Upload
others
View
17
Download
1
Embed Size (px)
Citation preview
The Fertilisers and Chemicals Travancore Ltd
(FACT)
Udyogamandal, Kochi, Kerala
Welcome
National Workshop organised by
Knowledge Exchange Platform, BEE 07.11.2016 – 08.11.2016
Online Fuel and Feed Stock Changeover
from Naphtha to RLNG
in FACT Ammonia Plant
T.K. Unnikrishna Prasad, Energy Manager
Incorporated in 1943, Public Sector Undertaking in 1962,
ISO 9001 & ISO 14001 Company
Started Production of Ammonium Sulphate of 10000 MT of nitrogen per Annum in 1947
1966 : 99000 TPA Ammonium Phosphate
1972 : 49500 TPA Ammonium Phosphate
1976 : 528000 TPA Ammonium Phosphate
1990 : 50000 TPA Caprolactam & 225000 TPA Ammonium Sulphate Plants
1998 : 990 TPD Ammonia Plant with Naphtha
2013 : Fuel & feed changeover to RLNG in 990 TPD Ammonia Plant
Major Products : Ammonium Phosphate , Ammonium Sulphate. Caprolactam
Intermediate Products : Ammonia, Sulphuric Acid, Phosphoric Acid
About FACT
SULPHURIC ACID
PHOSPHORIC ACID
AMMONIA
FACTAMPHOS
20:20
ROCK
PHOSPHATE
SULPHUR
NAPHTHA
Or RLNG
FACTAMFOS 20:20 Design Capacity 6,76,500 MT per Year
SULPHURIC ACID
AMMONIA
AMMONIUM
SULPHATE
SULPHUR
NAPHTHA
Or RLNG
AMMONIUM SULPHATE-DN Route Design Capacity 2,25,000 MT per Year
FACT
Udyogamandal Complex
FACT
Cochin Division
FACT Engineering
& Design Organisation
FEDO
FACT Engineering
Works
FEW
FACT R&D
Divisions of FACT
FACT Ammonia Plants - Evolution
1947
Wood Gasification Process 40 MTPD
1962
Texaco Gasification Process 80 MTPD
1966
Texaco Gasification Process 140 MTPD
1972
Steam Reforming Process 120 MTPD
1973
ICI Steam Reforming Process 600 MTPD
1998
Steam Reforming Process of Naphtha 990 TPD
2013 Feed & fuel change over to RLNG
FACT Ammonia Complex
Commissioned in 1998
Project Cost Rs.638 Cr
Installed Capacity-990 TPD
Process Licensor - Haldor Topsoe, Denmark
CPP - 6 MW Turbo Generator with 2X60 TPH Boilers
( BHEL / BHPV make)
RLNG Conversion in Oct 2013 with
project cost Rs.47 Cr
Standalone Ammonia Plant included in
PAT from its cycle I period
Plant Boundary Scheme
CPP
AMMONIA PLANT
Ammonia
Re-gasified LNG (A)
Grid Electricity (B)
Steam Power
Ammonia Plant - Boundary
Modified Process Layout after Conversion
HT Shift Converter
Methanator
Methanator
Final Desulphurization
NH3 Synthesis
Section
CO2 Removal
Purge Recovery
Refrigerant
Primary Reforming
(Indirect heating by Firing)
Secondary Reforming
(Direct heating)
Reforming
CO Conversion HT Shift
Converter LT Shift
Converter
MDEA for Regeneration
Inert Gas as fuel
H2
MDEA
Purge
H2
Product Ammonia
RLNG Process Air
Steam
Flow Meter Arrangement
Background for conversion
Implementation of Nutrient Based Subsidy (NBS) for Phosphatic and Potassic (P&K) fertilisers w.e.f 1.4.2010 to follow fixed subsidy and floating MRP
Direction from Government of India (GoI) for captive ammonia units to convert from naphtha to NG/LNG.
Availability of LNG in Kochi through Petronet Terminal
Operation with LNG was envisaged in the initial design of the Ammonia Plant with minimum plant modifications and investment
LNG DISTRIBUTION NET WORK
Petronet LNG Ltd Terminal, Kochi, JV by Govt of India, Promoted by ONGC, IOC & BPCL
Storage in 2 Cryogenic tanks of 1,55,000 m3 and Gasification process in the Terminal
Gas Pigging Station in Eloor at a pipeline distance of 17km from Terminal
Gas Receiving / Metering station in
FACT battery limit
Distribution to Plants
Unique features of the changeover
All Construction activities were carried out concurrently while the plant was running
Changeover completed without any unsafe incidents or operational threats
Detailed Standard Operating Procedure(SOP) was developed with in house Operating/Design expertise with active support of process licensor
Savings in start up energy and cost savings above Rs.3Cr due to online changeover
FIRST ONLINE CHANGE OVER BY THE PROCESS LICENSOR IN INDIA
MAJOR PLANT MODIFICATONS FOR THE CHANGEOVER SCHEME
New Gas Receiving Station in FACT premises
Addition of RLNG preheater H206 for superheating RLNG
Addition of Sulphur Absorber
R 202 A before the existing unit
MAJOR PLANT MODIFICATONS FOR THE CHANGEOVER SCHEME
Addition of LNG Fuel Preheater E 207
New water dosing unit with its electrics before FDS reactor to prevent hydro cracking reactions
New Dimethyl Disulfide(DMDS)unit with its electrics to maintain minimum sulphur
Online upgradation/addition of hardware & software in DCS, development of control & shutdown schemes
GAS Receiving Station
RLNG Heater H206
Under Construction
Fuel Preheater E207
RLNG Heater H206
Under construction
Sulphur Absorber R 202A
Under construction
RLNG Heater H206
Operation Stage
FDS after Conversion
CPP Boiler
Conversion
MAJOR PLANT MODIFICATONS FOR THE CHANGEOVER SCHEME IN CPP
CPP
2X60 TPH Boilers &
6 MW Turbo Generator
Online fuel conversion from
FO to RLNG
Dual mode operational philosophy
Savings in internal steam
consumption by 3MT/hr/boiler
Investment
Rs. 13 Cr
Savings in steam required for Steam Coil Air Preheater (SCAP),FO heating,
soot blow & fuel atomization
MAJOR CHALLENGES DURING THE ONLINE CHANGEOVER PROCESS
During initial admission of gas in Fuel system for checking of valves, vent valve got stuck up in its closed condition
RLNG heater tripped after its initial lighting up on low Fuel gas Pressure
( Fuel Strainers were blocked due to dust carry over)
During the Online Change Over, Naphtha feed was reduced by 10% per day with increase of gas flow by 10 %. Since molecular weight measurement by Vortex Flow meter had problems, manual inputs were used for Controls
CHALLENGES DURING THE ONLINE CHANGEOVER PROCESS
Ultra filters at the gas receiving station was getting blocked by dust carry over and filter cleaning was required frequently.
On feeding of second consignment of gas, specific gravity along with methane content changed due to varied gas composition. Corrective measures in Controls were required at this instant
Sulphur content in the gas was varying on wide ranges which required close monitoring
Equipments Eliminated during conversion
Pre Desulphurization Section (PDS)
Naphtha Pre Heater E 216 & Naphtha Super Heater H205 in Final Desulphurization Section(FDS)
CHALLENGES AFTER THE CONVERSION PROCESS
Allocation of Natural Gas for Fertliser Sectors to be addressed
Any further reduction in Specific Energy Consumption (SEC) requires huge investment
ADVANTAGES OF NG USAGE IN FERTILSER SECTOR
Utilization of Energy value attribute as well as Chemical Value attribute unlike other sectors
Clean Fuel and Feed available for Fertilser Production
MAJOR IMPACT OF RLNG CONVERSION (75% PLANT LOAD)
Reduction of steam intake to Reformer by 28%
( Due to low Steam Carbon ratio for RLNG)
Reduction of Carbon Dioxide Emission by 28%
Reduction of Power Consumption by
300 Units /Hr ( Due to stoppage of PDS Section )
Reduction of Fire Load in the plant by 20%
( RLNG is much safer than naphtha in handling)
Over all reduction in steam intake to plant by
7 MT/Hr
RLNG Conversion - Summary
Online Conversion
1.67% savings in
SEC
Capital Investment – Rs. 47 Cr
Project Duration – 28 months
Changeover process –
5 days
FACT
Ceremonial Pumping of Gas to FACT 28 August, 2013
Sri. K. Jayachandran, Sri. K.S. Harikumar, Sri. Mathew P.J. Sri. Babu Jose, Sri. K.P. Reji, Sri. Faizal Latheef K.A., Smt. Emin .P. Mathew