Weekly Status Report Week ending June 17, 2016 · Weekly Status Report – Week ending June 17, 2016 ... No traffic control was required for this project this week. Anticipated Project

  • Upload
    hatram

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Weekly Status Report Week ending June 17, 2016 · Weekly Status Report – Week ending June 17, 2016 ... No traffic control was required for this project this week. Anticipated Project

S:\Camden County\Project Files\HCM00601.01 - HATV Haddon Ave Transit Village Roadway Improvements CR561\Correspondence\16-06-21 Weekly Status Report - WE June 17th.doc

Weekly Status Report – Week ending June 17, 2016

Haddon Avenue Transit Village Roadway Improvements- Phase II The Haddon Avenue Transit Village Roadway Improvements – Phase II Project was awarded to Jersey Construction, in the amount of $4,234,075.58. Please see the attached status breakdown for the various components involved in this project. Streetscaping Improvements

The contractor installed 2” Rigid Non-Metallic Conduit, 3” Metallic Rigid Conduit, Lighting, Foundations, 5” Concrete Sidewalk, Reinforced, 9”x18” Concrete Vertical Curb, and 6”x18” Concrete Curb Retaining Wall along the back of sidewalk on Haddon Ave.

Page 2: Weekly Status Report Week ending June 17, 2016 · Weekly Status Report – Week ending June 17, 2016 ... No traffic control was required for this project this week. Anticipated Project

June 21, 2016 Our File No. HCM00601.01 Page 2

S:\Camden County\Project Files\HCM00601.01 - HATV Haddon Ave Transit Village Roadway Improvements CR561\Correspondence\16-06-21 Weekly Status Report - WE June 17th.doc

Clearing Site

Contractor performed excavation 5” deep on Haddon Ave. to center line of Road

Road opening was restored with 6” Thick DGA (R-Blend) Base course.

Storm Sewer

No work for this portion of the project was completed this week.

Environmental Remarks

No remarks from this project this week.

Shop Drawing Submittals

No work for this portion of the project was completed this week.

Utility Pole Relocation

No work for this portion of the project was completed this week.

Page 3: Weekly Status Report Week ending June 17, 2016 · Weekly Status Report – Week ending June 17, 2016 ... No traffic control was required for this project this week. Anticipated Project

June 21, 2016 Our File No. HCM00601.01 Page 3

S:\Camden County\Project Files\HCM00601.01 - HATV Haddon Ave Transit Village Roadway Improvements CR561\Correspondence\16-06-21 Weekly Status Report - WE June 17th.doc

Roadway Reconstruction

No work for this portion of the project was completed this week.

Changes to the Initial Contract Items

No work for this portion of the project was completed this week.

NJDOT Comments

No comments from the NJDOT have been made this week.

Traffic Control Installation

No traffic control was required for this project this week.

Anticipated Project Closeout

The contractor anticipates the work to be completed by October 2016.

.