Click here to load reader
Upload
hatram
View
212
Download
0
Embed Size (px)
Citation preview
S:\Camden County\Project Files\HCM00601.01 - HATV Haddon Ave Transit Village Roadway Improvements CR561\Correspondence\16-06-21 Weekly Status Report - WE June 17th.doc
Weekly Status Report – Week ending June 17, 2016
Haddon Avenue Transit Village Roadway Improvements- Phase II The Haddon Avenue Transit Village Roadway Improvements – Phase II Project was awarded to Jersey Construction, in the amount of $4,234,075.58. Please see the attached status breakdown for the various components involved in this project. Streetscaping Improvements
The contractor installed 2” Rigid Non-Metallic Conduit, 3” Metallic Rigid Conduit, Lighting, Foundations, 5” Concrete Sidewalk, Reinforced, 9”x18” Concrete Vertical Curb, and 6”x18” Concrete Curb Retaining Wall along the back of sidewalk on Haddon Ave.
June 21, 2016 Our File No. HCM00601.01 Page 2
S:\Camden County\Project Files\HCM00601.01 - HATV Haddon Ave Transit Village Roadway Improvements CR561\Correspondence\16-06-21 Weekly Status Report - WE June 17th.doc
Clearing Site
Contractor performed excavation 5” deep on Haddon Ave. to center line of Road
Road opening was restored with 6” Thick DGA (R-Blend) Base course.
Storm Sewer
No work for this portion of the project was completed this week.
Environmental Remarks
No remarks from this project this week.
Shop Drawing Submittals
No work for this portion of the project was completed this week.
Utility Pole Relocation
No work for this portion of the project was completed this week.
June 21, 2016 Our File No. HCM00601.01 Page 3
S:\Camden County\Project Files\HCM00601.01 - HATV Haddon Ave Transit Village Roadway Improvements CR561\Correspondence\16-06-21 Weekly Status Report - WE June 17th.doc
Roadway Reconstruction
No work for this portion of the project was completed this week.
Changes to the Initial Contract Items
No work for this portion of the project was completed this week.
NJDOT Comments
No comments from the NJDOT have been made this week.
Traffic Control Installation
No traffic control was required for this project this week.
Anticipated Project Closeout
The contractor anticipates the work to be completed by October 2016.
.