48
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA flo.. E 0 US DiSTRICT C OISTA!CT OF NEB AUG 19 2005 SINCO, INC., v. ) ) Plaintiff, ) ) ) ) 8:03CV315 U.S. CHICORY INC., ) ) Defendant. ) ---------------------- ) JURY INSTRUCTIONS

  · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

  • Upload
    others

  • View
    22

  • Download
    0

Embed Size (px)

Citation preview

Page 1:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

flo.. E 0US DiSTRICT C

OISTA!CT OF NEB

AUG 19 2005

SINCO, INC.,

v.

))

Plaintiff, )))) 8:03CV315

U.S. CHICORY INC., ))

Defendant. )

---------------------- )

JURY INSTRUCTIONS

Page 2:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 1 of 33

Instruction No. I

Members of the jury, the instructions I gave at the beginning of the trial and during

the trial remain in effect. I now give you some additional instructions.

You must, of course, continue to follow the instructions I gave you earlier, as well as

those I give you now. You must not single out some instructions and ignore others, because

all are important. This is true even though some of those I gave you previously are not

repeated here.

The instructions I am about to give you now as well as those I gave you earlier are in

writing and will be available to you in the jury room. Again, all instructions, whenever given

and whether in writing or not, must be followed.

Page 3:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 2

Page 2 of 33

Neither in these instructions nor in any ruling, action or remark that I have made

during the course of this trial have I intended to give any opinion or suggestion as to what

your verdict should be.

Page 4:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No.3

Page 3 of 33

In deciding what the facts are, you may have to decide what testimony you believe

and what testimony you do not believe. You may believe all of what a witness said, or only

part of it, or none of it.

In deciding what testimony to believe, you may consider a witness' intelligence, the

opportunity a witness had to see or hear the things testified about, a witness' memory, any

motives a witness may have for testifying a certain way, the manner of a witness while

testifying, whether a witness said something different at an earlier time, the general

reasonableness of the testimony, and the extent to which the testimony is consistent with any

evidence that you believe.

In deciding whether or not to believe a witness, keep in mind that people sometimes

hear or see things differently and sometimes forget things. You need to consider therefore

whether a contradiction is an innocent misrecollection or lapse of memory or an intentional

falsehood, and that may depend on whether it has to do with an important fact or only a small

detail.

Page 5:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No.4

Page 4 of 33

You are the sole judges of the credibility of the witnesses and the weight to be given to

their testimony. You may believe all of what a witness said, or only part of it, or none of it.

In determining this, you may consider the following:

I. The conduct and demeanor of the witness while testifying;

2. The sources of information, including the opportunity for seeing or knowing the things about which the witness testified;

3. The ability of the witness to remember and to communicate accurately;

4. The reasonableness or unreasonableness of the testimony of the witness;

5. The self-interest or lack of self-interest of the witness in the result of this case;

6. The apparent fairness or bias of the witness, or the witness's relationship to the parties;

7. Any previous statement or conduct of the witness that is consistent or inconsistent with testimony of the witness at this trial; and

8. Any other evidence that affects the credibility of the witness or that tends to support or contradict the testimony of the witness.

Page 6:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 5

Page 5 of 33

In these instructions you are told that your verdict depends on whether you find

certain facts have been proved. The burden of proving a fact is upon the party whose claim

depends upon that fact. The party who has the burden of proving a fact must prove it by the

greater weight of the evidence. To prove something by the greater weight of the evidence is

to prove that it is more likely true than not true. It is determined by considering all of the

evidence and deciding which evidence is more believable. If, on any issue in the case, the

evidence is equally balanced, you cannot find that issue has been proved.

The greater weight of the evidence is not necessarily determined by the greater

number of witnesses or exhibits a party has presented.

You may have heard of the term "proof beyond a reasonable doubt." That is a

stricter standard which applies in criminal cases. It does not apply in civil cases such as

this. You should, therefore, put it out of your minds.

Page 7:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No.6

Page 6 of 33

The plaintiff and defendant are corporations.

A corporation can act only through its employees or agents. A corporation is bound

by the knowledge possessed by its employees and agents. It is also bound by such acts or

omissions of its employees as are within the scope of their employment, and by such acts or

omissions of its agents, are within the scope of their authority as agents.

All of the parties to a lawsuit are entitled to the same fair and impartial consideration,

whether they are corporations or individuals.

Page 8:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No.7

Page 7 of 33

The evidence from which you are to find the facts consists of the following:

1. The testimony of the witnesses;

2. Documents and other things received as exhibits; and

3. Any facts that have been stipulated-that is, formally agreed to by the

parties.

The following things are not evidence:

1. Statements, arguments, and questions of the lawyers for the parties in this case;

2. Objections to questions;

3. Any testimony I told you to disregard; and

4. Anything you may have seen or heard about this case outside the courtroom.

Page 9:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No.8

Page 8 of 33

There are two kinds of evidence, direct and circumstantial.

Direct evidence is either physical evidence of a fact or testimony by someone who has

first-hand knowledge of a fact by means of his or her senses.

Circumstantial evidence is evidence of one or more facts from which another fact can

logically be inferred.

You are instructed that you should not be concerned with those terms. The law makes

no distinction between these two kinds of evidence. A fact may be proved by either direct

evidence or circumstantial evidence or both. You should give all evidence the weight and

value you believe it is entitled to receive.

Page 10:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No.9

Page 9 of 33

A witness who has special knowledge, skill, experience, training, or education in a

particular area may testify as an expert in that area. You determine what weight, if any, to

give to an expert's testimony just as you do with the testimony of any other witness. You

should consider the expert's credibility as a witness, the expert's qualifications as an expert,

the sources of the expert's information, and the reasons given for any opinions expressed by

the expert.

Page 11:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 10

Page 10 of 33

During the trial, testimony was presented to you by written deposition and by video

deposition. Such testimony is under oath and is entitled to the same fair and impartial

consideration you give other testimony.

Page 12:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 11

Page II of 33

The law forbids you to return a verdict determined by chance. You may not, for

instance, agree in advance that each juror will state an amount to be awarded in damages, that

all of those amounts will be added together, that the total will be divided by the number of

jurors, and that the result will be returned as the jury's verdict. A verdict determined by

chance is invalid.

Page 13:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 12 of 33

Instruction No. 12

STATEMENT OF THE CASE

You are instructed that, as a matter of law, the plaintiff and the defendant did enter

into the Dryer Removal Contract and the Time and Materials Contract.

In order for a party to be bound to a specific contractual obligation, there must be a

meeting of the minds between the parties as to that particular term. The parties disagree as

to the terms of both contracts.

Your job, as the finder of fact, is to decide what terms were included in the Dryer

Removal Contract and the Time and Materials Contract.

I. THE DRYER REMOVAL CONTRACT

The parties agree that March of 2001, plaintiff and defendant entered into a contract

whereby plaintiff would move two rotary pulp dryers and a dust collection system from

Renville, Minnesota to and install them in defendant's chicory plant in Scottsbluff, Nebraska

in exchange for a sum not to exceed $578,495.40.

Plaintiff claims that it performed all work pursuant to the Dryer Removal Contract

and alleges that defendant breached the Dryer Removal Contract by failing to pay to plaintiff

the sum of $17,519.11 for work performed and completed by plaintiff under the terms of

the Dryer Removal Contract.

The defendant agrees that the contract price was $578,495.40, but claims that, as part

of the Dryer Removal Contract, plaintiff also agreed to install the pulp dryers and dust

Page 14:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

collection system in the chicory processing plant so that it would be functional in time for

Page 13 of 33

the chicory harvest campaign which was to take place in the fall of 2001. The plaintiff

disputes that it agreed to install the pulp dryers and dust collection system in the chicory

processing plant so that it would be functional in time for the chicory harvest campaign

which was to take place in the fall of2001.

The defendant contends that the plaintiff did not substantially complete the work that

plaintiff agreed to perform in that the dryers were never functional, and that the plaintiff

failed to perform the work agreed upon in a timely, reasonable, and workmanlike manner.

Defendant claims that as a result of plaintiff's breach of the Dryer Removal Contract,

defendant was required to pay other contractors the sum of$65,688.00, in addition to the

sum of $548,880.00, which it paid to plaintiff.

A. Elements of Proof- Plaintiffs Claim for Breach of the DryerRemoval Contract

If you find the plaintiff has proven, by the greater weight of the evidence, that

1. the plaintiff did not agree to install the pulp dryers and dust collection system in the chicory processing plant so that it would be functional in time for the chicory harvest campaign which was to take place in the fall of2001, and

2. the plaintiff substantially performed all its work pursuant to the DryerRemoval Contract,

then your verdict must be for the plaintiff and against the defendant on plaintiff's claim for

breach of the Dryer Removal Contract and you must determine the amount of damages that

should be awarded to the plaintiff under Instruction No. 22.

Page 15:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

If the plaintiffhas not proven these matters by the greater weight of the evidence, then

Page 14 of 33

your verdict must be for the defendant and against the plaintiff on plaintiffs claim for breach

of the Dryer Removal Contract.

B. Elements of Proof- Defendant's Counterclaim for Breach of theDryer Removal Contract

If you find the defendant has proven, by the greater weight of the evidence,

1. that the plaintiff did agree to install the pulp dryers and dust collection system in the chicory processing plant so that it would be functional in time for the chicory harvest campaign which was to take place in the fall of2001, and the plaintiff did not substantially complete the work in a timelymanner,

2. the plaintiff did not substantially complete the work m a good and workmanlike manner,

then your verdict must be for the defendant and against the plaintiff on the defendant's

counterclaim for breach of the Dryer Removal Contract and you must determine the amount

of damages that should be awarded to the defendant under Instruction No. 22.

If the defendant has not proven these matters by the greater weight of the evidence,

then your verdict must be for the plaintiff and against the defendant on defendant's

counterclaim for breach of the Dryer Removal Contract.

II. BREACH OF THE TIME AND MATERIALS CONTRACT

Plaintiff alleges that, pursuant to the Time and Materials Contract, plaintiff agreed to

provide additional work on the U.S. Chicory plant on a time and materials basis, and that

defendant agreed to pay plaintiff for this additional work on the basis of time and materials.

Page 16:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 15 of 33

The plaintiff claims that it performed all work to be completed pursuant to the Time and

Materials Contract and that the defendant breached the Time and Materials Contract by

failing to pay to plaintiff the sum of $517,098.23 for work performed and completed on a

time and materials basis.

The defendant claims that, in the Time and Materials Contract, the plaintiff agreed to

design and construct a chicory processing plant on defendant's property in Scottsbluff,

Nebraska in a reasonable, workmanlike, and timely manner for a sum not to exceed $1.3

million, excluding the Dryer Removal Contract, and that all the work would be completed

so that the equipment would be functional in time for the chicory harvest campaign which

was to take place in the fall of 2001.

The plaintiff denies that the Time and Materials Contract included a $1.3 cap and

denies that there was any agreement about the completion date. Plaintiff also argues that

defendant waived the alleged $1.3 million cap by approving invoices for payment in excess

of that amount, and that the defendant waived the alleged fall 2001 deadline by consenting

to the continuance of the work beyond that date.

A. Elements of Proof- Plaintiffs Claim for Breach of the Time andMaterials Contract

If you find plaintiff has proven, by the greater weight of the evidence, that

1. The plaintiff did not agree to complete all work in the chicory processing plant so that it would be functional in time for the fall2001 chicory harvest campaign, or that the defendant waived any such deadline by consenting to the continuance of the work beyond that date,

and

Page 17:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 16 of 33

2. The Time and Materials contract did not include a $1.3 million cap, or that the defendant waived any $1.3 million cap by consenting to the continuance of the work beyond that date,

then your verdict must be for the plaintiff and against the defendant on plaintiff's claim for

damages with regard to the Time and Materials Contract and you must determine the amount

of damages that should be awarded to the plaintiff under Instruction No. 22.

If the plaintiff has not proven these matters by the greater weight of the evidence,

then your verdict must be for the defendant and against the plaintiff on plaintiff's claim for

breach of the Time and Materials Contract.

B. Elements of Proof- Defendant's Counterclaim for Breach of theTime and Materials Contract

If you find defendant has proven, by the greater weight of the evidence, that

1. The plaintiff did agree to complete all work in the chicory processing plant so that it would be functional in time for the fall 2001 chicory harvest campaign, and plaintiff has not proven by the greater weight of the evidence that the defendant waived any such deadline by consenting to the continuance of the work beyond that date,

and

2. The Time and Materials contract did include a $1.3 million cap, and plaintiff has not proven by the greater weight of the evidence that the defendant waived the $1.3 million cap by consenting to the continuance of the work beyond that date,

then your verdict on the defendant's counterclaim for breach of the Time and Materials

Contract must be for the defendant and against the plaintiff and you must determine the

amount of damages that should be awarded to the defendant under Instruction No. 22.

Page 18:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 17 of 33

If the defendant has not proven these matters by the greater weight of the evidence,

then your verdict must be for the plaintiff and against the defendant on defendant's

counterclaim for breach of the Time and Materials Contract.

Page 19:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 13

Page 18 of 33

A party's performance is substantial if the party made a good faith effort to live up to

the party's part of the contract and any deviations from the requirements of the contract are

relatively minor and unimportant.

Page 20:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 14

Page 19 of 33

Every contract for work or services includes an implied duty to perform the work or

service skillfully, carefully, diligently, and in a workmanlike manner. Accompanying every

contract is a common-law duty to perform with care, skill, reasonable expedience, and

faithfulness of the thing to be done.

Page 21:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 15

Page 20 of 33

In the absence of a stated time for performance, the law will imply a time of

performance within a reasonable time under the circumstances.

Page 22:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 16

Page 21 of 33

Where, after a contract is made, a party's performance is made impracticable without

his fault by the occurrence of an event, the non-occurrence of which was a basic assumption

on which the contract was made, his duty to render that performance is discharged, unless

the circumstances indicate the contrary.

Page 23:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 17

Page 22 of 33

Where a contractor is delayed by causes beyond his control, it excuses the resultant

delay as well. If a contractor's conduct in not completing the work on time was due to

circumstances beyond his control, or the result of the delay caused by the owner, the owner

does not have a valid claim for damages for the delay. A contractor may be excused from

liability for delays attributable to defective plans and specifications provided by the owner.

Page 24:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 18

Page 23 of 33

A "time and materials contract" is a contract where one hires a contractor to do work

but does not make a specific contract for a definite sum. When this type of contract occurs,

it is generally understood to be for time and material as that contractor does business, that

is, his or her usual charges for such work.

Page 25:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 19

Page 24 of 33

Under a time and materials contract, a contractor is allowed all costs and charges

incurred that are reasonably necessary to the completion of the project. A time and materials

contract is one in which a contractor is compensated for labor based upon fixed hourly rates

and reimbursed for the materials required to perform the work based upon the cost of

acquisition, unless the parties specifically agree otherwise. With respect to materials, a

contractor's cost of acquisition normally consists of the price paid to a supplier to procure the

materials plus a fixed percentage to cover the contractor's general and administrative

expenses.

Page 26:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 20

Page 25 of 33

A time and materials contract contains no minimum or maximum contract amount,

unless one is specifically agreed to by the parties. The owner bears the risk and burden of

all allowable costs under a time and materials contract.

Page 27:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 21

Page 26 of 33

Parties to a contract may agree to waive performance requirements and may agree to

suspend the contract, in which case# neither party has the obligation to perform.

A waiver is the intentional relinquishment of a known right after knowledge of all the

relevant facts. An express or implied acceptance of work as in compliance with a building

contract operates as a waiver of defective performance, thus preventing the owner from

avoiding payment on the basis of the defective performance. However, a party cannot be

presumed to waive an unknown defect.

An owner may, either expressly or by implication, waive or extend the time within

which a building contract is to be performed by the contractor. If, after the time for

completion of the work has expired, the owner assents to the continuance of the work

without objection to the delay, he will be deemed to have waived the provision as to time of

performance and thereby release any claim to damages by reason of the delay in completion

of the project.

Page 28:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Instruction No. 22

Page 27 of 33

DAMAGES

I. THE DRYER REMOVAL CONTRACT

A. Plaintiffs Claim for Breach of the Dryer Removal Contract

If, pursuant to Instruction No. 12, you find in favor of the plaintiff and against the

defendant on plaintiff's claim for breach of the Dryer Removal Contract, then you must

determine the amount of plaintiff's damages.

The plaintiff is entitled to recover the following:

I. The contract price,

2. Minus any payments already received for its work.

If you find in favor of the plaintiff on its claim for breach of the Dryer Removal Contract,

but do not find any actual damage, then you may award the plaintiff no more than a nominal

sum.

B. Defendant's Counterclaim for Breach of the Dryer Removal Contract

If, pursuant to Instruction No. 12, you find in favor of the defendant and against the

plaintiff on the defendant's counterclaim for breach of the Dryer Removal Contract, then you

must determine the amount of defendant's damages. In that event, the defendant is entitled

to recover its reasonable costs incurred for paying other contractors to complete necessary

work on the Dryer Removal Contract so that defendant's chicory processing plant would be

functional for the fall2001 chicory harvest campaign.

Page 29:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 28 of 33

If you find in favor of the defendant on its counterclaim for breach of the Dryer

Removal Contract, but do not find any actual damage, then you may award the defendant no

more than a nominal sum.

II. THE TIME AND MATERIALS CONTRACT

A. Plaintiffs Claim for Breach of the Time and Materials Contract

If, pursuant to Instruction No. 12, you find in favor of the plaintiff and against the

defendant on plaintiffs claim for breach of the Time and Materials Contract, then you must

determine the amount of plaintiffs damages.

The plaintiff is entitled to recover the following:

1. The reasonable cost of the work performed,

2. Minus any payments already received for its work.

If you find in favor of the plaintiff on its claim for breach of the Time and Materials

Contract, but do not find any actual damage, then you may award the plaintiff no more than

a nominal sum.

B. Defendant's Counterclaim for Breach of the Time and Materials Contract

If, pursuant to Instruction No. 12, you find in favor of the defendant and against the

plaintiff on the defendant's counterclaim for breach of the Time and Materials Contract, then

you must determine the amount of defendant's damages. In that event, the defendant is

entitled to recover its reasonable costs incurred for paying other contractors to complete

necessary work on the Time and Materials Contract so that defendant's chicory processing

plant would be functional for the fall 2001 chicory harvest campaign.

Page 30:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 29 of 33

If you find in favor of the defendant on its counterclaim for breach of the Time and

Materials Contract, but do not find any actual damage, then you may award the defendant no

more than a nominal sum.

Page 31:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 30 of 33

Instruction No. 23

In conducting your deliberations and returning your verdict, there are certain rules you must

follow.

First, when you go to the jury room, you must select one of your members as your

foreperson. That person will preside over your discussions and speak for you here in court.

Second, it is your duty, as jurors, to discuss this case with one another in the jury room.

You should try to reach agreement if you can do so without violence to individual judgment,

because a verdict must be unanimous.

Each of you must make your own conscientious decision, but only after you have considered

all the evidence, discussed it fully with your fellow jurors, and listened to the views of your fellow

Jurors.

Do not be afraid to change your opinions if the discussion persuades you that you should.

But do not come to a decision simply because other jurors think it is right, or simply to reach a

verdict. Remember at all times that you are not partisans. You are judges - judges of the facts.

Your sole interest is to seek the truth from the evidence in the case.

Third, if you need to communicate with me during your deliberations, you may send a note

to me through the courtroom deputy, signed by one or more jurors. I will respond as soon as

possible either in writing or orally in open court. Remember that you should not tell anyone -

including me- how your votes stand numerically.

Fourth, your verdict must be based solely on the evidence and on the law which I have

given to you in my instructions. Nothing I have said or done is intended to suggest what your

verdict should be - that is entirely for you to decide.

Finally, the verdict form is simply the written notice of the decision that you reach in this

case. The form reads:

Page 32:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 31 of 33

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

SINCO, INC.,

v.

))

Plaintiff, ))))

8:03CV315

VERDICTU.S. CHICORY INC., )

)Defendant. )

)

I. CLAIMS FOR BREACH OF THE DRYER REMOVAL CONTRACT

A. On plaintiff's claim against the defendant for breach of the Dryer RemovalContract, select one of the two options listed:

We find in favor of the plaintiff, Sinco, Inc., and against the defendant, U.S. Chicory, Inc., in the amount of$ _

OR

We find in favor of the defendant, U.S. Chicory, Inc., and against the plaintiff, Sinco, Inc.

B. On defendant's counterclaim against the plaintiff for breach of the Dryer RemovalContract, select one of the two options listed:

We find in favor of the defendant, U.S. Chicory, Inc., and against the plaintiff, Sinco, Inc.,in the amount of$ _

OR

We find in favor of the plaintiff, Sinco, Inc. and against the defendant, U.S. Chicory, Inc.

Page 33:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 32 of 33

II. CLAIMS FOR BREACH OF THE TIME AND MATERIALS CONTRACT

A. On plaintiffs claim against the defendant for breach of the Time and MaterialsContract, select one of the two options listed:

We find in favor of the plaintiff, Sinco, Inc., and against the defendant, U.S. Chicory, Inc., in the amount of $ _

OR

We find in favor of the defendant, U.S. Chicory, Inc., and against the plaintiff, Sinco, Inc.

B. On defendant's counterclaim against the plaintiff for breach of the Time andMaterials Contract, select one of the two options listed:

We find in favor of the defendant, U.S. Chicory, Inc., and against the plaintiff, Sinco, Inc.,in the amount of $ _

OR

We find in favor of the plaintiff, Sinco, Inc. and against the defendant, U.S. Chicory, Inc.

DATED:

Presiding Juror

Page 34:   · Web view2014. 9. 4. · Instruction No.6. Instruction No.6. Instruction No. 12. Instruction No. 12. Instruction No. 22. Instruction. No. 22. collection system in the chicory

Page 33 of 33

You will take this form to the jury room, and when each of you has agreed on the

verdict, your foreperson will fill in the appropriate forms, sign and date them, and advise the

courtroom deputy that you are ready to return to the courtroom.

A verdict reached during the first six hours of your deliberation must be agreed to by

all of you, that is, it must be unanimous. After six hours of deliberation, you may reach a

verdict agreed to by ten or eleven of you. If your verdict is unanimous, it should be signed by

the foreperson only. If your verdict is not unanimous, it should be signed by each of the ten or

eleven jurors who so agree to it.

If you do not agree on a verdict by 5:00 o'clock p.m., you may separate and return for

deliberation at 9:00 o'clock a.m. on Tuesday, August 23, 2005. You may deliberate after 5:00

o'clock p.m., but if so, please advise the courtroom deputy of your intention to do so. You may

also separate for meals during the course of your deliberations, but if you do separate for meals

please contact the courtroom deputy to advise her of your intention to separate and when you

expect to return to the jury room to reconvene your deliberations. If you do separate, then

during that time, you are not allowed to discuss this case with anyone, even another juror.

SUBMITTED ____________ p.m.

DATED _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

BY THE COURT: