web Trns•port – web Trns•port – Beta Testing and ImplementationBeta Testing and Implementation
TUG Roundtable DiscussionElizabeth Rodgers
Info Tech, Inc.October 9, 2007
TopicsTopics• Web Trns•port Preconstruction Release
Schedule
• Preliminary Release
• Beta Testing
• Beta Testing – Pre-install Checklist
• Beta Testing Tasks
• Beta Testing Time Frame
• Agency Implementation & Migration Tasks
• Helpful Links and Contact Information
Preconstruction Release SchedulePreconstruction Release Schedule
Release Content
Preconstruction Release 1
(“Pre-Production Release”)
September ’07 sprint results
Preconstruction Beta February ’08 sprint results
Preconstruction Release 2
(“Full Production Release”)
June ’08 sprint results
Actual release dates are dependent on TRT and TTF approvals of sprint results and release deliverables.
Preliminary Release (Pre-Production)Preliminary Release (Pre-Production)
• Evaluation license available to all agencies– No evaluation fee for Release 1– Provide standard level of evaluation licensee
support
• Early feedback prior to Beta and Production release is important
• Agencies should contact a TTF member– [email protected]
Beta TestingBeta Testing
• 3 month beta period (March through May 2008)• Beta site mobilization complete at least one sprint
in advance• Beta begins with February 2008 sprint results
– At least 85% of planned business functionality complete
• March and April sprint results provided to sites– 100% planned business functionality in April results– Will also include beta issue resolutions
Beta Testing – Pre-install ChecklistBeta Testing – Pre-install Checklist
• Agency has the latest client/server Trns•port releases installed for interface testing
• Agency Cloverleaf access to download software.• Agency Team Track access for beta issue
reporting.• ITI has access to test and development database
and web servers. Validate required client/server interface
environment. Have agency review instructions for the prior sprint
in order to identify possible issues with the release sprint
Beta Testing TasksBeta Testing Tasks
• Database install
• Data migration
• Web server install
• Acceptance test execution
• Agency customizations
• ‘Day-in-the-life’ testing of base product functionality
• Interface testing
• Application of sprint updates
Beta Testing Tasks - DetailedBeta Testing Tasks - Detailed
• For full testing, two concurrent complete installations will be used: Test and Development– Test
• Delivered Acceptance test validation area– Development
• Agency specific web Trns•port validation area
NOTE: Each database and web site can be set up on the same computer, or separate as needed to follow an agency’s standard environment.
Beta Testing Tasks - DetailedBeta Testing Tasks - Detailed
• For migration testing, only one database will be used; the web server environment won’t be used– ‘Migrating to Trns•port’ document will be located
on Cloverleaf and will cover database requirements.
– The migration process will occur on the Development environment.
Beta Testing – Ongoing ActivitiesBeta Testing – Ongoing Activities
• Testing• Issue reporting• Resolution validation• Status meetings via webinar/conference call
between agency and Info Tech (include TTF or TRT as needed)
Beta Testing – Primary Resources RequiredBeta Testing – Primary Resources Required
• Database Administrator (DBA) • Internet Information Services Administrator
(IISA)• Trns•port Managers and Users
Beta Testing – Detailed Resources/TasksBeta Testing – Detailed Resources/Tasks
• Database install– DBA – creating, modifying, and executing database
scripts• Data migration
– Trns•port data manager – running migration, resolving data issues
– DBA – on call• Web server install
– IISA – perform install and configure server• Acceptance test execution
– IISA – perform install and execute tests– DBA – on call
Beta Testing – Detailed Resources/Tasks Beta Testing – Detailed Resources/Tasks Continued…Continued…• Agency customizations
– Users• Trns•port system manager• Trns•port business manager• IISA – if needed to provide access to server
– Changes• Page layout• Data validation • Report customization
Beta Testing – Detailed Resources/Tasks Beta Testing – Detailed Resources/Tasks Continued…Continued…• ‘Day-in-the-life’ testing of base product
functionality– All types of Trns•port users– IISA – on call– DBA – on call
• Interface testing (standard interfaces to other Trns•port modules)– Trns•port data manager
Beta Testing – Detailed Resources/Tasks Beta Testing – Detailed Resources/Tasks Continued…Continued…
• Application of sprint updates– DBA – apply database updates– IISA – apply web server updates and run
acceptance tests– Trns•port users – end user testing
Beta Testing Time FrameBeta Testing Time Frame
• Phase 1 – Agency acquire and install hardware and software required for beta testing– February 2008 timeframe
• Phase 2 – receive sprint– March 2008 timeframe – beta testing begin
• Web Install• Database install• Migration testing• Application testing
• TTF requests beta site volunteers by November 16, 2007
Agency Implementation & Migration TasksAgency Implementation & Migration Tasks
• Implementation and migration planning
• Technical training, if required
• Acquire, install, & configure hardware and software
• Install web Trns•port
• Configure system (workflows, installation options, etc.)
Agency Implementation & Migration Tasks Agency Implementation & Migration Tasks Continued…Continued…
• Migrate data from existing system
• Create new required data (e.g., new code tables)
• Customize user interface and reports
• Apply existing agency customizations
• Testing throughout the installation and migration process
Agency Implementation & Migration Tasks Agency Implementation & Migration Tasks ContinuedContinued
• User training– web Trns•port should be easier to train new
users– Encourage the use of web Trns•port online help– web Trns•port and PES/LAS client/server
differences document is included with the software
– Info Tech services are available
• Parallel testing• Production
Helpful Links and Contact InformationHelpful Links and Contact Information• Email TTF:
– [email protected]• http://www.cloverleaf.net/NGT
– web Trns•port logical architecture paper– web Trns•port preview site– Summary of changes between web Trns•port and client
server– Preconstruction product backlog– Hardware and software requirements
• Info Tech Demo Room – Located in the Lewis & Clark room– web Trns•port overview document
• Including beta requirements guide