Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give you some of the basic information on the project including: where we are in the process of the engineering and environmental analysis what improvements are included with the project And some of the benefits of these improvements After this presentation, please take your time and review the displays in the back of the meeting room and ask our staff any questions you have about the project. 1

Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

Welcome to the Public Information Meeting for the New York Gateway Project.

This introductory presentation will give you some of the basic information on the project including:

•where we are in the process of the engineering and environmental analysis

•what improvements are included with the project

•And some of the benefits of these improvements

After this presentation, please take your time and review the displays in the back of the meeting room and ask our staff any questions you have about the project.

1

Page 2: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

This project is one of several initiatives proposed by Governor Cuomo for the Western New York Area. 

It is fully funded and is intended to be completed within the next couple of years.

Other initiatives on the Governor’s list include the Canalside Project, the Outer Harbor Development and the redevelopment in Downtown Niagara FallsDevelopment and the redevelopment in Downtown Niagara Falls.

2

Page 3: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

The project is following the traditional environmental review process established through the National Environmental Policy Act or NEPA.  

As you can see we are currently in the process of developing the draft environmental impact statement and will be having a public hearing in December.  

You will have another opportunity to review what is proposed and provide input at the public hearingpublic hearing. 

The final environmental impact statement and the record of decision will be prepared and completed  in the spring of next year, with construction to begin in the summer.

3

Page 4: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

h i l d f hi j i l d i f d fThe improvements planned for this project include construction of new ramps to and from the existing peace Bridge Plaza.

The new ramp from the plaza is called Ramp D and will take you directly off the plaza and onto the northbound thruway.

The new ramp to the plaza is called Ramp PN and will take you from Porter Avenue to the PlazaPlaza.

The combination of these two new ramps will allow us to remove Baird Drive from Front Park.

In conjunction with the new ramps will be improvements to the Shoreline Trail also known as the Riverwalk.

The project will also include the replacement of the existing deteriorated Porter Ave. bridge over the thruway and 

with the removal of Baird Drive, and the replacement of the Porter Ave bridge,  improvements will be made to the existing pedestrian and bicycle facilities within Front Park and along Porter Avenue.

4

Page 5: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

As noted earlier the construction of the two new ramps will allow the removal of Baird Drive from Front Park.

The benefits of removing the road from the park include:

•The removal of all vehicles coming through Front Park to get to the Plaza which is about 440 per hour.

•The removal of all vehicles coming from the Plaza area through Front Park to Porter Ave. which is about 300 per hour.

•It allows for expanded use of soccer fields by neighborhood children in Front Park and adds 4.3 additional acres of contiguous park area.

5

Page 6: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

It increases the safety for children playing and citizens walking or biking within Front Park.

Elimination of the traffic signal at the north end of Baird Drive at its intersection with Ramp A into the Plaza allows unimpeded flow onto the Peace Bridge.

And the reconnection of the pathways within Front Park, without any crossing of busy roads, reduces the possibility for pedestrian and vehicle conflicts.

6

Page 7: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

Besides the removal of Baird Drive, the benefits of building Ramp D also include:

•The reduction in crisscrossing traffic within the Plaza.

•All traffic from Canada will exit the Plaza at one location.

•There will be much less confusion for travelers leaving the Plaza.

•There will also be better security on the plaza with only one point of ingress and egress

•And it will provide for a safer work environment for plaza operators.

7

Page 8: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

There are also other benefits of building Ramp PN as well including:

•All Canada bound traffic will enter the plaza at one location via Ramp A

•This will allow for the removal of the Baird Drive traffic signal and result less idling vehicles.

8

Page 9: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

Along with construction of the new ramps,  improvements will be made to the existing Pedestrian and Bicycle Facilities

Removal of Baird Drive will result in a safer use of pathways within  Front Park. 

Also, all pedestrians would travel on a new wide multi‐use pathway along the south side of Porter Ave and away from the ramps along the north side of PorterPorter Ave and away from the ramps along the north side of Porter.

This would also provide for a safer pathway to LaSalle Park .

9

Page 10: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

As noted before the project will include the replacement of the Porter Ave. Bridge over the thruway

This allows for the multiuse pathway across the south side of the bridge to LaSalle Park.

It allows for a narrower roadway (2 or 3 lanes wide)  over the bridge

It will combines construction of two separate projectsIt will combines construction of two separate projects

And it allows for the widening of the ramps and shoulders on the thruway under the bridge.

10

Page 11: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

As a result of the construction of Ramp D to the northbound thruway, the Shoreline Trail, or Riverwalk will be improved.

The current Shoreline Trail travels along and passes under the thruway.

With the relocation of the trail to stay above the thruway it will provide unobstructed panoramic views to the lake and river via a new overlookpanoramic views to the lake and river via a new overlook

It provides a better user experience.

It eliminates the current underpass at the thruway.

And it adds 700 feet of pathway along the water front

11

Page 12: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

This concludes our presentation.

We encourage you to review the exhibits here today and give us your thoughts via comment sheets that can be filled out and dropped off here today or mailed to the Department of Transportation.

You can also email your comments and visit the project website for more information onYou can also email your comments and visit the project website for more information on the project.

These addresses are on the comment sheet that is available at the registration table.

12

Page 13: Welcome to the Public Information Meeting for the New York ... · Welcome to the Public Information Meeting for the New York Gateway Project. This introductory presentation will give

Thank you for you attention and again we encourage you to review the displays here todayand ask our staff any questions you may have about the project.

Please remember you will have another opportunity to review the progress on the project and give us your comments during the Public Hearing coming up in December.