30
IMPORTANT: Please read before you begin installation. Weather Shield Telescoping Sliding Patio Door Installation Instructions The Telescoping Sliding Patio Door is shipped K.D. (Knocked Down) as shown above.

Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

IMPORTANT: Please read before you begin installation.

Weather Shield Telescoping SlidingPatio Door

Installation InstructionsThe Telescoping Sliding Patio Door is shipped K.D. (Knocked Down) as shown above.

Page 2: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

Weather Shield Telescoping Sliding Patio DoorInstallation Instructions

Thoroughly read and follow these instructions, failure to install as recommended will void any warranty,expressed or implied. Check building codes for the area in which the doors are being installedbefore installation to insure proper compliance. The installation instructions that follow are based ontypical frame construction. Specific applications may differ. Weather Shield Mfg., Inc. recommends thatyou consult a qualified installation professional. Weather Shield Mfg., Inc. is not responsible forinstallation.

IMPORTANT:

IMPORTANT: A number of jurisdictions have adopted building code design pressurerequirements that require door products be installed in the same way they were installed forlaboratory testing. To comply with these requirements, we are pleased to supplement the installationinstructions with the following:

• Apply a generous bead of silicone sealant on the back side of the nailingfin.

• When sealant is applied to the rough opening it must be applied directly tothe building’s sheathing and not the building wrap.

• Exterior house wrap must be cut and temporarily taped back away fromrough openings.

• The nailing fin must contact the sealant continuously along the entireperimeter of the unit and must fully contact exterior face of the wall aroundthe door’s entire perimeter.

• Exterior housewrap must be trimmed and reapplied over the nailing fin. Itmust be sealed to the fin along the entire perimeter with silicone sealant.

• Refer to the chart on the following page for the fastening method thatmeets test specifications.

Throughout these instructions DPR equals “ForDesign Pressure Rating”. Any procedure so titledmust be completed to maintain the rating validity. Non-DPR is for installations not requiring maintenance of design pressure ratings. In thiscase you can follow procedures for either DPR ornon-DPR.

Definition:

ii

Weather Shield Mfg., Inc. reserves the right, as necessary, to change product specifications, installation procedures, materials,prices and terms of purchase without notice.

Page 3: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

Weight of door unit(s) and accessories will vary. Usea reasonable number of people with sufficientstrength to lift, carry and install window or door unit(s)and accessories. Always consider site conditions anduse appropriate techniques when installing.

Falling from door opening may resultin serious injury or death. DO NOTleave openings unattended when children are present.

Screen will not stop children,any one or anything fromfalling out door.

Keep children and objectsaway from open door.

CUT HAZARD*Non-safety Glass.*May cause seriousinjuries if broken.

*Do not install wheretempered safety glassis required.

Recognize this symbol. This is the Safety-Alert symbol. When you see this symbol bealert to the potential for personal injury or product damage.

Design Pressure Performance – Fastening Method

Aluminum Doors With Pre-Punched Fastener Holes

Unit Description Fastener How to Fasten

INSTALL NOTES:A shim space, not to exceed 1/4", is required. If a shim space greater than 1/4" exists on theinterior or exterior of the unit, use solid material to fill this space until the maximum 1/4" shimallowance is achieved.

ADDITIONAL NOTES:• Doors do not require a 1/4" shim space at the sill.

• For installation that has exposed fasteners, it is recommended to use fasteners made of 300series stainless steel. Follow your local codes if they specify a different series of stainlesssteel.

• Certain options, accessories and warranty considerations require the unit be installed usinginstallation clips. The clip install method has not been tested for design pressure ratings andshould not be used where design pressure ratings must be maintained. Contact your customer service representative for additional assistance.

Aluminum Nailing Fin withPre-Punched Fastener Holes/ No Brick Mould

#8 Steel screws long enoughto penetrate framing materialby at least 1-1/2".

Place a screw in a pre-punched nailing fin hole andfasten securely into framingmembers. Distancebetween screw centerlinesis to be 8" to 10". Do notuse holes which are within4" of each other.

iii

Page 4: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

iv

TABLE OF CONTENTS AND TOOL / MATERIAL REQUIREMENTSSTART PAGE

Preserving Design Pressure Test Ratings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii

Definition DPR and non-DPR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii

Design Pressure Performance – Fastening Method (chart); Safety Alert Symbol . . . . . . . . . . . . iii

Housewrap & Caulking Rough Opening Details For Preserving Design Pressure RatingsOn Structure With Housewrap . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . v

Measuring Tape, Clear Silicone Sealant, Caulking Gun, Utility Knife, Cloth Tape

Rough Opening Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1Measuring Tape & Level

Straighten and Level Subfloor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2Level, Hammer, Nails, Nailset, Plane

Sill Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3Weather Barrier Self-Adhering Tape (Ice Storm Shield), Utility Knife, Measuring Tape,Rubber Roller,Caulk, Caulking Gun

Frame Assembly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4Square, Phillips Screwdriver, (12) #8 x 2-1/2" Phillips Stainless Steel Flathead Screws, (2) #8 x 1/2"Phillips Flathead Screws

Apply Silicone to Rough Opening & Sill . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6Caulk, Caulking Gun

Frame Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7Measuring Tape, Hammer, #8 Steel Screws (long enough to penetrate framing material at least 1-1/2"), Electric Drill w/Screwdriver Bit, Pry Bar, Shims, Straightedge, Level

Weather Barrier Self-Adhering Tape Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8Weather Barrier Self-Adhering Tape (Ice Storm Shield), Utility Knife, Measuring Tape, Rubber Roller

Straighten the Interior, Secure Side Jambs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9Measuring Tape, Shims, Level, Fiberglass Insulation, Hammer, Pry Bar, (Qty 6)#8 x 2-1/2" PhillipsStainless Steel Flathead Screws (provided for side jambs), Phillips Head Screwdriver

Panel Identification, Installation & Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Install Inactive Fixed Panel. Panel & Head Stop Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14(4) #10 x 3/4" Phillips Stainless Steel Panhead Screws (provided), Phillips Head Screwdriver

Install Inactive Head Bracket on Inactive Fixed Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18(1) Stationary Panel Head Bracket 1 per Stationary Panel (provided), (3) #10 x 3/4" PhillipsStainless Steel Panhead Screws (provided), Phillips Head Screwdriver

Install Active Secondary Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19#8 x 2-1/2" Phillips Stainless Steel Flathead Screws (provided), Phillips Head Screwdriver,Straightedge

Install Active Primary Operating Panel; Re-Install Wood Interior Head Stop; Roll Adjustment 20#8 x 3" Phillips Stainless Steel Flathead Screws (provided), Phillips Head Screwdriver, Flat Bar

Install Handle Sets; Active Handle Set Installation Instructions . . . . . . . . . . . . . . . . . . . . . . . . . 21Phillips Head Screwdriver

Install Handle Sets; Dummy Handle Set Installation Instructions . . . . . . . . . . . . . . . . . . . . . . . . 22Phillips Head Screwdriver

Adjusting the Latches Horizontally on Active Handle Set; Side Jamb Keeper (pre-installed) for 2, 3 & 4 Panel Doors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .23

Hex Wrench (included in handle set kit) Electric Drill, 7/64" drill bit, (2) #8 x 3" Phillips StainlessSteel Flathead Screws (provided), Phillips Head Screwdriver

Door Bumper Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24Tape Measure, Pencil, Phillips Head Screwdriver, Door Bumper packages (2) per door as described on page 12 & 13

Page 5: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

1

1. Measure the rough opening to ensure that it is notmore than 3/4" wider in overall Width or 1/2" taller inoverall Height than the outside width or height ofyour entire door frame assembly (FIGURE 1).

FIGURE 2

H

W

FIGURE 1

A

2. Measure the rough opening diagonally from corner-to-corner in both directions. There should beno more than 1/4" difference between the two measurements (FIGURE 1 & 2).

FIGURE 3

Rough Opening Preparation

IMPORTANT: High-quality, exterior, neutral-cure, clear, silicone sealant (compatible with aluminum extrusion and exterior face of the wall) is to beused for all procedures in the following instructions which call for caulking or sealant.

IMPORTANT: Check to make sure you have the correct door type and the correct door size (Width andHeight) for your rough opening (FIGURE 1).

Before you begin, check the following:

SAFETY INSTRUCTIONSRead installation instructions completelybefore beginning procedure.

Wear gloves, safety glasses, goggles oreye shields appropriate to procedure.

IMPORTANT: If unit is to meetdesign pressure ratings, a maximum 1/4" shimspace is allowed around perimeter. A shimspace greater than 1/4" could result in lowerproduct performance and may be considerednon-compliant with certain building codes.

Note: Doors do not require 1/4" shim space at thesill.

2. Make sure walls are plumb and not twisted.Make necessary corrections where possible toensure walls are plumb and straight (FIGURE 3 & 3A).

Page 6: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

2

FIGURE 11. Masonry installation requires 2 x 6 sill plate to bepresent. Check sill for level (FIGURE 1).

FIGURE 22. To straighten and level the subfloor, identify theareas that are above level and countersink nails inthe floor area that will be under the door (FIGURE 2).

3. Check for level as in (FIGURE 1). Plane areathat will be under the door until it is straight andlevel (FIGURE 3).

FIGURE 3

Improper use of hand and power tools couldresult in personal injury and/or product damage.Follow equipment manufacturers’ instructions forsafe operation. Always wear safety glasses.

Straighten & Level Subfloor

Page 7: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

3

FIGURE 1

FIGURE 2

1"

CUT &

FOLD

DOWN

1"

6"

1. Cut a piece of weather barrier self-adhering tape(ice storm shield) 4" wide and as long as the opening width plus 8" (FIGURE 1). Apply to face ofexterior wall so 1" extends above the opening and 4"extends beyond each side of the opening. Cut alongthe corners of rough opening and fold down onto thesill (FIGURE 1A).

2. Apply a second continuous piece of weatherbarrier self-adhering tape on the top surface of therough opening sill. Use a rubber roller to apply barrier to surface (FIGURE 2).

Cut barrier tape the thickness of the wall and 12"longer than the width of the opening. Extend theedge of the tape 1" past the exterior wall surface(FIGURE 2). Start the piece (approximately 6") upthe side of the rough opening and run it to the bottom of the opening, to the other side of the opening, and 6" up the other side (FIGURE 2A).

Note: Final sill preparation is continued on page 6.

A

Improper use of hand and power tools couldresult in personal injury and/or product damage.Follow equipment manufacturers’ instructions forsafe operation. Always wear safety glasses.

Sill Preparation

FIGURE 2A

Page 8: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

FIGURE 1 FRAME LAYOUT

Working from the exterior of the construction or from theside where the nail fin will be fastened.

Note: Place the frame pieces', with the aluminum part ofthe frame facing up on a clean, dry, flat surface (FIGURE1). Head and side jamb pieces nailing fin will face out fromthe center of the frame (FIGURE 1).

STEP 1:Place the head, with the aluminum part of the framefacing up and the nailing fin facing away from the center of the frame (FIGURE 1).

STEP 2:Place the side jambs vertically on each side of the headframe piece (FIGURE 1).

Note: Side jambs have a foam gasket on the bottom ofone end that gets placed at the sill (FIGURE 1A) and apre-installed corner key that gets installed into the headframe piece (FIGURE 1B).

STEP 3:Place the sill at the bottom of the frame assembly (FIGURE 1).

SIDE JAMB

SIDE JAMB

SILL

HEAD

FIGURE 1A

FIGURE 1B

ALUMINUMEXTERIORON FRAME,FACE UP.

SILL FOAM GASKET

CORNER KEY

IMPORTANT! Use a clean, dry, flat surface for assembling the door frame, ensuring thatframe parts are protected from damage whileassembling.

IMPORTANT! Use adequate number ofpeople to perform this task. Remove all packaging

and shipping material from the frame and hardwarepackage.

NAILING FINON HEADAND SIDEJAMBS FACEOUT

SIDE JAMB

4

Frame Assembly

Page 9: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

FIGURE 2

FIGURE 4

STEP 4:Fasten the head and side jamb pieces together first. Notes:From the hardware package remove:

• (12) #8 x 2-1/2" stainless steel flathead screws (3) for each corner. • (2) #8 x 1/2" Phillips flathead screws for fastening each head corner key.

- Starting at one upper corner, insert the pre-installedside jamb corner key into the head receiver corner keybracket. Ensure that the key slides in to the receiver'slegs (FIGURE 2).- Using a phillips screwdriver install (3) #8 x 2-1/2" stainless steel flathead screws, one into each of thepre-drilled holes to fasten the head and side jambtogether (FIGURE 3 & 3A). Ensure that the screws fasten into the screw bosses on the head frame piece(FIGURE 3). - Use a square to ensure that the frame corners fittogether flush (FIGURE 4). - Install (1) #8 x 1/2" Phillips flathead screw into pre-drilled hole where the head corner key is installed(FIGURE 5). - Fasten opposite top corner in same sequence asdescribed in STEP 4 above.STEP 5:Screw bottom side jambs and sill corners together with(3) #8 x 2-1/2" stainless steel flathead screws for eachcorner. Ensure that the screws engage with sill screwbosses and the corners are flush (FIGURES 3, 3A & 4).

CORNER KEYRECEIVERBRACKET

PRE-INSTALLEDCORNER KEY

FIGURE 3

FIGURE 3A

(3)SCREWBOSSES

PRE-DRILLEDHOLESON SIDEJAMBS

(3) #8 X 2-1/2"STAINLESSSTEEL SCREWSPER CORNER

5

FIGURE 5

Frame Assembly (continued)

Page 10: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

CAULK BEAD ON

SUBFLOOR

CAULK BEAD ON

EXTERIOR OF

ROUGH OPENING

1. Apply a continuous 1/2" bead of high-qualitycaulk (compatible with aluminum extrusion andexterior face of wall) to the exterior face of the walllocated 1/4" from the rough opening edge. Thecaulk bead must contact the nailing fin continuous-ly on sides and top when the unit is placed into theopening (FIGURE 1).

2. Apply (3) beads of caulk on top of the subfloor membrane 1/2" from the walls exteriorsurface (FIGURE 1) and 1/2" away from eachother.

FIGURE 1

6

Apply Silicone to Rough Opening & Sill

(3) CAULK BEADSON SUB-FLOOR

Page 11: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

7

3. Slide the bottom of the door frame left or right untilthe diagonal measurements of the entire door frameassembly are exactly the same (FIGURE 3A & 3B).

4. Once the diagonal measurements are the same,secure the other three corners in the same manneras the first corner (FIGURE 2).

5. Use a straightedge and shims to straightenthe side and top jamb (FIGURE 3C & 3D).

Frame Installation

IMPORTANT: High-quality exterior neutral cure silicone caulkis to be used for all procedures in the following instructions which call for caulking.

2. Immediately center the frame into opening(FIGURE 1), after silicone caulk has been appliedto the exterior of the rough opening and the subsill(FIGURE 5 Page 6). Secure one side top cornerwith a #8 steel screw long enough to penetrateframing material by at least 1-1/2" (FIGURE 2).

IMPORTANT: The diagonal measurements are to be taken fromthe entire door frame assembly.

FIGURE 3

FIGURE 1

A B

C D

Improper use of hand and power tools couldresult in personal injury and/or product damage.Follow equipment manufacturers’ instructions forsafe operation. Always wear safety glasses.

IMPORTANT: If unit is to meetdesign pressure ratings, a maximum 1/4" shimspace is required around perimeter. Unit mustbe secured with #8 steel screws, long enoughto penetrate framing material by at least 1-1/2".See “Design Pressure Performance – FasteningMethod” chart on Page iii for screw spacing.

Note: On six wide units a center support maybe used to help support the frame.

SCREW OPPOSITE

BOTTOMCORNER

FIGURE 2

Page 12: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

8

WIDTH OF VERTICAL TAPE

TOP NAILING FIN

FIGURE 1

FIGURE 3

1. On the exterior, apply a high-quality weather barrier self-adhering tape or equivalent (ice stormshield). Apply to the sides, start 4" up from the topof the head nailing fin and run it down so that itends at the bottom of the sill plate. Tape must coverthe entire nailing fin, including the installation holesand the joint between the fin and the building’s sheathing. Use a rubber roller to apply barrier tosurface (FIGURE 1).

2. Use a utility knife to cut a slit in the building wrapabove the top nailing fin. Cut slit the entire length ofthe door frame unit PLUS the width of the verticalweather barrier tape on each side of the unit (FIGURE 2).

3. After cutting the slit above the top nailing fin,slide the high-quality weather barrier self-adheringtape or equivalent under the building wrap makingsure the weather barrier tape covers the nailing fin(FIGURE 3).

FIGURE 2

Improper use of hand and power tools couldresult in personal injury and/or product damage.Follow equipment manufacturers’ instructions forsafe operation. Always wear safety glasses.

Weather Barrier Self-Adhering Tape Application

Page 13: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

9

Loosely insulate between the door frame and roughopening.

IMPORTANT: Do not over pack insulation.Do not use expandable foam.

Install panels.

IMPORTANT:Straighten and support the mull unit sills withwood shims under the ends of the jambs.

1. Shim the top and bottom ends of the side jamb onthe left or right to get the diagonal measurements(FIGURE 1 & 1A) of the entire door frame assembly exactly the same.

2. Using a level as a straightedge, place shimsbetween the frame and the rough opening to straighten the side jamb and sill (FIGURE 2A, 2B & 2C).

Secure Side Jambs1. Secure each side jamb with (3) #8 x 3" Phillips flathead screw, provided in hardware kit. Place screws 4" from each corner and one in the middle of the jamb. Screw into jamb into framingmaterial.

FIGURE 2

A

B

C

FIGURE 1

A

Straighten the Interior

Page 14: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

Panel Identification & Installation

IMPORTANT: High-quality exterior neutral cure silicone caulk is to be used for all procedures in the followinginstructions which call for caulking.

Note: One side jamb face of each panel has a v-groove running vertically and the other side is straight.The v-groove side on a 4 & 6 panel door always faces towards the center of the entire unit.On the 2 & 3 panel door the v-groove will face the side jamb.

STEP 1: Remove all shipping and packaging material from panels. Identify your panels using the following descriptions:

Door Panel Identification & ConfigurationPanel Identification: (FIGURE 1, 2 & 3)

Active Primary Operating Panels have holes for the hardware to be installed.Active Secondary Operating Panels have one roller adjustment screw hole at the bottom

of the panel that faces the side jamb when installed into frame. On 3 & 6 panel doors these DO NOThave holes for the handle set hardware. On 2 & 4 panel doors, there are holes for the handle set.

Inactive Fixed Panels have a fixed panel support bracket that runs horizontally at the bottom of the panel and two pre-drilled holes (when panel is installed, holes face towards the center of the unit) at the top side of the rail used to install the stationary panel fixed head panel bracket.

Panel Configuration and Order of Installation: (FIGURE 4 pg 12 & 13) 2 Panel Door BOTH PANELS OPERATE

(1) Active Primary Operating Panel rolls on the exterior sill track, install 1st, Receives active handleset, lock gear, strike & 2 bumpers.

(1) Active Primary Interior Operating Panel rolls on the interior sill track, install 2nd, Receives activehandle set, lock gear & strike.

3 Panel Door ONE INACTIVE FIXED PANEL AND TWO ACTIVE OPERATING PANELS (1) Inactive Fixed Panel (non-operating) install 1st; towards the exterior of the construction (nail finside) and rolls on the exterior sill track, has stationary bracket.

(1) Active Secondary Operating Panel rolls on the middle sill track, install 2nd. Receives (2) bumpers.

(1) Active Primary Operating Panel primary panel rolls on the interior sill track, which faces towardsthe interior of the construction, install 3rd. Receives active handle set, lock gear & strike.

FIGURE 1

10

Page 15: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

FIGURE 2 Top of Door Looking at the upper sill track. 3 & 6 PANEL DOORS

4 Panel Door ALL PANELS OPERATE (2) Active Secondary Operating Panels install in the exterior sill track towards the exterior of the construction, both install 1st. Each panel Receives active handle set, locking gear & (2) bumpers perpanel.(2) Active Primary Operating Panels roll on the interior sill track and face toward the interior of theconstruction, install both panels 2nd. Recieves 1 strike. One panel gets active handle set and one panelReceives the dummy handle set.

6 Panel Door TWO INACTIVE FIXED AND FOUR ACTIVE OPERATING PANELS (2) Inactive Fixed Panels (non operating) it on the exterior sill track, get installed 1st). Each panel hasa stationary bracket.

(2) Active Secondary Operating Panels roll on middle sill track, both get installed 2nd. Each panelhas (2) bumpers.

(2) Active Primary Operating Panels roll on the interior sill track, both get installed 3rd. One panelReceives dummy handle set and strike the other Receives the active handle set and lock gear.

INTERIOREXTERIOR

ACTIVE PRIMARYOPERATINGPANEL

ACTIVE SECONDARY OPERATING PANEL

INACTIVEFIXED PANEL

FIGURE 3

INTERIORWOOD HEADSTOP

EXTERIOSILL TRACK

MIDDLE SILLTRACK

INTERIORSILL TRACK

INACTIVE FIXEDPANEL SUPPORT

ACTIVEPRIMARYOPERATINGPANEL

11

Panel Identification & Installation (continued)

Page 16: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

12

FIGURE 42 PANEL DOORBOTH PANELS OPERATE(1) Active Primary Exterior Operating Panel rolls on

exterior sill track. Receives (2) bumpers.Installs 1st from exterior/ nail fin side. (1) Active Primary Interior Operating Panel rolls on interior

sill track. Installs 2ndBoth panels receive active handle sets.

Panel Identification, Installation & ConfigurationAs Viewed from the Exterior / Nail Fin Side of unit:

XX Right (when closed, the panel on the exterior silltrack is on the righthand side)XX Left (when closed, the panel on the exterior silltrack is on the lefthand side)X = Active operating panel

As Viewed from the Exterior / Nail Fin Side of unit:XXXX LeftXXXX RightX = Active operating panel

4 PANEL DOORALL PANELS OPERATE(2) Active Secondary Operating Panels roll on middle sill

track. Receives (2) bumpers per panel.Installs 1st(2) Active Primary Operating Panels roll on interior sill

track Installs 2ndThe primary panels get the handle sets (1) active & (1)dummy.

Page 17: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

(OXXXXO Left Shown)6 PANEL DOOR ELEVATION AS VIEWED FROM THE EXTERIOR / NAIL FIN SIDE

From the exterior the panel the active handle set is on the left-hand side primary operating panel.

Panel- LeftOperating

Active SecondaryOperating

Panel

Active Primary Active Primary

Panel

OperatingPanel - Right

Active SecondaryOperating

Panel

Fixed

Inactive Inactive

Fixed

Panel

(2) Inactive Fixed Panels sit on the exterior sill track.

Install both 1st(2) Active Secondary Operating Panels roll on middle sill track.

Receives (2) bumpers per panel.Install both 2nd(2) Active Primary Operating Panels roll on interior sill track. Install both 3rd

The primary panels get the handle sets (1) operating & (1) fixed.

6 PANEL DOOR 2 INACTIVE FIXED & 4 ACTIVE OPERATING PANELS

3 PANEL DOORONE INACTIVE FIXED PANEL AND TWO ACTIVE OPERATING PANELS(1) Inactive Fixed Panel sits on the exterior sill. Installs 1st(1) Active Secondary Operating Panel rolls on middle sill

track. Receives (2) bumpers.installs 2nd(1) Active Primary Operating Panel rolls on interior sill track.

Primary panel Receives the active handle set.Installs 3rd.

Panel Identification, Installation &ConfigurationAs Viewed from the Exterior / Nail Fin Side of unit:

OXX LeftXXO RightX = Active operating panelO = Inactive fixed panel

As Viewed from the Exterior / Nail Fin Side of unit:OXXXXO Left (Handle set)OXXXXO Right (Handle set)X = Active operating panelO = Inactive fixed panel

13

Page 18: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

14

Install Inactive Fixed PanelFor 3 & 6 Panel DoorsSTEP 1:Remove the interior, middle and outer panel head stops as shown in (FIGURE 1 & 2). Set aside screwsand head stops in a safe place until needed for re-installing.

FIGURE 1 Top of Door Looking at the upper sill track. 3 & 6 PANEL DOORS

INTERIOREXTERIOR

ACTIVE SECONDARY OPERATING PANEL

ACTIVE PRIMARYOPERATINGPANEL

INACTIVEFIXED PANEL

INTERIORWOOD HEADSTOP

MIDDLEHEAD STOP

OUTERHEAD STOP

FIGURE 2

Page 19: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

15

Panel and Head Stop Installation For 3 & 6 Wide Units

Page 20: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

16

Panel and Head Stop Installation For 2 & 4 Wide Units

Page 21: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

For 3 & 6 Panel DoorsNotes:

• You will need a Phillips screwdriverfor this procedure.

From the hardware package remove:• (4) #10 x 3/4" Phillips stainless

steel panhead screws for securing the interior stationary sill bracket.

STEP 2:Using adequate number of people, working fromthe interior of unit) lift and place the top of thepanel into the top exterior headtrack, then swingthe sill of the panel towards the sill track and setinto place. Making sure the inactive fixed panelsill support (FIGURE 3) sits on the outer part ofthe exterior sill track. Slide the panel against theside jamb.

FIGURE 3

EXTERIOROF UNIT

INACTIVEFIXEDPANEL

EXTERIORSILL TRACK

INACTIVEFIXED PANELSILL SUP-PORT

FIGURE 4STEP 4:Install the stationary head bracket.Place the bracket at the top of thepanel as shown in(FIGURE 5A), so that the bend in thebracket sits on top of the panel.Install the (3) #10 x 3/4" stainlesssteel panhead screws through theholes in the bracket.

STEP 5:Re-install the middle head stop.

INACTIVEFIXEDPANEL SILLSUPPORTBRACKET

FIGURE 5A FIGURE 5B

Install Inactive Fixed Panel (continued)

STEP 3:Secure the bottom stationary sill support bracket (FIGURE 4, 5A & 5B). Pre-dill pilot holes usingthe existing holes in the bracket as your guide.Use an electric drill with a 1/8" drill bit. Using aPhillips screwdriver, install #10 x 3/4" screwsinto all holes on the bracket.

17

Page 22: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

For Inactive Fixed panel onthe 3 & 6 Panel DoorsNotes:

• You will need a Phillips screwdriver for this procedure.

From the hardware package remove:• (1) Fixed panel head bracket

(1 per panel) • (3) #10 x 3/4" Phillips stainless steel

panhead screws

STEP 4:- Install the inactive fixed panel head bracket.

Place the bracket at the top of the panel as shown in (FIGURE 6), so that the bend in the bracket sits ontop of the panel (FIGURE 6A).- Install the (3) #10 x 3/4" stainless steel panhead

screws through the holes in the bracket (FIGURE 6B).

FIGURE 6A

FIGURE 6

FIGURE 6B

18

Install Inactive Fixed Panel Head Bracket

Re-install Middle Head Stop For 3 & 6 Panel DoorsREFERENCE PAGES 15 & 16 Holes will be placed between the existing holes for the middle head stop. Counterbore 1/4" using a 7/16" drill. Pre-drill pilot holes using a 1/8" drill.Starting at one side screw in #10 x 4" Phillips Flathead Stainless Steel screws into all pre-drilled holes.

Page 23: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

FIGURE 1

FIGURE 2

For 3, 4 & 6 Panel DoorsNotes:

• You will need a Phillips screwdriver.Working from the interior of constructionor from the interior sill track.

STEP 1: Remove the interior wood head stop. Head stop has#6 x 1-1/2" temporary shipping screws, do not usethese to re-install the head stop. Set the interior woodhead stop aside (FIGURE 1).

STEP 2:FOR 3 & 6 PANEL DOORSWith the straight edge of the active secondaryoperating door panel positioned near the middle of theinactive fixed panel, lift bottom onto the middle silltrack (FIGURE 2).

FOR 2 & 4 PANEL DOORSWith the straight edge of the active secondaryoperating panel facing the side jamb, lift the bottomonto the exterior sill track.

ALL DOORSSwing the top of the panel towards the head,compress the head jamb up towards the roughopening and swing the top of panel into the middlehead track (3 & 6 panel doors) or exterior head track(on 2 & 4 panel doors). Release the head frame (FIGURE 2A).

IMPORTANT: Interior head stop mustbe re-applied before operating the interior active panelsee(FIGURE 1).

STEP 3:Slide the panel so it engages with the stationary fixedpanel interlock. This will ensure that the panel will notrelease from the track (FIGURE 3).

STEP 4: Check panel for smooth operation and adjust bottompanel rollers up or down until panel operates smoothly (see roller adjustment page 17).

INTERIORWOODHEAD STOP

LIFT PANELONTO THE MIDDLE SILLTRACK

SWING HEADINTO UPPERMIDDLE SILLTRACK

A

19

PANELINTERLOCK

SLIDECLOSED

FIGURE 3

Install Active Secondary Panel

Page 24: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

Install Active Primary Operating Panel for ALL DoorConfigurations

STEP 1: Facing the center of the unit and using adequate number of people lift the bottom of the panelonto the interior sill track and swing the head into the head interior track. Compress the head jamb uptowards the rough opening to ensure that the head of the panel swings in to the track. Release thehead jamb.

FIGURE 1

STEP 2: Check panel for smooth operation and adjust the rollers at the bottom of the panel until paneloperates smoothly (see roller adjustment).On 4 & 6 panel doors install other primary operating panel in same manner.

Roller Adjustment Notes:

• A phillips screwdriver and flat bar will be needed for this procedure.

• Rollers are located on the bottom of the panels, one on each end.

• Remove the hole plug, if installed. When adjustment is complete place hole plug (provided in hardwarepackage) over screw (FIGURE 1).

STEP 1 (FIGURE 2):To adjust panel for smoother operation, insert aphillips screwdriver into the adjustment screws inthe bottom rollers and turn clockwise to retract orraise the rollers into the panel, this will lower thepanel.Turn counter-clockwise to lower the roller and raisethe panel.

Note: To make it easier to lower the rollers, place aflat bar under the panel and lift slightly. Then adjustthe roller. Use adequate number of people to perform this procedure.

FIGURE 2

REMOVE HOLEPLUG IF PRESENT

TANDEM ROLLER ONE ON EACH END

BOTTOM OF PANEL

ADJUSTMENT SCREW

CLOCKWISE - ROLLER RETRACTS INTO PANELCOUNTER-CLOCKWISE - LOWERS ROLLER

20

Re-install Wood Interior Head StopRe-install the interior wood head stop with #8 x 3" stainless steel flathead screws (included with thehardware kit). Qty 7 for the 2 panel door, qty 11 for the 3 panel door, qty 15 for the 4 panel door andqty 26 for the 6 panel door. Also see pages 15 and 16.

Page 25: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

21

Active Handle Set Installation Instructions• Active Handle Set: All panel configurations; identify panel that will receive the active handle set (page12) and install according to diagram below.

1.) Insert shorter end of Spindle approximately 15/16" into Outside Lever making sure the "V-Groove" in the Spindle is facing down. Tighten the Set Screw until it comes into contact with the "V-Groove" in the Spindle (FIGURE 1).

2.) Insert Lever & Spindle assembly through Guide Ring and Outside Escutcheon.3.) Place the Foam Gasket onto the Spindle and slide tight to the Outside Escutcheon.4.) Insert the assembly through the door.5.) Place the Inside Escutcheon and Guide Ring onto the inside of the door so that Spindle protrudes

through the inside Guide Ring hole.6.) Slide the Inside Lever onto the Spindle so it is tight to the Inside Escutcheon.7.) Fasten the Inside & Outside Escutcheon to the door with the Escutcheon Plate Screws provided.8.) Align and insert Half Cylinder through lower hole of the Inside Escutcheon, at the same time,

insert Flat Head Screw (packaged with cylinder) through open hole near the bottom of the 2 PointLock and tighten securely.

9.) Tighten Escutcheon Plate Screws. Push the Inside & Outside Levers tight to the door and tightenthe Inside Lever Set Screw.

Cleaning:• Clean your Hardware as needed, using a mild detergent and a soft cloth.• Avoid abrasive cleaners, clothes or brushes.

Caution:Do Not apply harsh chemicals and cleaners such as Hydrogen Chloride, (Hydrochloric acid) Sodium Hyperchlorite (chlorine bleach) or Hydroxyacetic Sulfanacide (mineral deposit remover) to Hardware.Do not use organic solvents for cleaning purposes. Coating damage could occur.

Your Weather Shield Door Hardware has been manufactured of high quality solid brasswith various coatings applied for protection and durability. Climate, location and exposure to corrosiveenvironments such as industrial areas, pesticides, herbicides or salts will affect the amount of carerequired to maintain the Hardware's beauty and characteristics.

Page 26: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

22

3

Dummy Handle Set Installation Instructions• Dummy Handle Set - On 4 & 6 wide panel doors only, identify panel that will receive the dummy handle set (page 12 & 13) and install according to diagram below.

1.) Insert Spindle approximately 15/16" into Outside Lever and tighten until Set Screw comes intocontact with the v-groove in the spindle (FIGURE 1).

2.) Insert Lever & Spindle assembly through Guide Ring and Outside Escutcheon.3.) With round hole of the Fixed Handle Plate Insert up, insert the Spindle through the square hole.

Slide the Fixed Handle Plate Insert onto the top stud of the Outside Escutcheon.4.) Place the Foam Escutcheon Plate Gasket onto the Spindle and slide tight to the Outside

Escutcheon.5.) Insert the assembly through the door so the v-groove in the spindle faces down.6.) Place the Inside Escutcheon and Guide Ring onto the inside of the door so that Spindle protrudes

through the inside Guide Ring hole.7.) Slide the Inside Lever onto the Spindle so it is tight to the Inside Escutcheon.8.) Fasten the Inside & Outside Escutcheon to the door with the Escutcheon Plate Screws provided.9.) Tighten Escutcheon Plate Screws. Push the Inside & Outside Levers tight to the door and tighten

the Inside Lever Set Screw.

Cleaning:• Clean your Hardware as needed, using a mild detergent and a soft cloth.• Avoid abrasive cleaners, clothes or brushes.

Caution:Do Not apply harsh chemicals and cleaners such as Hydrogen Chloride, (Hydrochloric acid) Sodium Hyperchlorite (chlorine bleach) or Hydroxyacetic Sulfanacide (mineral deposit remover) to Hardware.Do not use organic solvents for cleaning purposes. Coating damage could occur.

Your Weather Shield Door Hardware has been manufactured of high quality solid brasswith various coatings applied for protection and durability. Climate, location and exposure to corrosiveenvironments such as industrial areas, pesticides, herbicides or salts will affect the amount of carerequired to maintain the Hardware's beauty and characteristics.

Page 27: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

FIGURE 1

FIGURE 2

Note:You will need:

• Electric Drill, 7/64" drill bit, Phillips screwdriver and (2) #8 x 3"stainless steel flathead screws (screws included in handle set kit)will be needed for this procedure.

• Keeper may be located on the side jambs and / or on the panel,depending on your doorconfiguration.

STEP 1:Close the primary door and check alignment of thelatches and the keeper. Keeper has a vertical adjustment. Keeper has (2) screws holding it in place. Loosenslightly until the keeper can be moved vertically.Move up and down until latches align with thekeeper latch holes (FIGURE 1). Tighten middlescrews when final adjustment is made. Pre-drill (2)pilot holes using a 7/64" bit and electric drill, one onthe bottom and one on the top of the keeper.

STEP 2:In the top hole of the keeper install one #8 x 3"stainless steel flathead screws, install secondscrew into the bottom hole of the keeper (FIGURE 2).

Note:From the hardware package remove:

• You will need a hex wrench,included in the handle set kit, will be needed for thisprocedure.

STEP 1: Place hex wrench into the bottom hole on thelatch (FIGURE 2). Turn clockwise to movelatch away from the panel side jamb andcounter-clockwise to move latch towards thepanel side jamb. Close door and check the latching, adjust until latch engages smoothlywith the keeper.

PRE-DRILL HOLE

KEEPER

LOOSEN SCREWSTO ADJUST UP orDOWN

PRE-DRILL HOLE

FIGURE 2FIGURE 1

23

Adjusting the Latches Horizontally on Active Handle Set

Side Jamb Keeper (pre-installed) Adjustment for 2, 3 & 4 Panel Doors

Page 28: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

24

Door Bumpers - (2 per panel as describedbelow)Note:You will need:

• Tape measure • Pencil• Phillips Head screwdriver

From the hardware package remove:• (2) Bumper packages per door

IMPORTANT!- Quantity (2) bumpers are to be installed on the

interior of the active secondary operating panel (on 3, 4 & 6 panel doors).- On the 2 panel door the active primary exterior

operating panel Receives the (2) bumpers.

IMPORTANT!:Before attaching the bumper to the active secondary operating panel (3 & 6 wide doors) or tothe inactive fixed panel (2 & 4 panel doors), holdbumper in place and slide the primary operatingpanel towards side jamb until it comes into contactwith the bumper. Check the clearance of the handle-set on the active primary operating door andthe active secondary operating door. When doorhits bumper the clearance between the door andhandle set should be 1" (FIGURE 4).

STEP 1: Measure 2" over on the side jamb closest to theframe, top and bottom. Mark lightly with a pencil(FIGURE 1).

STEP 2:Top Bumper Location: From the top of the panel measure down 2", this willintersect with your first mark and this is where themiddle edge of the bumper is to be located andinstalled (FIGURE 2).

STEP 3:Bottom Bumper Location:Place measuring tape on the sill and measure up 3-1/2", mark lightly with pencil. This is where themiddle edge of the bottom bumper will be installed(FIGURE 3).

FIGURE 2

FIGURE 1

TOP OF PANEL

FLUSH

FIGURE 3

2"

ACTIVE SECONDARYPANEL

MINIMUM 1" CLEARANCE

ACTIVE PRIMARY PANEL

FIGURE 4

Top & Bottom Door Bumper Installation

Page 29: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

Recommended Finishing Instructions

For Aluminum SurfacesThe aluminum surfaces may be cleaned with mild soap and water. Hard to remove stainsand mineral deposits may be removed with mineral spirits.

• Do NOT use abrasive materials against vinyl or aluminum surfaces.• Do NOT scrape or use tools that might damage the surface.• Do NOT paint vinyl or aluminum surfaces.

For Wood SurfacesFor best results, the interior wood should be sealed immediately upon installation or uponreceipt especially if unit is being stored for ANY length of time. Remove all constructionresidue before finishing.

1. Lightly sand surfaces being finished with 180 grit or finer sandpaper. Be carefulnot to scratch the glass.

2. After sanding, clean-off sanding dust from the surface using lacquer thinnerapplied to a cloth so the cloth is slightly damp. Let surface dry.

-If painted surface is desired:1. Use only oil-based primer coats. Use compatible oil or water-based finish coats.

Refer to the manufacturers’ instructions.2. Prime all exposed wood surfaces. Priming all surfaces helps prevent end splitting,

warping and/or checking.3. Once primed, apply two (2) coats of paint (again on all exposed sides) to each

item.

-If a stained surface is desired:1. Use only oil-based stain and sealer for the first coat. Clear top coat may be oil or

water-based. Apply desired stain to the manufacturers’ instructions and let dry.

2. Apply one (1) coat of sealer to the surface and let dry.

If no sealer is applied over the stain, the wood will weather very rapidly and defects will occur.

3. Lightly sand with 180 grit sandpaper. Clean off sanding dust and wipe with a tackcloth.

4. Apply one (1) coat of desired finish to surface and let dry.

5. For any additional coats of finish, repeat steps 3 and 4.

Always follow chemical manufacturers’ safetyinstructions when using chemicals to avoidinjury or illness

25

Page 30: Weather Shield Telescoping Sliding Patio Door Installation ... · the floor area that will be under the door (FIGURE 2). 3. Check for level as in (FIGURE 1). Plane area that will

Weather Shield Products With Synthetic Stucco

Part No. 1159296 02/04 Printed in U.S.A. ©2004 Weather Shield Mfg., Inc.

www.weathershield.com

Serious concerns have been raised about excessive moisture problems in homes and other buildings thathave Exterior Insulation Finish Systems, commonly referred to as EIFS or Synthetic Stucco.

Many experts agree that a certain amount of water or moisture can be expected to enter almost any building exterior system. The building system should allow such water and moisture to escape or “weep”to the exterior, so no damage occurs. However, some EIFS systems may not allow water or moisture thatpenetrates the wall system to “weep” to the exterior. This can cause excessive moisture to accumulatewithin the wall system, which can cause serious damage to wall and other building components. It hasbeen reported that so-called “barrier” EIFS systems are particularly prone to this problem.

Moisture problems in any type of building structure can be reduced by proper design and construction withappropriate moisture control considerations, taking into account prevailing climate conditions. Examplesof moisture control considerations include flashing and/or sealing of all building exterior penetrationpoints, use of appropriate materials and construction techniques, adherence to applicable building codes,and general attention to proper design and workmanship of the entire building system, includingallowances for management of moisture within the wall system.

Determination of proper building design, components and construction, including moisture management,are the responsibility of the design architect, the contractors, and the manufacturer of the exterior wall finish products. Questions and concerns about moisture management issues should be taken up withthese professionals. Weather Shield Mfg., Inc. is not responsible for problems or damages caused bydeficiencies in building design, construction or maintenance, failure to install our products properly, or useof our products in systems that do not allow for proper management of moisture within the wall system.