Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Water Treatment for Cedar Gulch 2
CEE 465 Capstone II
April 28, 2016
Deidre Beck, Deryn Beck, Luis Duque,
Jessica Lemmerman, and Mitchell Shearer
WATER SYSTEMS, INC. Brookings, SD
Project Background
Alternatives Analysis
Final Design
Acknowledgements
Presentation
Sioux Falls
Brookings
Rapid City
Pierre
Interstate 90
| 50 miles |
Pennington County
1 Mile
Interstate 90
Rapid City
Cedar Gulch 2
Rapid City Regional Airport
Project Background
Community Corps Project
Northern Virginia Professional
Chapter of Engineers Without
Borders USA (EWB-NOVA)
Drinking Water Issues
Water quality
Water storage
Water rights
Deep Well
Bra
dsk
yR
oad
Cedar Gulch 2
Well
DistributionSystem
Two 80 GallonWater Storage
Tanks
ChlorineFeed
System
Existing Water System
Water Quality
ParameterCG2 Well
(pCi/L)MCL
(pCi/L)
Gross Alpha 61.4 15
Radium 226 25.2 5
Radium 228 5.5 5
Water Quality
Consideration Ion Exchange Reverse Osmosis
Radium Removal Good Good
Gross Alpha Removal Adequate Good
Cost of Operation Low High
Ease of Operation Low High
Waste Stream Small Large
Water Rights
2 Options:
New Well
Buy Rights
No action
Population - 40 residents
Water Usage for Community
Includes:
Emergency needs
Irrigation and other outside usage
Does not include
Fire protection
Design Water Demand - 100 gpd/capita
Design Water Storage - 3,000 gallons
Design Water Demand
Description Water Demand (gpd)
ADD (Average Day Demand)
4,000
MDD (Max Day Demand)
12,000
PHD (Peak Hour Demand)
16,000
Design Water Demand
Alternative 1: Point of Entry (POE)
Alternative 2: Centralized Treatment
Alternative 3: Connection to City Water
Alternatives
Proposed Centralized Treatment Site
Deep Well
Bra
dsk
yR
oad
Life-Cycle Cost Analysis
Alternative Present Worth Cost
Point of Entry $258 Thousand
Centralized Treatment $326 Thousand
Connect to City Water $2.2 Million
Alternatives Analysis Matrix
Rank Consideration Weight
1 Cost 40%
2 Timeline 20%
3 Water Storage 15%
4 Water Rights 15%
5 Water District Responsibility 10%
Alternatives Analysis
Alternatives were ranked 1-3 with 3 being the best
Consideration Weight POE Centralized City Water
Cost 40% 3 2 1
Timeline 20% 3 2 1
Water Storage 15% 2 2 3
Water Rights 15% 1 1 3
Water District Responsibility
10% 1 1 3
Score 100% 2.35 1.75 1.80
Recommendation
Point of Entry
Individual Ion Exchange
Treatment (Water Softener) +
Additional Community Storage
Lowest Cost
Quick implementation
Improved Community Storage
Final Design: Centralized Treatment
Plan View
Ion exchange
Ion exchange
WRT Z88 Portable Exchange System (PES)
20 gpm
Radium removal 30 pCi/L to below 5 pCi/L
Gross alpha removal equivalent to Ra-226 removal
$49,500 + engineering and installation
$43,000 Media Exchange Service @ 3.8 million gallons (~3 years)
Chlorine System
Chlorine System
Liquid Chlorine (NaOCl)
8.25% conc. by weight
2 pumps( 1 is backup)
Storage Tank for Chlorine
15 gallon, doubled walled
Chlorine delivered every 14 days
$690 + engineering, installation and maintenance
Retention Tank
Retention Tank
WG23_watercat Water Retention Tank
Capacity: 300 gallon
Non-pressurized
Dimensions of Retention Tank:
Diameter – 46"
Height– 49.5"
$310 + engineering and installation
Storage Tank
Storage Tank
3,000-gallon HydropneumaticWater Storage Tank
Design Pressure: 100psi
Operating Pressure: 65-75 psi
Dimensions of Storage Tank:
Diameter – 60"
Length – 23'
$20,000 + engineering and installation
Foundation Structure
Cross sections
Column
Footing
Cost EstimateItem Description Unit Cost per Unit Quanitity Cost
1 Mobilization LS $ 5,250.00 1 $ 5,250.00
2WRT Ion Exchange System (25 gpm) LS $ 49,500.00 1 $ 49,500.00
3 Retention Tank LS $ 310.00 1 $ 310.00
4 Chlorine System LS $ 690.00 1 $ 690.00
5Hydroneumatic Storage Tank LS $ 20,000.00 1 $ 20,000.00
63" Schedule 40 PVC Pipe and Fittings FT $ 13.26 50 $ 663.00
7 Reinforced Concrete CU YD $ 100.00 30 $ 3,000.00
8 Prefabricated Building LS $ 5,000.00 1 $ 5,000.00
Subtotal 1 $ 84,413.00
Engineering/Installation (15%) $ 15,800.00
Contingency (5%) $ 5,250.00
Total $ 105,463.00
Dr. Kyungnan Min
EWB-NOVA
Bernard Krantz, PE, Bechtel National
Sara Schmieg, PE, Bechtel National Inc.
Jon Mulligan, EIT, The Engineering Groupe, Inc.
Catherine Eichel, EIT, Brown and Caldwell
Jim Jones, Midwest Assistance Program
Cedar Gulch 2 residents
Acknowledgements