POWER PLANT CONSTRUCTION ENGINEERING PURCHASE PROCESS MANAGEMENT COMMISSIONING AND TESTING PLANT ERECTION CIVIL WORKS TRANSPORTATION FABRICATION OF ITEMS Basic design Submission and approval of engineering set of drawings Permit and authorizations based on basic design HRSG and diffuser Gas treatment and Compression station gas turbine generator and gear box set steam turbine steam boiler steam condenser Site installation Plant civil works Construction control room and office building Gas cycle Steam Cycle Project management Site management Expediting and item pre-test to the supplier's plant Stack Transformer Station Detailed Engineering Detailed Engineering building Detailed Engineering gas cycle system Detailed Engineering civil works Detailed engineering steam cycle system KPO (control room and office) Aalborg engineering Steelcom (stack) Siemens GE Seeger engineering AG (Steam boiler) Alstom Power (steam condenser) SES Ltd (transformer yard) HRSG Diffuser Compressor Gas Turbine Steam Turbine Generator Gear box set Gas cycle Steam cycle B.O.M. and take-offs Request for proposal Gathering of proposals Competitive proposal analysis B.O.M. and take-offs Request for proposal Gathering of proposals Competitive proposal analysis Gas treatment and Compression station Stack Erection HRSG and Diffuser erection Steam Turbine Erection Steam boiler erection Steam condenser erection Electrical Items Generator and gear box set erection Transformer erection Order of components Order of components Supervising Control Erection Process UK KPO (Control room and office) GE Generator Gearbox SES Ltf (transformer yard) Denmark Aalborg engineering Steelcom (Stack) HRSG Diffuser Germany Siemens Seeger engineering AG (Steam boiler) Compressor Gas turbine Steam turbine France (Alstom Power, Steam condenser)

WBS

  • Upload
    ziva

  • View
    25

  • Download
    0

Embed Size (px)

DESCRIPTION

- PowerPoint PPT Presentation

Citation preview

Page 1: WBS

POWER PLANT CONSTRUCTION

ENGINEERING

PURCHASE PROCESS

MANAGEMENT

COMMISSIONING AND TESTING

PLANT ERECTION

CIVIL WORKS

TRANSPORTATION

FABRICATION OF ITEMS

Basic design Submission and approval of engineering set of drawings

Permit and authorizations based on basic design

HRSG and diffuser Gas treatment and Compression station gas turbine

generator and gear box set

steam turbine steam boiler steam condenser

Site installation Plant civil works Construction control room and office building

Gas cycle

Steam Cycle

Project management

Site management

Expediting and item pre-test to the supplier's plant

Stack Transformer Station

Detailed Engineering

Detailed Engineering building

Detailed Engineering gas cycle system

Detailed Engineering civil works

Detailed engineering steam cycle system

KPO (control room and office)

Aalborg engineering Steelcom (stack) Siemens GESeeger engineering AG

(Steam boiler)Alstom Power

(steam condenser)SES Ltd

(transformer yard)

HRSG

Diffuser

Compressor Gas Turbine Steam Turbine Generator

Gear box set

Gas cycle Steam cycle

B.O.M. and take-offs

Request for proposal

Gathering of proposals

Competitive proposal analysis

B.O.M. and take-offs

Request for proposal

Gathering of proposals

Competitive proposal analysis

Gas treatment and Compression station

Stack Erection

HRSG and Diffuser erection

Steam Turbine Erection

Steam boiler erection

Steam condenser erection

Electrical Items

Generator and gear box set erection

Transformer erection

Order of components Order of components

Supervising Control Erection Process

UK

KPO (Control room and office)

GE

Generator Gearbox

SES Ltf (transformer yard)

Denmark

Aalborg engineering

Steelcom (Stack)

HRSG

Diffuser

Germany

Siemens

Seeger engineering AG(Steam boiler)

Compressor Gas turbine Steam turbine

France (Alstom Power,Steam condenser)