SR 710/Warfield BoulevardProject Development & Environment Study
Big John Monahan Bridge Replacement
Project Development and Environment Study
December 10, 2008
Financial Management Number: 419348-3-22-01
Public HearingState Road 710 (Warfield Boulevard)
SR 710/Warfield BoulevardProject Development & Environment Study
Civil Rights Act, Titles VI and VIII
Martha Anderson,
District Equal Opportunity Compliance Manager
3400 West Commercial Boulevard
Fort Lauderdale, Florida 33309-3421
Phone: (954) 777 - 4389
Toll Free: (866) 336 - 8435 ext. 4389
orEqual Opportunity Office
605 Suwannee Street, MS #65
Tallahassee, Florida 32399-0450
Your Civil Rights
SR 710/Warfield BoulevardProject Development & Environment Study
Notice of this Public Hearing
Florida Administrative Weekly
November 14, 2008
The Stuart News & Indiantown News
November 19, 2008
December 1, 2008
SR 710/Warfield BoulevardProject Development & Environment Study
Purpose of this Public Hearing
Express your views on
the project’s
• location and design
• effects and impacts
SR 710/Warfield BoulevardProject Development & Environment Study
Purpose of this Public Hearing
The Reclassification of Access Management on SR 710
• Change from Class 6
to 5• Change from Class 4
to 3
SR 710/Warfield BoulevardProject Development & Environment Study
Project Location
BEGIN PROJECT
END PROJECT
SR 710/Warfield BoulevardProject Development & Environment Study
Separation of Studies
Bridge
Replacement
Bypass
Corridors Environmental Impact Statement (EIS)
SR 710/Warfield BoulevardProject Development & Environment Study
Major Stakeholders
• Indiantown CRA Neighborhood Advisory Committee
• CSX Railroad
• South Florida Water Management District
• Indiantown Marina
• Shipyard Planned Unit Development
• Riverland Mining & Reservoir Project
• U.S. Coast Guard
SR 710/Warfield BoulevardProject Development & Environment Study
Existing 3-Lane Roadway SectionSW Trail Drive to SW Citrus Blvd.
SR 710/Warfield BoulevardProject Development & Environment Study
Existing 2-Lane Roadway SectionSW Citrus Blvd. to SR 76 Connector Ramps
SR 710/Warfield BoulevardProject Development & Environment Study
Existing Traffic Conditions
• Current Daily Traffic Volumes = 14,000
vpd
• Existing Level of Service = “D”
• Level of Service Standard = “C”
(“Level of Service” = measure of congestion)
SR 710/Warfield BoulevardProject Development & Environment Study
Project Need
• Increased traffic demand
• Congested operating conditions
• Existing safety and geometric deficiencies on
bridge
• Hurricane Evacuation Route
• Strategic Intermodal System Highway
• Lack of pedestrian and bicycle facilities
• Obstacle to economic development
SR 710/Warfield BoulevardProject Development & Environment Study
PD&E Study Goals
• Address mobility for all modes of
transportation within the corridor
• Improve safety
• Minimize impacts
• Comply with NEPA
• Consistent with state and local plans
SR 710/Warfield BoulevardProject Development & Environment Study
PD&E Study Process
• Collect data
• Develop alternatives
• Analysis of alternatives
• Select preferred alternative
• Continued public involvement
SR 710/Warfield BoulevardProject Development & Environment Study
Agency Coordination
Community of Indiantown
Community of Indiantown
IndiantownCRA/NACIndiantownCRA/NAC
SR 710/Warfield BoulevardProject Development & Environment Study
Project Alternatives
• “Build” Alternative
• “No-Build” Alternative
SR 710/Warfield BoulevardProject Development & Environment Study
“No-Build” Alternative
• Increased Bridge Service Life
• Improved Safety
• Improved Navigational Clearances
ADVANTAGES
• Not meeting Level of Service Standard “C”
• Increased Congestion, Delays, Road User
Costs
• Deterioration of Air Quality
• Evacuation Route Function Impaired
DISADVANTAGES
SR 710/Warfield BoulevardProject Development & Environment Study
Access Management
Florida Statute 335.18• Rule 14-96 and 14-97
Rules Establish Minimums For:• Driveway Connection Spacing
• Directional Median Opening Spacing
• Full Median Opening Spacing
• Traffic Signal Spacing
SR 710/Warfield BoulevardProject Development & Environment Study
Access Management Reclassification(SW Trail Drive to SW Citrus Blvd.)
Access
Class
Median
Type
Driveway
Connection
Spacing
(feet)
Median OpeningSpacing (feet) Signal
Spacin
g
(feet)
Directiona
lFull
Proposed
5Restrictive 245 660 1320 1320
Existing
6
Non-
Restrictive245 ---- ---- 1320
SR 710/Warfield BoulevardProject Development & Environment Study
Access Management Reclassification (SW Citrus Blvd. to SR 76 Connector Ramps)
Access
Class
Median
Type
Driveway
Connection
Spacing
(feet)
Median OpeningSpacing (feet) Signal
Spacin
g
(feet)
Directiona
lFull
Proposed
3Restrictive 440 1320 2640 2640
Existing
4
Non-
Restrictive440 ---- ---- 2640
SR 710/Warfield BoulevardProject Development & Environment Study
SW Trail Dr., SW Fernwood Forest Road & SW Seminole Drive Intersections
SR 710/Warfield BoulevardProject Development & Environment Study
SW Citrus Blvd. & SR 76 Ramps Intersections
SW Citrus Blvd. SR 76 Connector Ramps
SR 710/Warfield BoulevardProject Development & Environment Study
“Build” Alternative
• Improved Traffic Flow
• Enhanced Mobility for Pedestrians and
Bicyclists
• Improved Safety
• Improved Evacuation Times
• Improved Stormwater Quality
• Extended Bridge Service Life
• Promotion of Economic Development
ADVANTAGES
• Short-Term Construction InconveniencesDISADVANTAGES
SR 710/Warfield BoulevardProject Development & Environment Study
Aesthetics
•Landscaping
•Sodding
•Street Lighting
•Multi-Column Bridge Piers
•Retaining Walls
Aesthetics to be coordinated during the Design Phase.
SR 710/Warfield BoulevardProject Development & Environment Study
Consistency with Local Plans
• Martin Metropolitan Planning Organization
• Indiantown Vision Plan
SR 710/Warfield BoulevardProject Development & Environment Study
• Natural
• Physical
• Social
• Cultural
Environmental Impact Assessment
SR 710/Warfield BoulevardProject Development & Environment Study
Evaluated according to:
Title 50, CFR Part 402
Executive Order 11990
Executive Order 11988
Title 23, CFR
1990 Clean Air ActConclusion:
No adverse impacts
Environmental Impact Assessment
SR 710/Warfield BoulevardProject Development & Environment Study
Stormwater quality would be improved as a result of the project
Water Quality Impacts
Conclusion:
SR 710/Warfield BoulevardProject Development & Environment Study
Impacts evaluated in accordance with Title 23, CFR Part 772
Noise Receptors and Impacts
Abatement measures found not to be feasible
SR 710/Warfield BoulevardProject Development & Environment Study
Contamination
Three potential sites
Additional testing recommended in the future
SR 710/Warfield BoulevardProject Development & Environment Study
Social & Cultural Impacts
No adverse impacts to
•Parks or recreation facilities
•Historic or archaeological sites
SR 710/Warfield BoulevardProject Development & Environment Study
Right of Way Requirements and Relocations
No Right of Way Acquisition
and
No Business or Residential
Relocations
SR 710/Warfield BoulevardProject Development & Environment Study
Estimated Project Costs
Preliminary Engineering . . . . . . . . . . 1.8
Right of Way . . . . . . . . . . . . . . . . . . . .
0
Design-Build . . . . . . . . . . . . . . . . . . 80.4
Construction Support . . . . . . . . . . . . 8.4
TOTAL . . . . . . . . . . . . . . . . . . . . . . . . 90.6
*Present Day Costs (2008)
(in $ millions*)
SR 710/Warfield BoulevardProject Development & Environment Study
Project Schedule
• Completion of PD&E Study June 2009
• Completion of Design-Build Criteria Package June 2011
• Begin Design-Build Phase Summer 2011
• Completion of Construction Summer 2014
SR 710/Warfield BoulevardProject Development & Environment Study
Previous Public Involvement
• Indiantown Neighborhood Advisory Committee
• Martin MPO Policy Board
• Martin MPO TAC/CAC
• Martin MPO BPAC
• Indiantown Town Meeting
• Public Kickoff Meeting
• Alternatives Public Workshop
SR 710/Warfield BoulevardProject Development & Environment Study
Staff Available to Answer Questions
SR 710/Warfield BoulevardProject Development & Environment Study
• Speak at the microphone
• Speak individually with the court reporter
Public Testimony
SR 710/Warfield BoulevardProject Development & Environment Study
Public Testimony
• Submit here today
• Submit by mail, email, or fax
SR 710/Warfield BoulevardProject Development & Environment Study
Mail Comments To:
Patrick Glass, P.E.FDOT Project Manager
Florida Department of Transportation, District IVPlanning and Environmental Management
3400 West Commercial BoulevardFort Lauderdale, Florida 33309-3421
Fax (954) 777- 4671
Email: [email protected]
All comments must be received by Monday, December 22, 2008
SR 710/Warfield BoulevardProject Development & Environment Study
• We look forward to receiving your comments
• Please Review the Plans and documents here todayBig John Monahan Bridge Replacement
Project Development and Environment Study
December 10, 2008
Financial Management Number: 419348-3-22-01
Public HearingState Road 710 (Warfield Boulevard)
• Chapter 23 of United States Code
• Title 40 of the Code of Federal Regulations Volume 31, Chapter V, Parts 1500 - 1508
• Title 40 of the Code of Federal Regulations Chapter I Part 93.105
• Title 23 of the Code of Federal Regulations Chapter I Part 450
• Title 23 of the Code of Federal Regulations Part 771, Section 771.111
• Title 49 of the Code of Federal Regulations, Subtitle A, Part 24
• Federal Highway Act of 1968, as amended
• Florida Statute 339.155
• Florida Statute 120.525
• Florida Statute 286.011
• Florida Statute 339.175
• Florida Statute 335.02(1)
• Florida Statute 479.106, Amended – HB 273
• 23 USC, Section 128
• 23 USC, Section 135
• 42 USC, Chapter 126, Section 12101
• 42 USC, Subchapter V, Sections 2000d-2000d-7
• 42 USC, Title 42, Chapter 55, Section 4321
• Florida Statute 120
• Americans with Disabilities Act of 1990
• Title VI of the Civil Rights Act of 1964, as amended
• Title VIII of the Civil Rights Act of 1968, as amended
• Florida Statute 335.18, “Access Management”
• Public Law 91-646 as amended by Public Law 100-17
• Public Law 109-59, Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU), August 25, 2005
• TEA-21, Transportation Equity Act for the 21st Century, June 9, 1998
• ISTEA Intermodal Surface Transportation Efficiency Act, 1991
• Executive Order Number 11988, “Floodplain Management”
• Executive Order Number 11990, “Protection of Wetlands”
• Executive Order Number 12898, “Environmental Justice”
• Executive Order Number 13166, “Improving Access to Services for Persons with Limited English Proficiency”
• Technical Advisory 6640.8A
• U.S. Department of Transportation Act of 1966
• Title 23 of the Code of Federal Regulations, “Highways”
• Title 40 of the Code of Federal Regulations, “Protection of Environment”
• Title 50 of the Code of Federal Regulations, “Wildlife and Fisheries”
This Public Hearing is being held in accordance with: