29
1 Welcome to the Army Installation Energy Resilience Update We will begin momentarily… November 30, 2018

Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

1

Welcome to theArmy Installation Energy Resilience Update

We will begin momentarily…

November 30, 2018

Page 2: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Army Installation Energy Resilience Update

30 November 2018

Page 3: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

3

Check out the boxes on the right hand side for more webinar information:

• Audio Information for Today’s Webinar

• Army Energy Links

• Webinar Presentation for Download

Page 4: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

4

Webinar Presenters

Acting DASA (E&S)Mr. J.E. “Jack” Surash,

P.E.

OEI ExecutiveDirector

Mr. Michael McGhee, P.E.

Special Assistant to the ASA IE&EDr. Bret Strogen,

P.E.

Chief, Energy and Utilities Branch Energy & Facilities Policy Division Operations

Directorate, ACSIM Mr. Thomas B. Delaney, Jr.,

P.E.

Army Energy Resilience Update

Office of Energy Initiatives Update

Energy Savings Performance

Contracts & Utilities Energy Service

Contracts Update

Installation Energy& Water Plansand Utilities

Privatization Update

Page 5: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Army Energy Resilience Update

Mr. J.E. “Jack” Surash, P.E. Acting Deputy Assistant Secretary of the Army

for Energy and Sustainability

Page 6: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Energy and water security/resilience ensure available, reliable, and quality power and water to continuously sustain critical missions

Energy and Water Resilience and Security Enables Army Readiness

Office of Energy Initiatives (OEI)11 Awarded Energy Projects325 MW Onsite Generation Capacity76% Islandable Projects (onsite generation,storage & controls)

Utilities Privatization: 152 Privatized Systems Water 35Wastewater 34Electric 45Gas 36Heat/Power 2

Energy Resilience & Conservation Investment Program (ERCIP):FY 2019: 6 Projects / $31.2 M

Energy Savings Performance Contracts (ESPCs)/ Utility Energy Service Contracts (UESCs)$2.8 B Total Third-Party Investment637 Total Task-Orders and ModsFY 2017: $289.3M Investment

9.6% Energy Use Intensity since FY15 vs 5% FY17 Goal

32% Water Use Intensity since FY07 vs 20% FY17 Goal

.

Army Universe Installation Population: 3,002,873Total Army Installations: 156National Guard & Reserve Centers: >2,800Total Land (acres): 13,591,251Buildings (ft2): 982,668,264

Army Energy and Water Universe

6

Combined Heat & Power (CHP) Strategy14 Projects / 109.2 MW

Sustainable Buildings: ≥ LEED Silver (FY05-17)919 Buildings

Demand Response: 16 Installations Participating

Enterprise Metering System> 21,000 Electric, Gas & Water Meters

Facility Related Control Systems

FY 2017 ARMY Energy & Water Cost / Consumption

$1.1B Energy 71.8T BTUs/year$86.9M Potable Water 31.2B GALs/year

Army Directive 2017-07, Installation Energy & Water Security Policy

(February 23, 2017)

Energy / Resource Energy Managers: 179

FY 2017 Energy Sources:• Electricity: 45.2% • Natural Gas: 34.6%• Fuel Oil 4.4% • Other 15.8%

Installation Energy & Water Plans: In Progress

November 2018

Page 7: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Addressing Vulnerabilities: Pivot from focus on efficiency and compliance to

ENERGY AND WATER RESILIENCE

SecArmy Directive 2017-07 (Installation Energy and Water Security Policy)- CRITICAL MISSION SUSTAINMENT (CMS): Critical

mission continuity of operations for a minimum of 14 days

- ASSURED ACCESS (AA): Dependable supply of energy and water needed to meet evolving mission requirements during normal and emergency response operations

- INFRASTRUCTURE CONDITION (IC): Infrastructure capable of on-site storage and flexible and redundant distribution networks to reliably meet mission requirements

- SYSTEM OPERATION (SO): Trained personnel conduct required energy and water security system planning, operations and sustainment activities

7

Energy and Water Resilience

“The Secretary of Defense shall ensure the readiness of the armed forces for their military missions by pursuing energy security and energy resilience”10 USC 2911 (2018 NDAA)

“It is now undeniable that the homeland is no longer a sanctuary. … attacks against our critical defense, government, and economic infrastructure must be anticipated”National Defense Strategy 2018

CYBERNATURALPHYSICAL

Page 8: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Black Swans = unknown, unknowns Pink Flamingos = known, knowns

8

Imagine ….

http://madsciblog.tradoc.army.mil/91-army-installations-a-whole-flock-of-pink-flamingos/

Army installations – A whole flock of pink flamingos?

The year is 2030: Army has invested in training and equipment but took risk in installation infrastructure

Authorized mobilization and deployment to counter the invasion in

allied nation

Cyber attack disrupted power supplies, including

communicationsSystems below the threshold of “critical,” disrupted

Key external utility, water, and energy control systems

under attack

The Army is unable to deploy

Page 9: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Efficiency and Conservation

Driver Federal Mandates

Assessment Footprints Square-footage and load

Risk Considerations N/A

Solutions Building load management strategies and onsite generation

Project Prioritization Cost effectiveness

9

BUILDING SQFT

AVAILABLE LAND

AVAILABLE RESOURCE

DEMAND RESPONSE

BUILDING LOAD

BUILDING LOAD

Page 10: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

10

Security and Resilience

Driver Critical mission requirements

Assessment Footprints Uninterruptable and critical footprints, interdependencies, and emergency response

Risk Considerations Threat/hazards with associated impact

Solutions Load management PLUS O&M, infrastructure, and onsite generation and storage

Project Prioritization Meeting mission need, reducing risk, cost effective alternatives analysis

BUILDING SQFT

BUILDING LOAD

AVAILABLE LAND

AVAILABLE RESOURCE

EFFICIENCY OPPORTUNITIES

DEMAND RESPONSE

BUILDING LOAD

Page 11: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Closing Gaps

11

Low Cost/ No Cost Management• Installation Planning• Best Management Practices• Energy Resilience Exercises

Appropriated Project Funding• Military Construction (MILCON)• Energy Resilience and Conservation

Investment Program (ERCIP)• Operations and Maintenance (O&M)

Third Party Financing• Energy Savings Performance

Contracts (ESPCs)• Utility Energy Service Contracts (UESCs)• Utilities Privatization (UP)

Private Financing• Power Purchase Agreements• Enhanced Use Leases

Schofield Barracks, HI: Lease Project: 50 MW / 30 day contingency microgrid where

Hawaiian Electric constructed, owns, operates and maintains a 50 MW biofuel/multi-fuel power generation plant, fuel storage tanks,

and controls.

Anniston Army Depot, AL: UESCReplacement and Modernization of Depot-wide central heating and process high pressure steam plants, HVAC equipment and

controls, interior and exterior lighting, compressed air equipment and distributions, and potable water fixtures.

Fort Campbell, KY: MILCONConceptual drawing a microgrid included in the FY2018 NDAA

Page 12: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Office of Energy Initiatives Update

Mr. Michael McGhee. P.E.Executive Director

Army Office of Energy Initiatives

30 November 2018

Page 13: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

13

The Office of Energy Initiatives

• The Army Office of Energy Initiatives (OEI) was established by the Secretary of the Army with the mission to develop projects that enhance energy security and resilience on or near Army installations using existing DoD land use and private financing authorities.

• OEI serves as the Army’s central program management office for the development, implementation and oversight of privately financed, energy resilience projects.

• OEI is focused on creating an “Islandable” capability – energy security projects that include onsite generation, storage, and controls – which contributes to the Army’s Directive to provide power to critical missions for a minimum of 14 days in the event of an electrical grid outage.

Redstone Arsenal, Alabama: 1 MW / 2 MW-hour battery energy storage system, coupled with a 10 MW solar array; Operational December 2017

Schofield Barracks, Hawaii: 50 MW multi-fuel power plant; 100% “Islandable” capability for 30 days; Operational May 2018

Fort Sill, Oklahoma: 36 MW natural gas and 14 MW solar array; 100% “Islandable” capability for 14+ days; In Development

Page 14: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

14

Army OEI Current EnergyProjects Portfolio

November 2018

Page 15: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

15

Energy Security Project, Operational:

Schofield Barracks, HIProject: 50 MW / 30 Day Contingency MicrogridHawaiian Electric constructed, owns, operates and maintains a 50 MW multi-fuel power generation plant, fuel storage tanks, and controls, on Schofield Barracks

Army Benefit Plant can provide 50 MW of “first call” and “black start” capability to three Army installations simultaneously; 5 days of fuel storage onsite, 30 days of fuel storage on island.

Utility Benefit Hawaiian Electric gained a critical generation facility above the tsunami strike zone, which powers the Oahu grid during normal operations.

Community Benefit As the only baseload power generation facility on Oahu located above the tsunami inundation zone, this project enhances grid resilience and could provide power to part of the surrounding community in the event of a grid outage.

Status Operational since May 2018

Operational May 2018

Construction

Page 16: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

16

Energy Security Project, Concept:

Fort Sill, OKProject Concept: 36 MW / 14 Day Minimum Contingency MicrogridPublic Service Corporation of Oklahoma would construct, own, operate and maintain a 36 MW natural gas fueled grid-facing power plant and up to a 14 MW solar PV array with controls.Army Benefit The project would enhance energy resilience by locating on-demand generating assets on Fort Sill that are capable of supplying reliable power to mission critical facilities during a commercial grid disruption.

Utility Benefit Utility gains a distributed asset enhancing grid reliability in normal operations that aligns with their Integrated Resource Plan. Power from the project would flow directly to the commercial grid.

Community Benefit The project provides additional operational flexibility that improves electrical service reliability to the surrounding Lawton community.

Status Project in pre-negotiation stage. NEPA is underway; in 1st public comment period and consultation phase.

Page 17: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

17

Energy Security Project, Concept:

Joint Forces Training Base – Los Alamitos (JFTB-LA), CA

Project Concept: 3 MW / 14 Day Minimum Contingency MicrogridDeveloper would construct, own, operate and maintain the energy resilience capabilities project, which includes power generation assets, energy storage, and microgrid components to “island” JFTB-LA in the event of a grid disruption.

Current Status:• Project Solicitation – 16 MAY 18

• Industry Day – 30 MAY 18

• RFP Closed – 20 AUG 18

• Conditional Selection Notice – NOV 18

• Lease Award Target – WINTER 19 Army Benefit Project will enhance energy security by providing “islandable” capability to power the base’s critical missions for a minimum of 14 days during a grid outage.

Developer Benefit During normal operations, the developer would benefit from selling power or services from the project to off-base customers via the electrical grid.

Community Benefit The project may enhance grid reliability by alleviating transmission line congestion or provide other electrical grid quality-enhancing services.

Status Conditional Selection Notice accepted by developer November 2018

Page 18: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Energy Savings Performance Contracts & Utilities Energy Service Contracts Update

Dr. Bret Strogen, P.E. Special Assistant to the Assistant Secretary of the Army

for Installations, Energy & Environment

Page 19: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

19

Energy Savings Performance Contracts (ESPC) Utilities Energy Service Contracts (UESC)

Program Summary• 637 task orders/mods at 96 installations• >13.9 Trillion BTU saved per year• $2.9B in private sector investments• >$300M more in development

• Servicing utilities and private companies provide initial private capital investment to executeprojects that recapitalize energy and water systems and infrastructure

• Army executes project at no up-front capital costs; payments offset via commodity savings• Army budget funds amortized repayments based on validated savings

0

50

100

150

200

250

300

350

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

ESPC UESC Projected

Third-Party Investments ($M)

Ft Knox ESPCControls to cycle off geothermal well

pumps during unoccupied hours

Rock Island ESPC Surface finishing process

improvements

Kwajalein ESPCPV array for Meck IslandAs of July 2018

Page 20: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

20

Kwajalein ESPC

Financial Summary• $40M third party investment for phase I• $2.2M projected annual cost avoidance• 20 year task order term• 55% reduction in diesel fuel consumption

on Meck Island• 64% reduction in lighting energy costs

Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll• Task Order for KWAJ ESPC phase 1 awarded in SEP 17, provides $40M of private capital investment• 2.4MW Solar PV array, 2 MW / 3 MWh Lithium-ion Energy Storage System (ESS), Microgrid control

system on Meck Island• HVAC – convert window A/C to split systems on Kwajalein, Meck, and Roi-Namur• Building Envelope Improvements on Kwajalein, Meck, and Roi-Namur• LED Lighting on Kwajalein, and Meck (Roi-Namur in Phase II)

Concept Plan for 2.4MW solar PV array

on Meck Island

Leveraging Private Sector Expertise and Financing in Support of Resilience

Construction camp for Kwajalein ESPCFuture Projects• ESPC Phases 2 & 3• Potential ESPC Phase 4

Page 21: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Installation Energy and Water Plans & Utilities Privatization

UpdateMr. Thomas B. Delaney, Jr., P.E.

Chief, Energy and Utilities BranchEnergy and Facilities Policy Division

Operations DirectorateOffice of the Assistant Chief of Staff for Installation Management

Page 22: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

22

Installation Energy and Water Plans

IEWP Development Steps

1. Identify requirements• Review installation performance metrics• Define IEWP stakeholders, scope, and goals• Establish energy and water (E&W) needs for

critical missions• Develop baseline

2. Assess risk and opportunities• Identify threats and hazards• Assess risks and mission impact• Evaluate conservation and efficiency

opportunities

3. Generate solutions• Scope best management practices• Develop project concepts

4. Develop an implementation plan• Prioritize solutions• Document the IEWP• Define the implementation

and funding approach

5. Execute and evaluate the IEWP• Report installation performance • Review and update the IEWP

Page 23: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

23

Use the IEWP Roadmap to Develop Solutions

Examples of Energy and Water Security Solutions:• MILCON – FY20 construction of a new substation inside the fence line at Detroit

Arsenal

• Energy Resilience and Conservation Investment Program (ERCIP) – FY19 construction of a connection between two substations at Fort Sill

• Restoration, Modernization, and Operations –‒ Electrical Repair, Clay Kaserne‒ Comprehensive energy and water plans to support resilience

planning required by FY18 NDAA

• Third-Party –‒ Partnering with local utility to build a biofuel plant on Schofield

Barracks to support USAG Hawaii in event of a grid outage‒ Prioritizing utilities privatization efforts to address critical

deficiencies in energy and water system

Conceptual drawing of substation interconnect at Fort SillNotional Picture of an Army Microgrid

Construction of Biofuel Plant at Schofield Barracks

Appropriated Third-Party Low Cost/No Cost

MILCON ESPC/UESC Planning

ERCIP UP BMPs

SRM OEI Exercises

Funding Sources

Page 24: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

24

Army UP Program Status

UP improves readiness by leveraging industry expertise and financing to upgrade and sustain utilities for safe, secure, efficient mission support.

Affordable

152 out of 356 U.S. systems privatized (43%): 45 Electric, 36 Gas, 35 Water, 34 Wastewater, (+2 Heat/Power)

29% Portfolio Average “Should-Cost” avoidance $3.4 B Net Present Value saved compared to continued Army ownership

FY17- FY18 UP Awards: 14 systems, $1.2 B cost avoidance (34%)

Strategic Investments for Critical Missions

Efficient Resilient Safe

Page 25: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

25

UP Evaluation Decision

DeficiencyCorrections

Upgrades + interest

Recurring50-Y

ear

$ Cos

t

“Should Cost”

Renewal & Replacement

O&M

29% Cost Avoidance

GovernmentOfferUP

Portfolio Average

Quo

O&M~75% Funded

Status

Self-Insured RiskLeaks & Losses

Selects best option for FULL SustainmentReduced risks + commodity savings are added benefits

Page 26: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

26

Risk Management

Actual

Incomplete Inventory

366 Leaks Detected92 Grade 1 Leaks Fixed

FY13 Fort Bragg Gas UP:1990: Fort Benjamin Harrison: Gas explosion killed 2, injured 27

NTSB found Army negligence

2013 Senate (Markey) Report:• 796 gas incidents 2002 to 2012: 116

fatalities, $811M in damage• Cast iron or bare steel mains leak:

18x more gas than plastic pipe and 57x more than protected steel

2010: San Bruno CA

383 Leaks Detected39 Grade 1 Leaks Fixed

FY16 Fort Hood Gas UP:

Page 27: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

Question and AnswerSession

Page 28: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

28

Q&A Session

Acting DASA (E&S)Mr. J.E. “Jack” Surash,

P.E.

OEI ExecutiveDirector

Mr. Michael McGhee, P.E.

Special Assistant to the ASA IE&EDr. Bret Strogen,

P.E.

Chief, Energy and Utilities Branch Energy & Facilities Policy Division Operations

Directorate, ACSIM Mr. Thomas B. Delaney, Jr.,

P.E.Army Energy

Resilience UpdateOffice of Energy

Initiatives UpdateEnergy Savings Performance

Contracts & Utilities Energy Service

Contracts Update

Installation Energy& Water Plansand Utilities

Privatization Update

We look forward to your questions! When submitting questions, please:• Identify yourself and organization• Indicate which speaker your question is for, if known

Page 29: Welcome to the Army Installation Energy Resilience Update...Nov 30, 2018  · Energy Savings Performance Contract (ESPC) for USAG Kwajalein Atoll • Task Order for KWAJ ESPC phase

29

Thank You

If you have any additional questions, please email:

Thank you for joining us today!

Army Energy & Sustainability

http://www.asaie.army.mil/Public/ES/

@ASArmyIEE

@ASAIEE

Army ACSIM

http://www.acsim.army.mil/

@OACSIM

Army OEI

www.oei.army.mil

@ArmyOEI

@ArmyOEI

[email protected]