Upload
vuongdiep
View
218
Download
2
Embed Size (px)
Citation preview
The Laws
Soviet Ideology
The Constitution (1992) (LPLI/1.1)
National Assembly Laws (C/74.2; LPLI/1.1) including thematic codes prescribed by the Standing Committee of the National Assembly under LPLI/93.2
National Assembly Resolutions (C/70.10)
NA Standing Committee Instruments (LPLI/1.1)
Ordinances (LPLI/1.1)
Presidential Orders and Decisions (LPLI/1.2(a))
Government Resolutions and Decrees (C/74.1; LPI/1.2(b)) and Prime Ministerial Directives (LPLI/1.2(b))
Ministerial Decisions, Directives and Circulars LPLI/1.2(c))
Supreme People’s Court Judicial Council Resolutions (LPLI/1.2(d)) and Supreme Court Inspectorate’s circulars (LPLI/1.2(d))
Certain Joint Resolutions and circulars (LPLI/1.2(dd)
People’s council Resolutions (LPLI/1.3) and People’s Committee’s Decisions and Directives (LPLI/1.3)
International Treaties (C/70.14)
Modes of application
Private individuals
Ministry or Agency
Informal Interpretation
Formal Interpretation
Legislature
Judiciary
Executive
Peculiarities
Breach of Contract
Assessed Damages
Art. 422.3
(Agreed Damages)
Art. 422.3
Agreed Penalty
Art. 422.1
Civil Code, No. 33 of 2005
Peculiarities
Breach of Contract
Assessed Damages
Art. 302
(No middle option)
Agreed Penalty
Art. 300
Commercial Law, No. 36 of 2005
Other main differences
Singapore Viet Nam
1. Sources of law • Statutes and judge made
law
• Statutes and formal
interpretations
2. Contractual terms • Freedom with limited
statutory control
• Uncertain freedom of
contract.
• Extensive mandatory
provisions
3. Discriminatory laws • No local vs. foreign
discrimination
• Special contractual
freedoms for foreign-
related projects
4. Security of performance • SOPA
• Freedom of contract
• Uncertain freedom of
contract
5. Standard/model forms • SIA Contract Form
• PSSCOC
• LTA Conditions
• Engineering
Procurement &
Construction, etc.
• FIDIC Book
Law review 2015
Arbitration Review
• New evidence in Court to challenge a
Tribunal Ruling
• Setting Aside of Award
Construction Review
• Performance Bond
Challenging jurisdiction – new evidence?
Gov’t of Laos v Sanum – 2015 High Court
Issue
• Is new evidence in Court allowed to
challenge a Tribunal ruling on jurisdiction?
Gov’t of Laos v Sanum – take away
• High Court: Allowed new evidence
• No absolute bar against new evidence
• 3 conditions
– Strong reason why evidence not produced at
arbitration
– Evidence is credible
– Evidence will (probably) have important influence
on case outcome
Setting aside of award – arbitration agreement
• S.2A(4)
“An arbitration agreement is in writing if its content
is recorded in any form ….” (emphasis added)
AQZ v ARA – 2015 High Court
• Issue #1 : Is one party’s written record of an arbit.
agrm. an “agreement in writing” even if not signed
or confirmed by the other party?
• S.2A(3) International Arbitration Act –
“An arbitration agreement shall be in writing”
Setting aside of award – sole arbitrator
AQZ v ARA - 2015 High Court
• Issue #2 : If the Arbit. Agrm. provides for a 3
member Tribunal, can the SIAC appoint a sole
Arbitrator?
AQZ v ARA – take away
• “In writing” requirement for Arbit. Agrm. - Very light touch
• Tip put any reference to Arbit. Agrm./objection in writing
• Tribunal size – consider Arbitral rules
• Tip if size matters, make clear agreed Tribunal size prevails
over Arbitral Rules
Setting aside of award - long delayed award
Coal & Oil LLC v GHCL Ltd – 2015 High Court
Issue
• Does ~ 2 year delay (19 months) from parties’ closing
submissions to Award allow setting aside Award?
Coal & Oil v GHCL – take away
• Delayed release is not ground to set aside Award
UNLESS
– Breach of a clearly specified time limit for Award
• Tips
– Specify express time limit for Award in Arbit.
Agrm.
– seek removal of Arbitrator for “undue delay”
before Award release (Art. 14 Model Law)
Setting aside of award – breach of natural justice
AKN v ALC – 2015 Court of Appeal
• Issue #1 - What is the standard to establish
breach of natural justice
– Category A : where the Tribunal fails to
consider an important issue in dispute
– Category B : where party not given opportunity
to present its case
AKN v ALC - standard of proof
Issue # 1 – Cat. A
Facts consistent with Tribunal Breach
Misunderstanding a party’s case /the law
Applying poor reasoning
Not dealing with a point
– thought unnecessary (perhaps due to
misunderstanding the law/ argument)
Tribunal (mistakenly) records that a particular
argument was withdrawn
– therefore does not consider it
X
X
X
✓
Natural Justice – Category B : Where party not given
opportunity to present its case
• Facts :
– The Buyers raised a new point on the final day of
hearing (which led to an Award of US$80m)
– No opportunity for the Sellers to present their case
in reply
• CA Held : ✓ Breach
AKN v ALC - standard of proof
Issue # 1 – Cat. B
AKN v ALC – Issue # 2
Breach of Natural Justice – Consequence
• Issue #2 - Is the entire Award set aside for
every breach of natural justice?
AKN v ALC – take away # 1
• NO RIGHT to a legally/factually “correct” Award
• ONLY RIGHT to :
– A decision on the dispute submitted
– Arrived at by a fair process, ie rules of natural justice
• Clear evidence of breach of natural justice
– “clear and virtually inescapable” inference
– Bar set deliberately high
AKN v ALC – take away # 2
• NO BREACH where Tribunal
– Misunderstands a point of submission, fact or law
– Fails to mention a point made by one party in Award
– Displays poor/incomplete reasoning
• BREACH where Tribunal
– Mistaken believes argument withdrawn & therefore
does not consider it
– Fails to allow party opportunity to present its case
Construction review: Performance Bonds
CKR v Asplenium – 2015 Court of Appeal
• On Demand Performance Bond (PB) call
• Issue: Can parties contractually exclude
unconscionability as a ground to restrain PB
call?
• Impact: Limit restrain to only fraud
Performance Bonds
CKR v Asplemium – Exclusion Clause
“… the Contractor agrees that except in the
case of fraud, the Contractor shall not …
restrain .. any [PB] call or demand … on
any ground including … unconscionability”
[emphasis added]
CKR v Asplenium – take away
• Likely to provoke a significant shift in drafting of on-
demand PBs
– To exclude unconscionability
• Fraud only remaining basis
• More difficult for contactors to resist on demand PB
calls
Security of Payment (SOP)
"… [The SOP Act] creates a statutory right to
progress payments, [but] does not compel a
claimant to [invoke it] … The option … is the
claimant’s … [A] contractual right … upon
service of a [Payment Claim], is elevated to a
statutory right under the Act".
(Kannan Ramesh JC, Libra Building v Emergent Engineering
[2015] SGHC 279 at [76])
Typical SOP Adjudication Steps
1 2 3 4 5 6 7
Pymt
Claim
Pymt
Response
7 day
Dispute
Settlement
Period
Notice
of
Intent
to Adj.
Adj.
App.
Adj.
Resp.
Adj. Det.
(for Const. Cont. + disputed Pymt Resp.)
Typical SOP Adjudication Steps
1 5 6
Pymt Claim Adj. App. Adj. Resp.
• UES Holdings
• LH Aluminium
• Libra Building
• Progressive Builders
• Eng Seng
• UES Holdings
• Newcon
• Libra Building
Citiwall Safety Glass
(for Const. Cont. + disputed Pymt Resp.)
Payment Claims (PC)
s 10 / r 5(1):
Claimant may serve one Payment Claim in respect
of a progress payment:
– at time specified in contract; or
– (if contract silent) by last day of each month
Payment Claims – Late Claims
UES Holdings v Grouteam – Quentin Loh J
• s. 10 timelines - "a mandatory condition” – breach
renders determination liable to be set aside
• SOP timelines - "a key feature of the scheme, [and]
must be complied with”
• Courts will insist on "strict adherence to the
timelines“ – because option of Court or Arbitral
proceedings remains
Payment Claims – “Repeat Claims”
LH Aluminium v Newcon - Lee Seiu Kin J
• "Repeat Claim”: where a Pymt Claim includes amounts
which already the subject of earlier Pymt Claim
• s 10: claimant may serve one Pymnt Claim in respect
of a progress payment
• Repeat claims allowed, unless earlier claim adjudicated
and dismissed on merits
(See: Doo Ree v Taisei; Terence Lee v Chua Sey Eng; JFC
Builders v Lioncity; Admin Const. v Vivaldi)
Payment Claims – Multiple Payment Claims
Libra Building v Emergent Engineering – Kannan Ramesh JC
• “claim period” - the period in which the claimant is permitted
to serve a payment claim
– s 10 / r 5(1): one Pymt Claim … at time specified by
contract or (if contract silent) by last day of each month
• "reference period" - the period of work covered by a payment
claim
• One Pymt Claim per claim period
• To avoid risk of Claimant being ambushed by multiple claims
Payment Claims – served by email
Progressive Builders v Long Rise – Lee Seiu Kin J
• S 37(1): "Where this Act… requires a document to be served
…, the document may be served on the person —
a) by delivering … personally;
b) by leaving … at … usual place of business …; or
c) by … post or facsimile …".
• Language of s. 37(1) permissive
• Email widely used in construction industry
Typical SOP Adjudication Steps
1 5 6
Pymt Claim Adj. App. Adj. Resp.
• UES Holdings
• LH Aluminium
• Libra Building
• Progressive Builders
• Eng Seng
• UES Holdings
• Newcon
• Libra Building
Citiwall Safety Glass
(for Const. Cont. + disputed Pymt Resp.)
Adjudication Applications – Late Applications
• UES Holdings v Grouteam – Quentin Loh J
• Eng Seng Precast v SLF Construction – Lee Seiu Kin J
– late application undermines the adjudicator's
jurisdiction
– determination will be set aside
– whether or not prejudice caused by the late
application
Typical SOP adjudication steps
1 2 3 4 5 6 7
Pymt
Claim
Pymt
Response
7 day
Dispute
Settlement
Period
Notice
of
Intent
to Adj.
Adj.
App.
Adj.
Resp.
Adj. Det.
(for Const. Cont. + disputed Pymt Resp.)
Adjudication Applications – premature
Newcon Builders v Sino New Steel – Quentin Loh J
• Entitlement to make an adjudication application" under s 12(2)
only arises if:
– no payment response, or
– unresolved dispute over a payment response
by the end of the dispute settlement period
• An adjudication application invalid if made before the
entitlement has arisen
• Whether or not there was prejudice is irrelevant
Adj. App. – accompanying documents
• Libra Building v Emergent Engineering – Kannan Ramesh
JC
– r 7(2)(e): Adj. App to be accompanied by copy of relevant
Pymt Claim
• UES Holdings v Grouteam – Quentin Loh J
– r 7(2)(d) – extracts relevant contractual provisions
• Courts rejected overly formalistic / pedantic / unduly technical
complaints where no prejudice caused by alleged breaches
Typical SOP adjudication steps
1 5 6
Pymt Claim Adj. App. Adj. Resp.
• UES Holdings
• LH Aluminium
• Libra Building
• Progressive Builders
• Eng Seng
• UES Holdings
• Newcon
• Libra Building
Citiwall Safety Glass
(for Const. Cont. + disputed Pymt Resp.)
Adjudication response - late
Citiwall Safety Glass v Mansource Interior (CA)
• Adj. Resp. lodged with SMC at 4.32pm on due date
• SMC's Adjudication Procedure Rules (Rule 2.2) :
– SMC’s “opening hours” are from 9.00am to 4.30pm
on weekdays, and 9am – 12 noon on eves of Xmas,
NY and CNY
– SMC reserves right to reject documents submitted after
hours
– But if accepted, documents are treated as being lodged
the next working day
Adjudication response - late
Citiwall Safety Glass v Mansource Interior
• Tan Siong Thye JC (HC):
– Adjudicator wrong to reject Adj. Resp.
– SMC has no role determining whether Adj.
Resp. late - role only to accept documents filed
and note time and date of filing
– Adj. Resp. within time if lodged by 11.59 pm on
due date
Adjudication response - late
Citiwall Safety Glass v Mansource Interior (CA)
• SMC has the power - to make rules restricting the
lodgement of documents to it's official closing time of
4.30pm see s 28(4)(e) & s 37
• SMC entitled to prescribe its business hours – SMC's
rule 2.2 was not ultra vires
• Irrelevant that the Adj. App. was only 2 minutes late
Key take away points
• Breaches of SOP timelines are not tolerated, even if no
prejudice is caused – so take them very seriously!
• Email service of documents is permitted under SOP Act
• Lodge docs with SMC within its “opening hours”
– 4.30pm on weekdays
– 12pm on eves of Xmas / NY / CNY
• Payment Claims (PC):
– Repeat claims allowed
– Maximum of one PC, per claim period
You cannot avoid conflicts but you can…
1. Run your projects so conflicts are less likely
2. Move through conflicts quickly when they happen
How does this work in practice
Interest based
negotiation
Communication
Low
Cost/Efficient
Rights based
resolution
Loop
Back
Who When
Uninvolved
Effective
Senior
Often
Early
Tiered dispute resolution (courtesy LTA)
Engineer’s
Decision
Amicable
Settlement
Mediation
Arbitration
Rights-Based
One-Sided
-
Who and How?
-
No Loop
Back
3 months
6 months
2 months
around a year
Power based solution
An effective model?
Dispute Arises
Negotiation
DB / Adjudication
Arbitration
Mediation
Blind Bidding