualification welding. The WPS proposals

    shall be endorsed by the Contractor's Welding Engineer. A Welding Procedure Register

    shall accompany the package. This shall list and identify all WPS/PQRs intended to be used

    for the contract, detailing as a tabulated summary welding processes, materials and qualified

    dimensional ranges.

    The qualification of dissimilar welds, between duplex stainless steel and other material

    groups, shall be in general accordance with this specification, except that welding

    consumables and specific test requirements will be agreed by the Company Welding TA - 2(or higher) for each application.

    Note: Any welding procedure qualified to meet project specific requirements for which the Company has

    paid/reimbursed the cost of qualification shall be owned by the Company. The Company will keep original

    PQR copies.

    328.2.1.2 Welding Procedure Specification

    The format of the WPS shall be equivalent to form E00006, shown as QW-482 in Appendix

    A of ASME IX, and shall contain the following applicable parameters, including

    explanatory details where necessary.

    •  Material specification of base metals.

    December 2004 Page 6 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    10/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    •  Welding process and whether manual or automatic.

    •  Wall thickness and diameter range for which the procedure is valid, (see 328.2.1.3 (c)and (d)).

    •  Geometry of the welding groove showing allowable tolerances.

    •  Root gap showing allowable tolerances.

    •  Welding position and direction.

    •  Filler metal specification and diameter.

    •  Filler metal classification and coating type.

    •  Specification of flux.

    •  Tungsten electrode type and specification.

    •  Gas shielding flow and composition.

    •  Gas backing flow and composition

    •   Number of weld passes for which gas backing is required.

    •   Number and sequence of all passes, indicating stringer or weave beads. For automaticwelding the weave amplitude, weave frequency and dwell time shall also be included.

    •  Welding current range, voltage range and polarity. If pulse welding is used, the background current and range of pulse parameters or unique program reference to be

    included.

    •  Where applicable, electrode stick-out and WFS range.•  Travel speed range for each pass.

    •  Heat input range.

    •  Preheat and interpass temperatures.

    •  Methods of joint preparation interpass cleaning and weld finishing.

    •  Method of clamping/tacking, including details of removal

    Test welding shall not commence until the WPS proposal has been stamped 'Approved for

    Qualification' with the date and the contract number, and signed by a Company welding

    TA-2.

    328.2.1.3 Essential Variables

    When changes in any of the parameters listed below are made beyond the indicated limits,

    the welding procedure shall be set up as a new WPS and shall be completely re-qualified.

    (a) Welding process A change to another welding process or a change from

    manual to automatic operation or vice versa.

    (b) Base materials Any change in UNS number. A change in the PREN

    exceeding –1.5 or +2.5. For super-duplex grades any

    change in manufacturer or product form shall be

    considered an essential variable. A procedure qualified

     by welding together products from different

    manufacturers or different product forms shall qualify

     both the combination and welds between each product..

    (c) Thickness For t > 5mm, a change in thickness at the joint outside

    the range 0.75t to 1.5t, but not < 5mm. For t < 5mm,a

    change outside the range t to 1.5t. For a fillet weld, in

    addition to material thickness, a change in throat

    thickness outside the range 0.75a to 1.5a.

    (See Appendix A of this specification for definitions of

    t).

    (d) Diameter (D) Change in pipe or branch diameter outside the

    following ranges:

    D

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    11/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    (e) Joint design Any change in joint configuration outside the specified

    tolerance.

    (f) Welding position Any change, except that, subject to the approval of the

    Company Welding TA-2, qualification of a joint in the

    fixed 45° inclined (6G) position shall qualify for all

     positions.

    (g) Welding

     progression

    A change from uphill to downhill or vice versa. 

    (h) Filler

    metal/electrode

    Any change in electrode/filler metal classification or

    trade name, except that for solid filler wire, a change to

    a different trade name may be accepted without re-

    qualification subject to the approval of the Company

    Welding TA-2. Any change in electrode or filler wire

    diameter.

    (i) Flux Any change in size, classification or trade name.

    (j) Shielding or backinggas

    A change in nominal flow rate of more than ±20%.Any change in nominal composition of shielding or

     backing gas. Any increase in maximum oxygen

    content of effluent backing gas.

    (k) Number and

    sequence of passes

    Any change in the sequence of filling or capping passes

     beyond that required to accommodate the qualified

    range of joint dimensions. Any decrease in the number

    of passes before cessation of backing gas.

    (l) Electrical

    characteristics

    A change of more than ±15% in the individual values

    for volts, amps and wire feed speed determined from

    the PQR. Changes in individual parameters and ofwelding speed, (clause (m)), shall be controlled such

    that heat input is maintained within the permitted range

    of clause (n).

    A change of electrode polarity or current type,

    including the addition or deletion of pulsating current.

    (m) Speed of travel Any change greater than ±15%. 

    (n) Heat input Any change in average welding heat input per pass

    outside the range ±10% of that qualified.

    (o) Preheat or interpass

    temperature

    An increase of more than 50°C in the specified

    minimum preheat temperatures or any increase in

    maximum interpass temperature.

    (p) Post-weld heat

    treatment

    The inclusion or deletion of PWHT or any change in

    PWHT parameters.

    328.2.1.4 Test Welding

    Sufficient test welds shall be made to extract all the destructive test specimens required for

    qualification testing. Test welding shall be witnessed by the Company Welding TA-3. The

    Contractor shall give the Company a minimum of 48 hours notice of the intention to proceed

    with test welding.

    December 2004 Page 8 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    12/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    The Contractor shall have a minimum of one Company-approved calibrated portable arc

    monitoring system with hard copy facility available at the test site to record welding

     parameters. No test welding is permissible without recording the welding parameters using

    a calibrated portable arc monitor . 

    Prior to the commencement of test welding, the Contractor shall have available at the test

    site the following documents for verification by the Company:

    •  Original copy of the WPS proposal, endorsed ‘Approved for Qualification’

    •  Material certificates or verified copies, traceable to the items to be welded.

    •  Batch certificates or verified copies, traceable to the welding consumables, (see

    328.3.1).

    •  Approved consumable handling procedure.

    Test welding shall not commence until the Company has reviewed and accepted the

    documentation. All test welding shall be witnessed by a Company representative having a

    Welding Technical Authority level 3 or higher. The Contractor’s Welding Coordinator who

    is approved by the Company shall supervise the entire welding procedure qualification

     process. The Contractor shall be responsible for examination and shall have a Company

    approved welding examiner (Welding Inspector) present throughout test welding and NDE

    of the welds. NDE shall be performed only by Company registered NDE subcontractors in

    accordance with SP-1176.

    The test weld shall simulate as closely as possible the actual production environment and

    welding set-up used, including as applicable, clamping, support and back purging

    arrangements. The longest length of internal purge tubing expected to be required for use

    with the procedure should be included in the test set-up to confirm that the required purging

    conditions can always be attained and monitored without affecting weld quality. Set-up

    details shall be recorded in the test welding record. In order that root oxidation can be

    assessed under ‘worst case’ conditions, welding should commence as soon as the maximum

    specified back purge oxygen level is reached.

    The following information shall be recorded for each pass of the test weld and shall form

     part of the PQR:

    •  Pass number

    •  Welding process

    •  Consumable diameter

    •  Consumable trade name and classification (including flux for SAW)

    •  Electrode polarity

    •  Gas composition

    •  Gas flow rate

    •  Arc voltage

    •  Current

    •  Wire feed speed

    •  Travel speed

    •  Preheat temperature

    •  Interpass temperature

    •  Pass sequence

    The test weld information shall be recorded on welding parameter sheets which shall be

    attached to the completed form E00007, shown as QW-483 in Appendix A of ASME IX.

    Pass sequence shall be shown in the sketch on the ASME form. The Approved for

    Qualification WPS, original or verified copies of the test coupon material and consumable

     batch test certificates and the original PAMS unit printout shall be included as part of the

    PQR. The welding records of the test welding shall be signed, dated, and endorsed by the

    Contractor's welding examiner (Welding Inspector) and the Company welding TA-3 presentat the time of test welding.

    December 2004 Page 9 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    13/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    If post weld heat treatment is required, a heat treatment record chart shall be produced and

    shall be endorsed by the Contractor, the heat treatment sub-contractor (if applicable), and the

    Company Welding TA-3 present during heat treatment. The chart shall be included in the

    PQR.

    328.2.1.5 Examination of the Test Weld

     NDE shall be witnessed by a Company Welding TA-3 (or higher) or by a Third Party

    Inspector nominated by the Company.

    The NDE shall consist of the following:

    •  Visual examination

    •  Liquid penetrant testing

    •  Radiographic testing

     NDE on all test welds shall be performed with the weld at ambient temperature using

    equipment and Company-approved procedures that will be employed for production. NDE

    of a test weld may serve as a qualification test for the NDE procedures.

    The acceptance criteria shall be as stated in Chapter VI of ASME B31.3 and the

    corresponding sections of this specification. Any weld that fails to meet the acceptance

    criteria shall not be offered for destructive testing. Visual examination of all butt welds shall

    include the pipe bore surfaces. The degree of oxidation present on these surfaces following

    welding shall be within the visual acceptance criteria of DEP 30.10.60.31-GEN.

    The radiographic report shall be signed by the technician and the Contractor's welding

    examiner prior to presenting the radiographs to the Company Welding TA-3 with

    interpretation qualification for viewing. After viewing, the Company Welding TA-3 shall

    sign and endorse the radiographic report and it shall be incorporated into the PQR.

    328.2.1.6 Destructive Testing of the Test Weld

    Testing for procedure qualification shall be performed in accordance with ASME IX and the

    additional requirements in Paragraphs (a) to (f), following. The Contractor shall appoint a

    Company-approved agency to witness the destructive testing. This agency shall certify that

    all tests are made in accordance with the controlling specifications. The Company shall

    have the option to witness the destructive testing or to appoint an agency to act on its behalf.

    All test reports shall be endorsed and signed by the testing organisation, the Contractor, and

    the third party inspector who witnessed the testing. The test reports shall be included in the

    PQR.

    (a) Macro-examination

    Two macro-sections shall be taken from a butt weld in pipe at the 12-1 o'clock and the6-7 o'clock positions. Where two welders have made the joint, the macro specimens

    shall be taken from the specified positions such that each welder's portion is sampled.

    For branch welds, four macro-sections shall be taken at 90° intervals through the centre

    of the joint, in line with the longitudinal or transverse axis of the run pipe.

    Specimens shall be prepared for macroscopic examination by grinding or other suitable

    method to a 600 grit paper finish. The prepared surfaces shall be etched using a suitable

    etchant to reveal the pass sequence, HAZ, defects etc. Metallographic examination of

    representative sections shall also be performed to confirm the microstructure of the

    weld/HAZ and the absence of deleterious phases. Observations shall be included with

    the macroscopic examination report

    Macro-examination shall be carried out at a minimum magnification of x5. The

    acceptance criteria shall be as detailed in chapter VI of ASME B31.3 and shall include

    December 2004 Page 10 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    14/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    measurements for height of reinforcement and internal protrusion. Following the

    hardness measurements detailed below in paragraph 328.2.1.6(b), macrophotographs

    shall be produced for inclusion in the PQR.

    (b) Hardness survey

    For pipe, a hardness survey shall be performed on each macrosection. The hardness,shall be measured in accordance with ASTM E92 using a 10 Kg load. For pipe butt

    welds, the hardness indentations shall be as shown in Figure 1 of this specification and

    shall be clearly visible in the macrophotographs. For pipe of t less than 10 millimetres,

    the mid-thickness traverse may be omitted. One indent of each HAZ set of three shall

     be as close to the fusion line as possible but shall not intercept it.

    The sections of the weld taken for macroscopic examination and hardness testing shall

    also be used for the ferrite measurements required in the following clause, 328.2.1.6(c).

    The maximum hardness values from each traverse shall not exceed 325 HV10.

    (c) Ferrite measurement

    The ferrite content shall be determined by microscopic point counting in accordance

    with ASTM E562 and Appendix D of this specification, For DSS, a magnetic

    measurement technique using an instrument calibrated to AWS 4.2 may be used.

    Ferrite determinations shall be made in the weld metal and both HAZ areas at a depth of

    1mm from the inside and from the outside surfaces, or for magnetic techniques, as close

    to the surface as is practicable. Additional checks shall be made in the centre of the

    unaffected base material on each side of the weld.

    Ferrite content determined by microscopic point counting shall be in the range 40 - 60%

    for the parent material and 35 - 65% in the weld/HAZ regions. The ferrite range for

    magnetic measurements shall be between 30 – 70 FN. In the event that borderline

    unacceptable or otherwise doubtful results are obtained using magnetic measurement, acheck point-counting determination may be made if agreed by the Company Welding

    TA-2. If the results of these repeat tests are satisfactory, the ferrite content shall be

    considered to be acceptable.

    (d) Charpy V-notch impact tests

    Each procedure qualification shall include impact testing unless the nominal pipe wall

    thickness is less than 4.8 mm. The sampling area of the weld shall be as shown in

    Figure QW-463.1(f) of ASME IX.

    One set of three specimens shall be taken at each of the following positions:

    •  root weld centre line

    •  root fusion line (50% intersection of notch)

    •  root fusion line + 2 millimetres

    When the wall thickness exceeds 20 millimetres, an additional set of three specimens

    shall be taken at each of the following positions:

    •  cap weld centre line

    •  cap fusion line (50% intersection of notch)

    •  cap fusion line + 2 millimetres

    These requirements are summarised in Figure 2 of this specification.

    December 2004 Page 11 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    15/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    Specimens shall be 10 x 10 millimetres full size wherever possible. Where these

    dimensions are not possible, the largest obtainable standard sub-size specimens shall be

    extracted.

    Testing in accordance with ASTM A370 and this specification shall be conducted at

    minus 20°C or at the minimum design temperature, whichever is the lower. The test

    temperature shall remain the same for all specimen thicknesses.

    For each set of three specimens, only one of the individual values may be below the

    minimum average energy requirement with an absolute minimum as defined by the

    minimum individual acceptance criterion.

    The acceptance criteria are detailed in the Table below. For other standard specimen

    dimensions, the acceptance criteria shall be applied pro rata.

    Specimen size, mm Charpy Energy, Joules

    Minimum Average  Minimum Single 

    10 x 10 40 30

    10 x 7.5 30 23

    10 x 5 20 15

    (e) Corrosion testing

    A pitting corrosion resistance test shall be conducted in accordance with ASTM G48,

    Method A, using the total immersion ferric chloride test. A coupon specimen of

    dimensions 5 cm x 5 cm x full wall thickness shall be prepared to the requirements of

    ASTM G48, Section 5. No flattening of the coupon material shall be carried out. Theweld seam shall be located centrally and parallel to one axis. The edges of the specimen

    shall be rounded to minimise edge effects and the sides ground to 600 grit finish. Other

    surfaces shall be in the "as-finished" condition.

    The specimen shall be degreased, dried, weighed to three decimal places and the weight

    recorded.

    The specimen shall be held in the solution at an angle of 45°, with inside surface

    uppermost. Unless otherwise directed, the test shall be conducted for a period of 24

    hours at a temperature of 22°C ± 2°C. For the higher alloyed 25Cr duplex/superduplex

    grades the test temperature shall be 35-37ºC unless otherwise specified

    On completion of the test period the specimen shall be rinsed, cleaned, dried andreweighed using the procedures specified in ASTM G48A. The specimen shall be

    examined at a magnification of x20. No pitting shall be visible. Weight loss shall be

    expressed as total weight loss and weight loss per unit area. The latter shall not exceed

    8g/m2.

    All samples shall be made available for inspection by the Company.

    (f) Chemical analysis

    Chemical analysis shall be conducted of the root run weld metal. The weld metal

    sample shall be taken from an adjacent or equivalent location to that shown for the

    impact test specimens in Figure A. The elements required for calculation of the PRE(see Section 328.3.1) shall be determined. The PRE value shall exceed the minimum

    specified for the base material to be welded.

    December 2004 Page 12 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    16/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    328.2.1.7 Retests

    With the exception of Charpy tests and hardness tests, if any one mechanical test specimen

    fails to meet the minimum requirements, two additional test specimens shall be extracted and

    tested. The Contractor shall notify the Company of the test failure and obtain written

    Company approval to proceed with retests. If both of the retests are acceptable that

     particular test shall be deemed as acceptable. Should one or both of the retests fail then the procedure shall be rejected immediately.

    For hardness tests, if only one hardness result exceeds the specified maximum then a

    minimum of three further indentations shall be made in close proximity to that which failed

    such that they do not mutually interfere. If all of the further tests are below the maximum

    specified hardness the test shall be accepted. The Contractor shall notify the Company of the

    test failure and obtain written Company approval to proceed with retests

    For Charpy tests, if the specified minimum average value has been achieved and more than

    one specimen is below the specified average value, or one specimen is below the specified

    minimum individual value, a retest of three further specimens shall be made. All three

    individual retest values shall equal or exceed the specified minimum average value.

    Retesting of any corrosion specimen which fails to meet the pitting and/or weight loss

    acceptance criteria in the ASTM G48A corrosion test shall be permitted only if failure can

     be reasonably attributed to test conditions or sample preparation. Where retesting is agreed

     by the Company, two further specimens shall be prepared and tested. Both of the additional

    specimens shall meet the acceptance criteria.

    If the test joint fails to meet the minimum requirements, a new WPS proposal shall be

    established and qualification welding and testing repeated.

    328.2.1.8 Approval of the WPS

    Subsequent to successful non-destructive and destructive testing, the Contractor shall submitthe original PQR showing endorsement and signatures of the Contractor, the testing

    subcontractor, and the Company. The Contractor shall also submit a copy of the WPS to be

    used for production welding and, if necessary, a revised welding procedure register for

    review and approval by a Company Welding TA level 2 or higher.

    Production welding shall not commence until the WPS has been endorsed 'Approved for

    Fabrication' with the date and the contract number, and signed by a Company welding

    Technical Authority level 2. Only those WPSs shown on the approved WPS register shall

     be used in production.

    328.2.1.9 Performance Qualification

    Welders and welding operators shall be qualified in accordance with the requirements of

    ASME IX and of this specification.

    For Super DSS any change which necessitates requalification of the WPS shall also require

    requalification of the welder. For DSS, the following essential variables shall be applied for

    welder qualification:

    (a)  A change in joint thickness to more than twice the thickness of the test joint.(b)  A change in pipe or branch diameter outside the range 0.5D to 2 D, where D is the test

     pipe diameter.

    (c)  A major change in joint configuration, e.g. ‘U’ to ‘V’ preparation(d)  A change in welding progression from uphill to downhill or vice versa.(e)  For manual welding electrodes, a change from one coating type to another

    (f)  Any change in the nominal composition of the shielding gas.

    December 2004 Page 13 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    17/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    Welders shall have a valid Company qualification within the validity defined in this

    specification or they shall be qualified on contract materials using a WPS endorsed

    ‘Approved For Fabrication’. A calibrated portable arc monitor shall be used to record

    welding parameters. Qualification shall be valid for a period of six months. This period

    may be extended by a further six months when it can be shown by  NDT from production

    welding that the welder has produced satisfactory welds using the approved for construction

    WPS. After 12 months the welder shall be re-qualified, unless otherwise agreed by theCompany Welding TA-2. The Company reserve the right to disqualify any welder whose

     performance during production welding is not satisfactory.

    The Company shall be given a minimum of 48 hours notice of intention to perform welder

    qualification in order to witness the test welding. Welding and testing shall be witnessed by

    a Company Welding TA-3. Butt weld test pieces shall be subjected to visual examination,

    radiography, bend testing and macroscopic examination to the requirements of ASME IX,

    QW-302 and this specification.

    A welder who fails to meet the acceptance criteria shall be allowed an immediate retest. A

    welder who fails to meet the acceptance criteria after the first retest shall not be allowed a

    second retest within seven days. The Contractor shall demonstrate that the welder has

    undergone training in that period. Failure to demonstrate training shall prevent the welder

    from being retested. Should the second retest fail then that welder shall be disqualified for

    the duration of the contract.

    Performance qualification data shall be recorded by the Contractor on ASME form E00008

    (QW-484) or other format agreed by the Company. The ASME form shall then be endorsed

    and signed by the Contractor and the Company Welding TA-3 who witnessed the test

    welding. The completed record forms shall be submitted to the Company Welding TA-3

    who shall issue a welder's card which shall show the WPS for which the welder is qualified,

    the welder's unique identification, and the Company TA-3 signature and endorsement. The

    welder shall maintain the card in his possession at the job site and shall produce it upon

    request by the Company. Failure to produce the card shall prevent the welder from welding

    until such time as it is produced. The card shall be the property of the Company and shall berevocable by the Company.

    The Contractor shall assign an identifying number, letter, or symbol to the qualified welder

    which shall be used to ensure traceability to specific welds. If a welder ceases to work for

    the Contractor, the unique identification shall not be reassigned to another welder.

    328.2.2 Procedure Qualification by Others

     Delete section and replace as follows:

    Procedure qualification by others, as defined in ASME B31.3 shall not be permitted.

    328.2.3 Performance Qualification by Others

     Delete section and replace as follows:

    Performance qualifications made for another employer shall not be accepted.

    328.2.4 Qualification Records

     Delete section and replace as follows:

    See sections 328.2.1.2, 328.2.1.4 and 346.1 of this specification.

    December 2004 Page 14 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    18/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    328.3 Welding Materials

    328.3.1 Filller Metal

     Add the following, including new sub-sections 328.3.1.1 and 328.3.1.2:

    Only consumables from Company approved suppliers shall be used. Approval shall includethe manufacturing plant and shall be verified by a third party inspection agency.

    Each batch of consumables shall be tested in accordance with the AWS procedures specified

    for the consumable classification. The tests shall be conducted with third party witness and

    verification at a Company approved facility. Batch testing is required, irrespective of

    whether the consumables are supplied with a verified copy of the Supplier’s/Manufacturer's

     batch certificate. The definition of a batch is given in Appendix A of this specification.

    All filler metals shall have classification society, (e.g., Lloyd's, DNV), type approval.

    Filler metals should be of matching specification to the base material to be welded with the

    exception of the following:

    •  The chromium and nickel contents of each batch should be equal to or higher than thoseof the filler used in the corresponding procedure qualification test.

    •  The PRE of the filler metal, as calculated from the batch test certification on the basisdefined below, should be at least 2 units higher than the minimum specified PRE of the

     base material to be welded.

    PRE = (%Cr) + 3.3(%Mo + 0.5%W) + 16(%N)

     NOTE: Tungsten (W) analysis need be considered only if specified as an alloying addition. 

    328.3.1.1 Storage and Handling of Filler Metals and Fluxes

    Electrodes, filler wires and fluxes shall be stored in a dry storage room in accordance with

    the manufacturer's instructions. Consumables shall remain in their original containers which

    shall be marked with the manufacturer's name, the consumable trade name, and the batch

    number. Consumables in containers that are not identifiable and traceable shall be removed

    from the job site to the satisfaction of the Company. The storage room should be maintained

    at a maximum relative humidity of 50%, which shall be monitored in accordance with an

    agreed procedure.

    Consumables delivered in containers that exhibit physical damage, shall be examined for

    damage. Consumables that show signs of damage or deterioration shall be disposed of to

    the satisfaction of the Company. All manual electrodes shall be properly identifiable up to

    the time of usage, each electrode being distinguishable by a coding marked near the grip

    end. Electrodes without a code marking shall not be used. Wire spools shall be stored in

    cabinets with the supplier's wrapping in place and shall remain clearly identifiable up to the

     point of usage. Unidentifiable wire shall not be used.

    Flux shall be handled and stored in accordance with the flux manufacturer's

    recommendations. The Contractor shall furnish the Company with datasheets for the flux

     prior to its arrival at site. Flux shall remain identifiable and traceable. Recycling shall not

     be permitted.

    Wherever available, basic coated electrodes should be supplied in sealed vacuum packs

    having a guaranteed hydrogen content. Electrodes not supplied in such vacuum packs shall

     be removed from the containers and baked in ovens in accordance with the manufacturer's

    instructions. The electrodes shall be transferred to holding ovens set at 150°C after baking,from where they shall be issued to heated quivers maintained at a minimum temperature of

    December 2004 Page 15 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    19/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    70°C. Duplex stainless steel electrodes shall not be stored in the same heated cabinets a

    electrodes of other materials. The maximum stacking height shall be four layers. The

     baking ovens and the holding ovens shall have automatic heat controls and a temperature

    read-out display. A ‘map’ or other acceptable method shall be employed so as to identi

    the contents and their location in the baking and holding ovens. Oven internal storage

    arrange

    s

    fy

    ments shall not allow intermixing of different electrodes (manufacturers and/or

    sizes).

    r

    e

    one re-bake. The Contractor shall have a system for identification of re-baked electrodes.

    e

    e consumable

    handling procedure has been approved by the Company Welding TA - 2.

    328.3.1.2 Shielding Gases

    ed on the WPS and shall be the same for procedure qualification and

     production welding. 

    Gases in containers that are unidentifiable shall not be used.

    328.3.2 Weld Backing Material

     Delete existing section and replace as follows:

    Backing rings shall not be used. 

    328.3.3 Consumable Inserts

     Delete existing section and replace as follows:

    Consumable inserts shall not be used.

    328.4 Preparation for Welding

    328.4.1 Cleaning

     Delete existing section and replace as follows:

    all be

    ing, the end preparation shall

     be degreased with a non-chlorinated solvent such as acetone.

    328.4.2 End Preparation

    (a) General

     Delete existing clause (1) and replace as follows:

    Consumable control shall be such that any basic coated electrodes shall be used within fou

    hours of issue to a quiver. Where this is not possible due to operational reasons, vacuum

    seal packed electrodes shall be used, (for which the requirement for issue into a heated

    quiver shall still apply). Those electrodes not used within four hours shall be returned to th

     baking oven. Electrodes shall be baked a maximum of two times, i.e. one initial bake and

    Prior to the commencement of qualification or production welding, whichever is sooner, th

    Contractor shall submit a consumable handling procedure to the Company for review and

    approval. Test welding or production welding shall not commence until th

    The shielding and purge gas shall be certified as complying with ISO 14175, AWS 5.32 or 

    equivalent. Hydrogen shall not be added. The purity or component concentrations of the

    gas shall be as specifi

    Fusion faces and the surrounding surfaces within a minimum of 25 mm of the joint sh

    free from heavy scale, moisture, oil, paint, or any other substance which may have a

    deleterious effect on the weld quality or progress. Before weld

    December 2004 Page 16 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    20/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    (1) Bevels shall normally be machined or prepared by grinding. Preparation of weld

    edges by plasma cutting is permissible provided a mechanically guided torch is

    used. Prepared edges shall meet the cleanliness requirements of clause 328.4.1 of

    this specification. Equipment/consumables used for grinding and cleaning of edge

     preparations shall be dedicated for stainless steel work and identified by colour

    coding or other suitable means. Wire brushes shall be of stainless steel.

     Add the following new clauses (3) to (5):

    (3) The cut surface shall be ground to a smooth, bright uniform finish by removing

    approximately 0.5 mm of metal. After grinding, the weld edges and surrounding

    material shall be cleaned and visually examined to ensure freedom from cracks,

    notches or other defects which may affect weld quality. Any bevelled edge that has

     been damaged shall be restored by machining or grinding within the tolerances

    required by the welding procedure to be applied. Restoration involving welding

    shall not be permitted.

    (4) All preparations in pipe of 273 mm OD and above and/or wall thickness of 12.7

    mm and above and all cut-backs made to rectify defective end preparation,

    irrespective of pipe size, shall be inspected as follows:

    •  The pipe shall be ultrasonically examined for laminations over a zone of 50mm back from the new bevel edge. The acceptance criteria shall be that the

    maximum dimension of the minor axis of the lamination shall not exceed 6.3

    mm and the maximum product of the major and minor axes shall not exceed 50

    mm2.

    •  The new bevel shall be liquid penetrant examined and shall be free fromrelevant linear indications.

    •  All examinations shall be in accordance with Company approved procedures.

    (5) Prior to a cut-out for a branch connection, a zone 50 mm wide around the outside

    diameter of the proposed hole shall be utrasonically checked for laminations. Thecompleted bevel shall be liquid penetrant examined. The procedures and

    acceptance criteria shall be those specified for cut-backs in the preceding

     paragraph.

    (b) Circumferential welds

     Delete existing clause (4) and replace as follows:

    (4) The deposition of weld metal to rectify internal misalignment shall not be

    328.4.3 Alignm

    ntial welds

     se (1):

    a maximum of 1 mm provided it is distributed equally

    around the circumference. If the misalignment exceeds the above value, provided it

     Add 

     permitted.

    ent

    (a) Circumfere

     Add the following to clau

      Misalignment is permitted to

    is caused by dimensional variations within the specified tolerance or the use of two

     piping components of different nominal thickness and the same out side diameter,

    trimming at the internal diameter of the thicker member to a taper of 1:4 may be

    carried out. Wherever possible, such rectification should be carried out by

    machining in a shop rather than by grinding in the field.

    the following new clause, (3): 

    December 2004 Page 17 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    21/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    (3) Line-up clamps shall be employed where possible. These shall have stainless steel

    inserts or shall be clad with a suitable material to prevent contact between the

    duplex stainless steel pipe and carbon steel. Stainless steel spacing tools shall be

    used in conjunction with the line-up clamp to ensure proper joint spacing. Root

     bead segments used with external line-up clamps shall be cleaned, feathered at each

    end, and visually inspected prior to completion of the root pass.

     Add the following new sub-section (e): 

    (e) Weld separation

    The toes of adjacent circumferential welds shall be separated by a minimum distance

    equal to the nominal outside diameter of the pipe. Where the above requirement cannot

     be met, the minimum distance between the toes of adjacent circumferential welds shall

    not be less than five times the nominal wall thickness or 50 mm whichever is greater.

    And both joints shall be subjected to RT and PT checks.

    When circumferential welds are to be made in pipe of welded manufacture, the

    longitudinal welds shall be so positioned that:

    •  the weld is at the upper segment of 120° of the pipe line

    •  any two adjacent longitudinal welds shall be at least 45° apart.

    328.5 Welding Requirements

    328.5.1 General

    The material certificates shall be verified and approved by the contractor Quality Assurance

    Engineer and made available for review to the Company before the commencement of

    welding / fabrication.

    (a) WPS

     Add the following: 

    All welding shall be in accordance with the ‘Approved for Fabrication’ WPS.

    (b) Weld identification

     Delete the last sentence and replace as follows: 

    The Contractor shall maintain records of the weld number and the welder identification

    for each weld for inclusion in the document package. The production records shall also

    include the results of monitoring and verification of the welding parameters (volts,

    amps, travel speed and heat input) representing one pass per WPS, per welder, per day(excluding the capping runs) unless agreed otherwise with Company Welding TA-2

    authority. A calibrated portable arc monitor shall be used to record welding parameters.

    (c) Tack welding

     Delete existing sub-section and replace as follows:

    Root tack welding shall not be permitted. Where tack welding is necessary, only bridge

    or bar tacks may be used. These shall be welded using the electrodes and parameters

    shown in the approved WPS for the fill passes. Welding shall not encroach on the root

    area. The bridge or bar material shall match the composition of the parent material.

    The tack welds shall be removed by grinding as welding progresses around the joint.

    (d) Weld Finishing

    December 2004 Page 18 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    22/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

     Delete existing sub-section and replace as follows:

    Welds shall be left as welded and shall not be treated with a flame torch or other

    mechanical means to change their appearance other than the cleaning and dressing

    operations specified in the WPS. Welds shall not be peened.

    When fabrication is completed, all surfaces adjacent to the welds shall be cleaned ofspatter, burrs, and other imperfections that could interfere with radiographic or

    ultrasonic inspection.

    (e) Weather protection

     Delete existing sub-section and replace as follows: 

    Work shall not be performed when the weather and/or degree of protection does not

     permit satisfactory workmanship.

    For site welding, shelters giving adequate protection at all times to the weld area from

    wind, rain and moisture shall be provided. In windy conditions the pipe ends shall be

    sealed to prevent through draughts

    Weld surfaces shall be thoroughly cleaned and dried before welding. Moisture shall be

    removed by means of blowers, or in exceptional cases a torch may be used in

    accordance with Section 330.1.1 of this specification.

     Add new sub-sections, (g) to (k):

    (g) Application of welding processes

    (1) Gas Tungsten Arc Welding (GTAW)

    Manual or automatic GTAW with filler metal addition shall be used for the root andsecond pass of all single sided butt welds. These processes may also be used for

    filling and capping passes. Automatic GTAW may be used in uphill and downhill

     progression. The manual GTAW process shall be restricted to uphill progression.

    U-groove preparation without root gap should be used for automatic welding.

    The tungsten electrode shall be AWS class EWTh-2 or EWCe-2. The GTAW

     power source shall have a high frequency starting circuit, slope-out control and gas

    delay facility as a minimum.

    Argon, Helium or Argon/Helium mixtures of at least 99.99% purity shall be used as

    shielding and backing gas. The use of argon containing an addition of up to 2%

    nitrogen is also permissible. Hydrogen additions are not permitted.

    Flushing with backing gas shall be carried out before welding. The oxygen content

    of the exit gas shall be monitored using suitable oxygen measuring equipment and

    welding shall not commence until a level of 0.2% or less is attained. Monitoring

    shall be continued during welding to ensure that this limit is not exceeded.

    Unless otherwise approved, gas back purge shall be maintained during the welding

    of all full penetration butt joints until a minimum of 6 mm. thickness of weld metal

    has been deposited. Continuation of back purging for further layers may be

    necessary, subject to the root weld inner surface meeting the specified visual

    acceptance criteria, as determined in procedure qualification. The same criteria

    shall be applied to confirm the acceptable maximum depth of partial penetration

    repair welds.

    (2) Submerged Arc Welding (SAW)

    December 2004 Page 19 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    23/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    SAW shall be used only for filling and capping in the flat position with the pipe

    rotated. Wire and flux shall be from the same manufacturer.

    (3) Shielded Metal Arc Welding (SMAW)

    The SMAW process shall be used only for filling and capping and only in the

     positions recommended by the consumable manufacturer. Welding shall not be performed in the downhill direction.

    (4) Other welding processes

    Welding shall normally be restricted to the processes listed in (1) to (3) above.

    Proposals to use other processes may be submitted to the Company Welding TA-2

    for consideration in exceptional cases.

    (h) Arc strikes

    Arc strikes shall be ground out to a smooth profile. The ground area shall be examined

     by liquid penetrant examination and thickness checked. The area shall be free from

    cracks. Where the thickness is below the specified minimum that section of pipe shall

     be removed.

    The Contractor shall ensure a good earth connection and periodically examine the

    condition of the earth cables and attachments. Any arcing from a poor connection shall

     be treated as an arc strike. Connections of current return cables shall be made directly

    to the work using clamps having stainless steel contact surfaces.

    (i) Inter-run cleaning

    Each run of weld metal shall be cleaned before a further run is deposited. Visible

    defects such as cracks, cavities, and other deposition faults shall be removed by

    grinding prior to deposition of further weld metal.

    (j)  Temporary attachments

    Temporary attachments shall not be used. 

    (k) Transition joints between dissimilar metals

    The Contractor shall consult with the Company and agree the WPS and qualification

    requirements.

    328.5.2 Fillet and Socket Welds

     From 1st sentence, delete”(including socket welds)”.

     Add to sub-section (a), the following::

    Socket welding shall not be permitted.

     Delete existing sub-section (b) and replace as follows 

    (b) Where the use of slip-on flanges is agreed by the Company, attachment shall be by

    continuous double fillet welds.

     Add following new sub-section:

    December 2004 Page 20 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    24/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    (c)

    tails

    may be supported by appropriate butt weld qualifications. Otherwise separate

    h ASME IX and this specification shall be required.

    328.5.4 s

     A

    (i) hall be prepared for each type of branch weld detail. Separate

    qualification of branch welds shall be carried out in accordance with ASME B31.3 and

    n.

    328.6

    ion and replace as follows:

    328.6.1

    All repairs shall be executed by welders qualified in accordance with ASME B31.3 and this

    l be

    g TA-2. The

    WPS shall be qualified using simulated repairs to an appropriate test weld, except that

    a by this specification, the WPS shall show the following:

    •  The method of excavation

    e total length of excavation shall

    not exceed 30% of the weld length. For full penetration repairs, the total length of

    Each type of repair shall be separately qualified, including full penetration, partial

    f the

    excavation there shall be a gradual taper from the base of the excavation to the surface of the

    e

    original weld. Surfaces shall be thoroughly cleaned before depositing

    further weld metal. Back welding to repair a root mismatch (Hi-Lo) is only permissible if

    d for the original weld to a length extending 50 mm beyond each end of the

    repair. Should further unacceptable defects be found on re-inspection then the weld shall be

    A specific WPS shall be prepared for each fillet weld attachment detail. Subject to

    review and acceptance by the Company Welding TA-2, qualification of these de

    qualification in accordance wit

    Welded Branch Connection

    dd following new sub-section:

    A specific WPS s

    this specificatio

    Weld Repair

     Delete entire sect 

    General

    specification. The Contractor shall maintain records of repair work.

    Repair welding procedures shall be prepared and qualified for each type of repair to be

     performed in accordance with Section 328.2 of this specification. A separate WPS shal

     produced for repair welding and shall be approved by the Company Weldin

    repairs to fillet welds may be qualified by a suitable butt weld repair PQR.

    In ddition to the items required

    •  The NDE technique employed to ensure removal of defects

    Cracks shall not be repaired. When cracking is observed in the completed weld, the weld

    shall be cut out entirely. For partial penetration repairs, th

    excavation shall not exceed 20% of the weld length.

     penetration and cap welds.

    Excavation shall be by machining or grinding. After excavation, visual and liquid penetrant

    inspection shall be performed to confirm defect removal. At the ends and the sides o

    weld metal. The profile shall be such that adequate access for welding is achieved. 

    Undersize welds shall be rectified by the deposition of additional weld metal, using the sam

     procedures as for the

    covered by a PQR.

    After completion of repair welding, the full extent of the repair shall be inspected by the

    method prescribe

    cut out entirely.

    December 2004 Page 21 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    25/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    328.6.2

    The initial butt weld shall be welded to the appropriate qualified WPS. The maximum depth

    of

    s been agreed, separate qualification shall be made. Generally, test

    repair weld excavations should be centred at the fusion line so as to include weld metal and

    shall be shown on the WPS and agreed by the Company.

    for

    ing.

    328.6.3

    d procedure is representative of the original weld qualification, the

    ructive tests shall be performed on butt weld repairs, (cap repairs should be

    cedure qualification tests shall apply. Destructive

    -

    - ferrite measurements, which shall include measurements made in the new HAZ formed in

    , where appropriate, shall include samples notched in the new HAZ

    e original weld.

    ing, to include the junction of new and original weld metal

    330 Preheating

    330.1 General

    330.1.1

    Preheat will not normally be required by the WPS. If welding is likely to be performed

    mited

     preheat may also be applied in highly constrained conditions provided that this does not

    es

    ern nozzles. Welding or cutting torches shall not be used. 

    rpass temperature shall be 150oC, unless a lower value is specified on the

    approved WPS. Temperature measurement shall be by thermocouple, thermomelt crayon,

    ermomelt crayons shall not be applied

    within the bevel area.

    330.1.4

    The heated area shall extend for a minimum of 75mm either side of the joint and shall be

    maintained over the full length of the joint until the weld is completed. A period of

    Welding of Test Repair Welds

    of partial penetration repair welds shall the lesser of 0.5t or t-6 mm. Where the execution

    single run repairs ha

     parent material. The location

    Each repair shall be of sufficient length to provide the specified number of specimens

    destructive test

    Testing of Repair Welds

     Non-destructive testing of the repair test weld shall be performed as specified for the

    original weld.

    Provided the repair wel

    following dest

    tested as fillet welds). Otherwise, full pro

    testing shall be in accordance with the methods and acceptance criteria of Section 328.2.6:

    - 1 transverse tensile

     bend test

    - 1 macroexamination and hardness test

    the original weld.

    - Charpy testing which

    formed in th

    - corrosion test

    Requirements and Recommendations

     Delete existing section and replace as follows: 

     below 15°C or condensation of moisture on the weld area is possible, a minimum preheat of 

    50°C shall be applied to a bandwidth of at least 75mm either side of the joint. A li

    contravene the essential variables of the qualified WPS, (see 328.2.1.3(p)).

    Acceptable methods of pre-heating are electrical resistance heaters or oxy-propane torch

    fitted with rosebud patt

    The maximum inte

    contact pyrometer or a combination of these. Th

    Preheat Zone

     Delete existing section and replace as follows: 

    December 2004 Page 22 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    26/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    equalisation shall be allowed, based on two minutes per 25mm thickness, prior to

    confirmation that the specified temperature has been attained.

    330.2 Specific Requirements

    330.2.4 Interrupted Welding

    Interruption of welding should be avoided. Where interruption is unavoidable, a minimum

    he joint thickness, whichever is greater, shall have been

    331 Heat Treatment

    fied only in exceptional circumstances. Individual

    agreed with the Company as necessary.

    332 Bending and Forming

     Delete existing section entirely and replace as follows: 

    332.1

    all

    nds or any other

    shop forming operations becomes necessary, this shall be restricted to cold working

    ontamination of the work by carbon steel.

    t procedures shall be approved by the Company prior

    333 oldering

    elete the existing section entirely. Brazing and soldering processes are outside the scope

    of this specification.

    336 Handling and Storage

    336.1

    osure

    ,

    ds beads and for

     preventing oxidation during welding, are included in Sections 328.4, 328.5.1 and 332.1 of

     Delete existing section and replace as follows: 

    of three passes or one third of t

    deposited.

     Delete existing section and replace as follows: 

    Post weld heat treatment will be speci

    requirements and procedures shall be

    General

    Field bending of duplex stainless steel pipework shall not be permitted. Maximum use sh

     be made of factory produced components. Where shop fabrication of be

    techniques. Contact faces of forming equipment shall be of stainless steel or lined with

    suitable material to prevent c

    Detailed fabrication and heat treatmen

    to commencement of work.

    Brazing and S

     D

     Add the following new section:

    General

    All necessary precautions shall be taken throughout fabrication to minimise contamination

    of duplex stainless steel materials resulting from direct contact with carbon steels, exp

    to ferrous dust, swarf or other debris and from residual deposits on or near fusion faces

    during welding. Specific requirements to prevent contamination during edge preparation

     joint alignment or site fabrication, for cleaning fusion faces and wel

    this specification. General precautions to be applied during the handling and storage ofduplex stainless steels are outlined in clauses 336.2 - 3, following.

    December 2004 Page 23 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    27/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    Surface oxidation or metallic contamination that does not respond to washing or degreasing

    treatments shall be removed using power tools or by a pickling treatment. Pickling

     procedures shall be subject to prior approved by the Company. The Contractor shall ensure

    the safe use and disposal of chemical solutions and the thorough cleaning and drying of

    shing shall be performed with potable water.

    336.2

    nmental contamination.

    (b) Duplex stainless steels shall be clearly identified and segregated from other stored

    336.3

    ge or contamination of the duplex pipework.

     blies shall be of

     Nylon or similar compatible material.(c) Pipe handling by means of hooks in pipe ends shall not be permitted.

     pipework. Wa

    Storage

    (a) Components stored in an open site or within a fabrication workshop shall be protected

    from enviro

    materials.

    Pipe Handling

    (a) Supports, rollers and other pipe handling equipment shall be of compatible material or

    shall be suitably lined to prevent dama

    (b) Slings and supports for lifting duplex stainless steel pipe and assem

    December 2004 Page 24 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    28/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    Chapter VI Inspection, Examination and Testing

    341 Examination

    341.2 Responsibility for Examination

     Add the following new sub-sections (d) and (e):

    (d) The Contractor shall supply all labour, materials, and equipment necessary to perform

    the required examinations.

    (e) The Company shall have the final disposition on any weld. Those welds not accepted

     by the Company shall be rectified in accordance with ASME B31.3 and this

    specification.

    341.3 Examination Requirements

    341.3.1 General

     Insert the following in front of the first paragraph:

    Before commencing production, the Contractor shall examine free-issue materials for

    all

    the

    341.3.2 Acceptance Criteria

     Delete existing section and replace as follows:

    The acceptance criteria shall be as stated in ASME B31.3 and this specification.

    Limits on imperfections shall be assessed in accordance with Table 341.3.2 with the

    nated

    341.4 Extent of Required Examination

    341.4.1 Examination Normally Required

    (a) Visual Examination

     Delete all clauses of existing sub-section and replace as follows: 

    Visual examination prior to welding shall be in accordance with the provisions of

    (b) Other examination

     Delete all clauses of existing sub-section and replace as follows: 

    The extent of examination for all butt welds shall be in accordance with Table 1.

    Ultrasonic examination may supplement radiography and shall be used to interpret

    damage and compliance with the relevant materials specification. This examination sh

    include a review of the materials certificates. Items supplied without materials certificates

    shall not be used. All damage and discrepancies shall be reported immediately to the

    Company. After signed acceptance by the Contractor, any discovered damage shall be

    responsibility of the Contractor.

    exception that Incomplete Penetration shall not be permitted, (symbol ‘A’ to be desig

    for girth/mitre groove welds and branch connections).

    sections 328.4 and 341.3 of ASME B31.3 and this specification. All completed welds

    shall be visually examined. Wherever accessible, the extent of oxidation on the root

    and HAZ surfaces of single-sided welds shall be assessed for comparison with the

    visual acceptance criteria of DEP 30.10.60.31-Gen.

    December 2004 Page 25 SP-1096

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    29/44

    Version 2.0 Specification for Welding of Duplex Stainless Steel Piping

    doubtful indications in the radiographs. Fillet welds shall be subjected to visual, and

    liquid penetrant examination at the same frequency as radiography for butt welds per

    fluid service and class.

    Branch connection welds shall be radiographically examined where possible. Where

    radiography is not possible, ultrasonic examination shall be employed. Where

    ll inform the Company of cases where neither radiography nor

    ultrasonic examination can be performed and obtain written Company approval for

     pecified, the Contractor shall ensure that

    a minimum of 2% of the welds made by each welder is included in the overall

    shall not substitute for the specified NDE.

    342 Ex

    rtification

    id qualification of one of the following listed

     below and should have previous experience of duplex stainless steel welding or have

    •  AWS CWI with 10 years experience

     pany as equivalent to the above.

    the method of

     NDE to be carried out in accordance with ISO 9712. The roles and responsibilities of NDE

    Level

    y, welding examination or non-destructive examination

     personnel fail to perform to a satisfactory standard they shall be disqualified from the works

    343 es

    specified examination shall be prepared bythe Contractor and submitted for Company approval (by an Inspection TA-2) a minimum of

    ultrasonic examination is not possible, liquid penetrant examination shall be performedon the final weld.

    The Contractor sha

    liquid penetrant examination to be used alone.

    When random non-destructive examination is s

     percentage examined.

    In-process examination

    amination Personnel

    342.1 Personnel Qualification and Ce

     Delete existing section and replace as follows: 

    Welding examination personnel shall hold a val

    received a period of specialised training satisfactory to the Company welding TA-2.

    Acceptable qualifications for welding examiners are as follows:

    •  CSWIP 3.1 with 10 years experience

    •  Other qualification agreed by the Com

     Non-destructive examination personnel shall be qualified and certificated for 

     personnel shall be as defined in the levels of competence in ISO 9712. Personnel certified to

    ASNT Level II in accordance with ASNT-TC-1A by examination are acceptable provided

    that the certifying Level III NDE Engineer has been approved by the Company. The

    Company approved Level III NDE Engineer (full time employee of NDE Company) shall

    continuously (monthly) monitor the performance of NDE Personnel certified to ASNT

    II and shall take corrective measures whenever the performance of ASNT Level II

    technicians is not satisfactory.

    If, in the opinion of the Compan

    until such time that it can be demonstrated by the Contractor that they have achieved a

    satisfactory standard by undertaking, at the Contractor's expense, a test by a third party

    agency approved by the Company.

    Examination Procedur 

     Delete existing section and replace as follows:

    Written NDE procedures covering each type of

    December 2004 Page 26 SP-1096  

  • 8/18/2019 Welding of Duplex Stainless Steel Pipelines

    30/44

    Specification for Welding of Duplex Stainless Steel Piping Version 2.0

    two weeks prior to test or production welding as applicable. The procedures shall be projec

    specific and shall show the project name and contract number. Company approval shall be

     based on qualification tests, which may be conducted as part of the Welding Procedure

    Qualification testing. The procedures shall incorporate the requirements of SP-1176.

    Types of Examination

    t

    344

    ing section and replace as follows: 

    ance with a documented procedure

    complying with Article 9 of ASME BPV Code Section V. The examiner shall maintain and

    hapter

    rior to examination.

    344.3

    344.4 nt Examination

     s: 

    in accordance with a documented

     procedure complying with Article 6 of ASME BPV Code Section V and incorporating the

    ll be as stated in Chapter VI of ASME B31.3 and this

    specification. The technician and the Contractor's Welding Co-ordinator shall sign and

    he

    344.5

    ing section and replace as follows: 

    accordance with a documented procedure

    complying with Article 2 of ASME BPV Code Section V and incorporating the

    iography shall be by X-ray. Gamma radiography shall not be

    used for wall thicknesses less than 10mm. Where the use of X-radiography is agreed by the

    used for radiography performed to this

    specification. Sensitivity shall be 2% or better. IQIs shall be wire type, of stainless steel orequivalent.

    344.2 Visual Examination

    344.2.2 Method

     Delete exist 

    Visual examination shall be